SlideShare a Scribd company logo
CROSSTOWN LRT
Construction Liaison
Committee
April 4, 2018
Chaplin Construction Updates
3
Chaplin Station: What to Expect March 2018
ACTIVITY AREA IMPACT DURATION START DATE
Support of
Excavation - Piling
Within northeast work
zone on Eglinton Ave
W west of 564
Eglinton Ave W
Driveway
• Noise and vibration from drilling activity Ongoing February 2018
Shallow Excavation,
Struts and Walers
Installation
Within northeast
work zone on
Eglinton Ave W
• Noise from excavation equipment
• Generator running during day shift
• Noise from grinding operations
6-8 months March 16, 2018
Support of
Excavation - Piling
Main Entrance • Noise and vibration from drilling activity Complete March 16, 2018
Valve Chamber
Construction and
Watermain Bypass
Southwest work zone
on Eglinton Ave W
• Noise from construction activity
• Noise from a pump and surface equipment
7 weeks
remaining
January 22,
2018
Sanitary Diversion
Northeast work zone
on Eglinton Ave W in
front of 564 EAW
• Noise from a pump and surface equipment 3 days remaining March 28, 2018
4
Current Construction Staging
February 26, 2018 until early April 2018
5
Upcoming Construction Staging
Until early April 2018 until mid-May 2018
6
Future Construction Staging
Mid-May through December 2018
7
Progress Photos
SUPPORT OF
EXCAVATION
8
Progress Photos
MAIN ENTRANCE
WORK ZONE
9
Chaplin Station Main Entrance Rendering
10
Chaplin Station Secondary Entrance Rendering
11
Chaplin Station Tertiary Entrance Rendering
12
Chaplin Station Exterior Plaza Rendering
13
Chaplin Station Aerial Rendering
14
Chaplin Station Interior Renderings
15
Chaplin Station Plan View
16
Avenue Construction Updates
17
Short Term Activities Area & Impacts Duration
Tentative
Date
Dewatering work
(daytime) Installation
and trenching
• Eglinton north and south from Oriole
Pkwy to Lascelles
• Sidewalk, road and parking impacts
depending on location of trench and
equipment
• Pedestrians will be routed around
location of work
Approx. 3 weeks
remaining
Underway
Sewer Lining – final
piece
• Burnaby Road and Eglinton One overnight
period, 6-8 hours
April
Watermain Valve
Installations
• Watermain valve installations
required in two locations
• NW corner, inside site
• SW corner, sidewalk area –
pedestrians rerouted around
workzone
• Both installations will include a
water shut off from Avenue Road
to Elmsthorpe Ave.
Approx. 3 days
of work per
valve
One overnight
water shut off
per valve
(*pending
permit)
May
Avenue Station: What to Expect 2018
18
Watermain Lining & Temporary Water Service
Short Term
Activities
Area & Impacts Duration Tentative Date
Watermain
lining
• Properties from 282 Eglinton Ave to the
east will be serviced through the laneway
• Properties from 284 Eglinton Ave to the
west will be serviced from the front
• Temporary water supply pipes will be
installed in the City right of way
• An area in front of each property will be
excavated to access the water connection
and it will be plated for the duration of
the lining (one to two months)
• After the lining is completed, the area will
be restored and that will take
approximately one week
• Access to laneway maintained during
works, there may be 2-5 min delay while
equipment is moved
2 weeks to install
temporary
service
4 – 6 weeks for
lining
Approximately
one week of
overnight work
remaining for
temporary
service
installation
Lining operations
upcoming.
19
Temporary Water Service Installation (for watermain lining)
• Work is planned from 7pm to 7am
• Excavation in front of each property (shown in blue)
• Parking will be unavailable during work hours (red hash marks)
• Pedestrians will have a 1.5m walkway around the work zone (shown in green)
• Minor trenching in laneway between 280 Eglinton Avenue and Oriole Parkway
and on Oriole Parkway from closure to laneway (shown in red)
20
Main Entrance Installation
Short Term
Activities
Area & Impacts Duration Tentative Date
Crane Delivery and
Installation
- A Gantry Crane
will be erected
above the Main
Entrance excavation
shaft
• The crane will be delivered to the
Main Entrance site.
• Due to the size of the beams for the
crane supports, the deliveries may
temporarily delay traffic movements
while the truck enters the site to
deliver the materials.
Periodic during 1
week
PENDING
21
Short Term
Activities
Area & Impacts Duration Tentative Date
Monitoring Work
• Equipment is
installed in
various
locations
around the
station area to
monitor ground
movement
during
construction.
• To install the monitoring equipment in
the ground, crews move from location
to location around the station area.
Typically a drilling machine is used to
drill the hole where the monitor will be
installed.
• If on the sidewalk, pedestrians may
need to be routed around the work
zone (sidewalks stay open). If on the
roadway, a short term lane closure may
be required.
Installations
planned to be
complete in the
next few months.
Readings will be
taken regularly
for the duration
of the project.
Ongoing
Currently
focused around
the Main
Entrance site.
Avenue Station: What to Expect 2018
22
CLC SITE VISIT
23
CLC SITE VISIT
24
Avenue Station – Secondary Entrance
25
Avenue Station – Main Entrance
26
SAMPLE MURALS - OAKWOOD
27
SAMPLE MURALS - LAIRD
28
Avenue Aerial View
90% Design
29
Avenue Main Entrance
90% Design
30
Avenue Secondary Entrance
90% Design
31
Avenue Aerial View
90% Design

More Related Content

What's hot

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
Crosstown TO
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleSpring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Crosstown TO
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Crosstown TO
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Crosstown TO
 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021
Crosstown TO
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Crosstown TO
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
Crosstown TO
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
Crosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
Crosstown TO
 

