Introduction to Environmental
Impact Assessment
Dr.P. Venkateswara Rao
Fundamental Approach to
Environmental Impact Assessment (EIA)
BASIC CONCEPTS OF EIA :
• EIA is an activity designed to identify and predict the
impact of a project on bio-geo-physico-chemical
environment and on human health so as to
recommend appropriate legislative measures,
programs, and operational procedures to minimize
the impact.
BASIC CONCEPTS OF EIA
• EIA is an exercise to be carried out before any
project or major activity is undertaken to
ensure that it will not in any away harm the
environment on a short-term or long-term
basis.
• Any developmental activity requires EIA to be
done before executed to know the effect of a
proposed development on the environment.
EIA: Purpose
• To provide information for decision-making on
the environmental consequences of proposed
actions;
and
• To promote environmentally sound and
sustainable development through the
identification of appropriate enhancement
and mitigation measures.
Sustainable development
‘development that meets the needs of today’s
generation without compromising those of
future generations’
Why EIA is important
• Reducing the burden of environmental impacts is
necessary if development is to become
sustainable.
• These impacts are more complex, larger in scale
and further reaching in their potential
consequences than thirty years ago when EIA was
first introduced.
• As a result, EIA has become of ever increasing
importance as a tool for development decision-
making.
Why EIA is important
• In practice, EIA is applied primarily to prevent
or minimise the adverse effects of major
development proposals, such as a power
station, dams and reservoirs, industrial
complexes, etc.
• This process is also used as a planning tool to
promote sustainable development by
integrating environmental considerations into
a wide range of proposed actions.
What are the aims and objectives of EIA?
The aims and objectives of EIA can be divided into two
categories.
• The immediate aim and ultimate (long term) aim
• The immediate aim of EIA is to inform the process of
decision-making by identifying the potentially significant
environmental effects and risks of development proposals.
• The ultimate (long term) aim of EIA is to promote
sustainable development by ensuring that development
proposals do not undermine critical resource and ecological
functions or the well being, lifestyle and livelihood of the
communities and peoples who depend on them.
Immediate objectives of EIA are
To
• improve the environmental design of the
proposal;
• ensure that resources are used appropriately and
efficiently;
• identify appropriate measures for mitigating the
potential impacts of the proposal; and
• facilitate informed decision making, including
setting the environmental terms and conditions
for implementing the proposal.
Long term objectives of EIA are
To:
• protect human health and safety;
• avoid irreversible changes and serious damage
to the environment;
• safeguard valued resources, natural areas and
ecosystem components;
and
• enhance the social aspects of the proposal.
Limitations of EIA
• EIA is also a way of ensuring that environmental factors are
considered in decision-making process along with the
traditional economic and technical factors.
• Importantly EIA requires the scientific (technical) and value
issues to be dealt with in a single assessment process.
• This helps in the proper consideration of all advantages and
disadvantages of a proposal.
• Environmental considerations may, therefore, be set aside in
favour of what are felt to be more important considerations.
• Alternatively, predicted adverse effects on the environment
might lead to strict conditions being imposed to avoid these
effects or remedy any adverse effects, or perhaps lead to the
complete abandonment of a proposal.
Limitations of EIA
• However, it is most important to recognise that EIA
cannot be regarded as a means of introducing an
environmental “veto” power into administrative
decision-making processes.
• Decisions that are unsatisfactory from an
environmental point of view can still be made, but
with full knowledge of the environmental
consequences.
• The final decision about a proposal depends upon
the likely severity of the adverse effects, balanced
against other expected benefits.
Limitations of EIA
• In other words, EIA is an administrative process that identifies
the potential environmental effects of undertaking a proposal,
and presents these environmental effects alongside the other
advantages and disadvantages of the proposal to the decision-
makers.
• In the vast majority of EIA procedures this means that the
outcome of the EIA process provides advice to the decision-
makers – it does not provide a final decision.
• So, by itself, the EIA procedures cannot be expected to stop a
proposal – although this is an outcome that some members of
the general community and environment groups may expect.
Principles of EIA administration and practice
• EIA is one of a number of policy tools that are used to evaluate
project proposals.
• It is also a relatively recent development when compared to use of
economic appraisal methods.
• A number of factors led to the introduction of EIA in different
countries, including public concern about the quality of the
environment and the increasing effects of new technologies and
ever-larger development schemes.
• In addition, then available economic appraisal techniques, such as
benefit cost analysis, did not take account of the environmental and
social impacts of major projects.
• Today, EIA is applied in more than 100 countries, and by all
development banks and most international aid agencies.
• EIA has also evolved significantly, driven by improvements in law,
procedure and methodology.
Principles of EIA administration and practice
• To date, EIA has been applied primarily at the
project-level.
• This ‘first generation’ process is now complemented
by SEA (Sustainable Environmental Assessment) of
policies, plans and programmes, and both EIA and
SEA are being adapted to bring a greater measure of
‘sustainability assurance’ to development decision
making.
• These trends have brought new perspectives on
what constitutes EIA good practice and effective
performance.
Principles of EIA administration and practice
Three core values on which the EIA process is based:
• Integrity– the EIA process should meet
