ASSESSING LOSS AND EXPENSES CLAIM BY
PROLONGATION COST
RAIHA AZENE BINTI RAMLI
UNIVERSITI TEKNOLOGI MALAYSIA
ASSESSING LOSS AND EXPENSES CLAIM BY PROLONGATION COST
RAIHA AZENE RAMLI
A project report submitted in partial fulfilment of the
requirement for the award of the degree of
Master of Science (Construction Contract Management)
Faculty of Built Environment
Universiti Teknologi Malaysia
JANUARY 2015
iii
To my beloved husband, parents, sisters and brothers
Thank you for your support and confidence in me.
iv
ACKNOWLEDGEMENTS
First of all, I would like to say thank to all the lecturers for the program of
Master of Science (Construction Contract Management), especially my supervisor –
Assoc. Sr. Prof Dr. Maizon Hashim, for their guidance during the writing of this
master project. Without their supervision and advice, this project could not be
completed on time.
Secondly, I would like to express my gratitude to my dearest husband,
parents, brothers and sisters for their support and advice during these few months.
Not forgetting my classmates, a token of appreciation goes to them for giving
lots of advice on how to complete and write this project.
v
ABSTRACT
Contractor’s claims for loss and expenses have long been a contentious issue on
many building contract. Claims are usually resolved during the final account process,
but where negotiations fail, they frequently become disputes, with the parties
adopting legal route to resolve their differences. Claims to recover prolongation cost
arise in a number of contexts and it is importance for the claimant to understand the
principles upon which such claims might be evaluated. In valuing the loss and
expenses claim by prolongation cost, it is fundamental to prove delay and actual
related cost losses arise in an action of damages and failure to prove will not entitle
to a claim for damages. The objective of this study is to determine loss and expense
claims that is related to prolongation cost by head of loss claims. The head of loss
claims include site overheads, head office overhead, loss of profits, interest and
financing charges, loss of productivity and cost of preparing the claim. The loss
should be measured at the point in time in which the delay event arose, rather than
costs incurred at the end of contract. In valuing prolongation costs, the decision in
Costain v Haswell therefore provides a useful reminder of the importance of
distinguishing costs generated by time and by volume. This study was carried out
mainly through documentary analysis of law journals. The study also helps in adding
to the knowledge base of the literature on prolongation costs and construction
contracts.
vi
ABSTRAK
Tuntutan kontraktor untuk kerugian dan perbelanjaan telah lama menjadi
isu pertikaian di dalam kontrak secara amnya. Tuntutan biasanya diselesaikan semasa
proses akaun muktamad, tetapi jika rundingan gagal, mereka sering menjadi
pertikaian, maka penyelesaian secara undang-undang digunapakai bagi percanggahan
yang berlaku. Tuntutan untuk mendapatkan kembali kos pemanjangan timbul dalam
beberapa konteks dan ia adalah penting bagi pihak yang menuntut untuk memahami
prinsip-prinsip di mana tuntutan itu mungkin dinilai. Dalam menilai kerugian dan
perbelanjaan tuntutan dengan kos pemanjangan, ia adalah asas untuk membuktikan
kelewatan dan kos kerugian sebenar yang berkaitan timbul dalam sesuatu tindakan
kerosakan dan kegagalan untuk membuktikan tidak memberi hak kepada tuntutan
ganti rugi. Objektif kajian ini adalah untuk menentukan kerugian dan perbelanjaan
tuntutan berkaitan dengan kos pemanjangan berdasarkan kepada ‘head of claims’.
Tuntutan kepada head of loss claims termasuklah site overheads, head office
overhead, loss of profits, interest and financing charges, loss of productivity dan cost
of preparing the claim. Kerugian dan perbelanjaan haruslah diukur berdasarkan
kepada masa di mana kelewatan itu timbul daripada kos yang ditanggung oleh pihak
Kontraktor pada akhir kontrak. Dalam menilai kos pemanjangan, keputusan di dalam
kes Costain v Haswell itu memberi satu peringatan penting dimana perlu
membezakan kos samaada melalui time dan melalui volume. Kajian ini telah
dijalankan terutamanya melalui analisis dokumentari jurnal undang-undang. Kajian
ini juga membantu dalam menambah ilmu pengetahuan terhadap kos pemanjangan
dan kontrak pembinaan.
vii
TABLE OF CONTENTS
CHAPTER TITLE PAGE
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENTS iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLE xi
LIST OF FIGURE xii
LIST OF CASES xiii
1 INTRODUCTION
1.1 Background of Study 1
1.2 Problem Statement 3
1.3 Objective of Research 5
1.4 Scope of the Study 5
1.5 Significance of the Study 5
1.6 Organization of Chapters 6
1.6.1 Chapter 1: Introduction 6
1.6.2 Chapter 2: Loss and Expenses 6
1.6.3 Chapter 3: Prolongation Cost 7
1.6.4 Chapter 4: Research Methodology 7
1.6.5 Chapter 5: Assessment Loss and
Expenses Claim by Prolongation Cost
8
1.6.6 Chapter 6: Conclusion and
Recommendation
8
viii
CHAPTER TITLE PAGE
2 LOSS AND EXPENSES
2.1 Introduction 9
2.2 The Concept of Loss and Expenses Cost 12
2.3 Ground for Contractual Claims 13
2.3.1 Loss and Expenses under Standard
Form Provision
13
2.3.2 Notice requirements 17
2.3.3 Nature and form of notice/application 18
2.3.4 Conditions precedent and the failure to
give notice/application where the terms
of contract require it.
20
2.4 Quantification of Claims 23
2.5 Assessment of Loss and Expenses Claims 24
2.5.1 Additional Preliminaries 25
2.5.2 Labour Disruption 27
2.5.3 Material 29
2.5.4 Inflation 31
2.5.5 Head Office Overheads and Profit 31
2.5.6 Interest and Financing Charges 34
2.6 Conclusion 35
3 PROLONGATION COST
3.1 Introduction 37
3.2 Evaluating Prolongation Costs 41
3.2.1 The difference between claims for an
extension of time and prolongation cost
41
ix
CHAPTER TITLE PAGE
3.3.2 The difference between prolongation
costs arising from critical and non-
critical delays
43
3.3 Principle to Claim to Recover Prolongation Cost 46
3.4 Quantification of Prolongation Costs 48
3.4.1 On-Site Overhead 50
3.4.1.1 Actual cost 52
3.4.1.2 Estimated Cost 53
3.4.2 Off-Site Overheads 53
3.4.3 Subcontractors’ prolongation cost 55
3.4.4 Financing Costs 56
3.4.5 Cost related to claim preparation 56
3.4.6 Loss of profit opportunity 58
3.5 Conclusion 59
4 RESEARCH METHODOLOGY
4.1 Introduction 61
4.2 Methodology of Study 61
4.3 Limitations of the study 65
4.4 Conclusion 66
5 ASSESSMENT OF LOSS AND EXPENSES BY
PROLONGATION CLAIM
5.1 Introduction 67
5.2 Head of Loss Claim in Prolongation Cost 69
5.2.1 On-Site Overhead 70
x
CHAPTER TITLE PAGE
5.2.2 Off-site Overhead 75
5.2.3 Loss of profits 78
5.2.4 Interest and financing charges 81
5.2.5 Cost of preparing the claim 85
5.3 Conclusion 89
6 CONCLUSIONS AND RECOMMENDATIONS
6.1 Introduction 90
6.2 Summary of Research Findings 90
6.3 Problem Encountered During Research 95
6.4 Further studies 95
6.5 Conclusion 96
6.6 Recommendation 99
REFERENCES
xi
LIST OF TABLE
TABLE NO. TITLE PAGE
2.1 Example of a Calculation of a Disruption Claim 29
xii
LIST OF FIGURE
FIGURE NO. TITLE PAGE
4.1 Research Process ad Method of Approach 62
xiii
LIST OF CASES
NAME OF CASES PAGE
Ascon v McAlpine(1999) 66 Con LR 119, (2000) 16 Const LJ 316
(TCC)
74,75,92
Bremer Hadelsgesellschaft mbh v Vanden Avenne Izegem [1978] 2
LJoyds Rep 109
22
City Inn Limited v. Shepherd Construction Limited [2007] CSOH 190 44
Costain Limited v. Charles Haswell & Partners Limited
[2009] EWHC 3140 (TCC)
42,70
Ellis-Don Ltd v Parking Authority of Toronto (1978) 28 BLR 98 33
F.G.Minter Limited v Welsh Health Technical Services
Organization[1980] 13 BLR 1
14
Hadley vs. Baxendale (1854) 9 Ex 341 10,14,15,
35,69,82
John Doyle Construction Limited v Laing Management (Scotland)
Limited [2004] BLR 295
45
J Crosby & Sons Ltd v Portland UDC (1967) 5 BLR 126 13
James Longley & Co Ltd v South West Regional Health
Authority(1984) 25 BLR 56
57
JF Finnegan Ltd v Sheffield CC (1988) 43 BLR 124 33,76,93
London Borough of Merton v Stanley Hugh Leach [1985] 32 BLR 51 19,21
xiv
NAME OF CASES PAGE
Merton LBC v Stanley Hugh Leach Ltd (1985) 32 BLR 51. 13
Peak Construction Ltd v McKinney Foundations Ltd. [1970] 1 BLR
111
32,79,93
President of India v La Pintada Cia Navegacion SA [1985] AC 104. 34
Rees & Kirby Ltd v Swansea CC(1985) 30 BLR 1 34.82,84.93
Robinson v. Harman 1 Exch. 850 15,89
South Australia Asset Management Corporation v. York Montague
Ltd [1996] 3 All ER 365
16
Sunley Ltd v. Cunard White Star Ltd [1940] 1 KB 740 76,78
Wraight Ltd v P H & T (Holdings) Ltd (1968) 13 BLR 26 23,80
Wood v Grand Valley Railway Co., (1913) 30 O.L.R. 44 28
1
CHAPTER 1
INTRODUCTION
1.1 Background of Study
A contractor is entitled to payment for works including variations and may
also entitle to claim for additional time and money.1
There is no legal significance of
the term prolongation claim. It is not a type of claim described by the law and is
often called a delay claim. Many times it is also known as disruption claim. Only the
contractors and subcontractors can make this claim, not the Employer2
