Metrolinx is a transportation agency that serves the Greater Toronto and Hamilton Area. It operates GO Transit, UP Express, and manages the PRESTO fare payment system. Metrolinx aims to connect communities through regional transit and published a Regional Transportation Plan in 2008 to quadruple rapid transit access. Upcoming works on Eglinton Crosstown LRT stations in 2019-2020 include excavation, concrete pours, traffic configuration changes, and underpinning the existing subway line at Eglinton station to allow construction of the underground interchange station.
Central West Spring Open House Presentation Deck - March 3, 2020 Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Spring Open House held at Beth Tzedec Synagogue (1700 Bathurst St, Toronto) on March 3, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Central West Spring Open House Presentation Deck - March 3, 2020 Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Spring Open House held at Beth Tzedec Synagogue (1700 Bathurst St, Toronto) on March 3, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Central Eastern Works Open House - October 2019Crosstown TO
Contains current and upcoming stages of construction for the stations/stops of: Eglinton, Mount Pleasant, Leaside, Laird, Brentcliffe (Portal), Sunnybrook Park and Science Centre.
Leaside Laird CLC November 2019 PresentationCrosstown TO
This is a bi-monthly meeting hosted by Metrolinx and Crosslinx to provide construction and community relations updates to the members of Leaside and Laird Construction Liaison Committee (CLC).
Central Eastern Works Open House - October 2019Crosstown TO
Contains current and upcoming stages of construction for the stations/stops of: Eglinton, Mount Pleasant, Leaside, Laird, Brentcliffe (Portal), Sunnybrook Park and Science Centre.
Leaside Laird CLC November 2019 PresentationCrosstown TO
This is a bi-monthly meeting hosted by Metrolinx and Crosslinx to provide construction and community relations updates to the members of Leaside and Laird Construction Liaison Committee (CLC).
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Fall Virtual Open House, held on the Metrolinx Engage website, on October 14, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Central West Open House
1. Mission
We connect our communities
Vision
Getting you there better, faster and easier
Values
Play as a team
Think forward
Serve with passion
1 Metrolinx overview
2. go transit, up express, presto
2Metrolinx Overview
• Serve a population of more than seven million across more than 11,000 square
km stretching from Hamilton and Kitchener-Waterloo in the west to Newcastle
and Peterborough in the east, and from Orangeville and Beaverton in the north
to Niagara Falls in the south.
• In operation since 1967, GO now carries more than 70 million passengers a year.
• The PRESTO card is the smart card fare payment system seamlessly connecting 11
transit agencies across the GTHA and Ottawa.
• PRESTO replaces the need for tickets, tokens, passes or cash.
• UP Express connects the country's two busiest transportation hubs: Toronto
Pearson International Airport and Union Station in downtown Toronto, offering a
25-minute journey from end to end, with trains departing every 15 minutes.
4. Regional Transportation Plan
4
Vision: The GTHA will have a sustainable
transportation system that is aligned with land use,
and supports healthy and complete communities.
The system will provide safe, convenient and reliable
connections, and support a high quality of life, a
prosperous and competitive economy, and a
protected environment.
31 Priority Actions to Support the 5 Strategies
• Metrolinx published the first regional transportation
plan (RTP) for the Greater Toronto and Hamilton Area
(GTHA) in 2008.
• We are required to review the RTP at least every ten
years, in alignment with Ontario’s Growth Plan for the
Greater Golden Horseshoe.
• The legislative review of initial RTP led to the
development of the 2041 RTP. Key outcomes include:
o Quadrupling the number of people and doubling
the number of jobs within walking distance of
Frequent Rapid Transit
o 27x more kilometres of the Frequent Rapid
Transit
o In addition to the capital costs, successful
implementation will also require operating
funding for transit services, fare integration and
programs for walking and cycling
Metrolinx Overview
6. Fairbank Station Update
6
Year What to Expect
2019
• Construction of the station roof, including large concrete pours
• Deep excavation of the Main Entrance
• Traffic on Eglinton Ave will be shifted to the south, construction will
move to the north
• Shallow excavation on the north side of Eglinton Ave
2020
• Construction of the station roof, including large concrete pours
• Completion of major construction in the roadway
• Dufferin St and Eglinton Ave will return to two lanes in each
direction with some road occupancy for truck access
• Construction will continue underground and at the station
entrances
9. Oakwood Station – Renderings
SECONDARY ENTRANCE
MAIN ENTRANCEAERIAL VIEW
ENTRANCE INTERIOR
10. Oakwood Station Update
10
Year What to Expect
2019-2020
• 24 hour mining excavation work will continue to late 2019.
• Monitoring and dewatering well maintenance is ongoing.
• Permanent works are underway at the secondary entrance shaft and
will be complete in late 2019. Permanent works at the main entrance
shaft will commence in late 2019 and be underway until mid-2020.
• In mid-2019 final lining works will begin on sections of the caverns
where mining excavation is complete. This work will be ongoing to
early 2020.
• Waterproofing and concrete works for station foundation, walls,
ceiling and platforms will occur inside of the complete caverns.
• During concrete pour operations, there will be continuous
delivery of concrete to the surface site.