What's hot (20)

Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleSpring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to Cedarvale
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 

Similar to Chaplin & Avenue CLC - Construction Update - April 4, 2018

Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Brittany Maxwell
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Crosstown TO
 

Similar to Chaplin & Avenue CLC - Construction Update - April 4, 2018 (20)

Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
Eglinton - Mount Pleasant Construction Liaison Committee Meeting - June 2017
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
Andrew Griffith
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
ehbuaw
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
uptheratios
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
ahcitycouncil
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
Revenue Department Kerala State
 

Recently uploaded (20)

The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
一比一原版(UQ毕业证)昆士兰大学毕业证成绩单
 
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our OrganizationUp the Ratios Bylaws - a Comprehensive Process of Our Organization
Up the Ratios Bylaws - a Comprehensive Process of Our Organization
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
PPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services AgmtPPT Item # 7 - BB Inspection Services Agmt
PPT Item # 7 - BB Inspection Services Agmt
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
Counting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptxCounting Class for Micro Observers 2024.pptx
Counting Class for Micro Observers 2024.pptx
 

Chaplin & Avenue CLC - Construction Update - April 4, 2018

  • 3. 3 Chaplin Station: What to Expect March 2018 ACTIVITY AREA IMPACT DURATION START DATE Support of Excavation - Piling Within northeast work zone on Eglinton Ave W west of 564 Eglinton Ave W Driveway • Noise and vibration from drilling activity Ongoing February 2018 Shallow Excavation, Struts and Walers Installation Within northeast work zone on Eglinton Ave W • Noise from excavation equipment • Generator running during day shift • Noise from grinding operations 6-8 months March 16, 2018 Support of Excavation - Piling Main Entrance • Noise and vibration from drilling activity Complete March 16, 2018 Valve Chamber Construction and Watermain Bypass Southwest work zone on Eglinton Ave W • Noise from construction activity • Noise from a pump and surface equipment 7 weeks remaining January 22, 2018 Sanitary Diversion Northeast work zone on Eglinton Ave W in front of 564 EAW • Noise from a pump and surface equipment 3 days remaining March 28, 2018
  • 4. 4 Current Construction Staging February 26, 2018 until early April 2018
  • 5. 5 Upcoming Construction Staging Until early April 2018 until mid-May 2018
  • 9. 9 Chaplin Station Main Entrance Rendering
  • 10. 10 Chaplin Station Secondary Entrance Rendering
  • 11. 11 Chaplin Station Tertiary Entrance Rendering
  • 12. 12 Chaplin Station Exterior Plaza Rendering
  • 17. 17 Short Term Activities Area & Impacts Duration Tentative Date Dewatering work (daytime) Installation and trenching • Eglinton north and south from Oriole Pkwy to Lascelles • Sidewalk, road and parking impacts depending on location of trench and equipment • Pedestrians will be routed around location of work Approx. 3 weeks remaining Underway Sewer Lining – final piece • Burnaby Road and Eglinton One overnight period, 6-8 hours April Watermain Valve Installations • Watermain valve installations required in two locations • NW corner, inside site • SW corner, sidewalk area – pedestrians rerouted around workzone • Both installations will include a water shut off from Avenue Road to Elmsthorpe Ave. Approx. 3 days of work per valve One overnight water shut off per valve (*pending permit) May Avenue Station: What to Expect 2018
  • 18. 18 Watermain Lining & Temporary Water Service Short Term Activities Area & Impacts Duration Tentative Date Watermain lining • Properties from 282 Eglinton Ave to the east will be serviced through the laneway • Properties from 284 Eglinton Ave to the west will be serviced from the front • Temporary water supply pipes will be installed in the City right of way • An area in front of each property will be excavated to access the water connection and it will be plated for the duration of the lining (one to two months) • After the lining is completed, the area will be restored and that will take approximately one week • Access to laneway maintained during works, there may be 2-5 min delay while equipment is moved 2 weeks to install temporary service 4 – 6 weeks for lining Approximately one week of overnight work remaining for temporary service installation Lining operations upcoming.
  • 19. 19 Temporary Water Service Installation (for watermain lining) • Work is planned from 7pm to 7am • Excavation in front of each property (shown in blue) • Parking will be unavailable during work hours (red hash marks) • Pedestrians will have a 1.5m walkway around the work zone (shown in green) • Minor trenching in laneway between 280 Eglinton Avenue and Oriole Parkway and on Oriole Parkway from closure to laneway (shown in red)
  • 20. 20 Main Entrance Installation Short Term Activities Area & Impacts Duration Tentative Date Crane Delivery and Installation - A Gantry Crane will be erected above the Main Entrance excavation shaft • The crane will be delivered to the Main Entrance site. • Due to the size of the beams for the crane supports, the deliveries may temporarily delay traffic movements while the truck enters the site to deliver the materials. Periodic during 1 week PENDING
  • 21. 21 Short Term Activities Area & Impacts Duration Tentative Date Monitoring Work • Equipment is installed in various locations around the station area to monitor ground movement during construction. • To install the monitoring equipment in the ground, crews move from location to location around the station area. Typically a drilling machine is used to drill the hole where the monitor will be installed. • If on the sidewalk, pedestrians may need to be routed around the work zone (sidewalks stay open). If on the roadway, a short term lane closure may be required. Installations planned to be complete in the next few months. Readings will be taken regularly for the duration of the project. Ongoing Currently focused around the Main Entrance site. Avenue Station: What to Expect 2018
  • 24. 24 Avenue Station – Secondary Entrance
  • 25. 25 Avenue Station – Main Entrance