internationally accepted requirements and standards
of practice;
• Utility– the EIA process should provide the
information which is sufficient and relevant for
decision-making; and
• Sustainability– the EIA process should result in the
implementation of environmental safeguards which
are sufficient to mitigate serious adverse effects and
avoid irreversible loss of resource and ecosystem
functions.
EIA process
• The particular components, stages and activities of an EIA
process will depend upon the requirements of the country or
donor.
• However, most EIA processes have a common structure
• The application of the main stages is a basic standard of good
practice.
• Typically, the EIA process begins with screening to ensure time
and resources are directed at the proposals that matter
environmentally.
• It should end with some form of follow up on the
implementation of the decisions and actions taken as a result
of an EIA report.
EIA process
EIA practice and outcomes
• screens out environmentally unsound projects;
• modifies the design of feasible proposals to reduce their
environmental impact;
• identifies the best practicable environmental option;
• predicts the significant adverse effects of proposals with
reasonable accuracy;
• identifies mitigation measures that work successfully to avoid,
reduce and offset major impacts;
• influences decision making and approvals and the
implementation of terms and conditions; and
• results in environmental gains and benefits relative to other
options.
Deficiencies of EIA practice
• Technical shortcomings, expressed by the poor quality of many EIA
reports. The accuracy of impact predictions, the utility of mitigation and
management measures, and the relevance of reports for decision-making
often fall short of internationally accepted standards.
• Procedural limitations, including inconsistencies in process administration
and guidance. Time delays and costs of applying EA remain a serious
concern for project proponents. Affected communities are more
concerned with the lack of quality control of EIA studies or enforcement of
mitigation measures.
• Structural issues, stemming from the application of EIA as a separate
process, unrelated to the project cycle or the larger context of decision
making.
• In order to be effective, EIA requires a coherent policy-planning
framework and systematic follow up procedures.
Costs and benefits of EIA
• Although there are costs associated with undertaking EIA,
experience has shown that the potential savings over the life
of a project can repay the investment many times over.
• The savings can be economic (e.g. identification of least cost
alternative) as well as environmental (e.g. impact reduction,
maintaining other resource use opportunities).
• Generally the earlier EIA process is introduced in the project
cycle, the greater the potential returns.
• When EIA is integrated into the project preparation phase,
environmental design considerations can be introduced in the
first place rather than the proposal having to be modified
later.
Costs and benefits of EIA
Benefits
• The benefits of EIA can be direct, such as the
improved design or location of a project, or indirect,
such as better quality EIA work or raised
environmental awareness of the personnel involved
in the project.
• In these cases, there will be with flow-on effects in
their future work. As mentioned above, these
potential gains from EIA increase the earlier the
process is applied in the design process.
Costs and benefits of EIA
In general the benefits of EIA include:
• Better environmental planning and design of a proposal. Carrying out an EIA entails
an analysis of alternatives in the design and location of projects. This can result in
the selection of an improved technology, which lowers waste outputs or an
environmentally optimum location for a project. A well-designed project can
minimise risks and impacts on the environment and people, and thereby avoid
associated costs of remedial treatment or compensation for damage.
• Ensuring compliance with environmental standards. Compliance with
environmental standards reduces damage to the environment and disruption to
communities. It also avoids the likelihood of penalties, fines and loss of trust and
credibility.
• Savings in capital and operating costs. EIA can avoid the undue costs of
unanticipated impacts. These can escalate if environmental problems have not
been considered from the start of proposal design and require rectification later.
An ‘anticipate and avoid’ approach is much cheaper than ‘react and cure’.
Generally, changes which must be made late in the project cycle are the most
expensive.
• Reduced time and costs of approvals of development applications. If all
environmental concerns have been taken into account properly before submission
for project approval, then it is unlikely that delays will occur as a result of decision-
makers asking for additional information or alterations to mitigation measures.
Increased project acceptance by the public.
Costs and benefits of EIA
Costs
• It can be difficult to determine the exact costs of an EIA
because major projects typically require a large number of
investigations and reports, often for closely related purposes
(e.g. engineering feasibility studies of hydrology and surface
materials).
• The World Bank notes that the cost of preparing an EIA rarely
exceeds one per cent of the project costs and this percentage
can be reduced further if local personnel are used to do most
of the work.
• For Bank projects, the relative cost of an EIA typically ranges
from only 0.06 per cent to 0.10 per cent of total project costs.
• The total cost of an EIA might range from a few thousand
dollars for a very small project, to over a million dollars for a
large and complex project, which has a significant
environmental impact and requires extensive data collection
and analysis.
Costs and benefits of EIA
Costs
Although many proponents complain that EIA
causes excessive delays in projects, many of
these are caused by poor administration of the
process rather than by the process itself.
These occur when:
– the EIA is commenced too late in the project cycle;
– the terms of reference are poorly drafted;.
– the EIA is not managed to a schedule;
– the technical and consultative components of EIA are inadequate; and
– the EIA report is incomplete or deficient as a basis for decision making.
Thank you