. This claim
intends to allow the contractor to gain compensation in terms of money, if at all there
is a compensable delay that actually stops or hinders the contractor from completing
the work on time. The claim is made underlying the delay factors in which the
contract was prolonged or the completion of the project was delayed, that is, the
work took longer time by the contractor in completion than it was anticipated by the
contractor at the time when the contract was made.
Most of the contracts are developed clearly underlining on the agreement that
the contractor will finish the work within the given time-period. Furthermore, it
1
Murdoch, J.R. and Hughes, W. (2008) Construction Contracts: Law and Management, 4th ed.
Taylor and Francis, Oxford
2
Davenport, P. (2006). Construction Claims. Federation Press. pp.126
2
implicitly emphasizes on the requirement that the client will ensure that he/she avoid
in delaying the work of the contractor3
.
However, delays do occur in a number of construction contracts, where there
is an implicit and understood the requirement of compensating the party that has
suffered the loss. Due to these delays, it becomes obvious that the contract will not
be completed on time. As a result, the assessment of delays in contracts leads is
necessary, which involves identification of the specific cause for each delay,
followed by the assessment of the extent to which the delay has occurred and lastly,
attributing the responsibility of the delay4
. It is clearly stated that to assess the extra
payment due to the delay as a consequence of Employers prolongation, the
assessment of the claim must be related to the time when the act of delay occurred
and should not in exceed time of the contract. A simple example as follow:
“If party A tends to suffer a loss due to a delay caused by party B, then party
A is entitled to claim for the compensation of the damages in order to put
party A back into the position in which he was before the act of delay”.
Therefore, prolongation costs would be the costs that are actually incurred
from the time when delay occurred and started affecting the progress of the contract,
instead of the time extended for completing the contract. What should be considered
is the impact of delay on the progress, and it leads to have a clear assessment of the
impact of the delay for determining the additional overhead expenses and costs that
has been incurred5
.
This claim could be charged on when, and if, the project is prolonged or
extended beyond the anticipated completion time because of the delay in the progress
3
Ibid, pp.126
4
Ndekugri, I., Braimah, N., and Gameson, R. (2008). Delay Analysis within Construction Contracting
Organizations. J. Constr. Eng. Manage., 134(9), p.1279
5
Lo, T., Fung, I., and Tung, K. (2006). ”Construction Delays in Hong Kong Civil Engineering
Projects.” J. Constr. Eng. Manage., 132(6), p.636
3
of the work and activities and as a result the Contractor is required to employ extra
resources over and above the actual allowed price of the contract. Nevertheless,
there are some resources that could be extended with the span of original contractual
period due to some variations. These extended resources must be reimbursed to the
Contractor for further progress.
1.2 Problem Statement
In any construction projects, the contractor is legally obligated to complete
the project within the date set for completion or by the date that is set in the contract.
However, delays always tend to disrupt and disturb the performance of the work
performed by the contractor. This delay might be cause of either by the employer or
by the contractor himself or due to the events for which none of the party is
responsible.
As for delays or disruption caused to the Works, if these are caused through
some act or omission of the Employer or his agent (perhaps the architect, engineer or
the Superintending Officer) then contracts often allow the contractor to recover his
costs arising from the delay or disruption, again in the form of loss and expenses.6
Any claim for loss and expenses must be calculated on the basis of the actual
loss incurred. It is not unusual to see prolongation costs calculated on the basis of
sums derived from contract preliminaries. This is clearly incorrect as the figures
included in the contract are essentially estimates. Using the contract preliminaries is
unlikely to represent the true loss suffered by a contractor in the event of delay.7
6
Michael Charlton et al., Seminar Paper: Additional Payment under Malaysian Forms of Contract,
2001. p.1/34
7
Ibid. p.2/34
4
Having established the legal right to pursue a claim for loss and/or expense
and satisfied all the relevant procedural requirements, it is obligatory for the claimant
to identify with suitable precision the respective heads of loss claim entitlements that
need to be quantified and substantiated. The principal common areas of such claim
usually encountered in practice as follows:8
a. Site Overheads;
b. Head Office Overheads;
c. Loss of Profits;
d. Interest and Financing charges;
e. Loss of Productivity;
f. Inflationary Cost Increase of Materials and Labour; and
g. Cost of Preparing the Claim.
A typical claim for loss and/or expenses depends on the nature of the delay or
disruptive element. It may encompass either one, or all, or a number of the above-
listed heads of entitlements. Much also depends upon the relative strength of the
particular case in terms of the quality of proof (example: records and documents)
available in justification of the particular entitlement or entitlements. Though some
of the said entitlements appear relatively straight forward, these are nevertheless
fraught with legal uncertainties where the ultimate decision is swayed more by
subjective factors than objective considerations. Hence, the subsequent write-up
expands upon the scope of some of the rather contentious areas of the claim for
entitlements so as to shed some light for better understanding.
8
Ir Harban Singh KS. (2007). Demystifying direct loss and/or expense claims. Malayan Law Journal
Articles/2007/Volume 4/DEMYSTIFYING DIRECT LOSS AND/OR EXPENSE CLAIMS. 4 MLJ
xxix. P.
5
1.3 Objective of Research
Following is the objective of the study:
1. To determine potential heads of loss claim under loss and expense claims
due to prolongation cost.
1.4 Scope of the Study
This research will focused at relevant research papers, articles, books,
journals and court cases on loss and expenses claim on prolongation cost in heads of
loss claims in any jurisdiction. The court cases will not be restricted to Malaysian
cases only; reference is also made to cases in other countries such as United
Kingdom, United States, Canada and Hong Kong. The scope of the study is wide
enough to incorporate different cases, demonstrating a broader view of the research
topic.
1.5 Significance of the Study
Claims to recover prolongation costs arise in a number of contexts and it is
some importance for parties to understand the principle upon which head of loss
claims might be evaluated. The study helps in adding to the knowledge base of the
literature on loss and expenses claims and prolongation costs under construction
contracts. This study is to reduce the uncertainty and difficulties in the event of
6
claiming loss and expense that are deny under the reason upon the relative strength
of the particular case in terms of the quality of proof available in justification of the
particular entitlement or entitlements. Though some of the said entitlements appear
relatively straight forward, these are nevertheless fraught with legal uncertainties
where the ultimate decision is swayed more by subjective factors than objective
considerations. Hence, construction industry stake holders will be more aware and
clear understanding while dealing with heads of loss claims in contracts.
1.6 Organization of Chapters
1.6.1 Chapter 1: Introduction
The first chapter provides an overview of the research, including a brief
background of the topic along with describing brief concept of prolongation costs,
claims and delays, the problem that is focused in the research, the objectives that will
be achieved through literature study analysis. In addition, the section includes scope
of the study and the significance of the study.
1.6.2 Chapter 2: Loss and Expenses
In the second chapter, literature review on loss and expenses claim have been
studied to identify the contractor entitlement to recover loss and expenses claim
affected by specific events as set out in the relevant clauses and standard form of
contract. The assessment for contractor claims for loss and expenses perhaps most
argumentative issue in the post-contract financial management of building contract.
7
However, the recovery of loss and expense is a procedure under specific term
of the contract. The recovery of certain heads of claim may be permitted under
express contract terms which might not be recoverable as a claim for damage at
common law. A careful study of contract condition and appreciation of their legal