• Architectural works and track & systems installation will begin in 2020
11. Oakwood Station Staging & Mining Works
Cross Cut
Access
Adit
Main
Entrance
Cavern
Secondary
Entrance
Approx. 150m to be mined underneath Eglinton Ave – to connect the Main and Secondary Entrances
12. Oakwood Station Progress Photos
WATERPROOFING & FORM
WORK SECONDARY ENTRANCE
MAIN ENTRANCE
CAVERN
DRILLING PIPE UMBRELLAS
TUNNEL WORKS
14. Cedarvale Station – Ongoing and Upcoming Works
• In 2019, shoring activities (piling, tie-backs, and decking) will be completed. Deep excavation will
continue in preparation for underpinning of the TTC Line 1 Subway box.
• The current traffic configuration (below) will remain through to Summer 2019.
15. Cedarvale Station – Underpinning the TTC Line 1 Subway
• The next major feat at Cedarvale Station will be underpinning the TTC’s Line 1 Subway
box, allowing for excavation down to the bottom of the LRT station box (depicted
below).
• With the exception of some weekend closures, the subway will remain in operation
during underpinning, excavation, and station construction.
Rendering of
subway box
underpinning
16. Cedarvale Station – Construction Progress Photos
Deep excavation
underway
Decking
installation
17. Forest Hill Station Renderings
MAIN ENTRANCE SECONDARY ENTRANCE
PLATFORMLOBBY
18. Forest Hill Station Update
18
Year What to Expect
2019
• Pile installation, excavation and station roof construction on the
north side of Eglinton Ave
• Overnight utilities work
• Intersection closures for traffic bridge installation/removal and
large concrete pours
• Several traffic configuration changes
2020
• Completion of major construction in the roadway
• Bathurst St and Eglinton Ave will return to two lanes in each
direction with some road occupancy for truck access
• Construction will continue underground and at the station
entrances
22. Chaplin Station Update
22
Year What to Expect
2019
• Excavation and station roof construction, including concrete pours,
on the north side of Eglinton Ave
• Pile installation at the Tertiary Entrance
2020
• Completion of major construction in the roadway
• Gilgorm Rd will re-open at Eglinton Ave
• Chaplin Cres and Eglinton Ave will return to two lanes in each
direction with some road occupancy for truck access
• Construction will continue underground and at the station
entrances
25. Avenue Station – Renderings
Station Features
Accessible main entrance
Covered & uncovered bicycle parking
Retail space in main entrance??
SECONDARY ENTRANCE
MAIN ENTRANCE
MAIN ENTRANCE INTERIOR
AERIAL VIEW
26. Avenue Station Mining Works
Access Adit
Main Entrance
Secondary
Entrance
Cross Cut
Cavern
Avenue Rd Highbourne Rd Oriole Pkwy S. Eastbourne Ave Lascelles Blvd
27. Avenue Station Update
27
Year What to Expect
2019-2020
• 24 hour mining excavation work will continue to early 2020
• Monitoring and dewatering well maintenance is ongoing
• In mid-2019 final lining works will begin on sections of the caverns
where mining excavation is complete. This work will be ongoing to
mid-2020.
• Waterproofing and concrete works for station foundation, walls,
ceiling and platforms will occur inside of the complete caverns.
• During concrete pour operations, there will be continuous
delivery of concrete to the surface site.
• Additional connection holes to the tunnels will be required in
mid-2019 at the main entrance to facilitate final lining activities
and deliver concrete to the cavern level
• In late 2019, final lining works will begin in the main and secondary
entrance shafts.
• Architectural works and track & systems installation will begin in 2020
29. Eglinton Station – Renderings
Main Entrance
Future Main
Entrance Site
Future Main
Entrance Interior
Main Entrance Features
Accessible entrance
Connections to LRT and TTC Line 1
Subway
Interchange Station Features
Underground connections to all four
corners of the intersection including the
Yonge-Eglinton Centre and Canada Square
30. Eglinton Station – Ongoing and Upcoming Works
• Shoring activities (piling, tie-backs, and decking installation) will be ongoing on Eglinton Avenue at
Holly Street until Spring 2019.
• Deep excavation is underway in preparation for the underpinning of the TTC Line 1 Subway box.
– This work includes excavating to the bottom of the future station box (approximately 22 meters at the deepest
point).
– Spoils from the excavation will be extracted and hauled from the existing TTC bus depot site at the southeast
corner of Duplex Avenue and Eglinton Avenue West, and the Salvation Army site at the corner of Eglinton
Avenue East and Cowbell Lane.
– Excavation work has been starting as early as 4:00 a.m. to maintain schedule. Noise mitigation efforts will be
in place while this work gets underway.
The upcoming traffic
configuration (right) will be
in place as early as Spring
2019 and will remain for
the year.
31. Eglinton Station – Ongoing and Upcoming Works
• Construction of the TTC service building at Berwick Avenue continues with pre-cast concrete
installations:
• The subway will close on the weekends crews are working (1:30am Saturday to 6am Monday) to
safely carry out the work. For full information and confirmed dates on TTC closures, visit:
https://www.ttc.ca/Service_Advisories/Subway_closures/index.jsp
– Work will occur 24 hours a day on Berwick from 7am Friday to 7am Monday.
– Additional weekend subway closures are anticipated throughout 2019.
TTC Service
Building
Rendering
32. Eglinton Station – Underpinning the TTC Line 1 Subway
• The next major feat at Eglinton Station will be underpinning the TTC’s Line 1 Subway
box, allowing for excavation down to the bottom of the LRT station box (depicted
below).
• With the exception of some weekend closures, the subway will remain in operation
during underpinning, excavation, and station construction.
Rendering of
subway box
underpinning
33. Eglinton Station – Construction Progress Photos
Deep excavation
underway at the
Salvation Army site
Deep excavation
underway west of
Yonge St