More Related Content

Similar to eia.ppt

NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)HNaliniNirala
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentBimal Antony
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentBahadur Prasad
 
Environmental_impact_assessment_EIA.pptx
Environmental_impact_assessment_EIA.pptxEnvironmental_impact_assessment_EIA.pptx
Environmental_impact_assessment_EIA.pptxMohamedSherbiny7
 
UNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptUNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptkrpnath1
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfssusereef268
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)SANDEEP PATRE
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Ugandakayondo alex
 
SEA.pptx
SEA.pptxSEA.pptx
SEA.pptxQuasid
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfChandanLawrence
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfTausifAhmad53
 
Environmental Management_LEC04.pptx
Environmental Management_LEC04.pptxEnvironmental Management_LEC04.pptx
Environmental Management_LEC04.pptxMonirulIslamEstiak
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentVinod Burdak
 
strategic environmental environment SEA-FINAL-presentation-2 .pptx
strategic environmental environment SEA-FINAL-presentation-2 .pptxstrategic environmental environment SEA-FINAL-presentation-2 .pptx
strategic environmental environment SEA-FINAL-presentation-2 .pptxCLASHSQUADProFamily
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptxKalaimani
 

Similar to eia.ppt (20)

Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
NALINI ( topic for M. Sc Ag. Agroforestry assigment EIA and ERA.pptx)
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Introduction to Strategic Environmental Assessment
Introduction to Strategic Environmental Assessment Introduction to Strategic Environmental Assessment
Introduction to Strategic Environmental Assessment
 
Environmental_impact_assessment_EIA.pptx
Environmental_impact_assessment_EIA.pptxEnvironmental_impact_assessment_EIA.pptx
Environmental_impact_assessment_EIA.pptx
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 
EIA Process
EIA ProcessEIA Process
EIA Process
 
UNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).pptUNIT – I ptpg final (2).ppt
UNIT – I ptpg final (2).ppt
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdf
 
Environmental impact assessment (eia)
Environmental impact assessment (eia)Environmental impact assessment (eia)
Environmental impact assessment (eia)
 
Environment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in UgandaEnvironment impact Assessment (EIA) in Uganda
Environment impact Assessment (EIA) in Uganda
 
SEA.pptx
SEA.pptxSEA.pptx
SEA.pptx
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
 
Environmental Management_LEC04.pptx
Environmental Management_LEC04.pptxEnvironmental Management_LEC04.pptx
Environmental Management_LEC04.pptx
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
strategic environmental environment SEA-FINAL-presentation-2 .pptx
strategic environmental environment SEA-FINAL-presentation-2 .pptxstrategic environmental environment SEA-FINAL-presentation-2 .pptx
strategic environmental environment SEA-FINAL-presentation-2 .pptx
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptx
 

Recently uploaded

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 

Recently uploaded (20)