application and knowledge of the relevant case law has also been collected and
reviewed in this chapter.
1.6.3 Chapter 3: Prolongation Cost
In the third chapter, literature review for the prolongation cost has been
studied to substantiate the entitlement of the heads of loss claim. Contractually or
legally the contractor must prove his claim in order to have sufficient merit to
warrant certification of appropriate amount of entitle of the heads of loss claims.
Commonly the entitlement of head of loss claim brought under the following heads:
1) On-site overheads
2) Head office overheads
3) Interest and Financing Costs
4) Loss of Profit
5) Cost related to claim preparation
1.6.4 Chapter 4: Research Methodology
In the fourth chapter, the methodologies of this study has been separated into
few steps, namely identifying the research issue, literature review, data collection,
research analysis, and conclusion and recommendation. This approach is to ensure
8
that the collection of the information and the data analyzing can be precisely
implemented.
1.6.5 Chapter 5: Assessment Loss and Expenses Claim by Prolongation Cost
The fifth chapter provides analysis of different case studies by critically
reviewing and clarifying all the facts of the case studies. Furthermore, this chapter
will present, discuss and compare each issue identified from the case study in
accordance to the objectives of the research.
1.6.6 Chapter 6: Conclusion
Lastly, the sixth chapter will provide a discussion of the overall research
findings relating them with the objectives of the study. Moreover, this chapter will
also provide recommendations for the future study and limitations of the study.
98
REFERENCES
Aibinu, A. A. (2007). “Construction project claims and conflict in Singapore”,
Construction Management and Economics: Past, Present and Future Conference,
Proc., CME25 Anniversary Conference, W. P. Hughes.
Atkin Chambers (2010), Hudson’s Building and Engineering Contracts, 12th ed.
Sweet&Maxwell, London.
Assaf, S. A., Al-Khalil, M., and Al-Hazmi, M. (1995). Causes o f delay in large
building construction projects. Journal o f Management in Engineering, ASCE
Bartlett, A., Lloyd, H. and Palmer, N.E. (2002). Emden’s construction law, London:
Lexis Nexis Butterworths
Bennett, J. and Peace, S. (2006). Partnering in the construction industry. A code of
practice for strategic collaborative working, Oxford: Butterworth-Heinemann
Bramble, B. B., and Callahan, M. T. (1992). Construction delay claims, 2nd Ed.,
Wiley, New York.
99
Chappell, D., Powell-Smith, V. and Sims, J. (2008) Potential Heads of Claim, in
Building Contract Claims, Fifth Edition, Blackwell Publishing Ltd, Oxford
Construction Industry Development Board (‘CIDB’). (2000)
Davenport, P. (2006). Construction Claims. Federation Press.
Dr. Chandana Jayalath (2009). Claims on Prolongation Costs in Nutshell. Available
at http://www.articlesbase.com/construction-articles/claims-on-prolongation-costs-
in-nutshell-1413885.html. Accessed 10th
February 2014.
Eggleston, B. (2006) The NEC 3 engineering and construction contract. A
commentary, 2nded. pp.56-178 Oxford: Blackwell Science.
Dr Ronan Champion (2011). Prolongation Costs: Where Now After Constain v
Haswell. A paper presented to meetings of the Society of Construction Law in
Reading on 29th
March and Manchester on 9th
May 2011.
Eggleston, B. (2008) Relevant Events, in Liquidated Damages and Extensions of
Time: In Construction Contracts, Third Edition, Wiley-Blackwell, Oxford, UK.
Entrusty Group. (2005). What is Loss and/or Expense?. Master Builders 1st
Quarter
2005, 86-89.
Fisher, J. M. (2006). Understanding Remedies (2nd ed.). Newark, NJ: LexisNexis,
pp. 77-89.
100
Furst, S. and Ramsey, V. (2006), Keating on Construction Contracts, 8th ed.,
Sweet&Maxwell, London.
Goldberg, J., Sebok, A., & Zipursky, B. (2008). Tort law: Responsibilities and
redress. New York: Aspen, pp. 51-59
Gombos v. Ashe, 158 Cal. App. 2d 517 (1958).
Gray, C. and Hughes, W.P. (2000). Building Design Management. London:
Butterworth-Heinemann
Gruneberg, S.L. and Hughes, W.P. (2005), Understanding construction consortia:
theory, practice and opinions, RICS Research Papers.
Hackett, K. (2007) Change and its Effects, in K. Pickavance (2007) Construction
Law and Management (2007), Informa, London.
Harbans Singh, K., S., (2002). Commencement and Administration, Engineering and
Construction Contracts Management, Kuala Lumpur LexisNexis.
Hughes, W., Hillebfrandt, P., and Murdoch, J., (2000), The impact of contract
duration on the cost of cash retention, Construction and Management and
Economics, Vol.18, No.1, pp.11-14
Institution of Civil Engineering (ICE) 6th Edition.
Institution of Engineers Malaysia (‘IEM’) 1989.
101
Ir Harban Singh KS. (2007). Demystifying direct loss and/or expense claims.
Malayan Law Journal Articles/2007/Volume 4/DEMYSTIFYING DIRECT LOSS
AND/OR EXPENSE CLAIMS. 4 MLJ xxix
JCT Standard Form of Building Contract (Private Edition with Quantities)(1980
edition)
Keane, D. (2001). The RIAI Contracts: a Working Guide, 4th ed. Royal Institute of
the Architects of Ireland, Dublin.
Keith Pickavance. (2010). Delay and Disruption in Construction Contracts. 4th
Revised edition edition. Sweet & Maxwel
Knowles, J.R. (n. d.) Contractors and Subcontractor Claims the New Approach
Seminar Proceeding 4th December 1991 Jurys Hotel, Dublin.
Knowles, R. (2012). Loss and Expense/Additional Cost, in 200 Contractual
Problems and their Solutions, Third Edition, Wiley-Blackwell, Oxford, UK.
Lee, H. S., Ryu, H. G., Yu, J. H., and Kim, J. J. (2005). Method for calculating
schedule delay considering lost productivity. Journal o f Construction Engineering
and Management, ASCE, 131(11), 1147-1154
Lo, T., Fung, I., and Tung, K. (2006). ”Construction Delays in Hong Kong Civil
Engineering Projects.” J. Constr. Eng. Manage., 132(6), 636–649.
Long D, Nguyen. (2007). The Dynamics of Float, Logic, Resource Allocation, and
Delay Timing in Forensic Schedule Analysis and Construction Delay Claims.
ProQuest Pllc. 1-130
102
March, C. (2009) Finance and Control for Construction, Taylor and Francis, Oxford.
Majid, M. Z. A. and McCaffer, R. (1998). Factors of non-excusable delays that
influence contractors’ performance. Journal of Management in Engineering, ASCE,
14(3), 42-49.
McGovern, C. (2011). GCCC Contracts Experience to Date: A Review of the
Operation of theGCCC Contract on Civil Engineering Projects. Presentation to
Engineers Ireland (Thomond West Region) 8th March 2011. Available at
http://www.slideshare.net/cmcgoverntobin/gccc-contractsexperience-to-date-080311.
Accessed 8th
December 2014.
Mohd Norazman Zaini. (2001). Seminar on Additional Payment under Malaysian
Forms of Construction Contract. Loss and Expenses/Additional Cost. 18 June 2001.
JW Marriott Hotel, Kuala Lumpur. Lecture 4
Murdoch, J.R. and Hughes, W. (2008) Construction Contracts: Law and
Management, 4th ed. Taylor and Francis, Oxford.
Murray, M. and Langford, D. (Eds.) (2003). Construction reports 1944–98,
Oxford:Blackwell.
Ndekugri, I., Braimah, N., and Gameson, R. (2008). Delay Analysis within
Construction Contracting Organizations. J. Constr. Eng. Manage., 134(9), 692–700.
New South Wales Government Procurement System for Construction. (2008).
Handling Prolongation and Disruption Claims. Procurement Practice Guide.
103
Pertubuhan Akitek Malaysia (‘PAM’) 2006 (with quantities)
Philip Georgiou. (2008). Extensions of Time, Concurrent Delay, and Causation: City
Inn v Shepherd Judicial Guidance from the UK Courts at Long Last. Available at
http://www.jonesday.com/extensions-of-time-concurrent-delays-and-causation-city-
inn-v-shepherd-judicial-guidance-from-the-uk-courts-at-long-last-05-14-2008/.
Accessed 8th
December 2014.
Public Works Department (‘PWD’) Form 203A (rev.2010)
Ramus, J. Birchall, S. and Griffiths, P. (2006) Contract Practice for Surveyors 4th
ed. Butterworth Heinemann, London.
Roger Gibson. (2008). Construction Delays Extensions of Time and Prolongation
Claims. Taylor & Francis.
Society of Construction Law (SCL). (2002), “Delay and disruption protocol.” SCL,
London.
Tony Cunningham. (2014). Contractors’ Claims for Loss and Expenses under the
Principle “Traditional’ Forms of Irish Building Contract. School of Surveying and
Construction Management Dublin Institute of Technology.
The Surveyor Construction Handbook (2003). Ascertaining the Amount of Loss and
Expense Incurred in Building Projects, RICS Business Services Limited.
104
The Byron Partnership. (2002). Construction Claims Management. Prolongation
Claims. Available at www.byron10.com_uploads_Prolongation_Costs_20101116
Accessed 4th
January 2014.
Trickey, G. and Hackett, K. (2001). The Presentation and Settlement of Contractors
Claims, 2nd ed. Spon, London.
Vidogah, W., and Ndekugri, I., 1998, “Improving the management of claims on
construction contracts: Consultant’s perspective.”Constr. Manage. Econom, 16, 363–
372
Wigal, G. S. (1990). Interference with a contractor's early completion o f a
construction project. The Construction Lawyer, 10(4), 17-25.

