The document provides updates on construction activities at the Eglinton Crosstown LRT's Eglinton Station and Mount Pleasant Station in March 2019. At Eglinton Station, stage 6b excavation is underway and expected to last 4-6 weeks, with stage 7 excavation beginning in spring 2019. Overnight and weekend subway closures are planned in 2019 for TTC upgrades. Deep excavation and underpinning of the subway line will also take place throughout 2019. At Mount Pleasant Station, shallow excavation and station roof construction are underway, expected to last 1-2 months. A traffic configuration change is scheduled for March 21, 2019.