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 

eia.ppt

  • 1. Introduction to Environmental Impact Assessment Dr.P. Venkateswara Rao
  • 2. Fundamental Approach to Environmental Impact Assessment (EIA) BASIC CONCEPTS OF EIA : • EIA is an activity designed to identify and predict the impact of a project on bio-geo-physico-chemical environment and on human health so as to recommend appropriate legislative measures, programs, and operational procedures to minimize the impact.
  • 3. BASIC CONCEPTS OF EIA • EIA is an exercise to be carried out before any project or major activity is undertaken to ensure that it will not in any away harm the environment on a short-term or long-term basis. • Any developmental activity requires EIA to be done before executed to know the effect of a proposed development on the environment.
  • 4. EIA: Purpose • To provide information for decision-making on the environmental consequences of proposed actions; and • To promote environmentally sound and sustainable development through the identification of appropriate enhancement and mitigation measures.
  • 5. Sustainable development ‘development that meets the needs of today’s generation without compromising those of future generations’
  • 6. Why EIA is important • Reducing the burden of environmental impacts is necessary if development is to become sustainable. • These impacts are more complex, larger in scale and further reaching in their potential consequences than thirty years ago when EIA was first introduced. • As a result, EIA has become of ever increasing importance as a tool for development decision- making.
  • 7. Why EIA is important • In practice, EIA is applied primarily to prevent or minimise the adverse effects of major development proposals, such as a power station, dams and reservoirs, industrial complexes, etc. • This process is also used as a planning tool to promote sustainable development by integrating environmental considerations into a wide range of proposed actions.
  • 8. What are the aims and objectives of EIA? The aims and objectives of EIA can be divided into two categories. • The immediate aim and ultimate (long term) aim • The immediate aim of EIA is to inform the process of decision-making by identifying the potentially significant environmental effects and risks of development proposals. • The ultimate (long term) aim of EIA is to promote sustainable development by ensuring that development proposals do not undermine critical resource and ecological functions or the well being, lifestyle and livelihood of the communities and peoples who depend on them.
  • 9. Immediate objectives of EIA are To • improve the environmental design of the proposal; • ensure that resources are used appropriately and efficiently; • identify appropriate measures for mitigating the potential impacts of the proposal; and • facilitate informed decision making, including setting the environmental terms and conditions for implementing the proposal.
  • 10. Long term objectives of EIA are To: • protect human health and safety; • avoid irreversible changes and serious damage to the environment; • safeguard valued resources, natural areas and ecosystem components; and • enhance the social aspects of the proposal.
  • 11. Limitations of EIA • EIA is also a way of ensuring that environmental factors are considered in decision-making process along with the traditional economic and technical factors. • Importantly EIA requires the scientific (technical) and value issues to be dealt with in a single assessment process. • This helps in the proper consideration of all advantages and disadvantages of a proposal. • Environmental considerations may, therefore, be set aside in favour of what are felt to be more important considerations. • Alternatively, predicted adverse effects on the environment might lead to strict conditions being imposed to avoid these effects or remedy any adverse effects, or perhaps lead to the complete abandonment of a proposal.
  • 12. Limitations of EIA • However, it is most important to recognise that EIA cannot be regarded as a means of introducing an environmental “veto” power into administrative decision-making processes. • Decisions that are unsatisfactory from an environmental point of view can still be made, but with full knowledge of the environmental consequences. • The final decision about a proposal depends upon the likely severity of the adverse effects, balanced against other expected benefits.
  • 13. Limitations of EIA • In other words, EIA is an administrative process that identifies the potential environmental effects of undertaking a proposal, and presents these environmental effects alongside the other advantages and disadvantages of the proposal to the decision- makers. • In the vast majority of EIA procedures this means that the outcome of the EIA process provides advice to the decision- makers – it does not provide a final decision. • So, by itself, the EIA procedures cannot be expected to stop a proposal – although this is an outcome that some members of the general community and environment groups may expect.
  • 14. Principles of EIA administration and practice • EIA is one of a number of policy tools that are used to evaluate project proposals. • It is also a relatively recent development when compared to use of economic appraisal methods. • A number of factors led to the introduction of EIA in different countries, including public concern about the quality of the environment and the increasing effects of new technologies and ever-larger development schemes. • In addition, then available economic appraisal techniques, such as benefit cost analysis, did not take account of the environmental and social impacts of major projects. • Today, EIA is applied in more than 100 countries, and by all development banks and most international aid agencies. • EIA has also evolved significantly, driven by improvements in law, procedure and methodology.
  • 15.
  • 16. Principles of EIA administration and practice • To date, EIA has been applied primarily at the project-level. • This ‘first generation’ process is now complemented by SEA (Sustainable Environmental Assessment) of policies, plans and programmes, and both EIA and SEA are being adapted to bring a greater measure of ‘sustainability assurance’ to development decision making. • These trends have brought new perspectives on what constitutes EIA good practice and effective performance.