More Related Content

What's hot

Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
kmasz kamal
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
Susitra Anandan
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
Dr K M SONI
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
JIT KUMAR GUPTA
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
SivaSubramanian Sakthivel
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
Shankar Ramasamy
 
Tunneling
TunnelingTunneling
Tunneling
Safdar Ali
 
Tunnelling
TunnellingTunnelling
Tunnelling
Usama Zia
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineeringSaurabh Samant
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
SamsonFemiAdesope
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
Rajarshi Patty
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
Prof. A.Balasubramanian
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
Jagriti Mandal
 
Hoisting equipments
Hoisting equipmentsHoisting equipments
Hoisting equipments
vipul308
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
Ketut Swandana
 

What's hot (20)

Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
Tunneling
TunnelingTunneling
Tunneling
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Engineering Geology
Engineering Geology Engineering Geology
Engineering Geology
 
Tunneling & Drilling Equipments
Tunneling & Drilling EquipmentsTunneling & Drilling Equipments
Tunneling & Drilling Equipments
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
 
Hoisting equipments
Hoisting equipmentsHoisting equipments
Hoisting equipments
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 

Similar to Assessing Loss And Expenses Claim By Prolongation Cost

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
Against all odds
Against all odds Against all odds
Against all odds
Cerasela Angelescu
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
chandrats
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
Determinative forum - 19 August
Determinative forum - 19 AugustDeterminative forum - 19 August
Determinative forum - 19 August
Resolution Institute
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
Lin Hui
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Dr. Zaid Mahayni
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
mark woodward-smith
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET Journal
 
Apportionment the netting off approach c
Apportionment the netting off approach cApportionment the netting off approach c
Apportionment the netting off approach cJeremy Fearnsides
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
IJMER
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
Est
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
SHAZEBALIKHAN1
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET Journal
 

Similar to Assessing Loss And Expenses Claim By Prolongation Cost (20)

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Against all odds
Against all odds Against all odds
Against all odds
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Determinative forum - 19 August
Determinative forum - 19 AugustDeterminative forum - 19 August
Determinative forum - 19 August
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
Apportionment the netting off approach c
Apportionment the netting off approach cApportionment the netting off approach c
Apportionment the netting off approach c
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Lawyer-Monthly_Metehan-Sonbahar
Lawyer-Monthly_Metehan-SonbaharLawyer-Monthly_Metehan-Sonbahar
Lawyer-Monthly_Metehan-Sonbahar
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 

More from Jessica Navarro

Essay About Ecotourism
Essay About EcotourismEssay About Ecotourism
Essay About Ecotourism
Jessica Navarro
 
Example Discussion Essay
Example Discussion EssayExample Discussion Essay
Example Discussion Essay
Jessica Navarro
 
Bonnie And Clyde Essay
Bonnie And Clyde EssayBonnie And Clyde Essay
Bonnie And Clyde Essay
Jessica Navarro
 
Example Essay Argumentative
Example Essay ArgumentativeExample Essay Argumentative
Example Essay Argumentative
Jessica Navarro
 
Racism Today Essay
Racism Today EssayRacism Today Essay
Racism Today Essay
Jessica Navarro
 
Argumentative Essay Prompts
Argumentative Essay PromptsArgumentative Essay Prompts
Argumentative Essay Prompts
Jessica Navarro
 
Writing Border
Writing BorderWriting Border
Writing Border
Jessica Navarro
 
Essay Websites How To Start A College Admission Essay 12
Essay Websites How To Start A College Admission Essay 12Essay Websites How To Start A College Admission Essay 12
Essay Websites How To Start A College Admission Essay 12
Jessica Navarro
 
Printable Pig Stationery PaperCute PigWriting Pape
Printable Pig Stationery PaperCute PigWriting PapePrintable Pig Stationery PaperCute PigWriting Pape
Printable Pig Stationery PaperCute PigWriting Pape
Jessica Navarro
 
Terrorism Essay. Long A
Terrorism Essay. Long ATerrorism Essay. Long A
Terrorism Essay. Long A
Jessica Navarro
 
Website That Writes Essays For You Love You - There Is A Website That
Website That Writes Essays For You Love You - There Is A Website ThatWebsite That Writes Essays For You Love You - There Is A Website That
Website That Writes Essays For You Love You - There Is A Website That
Jessica Navarro
 
Pin On For The Boys
Pin On For The BoysPin On For The Boys
Pin On For The Boys
Jessica Navarro
 
Critical Analysis Of An Article - Critical Analysis Essay -
Critical Analysis Of An Article - Critical Analysis Essay -Critical Analysis Of An Article - Critical Analysis Essay -
Critical Analysis Of An Article - Critical Analysis Essay -
Jessica Navarro
 
How To Write An Effective Narrative Essay
How To Write An Effective Narrative EssayHow To Write An Effective Narrative Essay
How To Write An Effective Narrative Essay
Jessica Navarro
 
Use Custom Essay Writing Services And Know The Di
Use Custom Essay Writing Services And Know The DiUse Custom Essay Writing Services And Know The Di
Use Custom Essay Writing Services And Know The Di
Jessica Navarro
 
IB Extended Essay Topics For The Highest Grades
IB Extended Essay Topics For The Highest GradesIB Extended Essay Topics For The Highest Grades
IB Extended Essay Topics For The Highest Grades
Jessica Navarro
 
Home - Research - LibGuides At Uni
Home - Research - LibGuides At UniHome - Research - LibGuides At Uni
Home - Research - LibGuides At Uni
Jessica Navarro
 
10 Tips For Writing Effective Essay LiveWebTutors
10 Tips For Writing Effective Essay LiveWebTutors10 Tips For Writing Effective Essay LiveWebTutors
10 Tips For Writing Effective Essay LiveWebTutors
Jessica Navarro
 
Printable Sentence Strips - Printable Word Searches
Printable Sentence Strips - Printable Word SearchesPrintable Sentence Strips - Printable Word Searches
Printable Sentence Strips - Printable Word Searches
Jessica Navarro
 
Website That Does Essays For You
Website That Does Essays For YouWebsite That Does Essays For You
Website That Does Essays For You
Jessica Navarro
 

More from Jessica Navarro (20)

Essay About Ecotourism
Essay About EcotourismEssay About Ecotourism
Essay About Ecotourism
 
Example Discussion Essay
Example Discussion EssayExample Discussion Essay
Example Discussion Essay
 
Bonnie And Clyde Essay
Bonnie And Clyde EssayBonnie And Clyde Essay
Bonnie And Clyde Essay
 
Example Essay Argumentative
Example Essay ArgumentativeExample Essay Argumentative
Example Essay Argumentative
 
Racism Today Essay
Racism Today EssayRacism Today Essay
Racism Today Essay
 
Argumentative Essay Prompts
Argumentative Essay PromptsArgumentative Essay Prompts
Argumentative Essay Prompts
 
Writing Border
Writing BorderWriting Border
Writing Border
 
Essay Websites How To Start A College Admission Essay 12
Essay Websites How To Start A College Admission Essay 12Essay Websites How To Start A College Admission Essay 12
Essay Websites How To Start A College Admission Essay 12
 
Printable Pig Stationery PaperCute PigWriting Pape
Printable Pig Stationery PaperCute PigWriting PapePrintable Pig Stationery PaperCute PigWriting Pape
Printable Pig Stationery PaperCute PigWriting Pape
 
Terrorism Essay. Long A
Terrorism Essay. Long ATerrorism Essay. Long A
Terrorism Essay. Long A
 
Website That Writes Essays For You Love You - There Is A Website That
Website That Writes Essays For You Love You - There Is A Website ThatWebsite That Writes Essays For You Love You - There Is A Website That
Website That Writes Essays For You Love You - There Is A Website That
 
Pin On For The Boys
Pin On For The BoysPin On For The Boys
Pin On For The Boys
 
Critical Analysis Of An Article - Critical Analysis Essay -
Critical Analysis Of An Article - Critical Analysis Essay -Critical Analysis Of An Article - Critical Analysis Essay -
Critical Analysis Of An Article - Critical Analysis Essay -
 
How To Write An Effective Narrative Essay
How To Write An Effective Narrative EssayHow To Write An Effective Narrative Essay
How To Write An Effective Narrative Essay
 
Use Custom Essay Writing Services And Know The Di
Use Custom Essay Writing Services And Know The DiUse Custom Essay Writing Services And Know The Di
Use Custom Essay Writing Services And Know The Di
 
IB Extended Essay Topics For The Highest Grades
IB Extended Essay Topics For The Highest GradesIB Extended Essay Topics For The Highest Grades
IB Extended Essay Topics For The Highest Grades
 
Home - Research - LibGuides At Uni
Home - Research - LibGuides At UniHome - Research - LibGuides At Uni
Home - Research - LibGuides At Uni
 
10 Tips For Writing Effective Essay LiveWebTutors
10 Tips For Writing Effective Essay LiveWebTutors10 Tips For Writing Effective Essay LiveWebTutors
10 Tips For Writing Effective Essay LiveWebTutors
 
Printable Sentence Strips - Printable Word Searches
Printable Sentence Strips - Printable Word SearchesPrintable Sentence Strips - Printable Word Searches
Printable Sentence Strips - Printable Word Searches
 
Website That Does Essays For You
Website That Does Essays For YouWebsite That Does Essays For You
Website That Does Essays For You
 

Recently uploaded

special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
kimdan468
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
gb193092
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 

Recently uploaded (20)

special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBCSTRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
STRAND 3 HYGIENIC PRACTICES.pptx GRADE 7 CBC
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 