  • 17. Principles of EIA administration and practice Three core values on which the EIA process is based: • Integrity– the EIA process should meet internationally accepted requirements and standards of practice; • Utility– the EIA process should provide the information which is sufficient and relevant for decision-making; and • Sustainability– the EIA process should result in the implementation of environmental safeguards which are sufficient to mitigate serious adverse effects and avoid irreversible loss of resource and ecosystem functions.
  • 18.
  • 19. EIA process • The particular components, stages and activities of an EIA process will depend upon the requirements of the country or donor. • However, most EIA processes have a common structure • The application of the main stages is a basic standard of good practice. • Typically, the EIA process begins with screening to ensure time and resources are directed at the proposals that matter environmentally. • It should end with some form of follow up on the implementation of the decisions and actions taken as a result of an EIA report.
  • 21. EIA practice and outcomes • screens out environmentally unsound projects; • modifies the design of feasible proposals to reduce their environmental impact; • identifies the best practicable environmental option; • predicts the significant adverse effects of proposals with reasonable accuracy; • identifies mitigation measures that work successfully to avoid, reduce and offset major impacts; • influences decision making and approvals and the implementation of terms and conditions; and • results in environmental gains and benefits relative to other options.
  • 22. Deficiencies of EIA practice • Technical shortcomings, expressed by the poor quality of many EIA reports. The accuracy of impact predictions, the utility of mitigation and management measures, and the relevance of reports for decision-making often fall short of internationally accepted standards. • Procedural limitations, including inconsistencies in process administration and guidance. Time delays and costs of applying EA remain a serious concern for project proponents. Affected communities are more concerned with the lack of quality control of EIA studies or enforcement of mitigation measures. • Structural issues, stemming from the application of EIA as a separate process, unrelated to the project cycle or the larger context of decision making. • In order to be effective, EIA requires a coherent policy-planning framework and systematic follow up procedures.
  • 23. Costs and benefits of EIA • Although there are costs associated with undertaking EIA, experience has shown that the potential savings over the life of a project can repay the investment many times over. • The savings can be economic (e.g. identification of least cost alternative) as well as environmental (e.g. impact reduction, maintaining other resource use opportunities). • Generally the earlier EIA process is introduced in the project cycle, the greater the potential returns. • When EIA is integrated into the project preparation phase, environmental design considerations can be introduced in the first place rather than the proposal having to be modified later.
  • 24. Costs and benefits of EIA Benefits • The benefits of EIA can be direct, such as the improved design or location of a project, or indirect, such as better quality EIA work or raised environmental awareness of the personnel involved in the project. • In these cases, there will be with flow-on effects in their future work. As mentioned above, these potential gains from EIA increase the earlier the process is applied in the design process.
  • 25. Costs and benefits of EIA In general the benefits of EIA include: • Better environmental planning and design of a proposal. Carrying out an EIA entails an analysis of alternatives in the design and location of projects. This can result in the selection of an improved technology, which lowers waste outputs or an environmentally optimum location for a project. A well-designed project can minimise risks and impacts on the environment and people, and thereby avoid associated costs of remedial treatment or compensation for damage. • Ensuring compliance with environmental standards. Compliance with environmental standards reduces damage to the environment and disruption to communities. It also avoids the likelihood of penalties, fines and loss of trust and credibility. • Savings in capital and operating costs. EIA can avoid the undue costs of unanticipated impacts. These can escalate if environmental problems have not been considered from the start of proposal design and require rectification later. An ‘anticipate and avoid’ approach is much cheaper than ‘react and cure’. Generally, changes which must be made late in the project cycle are the most expensive. • Reduced time and costs of approvals of development applications. If all environmental concerns have been taken into account properly before submission for project approval, then it is unlikely that delays will occur as a result of decision- makers asking for additional information or alterations to mitigation measures. Increased project acceptance by the public.
  • 26. Costs and benefits of EIA Costs • It can be difficult to determine the exact costs of an EIA because major projects typically require a large number of investigations and reports, often for closely related purposes (e.g. engineering feasibility studies of hydrology and surface materials). • The World Bank notes that the cost of preparing an EIA rarely exceeds one per cent of the project costs and this percentage can be reduced further if local personnel are used to do most of the work. • For Bank projects, the relative cost of an EIA typically ranges from only 0.06 per cent to 0.10 per cent of total project costs. • The total cost of an EIA might range from a few thousand dollars for a very small project, to over a million dollars for a large and complex project, which has a significant environmental impact and requires extensive data collection and analysis.
  • 27. Costs and benefits of EIA Costs Although many proponents complain that EIA causes excessive delays in projects, many of these are caused by poor administration of the process rather than by the process itself. These occur when: – the EIA is commenced too late in the project cycle; – the terms of reference are poorly drafted;. – the EIA is not managed to a schedule; – the technical and consultative components of EIA are inadequate; and – the EIA report is incomplete or deficient as a basis for decision making.