Assessing Loss And Expenses Claim By Prolongation Cost

  • 1. ASSESSING LOSS AND EXPENSES CLAIM BY PROLONGATION COST RAIHA AZENE BINTI RAMLI UNIVERSITI TEKNOLOGI MALAYSIA
  • 2. ASSESSING LOSS AND EXPENSES CLAIM BY PROLONGATION COST RAIHA AZENE RAMLI A project report submitted in partial fulfilment of the requirement for the award of the degree of Master of Science (Construction Contract Management) Faculty of Built Environment Universiti Teknologi Malaysia JANUARY 2015
  • 3. iii To my beloved husband, parents, sisters and brothers Thank you for your support and confidence in me.
  • 4. iv ACKNOWLEDGEMENTS First of all, I would like to say thank to all the lecturers for the program of Master of Science (Construction Contract Management), especially my supervisor – Assoc. Sr. Prof Dr. Maizon Hashim, for their guidance during the writing of this master project. Without their supervision and advice, this project could not be completed on time. Secondly, I would like to express my gratitude to my dearest husband, parents, brothers and sisters for their support and advice during these few months. Not forgetting my classmates, a token of appreciation goes to them for giving lots of advice on how to complete and write this project.
  • 5. v ABSTRACT Contractor’s claims for loss and expenses have long been a contentious issue on many building contract. Claims are usually resolved during the final account process, but where negotiations fail, they frequently become disputes, with the parties adopting legal route to resolve their differences. Claims to recover prolongation cost arise in a number of contexts and it is importance for the claimant to understand the principles upon which such claims might be evaluated. In valuing the loss and expenses claim by prolongation cost, it is fundamental to prove delay and actual related cost losses arise in an action of damages and failure to prove will not entitle to a claim for damages. The objective of this study is to determine loss and expense claims that is related to prolongation cost by head of loss claims. The head of loss claims include site overheads, head office overhead, loss of profits, interest and financing charges, loss of productivity and cost of preparing the claim. The loss should be measured at the point in time in which the delay event arose, rather than costs incurred at the end of contract. In valuing prolongation costs, the decision in Costain v Haswell therefore provides a useful reminder of the importance of distinguishing costs generated by time and by volume. This study was carried out mainly through documentary analysis of law journals. The study also helps in adding to the knowledge base of the literature on prolongation costs and construction contracts.
  • 6. vi ABSTRAK Tuntutan kontraktor untuk kerugian dan perbelanjaan telah lama menjadi isu pertikaian di dalam kontrak secara amnya. Tuntutan biasanya diselesaikan semasa proses akaun muktamad, tetapi jika rundingan gagal, mereka sering menjadi pertikaian, maka penyelesaian secara undang-undang digunapakai bagi percanggahan yang berlaku. Tuntutan untuk mendapatkan kembali kos pemanjangan timbul dalam beberapa konteks dan ia adalah penting bagi pihak yang menuntut untuk memahami prinsip-prinsip di mana tuntutan itu mungkin dinilai. Dalam menilai kerugian dan perbelanjaan tuntutan dengan kos pemanjangan, ia adalah asas untuk membuktikan kelewatan dan kos kerugian sebenar yang berkaitan timbul dalam sesuatu tindakan kerosakan dan kegagalan untuk membuktikan tidak memberi hak kepada tuntutan ganti rugi. Objektif kajian ini adalah untuk menentukan kerugian dan perbelanjaan tuntutan berkaitan dengan kos pemanjangan berdasarkan kepada ‘head of claims’. Tuntutan kepada head of loss claims termasuklah site overheads, head office overhead, loss of profits, interest and financing charges, loss of productivity dan cost of preparing the claim. Kerugian dan perbelanjaan haruslah diukur berdasarkan kepada masa di mana kelewatan itu timbul daripada kos yang ditanggung oleh pihak Kontraktor pada akhir kontrak. Dalam menilai kos pemanjangan, keputusan di dalam kes Costain v Haswell itu memberi satu peringatan penting dimana perlu membezakan kos samaada melalui time dan melalui volume. Kajian ini telah dijalankan terutamanya melalui analisis dokumentari jurnal undang-undang. Kajian ini juga membantu dalam menambah ilmu pengetahuan terhadap kos pemanjangan dan kontrak pembinaan.
  • 7. vii TABLE OF CONTENTS CHAPTER TITLE PAGE DECLARATION ii DEDICATION iii ACKNOWLEDGEMENTS iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLE xi LIST OF FIGURE xii LIST OF CASES xiii 1 INTRODUCTION 1.1 Background of Study 1 1.2 Problem Statement 3 1.3 Objective of Research 5 1.4 Scope of the Study 5 1.5 Significance of the Study 5 1.6 Organization of Chapters 6 1.6.1 Chapter 1: Introduction 6 1.6.2 Chapter 2: Loss and Expenses 6 1.6.3 Chapter 3: Prolongation Cost 7 1.6.4 Chapter 4: Research Methodology 7 1.6.5 Chapter 5: Assessment Loss and Expenses Claim by Prolongation Cost 8 1.6.6 Chapter 6: Conclusion and Recommendation 8
  • 8. viii CHAPTER TITLE PAGE 2 LOSS AND EXPENSES 2.1 Introduction 9 2.2 The Concept of Loss and Expenses Cost 12 2.3 Ground for Contractual Claims 13 2.3.1 Loss and Expenses under Standard Form Provision 13 2.3.2 Notice requirements 17 2.3.3 Nature and form of notice/application 18 2.3.4 Conditions precedent and the failure to give notice/application where the terms of contract require it. 20 2.4 Quantification of Claims 23 2.5 Assessment of Loss and Expenses Claims 24 2.5.1 Additional Preliminaries 25 2.5.2 Labour Disruption 27 2.5.3 Material 29 2.5.4 Inflation 31 2.5.5 Head Office Overheads and Profit 31 2.5.6 Interest and Financing Charges 34 2.6 Conclusion 35 3 PROLONGATION COST 3.1 Introduction 37 3.2 Evaluating Prolongation Costs 41 3.2.1 The difference between claims for an extension of time and prolongation cost 41
  • 9. ix CHAPTER TITLE PAGE 3.3.2 The difference between prolongation costs arising from critical and non- critical delays 43 3.3 Principle to Claim to Recover Prolongation Cost 46 3.4 Quantification of Prolongation Costs 48 3.4.1 On-Site Overhead 50 3.4.1.1 Actual cost 52 3.4.1.2 Estimated Cost 53 3.4.2 Off-Site Overheads 53 3.4.3 Subcontractors’ prolongation cost 55 3.4.4 Financing Costs 56 3.4.5 Cost related to claim preparation 56 3.4.6 Loss of profit opportunity 58 3.5 Conclusion 59 4 RESEARCH METHODOLOGY 4.1 Introduction 61 4.2 Methodology of Study 61 4.3 Limitations of the study 65 4.4 Conclusion 66 5 ASSESSMENT OF LOSS AND EXPENSES BY PROLONGATION CLAIM 5.1 Introduction 67 5.2 Head of Loss Claim in Prolongation Cost 69 5.2.1 On-Site Overhead 70
  • 10. x CHAPTER TITLE PAGE 5.2.2 Off-site Overhead 75 5.2.3 Loss of profits 78 5.2.4 Interest and financing charges 81 5.2.5 Cost of preparing the claim 85 5.3 Conclusion 89 6 CONCLUSIONS AND RECOMMENDATIONS 6.1 Introduction 90 6.2 Summary of Research Findings 90 6.3 Problem Encountered During Research 95 6.4 Further studies 95 6.5 Conclusion 96 6.6 Recommendation 99 REFERENCES
  • 11. xi LIST OF TABLE TABLE NO. TITLE PAGE 2.1 Example of a Calculation of a Disruption Claim 29
  • 12. xii LIST OF FIGURE FIGURE NO. TITLE PAGE 4.1 Research Process ad Method of Approach 62
  • 13. xiii LIST OF CASES NAME OF CASES PAGE Ascon v McAlpine(1999) 66 Con LR 119, (2000) 16 Const LJ 316 (TCC) 74,75,92 Bremer Hadelsgesellschaft mbh v Vanden Avenne Izegem [1978] 2 LJoyds Rep 109 22 City Inn Limited v. Shepherd Construction Limited [2007] CSOH 190 44 Costain Limited v. Charles Haswell & Partners Limited [2009] EWHC 3140 (TCC) 42,70 Ellis-Don Ltd v Parking Authority of Toronto (1978) 28 BLR 98 33 F.G.Minter Limited v Welsh Health Technical Services Organization[1980] 13 BLR 1 14 Hadley vs. Baxendale (1854) 9 Ex 341 10,14,15, 35,69,82 John Doyle Construction Limited v Laing Management (Scotland) Limited [2004] BLR 295 45 J Crosby & Sons Ltd v Portland UDC (1967) 5 BLR 126 13 James Longley & Co Ltd v South West Regional Health Authority(1984) 25 BLR 56 57 JF Finnegan Ltd v Sheffield CC (1988) 43 BLR 124 33,76,93 London Borough of Merton v Stanley Hugh Leach [1985] 32 BLR 51 19,21
  • 14. xiv NAME OF CASES PAGE Merton LBC v Stanley Hugh Leach Ltd (1985) 32 BLR 51. 13 Peak Construction Ltd v McKinney Foundations Ltd. [1970] 1 BLR 111 32,79,93 President of India v La Pintada Cia Navegacion SA [1985] AC 104. 34 Rees & Kirby Ltd v Swansea CC(1985) 30 BLR 1 34.82,84.93 Robinson v. Harman 1 Exch. 850 15,89 South Australia Asset Management Corporation v. York Montague Ltd [1996] 3 All ER 365 16 Sunley Ltd v. Cunard White Star Ltd [1940] 1 KB 740 76,78 Wraight Ltd v P H & T (Holdings) Ltd (1968) 13 BLR 26 23,80 Wood v Grand Valley Railway Co., (1913) 30 O.L.R. 44 28
  • 15. 1 CHAPTER 1 INTRODUCTION 1.1 Background of Study A contractor is entitled to payment for works including variations and may also entitle to claim for additional time and money.1 There is no legal significance of the term prolongation claim. It is not a type of claim described by the law and is often called a delay claim. Many times it is also known as disruption claim. Only the contractors and subcontractors can make this claim, not the Employer2 . This claim intends to allow the contractor to gain compensation in terms of money, if at all there is a compensable delay that actually stops or hinders the contractor from completing the work on time. The claim is made underlying the delay factors in which the contract was prolonged or the completion of the project was delayed, that is, the work took longer time by the contractor in completion than it was anticipated by the contractor at the time when the contract was made. Most of the contracts are developed clearly underlining on the agreement that the contractor will finish the work within the given time-period. Furthermore, it 1 Murdoch, J.R. and Hughes, W. (2008) Construction Contracts: Law and Management, 4th ed. Taylor and Francis, Oxford 2 Davenport, P. (2006). Construction Claims. Federation Press. pp.126
  • 16. 2 implicitly emphasizes on the requirement that the client will ensure that he/she avoid in delaying the work of the contractor3 . However, delays do occur in a number of construction contracts, where there is an implicit and understood the requirement of compensating the party that has suffered the loss. Due to these delays, it becomes obvious that the contract will not be completed on time. As a result, the assessment of delays in contracts leads is necessary, which involves identification of the specific cause for each delay, followed by the assessment of the extent to which the delay has occurred and lastly, attributing the responsibility of the delay4 . It is clearly stated that to assess the extra payment due to the delay as a consequence of Employers prolongation, the assessment of the claim must be related to the time when the act of delay occurred and should not in exceed time of the contract. A simple example as follow: “If party A tends to suffer a loss due to a delay caused by party B, then party A is entitled to claim for the compensation of the damages in order to put party A back into the position in which he was before the act of delay”. Therefore, prolongation costs would be the costs that are actually incurred from the time when delay occurred and started affecting the progress of the contract, instead of the time extended for completing the contract. What should be considered is the impact of delay on the progress, and it leads to have a clear assessment of the impact of the delay for determining the additional overhead expenses and costs that has been incurred5 . This claim could be charged on when, and if, the project is prolonged or extended beyond the anticipated completion time because of the delay in the progress 3 Ibid, pp.126 4 Ndekugri, I., Braimah, N., and Gameson, R. (2008). Delay Analysis within Construction Contracting Organizations. J. Constr. Eng. Manage., 134(9), p.1279 5 Lo, T., Fung, I., and Tung, K. (2006). ”Construction Delays in Hong Kong Civil Engineering Projects.” J. Constr. Eng. Manage., 132(6), p.636
  • 17. 3 of the work and activities and as a result the Contractor is required to employ extra resources over and above the actual allowed price of the contract. Nevertheless, there are some resources that could be extended with the span of original contractual period due to some variations. These extended resources must be reimbursed to the Contractor for further progress. 1.2 Problem Statement In any construction projects, the contractor is legally obligated to complete the project within the date set for completion or by the date that is set in the contract. However, delays always tend to disrupt and disturb the performance of the work performed by the contractor. This delay might be cause of either by the employer or by the contractor himself or due to the events for which none of the party is responsible. As for delays or disruption caused to the Works, if these are caused through some act or omission of the Employer or his agent (perhaps the architect, engineer or the Superintending Officer) then contracts often allow the contractor to recover his costs arising from the delay or disruption, again in the form of loss and expenses.6 Any claim for loss and expenses must be calculated on the basis of the actual loss incurred. It is not unusual to see prolongation costs calculated on the basis of sums derived from contract preliminaries. This is clearly incorrect as the figures included in the contract are essentially estimates. Using the contract preliminaries is unlikely to represent the true loss suffered by a contractor in the event of delay.7 6 Michael Charlton et al., Seminar Paper: Additional Payment under Malaysian Forms of Contract, 2001. p.1/34 7 Ibid. p.2/34
  • 18. 4 Having established the legal right to pursue a claim for loss and/or expense and satisfied all the relevant procedural requirements, it is obligatory for the claimant to identify with suitable precision the respective heads of loss claim entitlements that need to be quantified and substantiated. The principal common areas of such claim usually encountered in practice as follows:8 a. Site Overheads; b. Head Office Overheads; c. Loss of Profits; d. Interest and Financing charges; e. Loss of Productivity; f. Inflationary Cost Increase of Materials and Labour; and g. Cost of Preparing the Claim. A typical claim for loss and/or expenses depends on the nature of the delay or disruptive element. It may encompass either one, or all, or a number of the above- listed heads of entitlements. Much also depends upon the relative strength of the particular case in terms of the quality of proof (example: records and documents) available in justification of the particular entitlement or entitlements. Though some of the said entitlements appear relatively straight forward, these are nevertheless fraught with legal uncertainties where the ultimate decision is swayed more by subjective factors than objective considerations. Hence, the subsequent write-up expands upon the scope of some of the rather contentious areas of the claim for entitlements so as to shed some light for better understanding. 8 Ir Harban Singh KS. (2007). Demystifying direct loss and/or expense claims. Malayan Law Journal Articles/2007/Volume 4/DEMYSTIFYING DIRECT LOSS AND/OR EXPENSE CLAIMS. 4 MLJ xxix. P.
  • 19. 5 1.3 Objective of Research Following is the objective of the study: 1. To determine potential heads of loss claim under loss and expense claims due to prolongation cost. 1.4 Scope of the Study This research will focused at relevant research papers, articles, books, journals and court cases on loss and expenses claim on prolongation cost in heads of loss claims in any jurisdiction. The court cases will not be restricted to Malaysian cases only; reference is also made to cases in other countries such as United Kingdom, United States, Canada and Hong Kong. The scope of the study is wide enough to incorporate different cases, demonstrating a broader view of the research topic. 1.5 Significance of the Study Claims to recover prolongation costs arise in a number of contexts and it is some importance for parties to understand the principle upon which head of loss claims might be evaluated. The study helps in adding to the knowledge base of the literature on loss and expenses claims and prolongation costs under construction contracts. This study is to reduce the uncertainty and difficulties in the event of
  • 20. 6 claiming loss and expense that are deny under the reason upon the relative strength of the particular case in terms of the quality of proof available in justification of the particular entitlement or entitlements. Though some of the said entitlements appear relatively straight forward, these are nevertheless fraught with legal uncertainties where the ultimate decision is swayed more by subjective factors than objective considerations. Hence, construction industry stake holders will be more aware and clear understanding while dealing with heads of loss claims in contracts. 1.6 Organization of Chapters 1.6.1 Chapter 1: Introduction The first chapter provides an overview of the research, including a brief background of the topic along with describing brief concept of prolongation costs, claims and delays, the problem that is focused in the research, the objectives that will be achieved through literature study analysis. In addition, the section includes scope of the study and the significance of the study. 1.6.2 Chapter 2: Loss and Expenses In the second chapter, literature review on loss and expenses claim have been studied to identify the contractor entitlement to recover loss and expenses claim affected by specific events as set out in the relevant clauses and standard form of contract. The assessment for contractor claims for loss and expenses perhaps most argumentative issue in the post-contract financial management of building contract.
  • 21. 7 However, the recovery of loss and expense is a procedure under specific term of the contract. The recovery of certain heads of claim may be permitted under express contract terms which might not be recoverable as a claim for damage at common law. A careful study of contract condition and appreciation of their legal application and knowledge of the relevant case law has also been collected and reviewed in this chapter. 1.6.3 Chapter 3: Prolongation Cost In the third chapter, literature review for the prolongation cost has been studied to substantiate the entitlement of the heads of loss claim. Contractually or legally the contractor must prove his claim in order to have sufficient merit to warrant certification of appropriate amount of entitle of the heads of loss claims. Commonly the entitlement of head of loss claim brought under the following heads: 1) On-site overheads 2) Head office overheads 3) Interest and Financing Costs 4) Loss of Profit 5) Cost related to claim preparation 1.6.4 Chapter 4: Research Methodology In the fourth chapter, the methodologies of this study has been separated into few steps, namely identifying the research issue, literature review, data collection, research analysis, and conclusion and recommendation. This approach is to ensure
  • 22. 8 that the collection of the information and the data analyzing can be precisely implemented. 1.6.5 Chapter 5: Assessment Loss and Expenses Claim by Prolongation Cost The fifth chapter provides analysis of different case studies by critically reviewing and clarifying all the facts of the case studies. Furthermore, this chapter will present, discuss and compare each issue identified from the case study in accordance to the objectives of the research. 1.6.6 Chapter 6: Conclusion Lastly, the sixth chapter will provide a discussion of the overall research findings relating them with the objectives of the study. Moreover, this chapter will also provide recommendations for the future study and limitations of the study.
  • 23. 98 REFERENCES Aibinu, A. A. (2007). “Construction project claims and conflict in Singapore”, Construction Management and Economics: Past, Present and Future Conference, Proc., CME25 Anniversary Conference, W. P. Hughes. Atkin Chambers (2010), Hudson’s Building and Engineering Contracts, 12th ed. Sweet&Maxwell, London. Assaf, S. A., Al-Khalil, M., and Al-Hazmi, M. (1995). Causes o f delay in large building construction projects. Journal o f Management in Engineering, ASCE Bartlett, A., Lloyd, H. and Palmer, N.E. (2002). Emden’s construction law, London: Lexis Nexis Butterworths Bennett, J. and Peace, S. (2006). Partnering in the construction industry. A code of practice for strategic collaborative working, Oxford: Butterworth-Heinemann Bramble, B. B., and Callahan, M. T. (1992). Construction delay claims, 2nd Ed., Wiley, New York.
  • 24. 99 Chappell, D., Powell-Smith, V. and Sims, J. (2008) Potential Heads of Claim, in Building Contract Claims, Fifth Edition, Blackwell Publishing Ltd, Oxford Construction Industry Development Board (‘CIDB’). (2000) Davenport, P. (2006). Construction Claims. Federation Press. Dr. Chandana Jayalath (2009). Claims on Prolongation Costs in Nutshell. Available at http://www.articlesbase.com/construction-articles/claims-on-prolongation-costs- in-nutshell-1413885.html. Accessed 10th February 2014. Eggleston, B. (2006) The NEC 3 engineering and construction contract. A commentary, 2nded. pp.56-178 Oxford: Blackwell Science. Dr Ronan Champion (2011). Prolongation Costs: Where Now After Constain v Haswell. A paper presented to meetings of the Society of Construction Law in Reading on 29th March and Manchester on 9th May 2011. Eggleston, B. (2008) Relevant Events, in Liquidated Damages and Extensions of Time: In Construction Contracts, Third Edition, Wiley-Blackwell, Oxford, UK. Entrusty Group. (2005). What is Loss and/or Expense?. Master Builders 1st Quarter 2005, 86-89. Fisher, J. M. (2006). Understanding Remedies (2nd ed.). Newark, NJ: LexisNexis, pp. 77-89.
  • 25. 100 Furst, S. and Ramsey, V. (2006), Keating on Construction Contracts, 8th ed., Sweet&Maxwell, London. Goldberg, J., Sebok, A., & Zipursky, B. (2008). Tort law: Responsibilities and redress. New York: Aspen, pp. 51-59 Gombos v. Ashe, 158 Cal. App. 2d 517 (1958). Gray, C. and Hughes, W.P. (2000). Building Design Management. London: Butterworth-Heinemann Gruneberg, S.L. and Hughes, W.P. (2005), Understanding construction consortia: theory, practice and opinions, RICS Research Papers. Hackett, K. (2007) Change and its Effects, in K. Pickavance (2007) Construction Law and Management (2007), Informa, London. Harbans Singh, K., S., (2002). Commencement and Administration, Engineering and Construction Contracts Management, Kuala Lumpur LexisNexis. Hughes, W., Hillebfrandt, P., and Murdoch, J., (2000), The impact of contract duration on the cost of cash retention, Construction and Management and Economics, Vol.18, No.1, pp.11-14 Institution of Civil Engineering (ICE) 6th Edition. Institution of Engineers Malaysia (‘IEM’) 1989.
  • 26. 101 Ir Harban Singh KS. (2007). Demystifying direct loss and/or expense claims. Malayan Law Journal Articles/2007/Volume 4/DEMYSTIFYING DIRECT LOSS AND/OR EXPENSE CLAIMS. 4 MLJ xxix JCT Standard Form of Building Contract (Private Edition with Quantities)(1980 edition) Keane, D. (2001). The RIAI Contracts: a Working Guide, 4th ed. Royal Institute of the Architects of Ireland, Dublin. Keith Pickavance. (2010). Delay and Disruption in Construction Contracts. 4th Revised edition edition. Sweet & Maxwel Knowles, J.R. (n. d.) Contractors and Subcontractor Claims the New Approach Seminar Proceeding 4th December 1991 Jurys Hotel, Dublin. Knowles, R. (2012). Loss and Expense/Additional Cost, in 200 Contractual Problems and their Solutions, Third Edition, Wiley-Blackwell, Oxford, UK. Lee, H. S., Ryu, H. G., Yu, J. H., and Kim, J. J. (2005). Method for calculating schedule delay considering lost productivity. Journal o f Construction Engineering and Management, ASCE, 131(11), 1147-1154 Lo, T., Fung, I., and Tung, K. (2006). ”Construction Delays in Hong Kong Civil Engineering Projects.” J. Constr. Eng. Manage., 132(6), 636–649. Long D, Nguyen. (2007). The Dynamics of Float, Logic, Resource Allocation, and Delay Timing in Forensic Schedule Analysis and Construction Delay Claims. ProQuest Pllc. 1-130
  • 27. 102 March, C. (2009) Finance and Control for Construction, Taylor and Francis, Oxford. Majid, M. Z. A. and McCaffer, R. (1998). Factors of non-excusable delays that influence contractors’ performance. Journal of Management in Engineering, ASCE, 14(3), 42-49. McGovern, C. (2011). GCCC Contracts Experience to Date: A Review of the Operation of theGCCC Contract on Civil Engineering Projects. Presentation to Engineers Ireland (Thomond West Region) 8th March 2011. Available at http://www.slideshare.net/cmcgoverntobin/gccc-contractsexperience-to-date-080311. Accessed 8th December 2014. Mohd Norazman Zaini. (2001). Seminar on Additional Payment under Malaysian Forms of Construction Contract. Loss and Expenses/Additional Cost. 18 June 2001. JW Marriott Hotel, Kuala Lumpur. Lecture 4 Murdoch, J.R. and Hughes, W. (2008) Construction Contracts: Law and Management, 4th ed. Taylor and Francis, Oxford. Murray, M. and Langford, D. (Eds.) (2003). Construction reports 1944–98, Oxford:Blackwell. Ndekugri, I., Braimah, N., and Gameson, R. (2008). Delay Analysis within Construction Contracting Organizations. J. Constr. Eng. Manage., 134(9), 692–700. New South Wales Government Procurement System for Construction. (2008). Handling Prolongation and Disruption Claims. Procurement Practice Guide.
  • 28. 103 Pertubuhan Akitek Malaysia (‘PAM’) 2006 (with quantities) Philip Georgiou. (2008). Extensions of Time, Concurrent Delay, and Causation: City Inn v Shepherd Judicial Guidance from the UK Courts at Long Last. Available at http://www.jonesday.com/extensions-of-time-concurrent-delays-and-causation-city- inn-v-shepherd-judicial-guidance-from-the-uk-courts-at-long-last-05-14-2008/. Accessed 8th December 2014. Public Works Department (‘PWD’) Form 203A (rev.2010) Ramus, J. Birchall, S. and Griffiths, P. (2006) Contract Practice for Surveyors 4th ed. Butterworth Heinemann, London. Roger Gibson. (2008). Construction Delays Extensions of Time and Prolongation Claims. Taylor & Francis. Society of Construction Law (SCL). (2002), “Delay and disruption protocol.” SCL, London. Tony Cunningham. (2014). Contractors’ Claims for Loss and Expenses under the Principle “Traditional’ Forms of Irish Building Contract. School of Surveying and Construction Management Dublin Institute of Technology. The Surveyor Construction Handbook (2003). Ascertaining the Amount of Loss and Expense Incurred in Building Projects, RICS Business Services Limited.
  • 29. 104 The Byron Partnership. (2002). Construction Claims Management. Prolongation Claims. Available at www.byron10.com_uploads_Prolongation_Costs_20101116 Accessed 4th January 2014. Trickey, G. and Hackett, K. (2001). The Presentation and Settlement of Contractors Claims, 2nd ed. Spon, London. Vidogah, W., and Ndekugri, I., 1998, “Improving the management of claims on construction contracts: Consultant’s perspective.”Constr. Manage. Econom, 16, 363– 372 Wigal, G. S. (1990). Interference with a contractor's early completion o f a construction project. The Construction Lawyer, 10(4), 17-25.