SlideShare a Scribd company logo
1 of 3
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2568
Influence of Stakeholders on Project Time Overrun
Sanya Sathyan Chakkalakal
Assistant Professor, Dept. of civil Engineering, SSJCET, Maharashtra, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract- The relationship between stakeholders governs
the overall performance of a construction project. Under the
company “Kochi Metro Rail Limited” a case study has been
conducted. The main aim wastoperformExternalStakeholder
Analysis, and to find out the key stakeholders who will have
influence on the successful outcome of the project and also to
find out the stakeholders who can be amenacetothecompany
on the basis of their power and influence level and find the
various factors that cause delay has been done using pareto
analysis. The proposed analysis was able to indicate the
factors that causes 80 percentage of the delay and also to find
out the stakeholder groups that influencetheprojectschedule.
Key Words: Stakeholders Prioritizations, Power Interest
Method, Key Stakeholders, Pareto Analysis.
1. INTRODUCTION
Individuals or groups that benefit from an organization may
be called as stakeholders. A case study at Kochi Metro under
the company ―KMRLwasdone.Thestakeholdersassociated
with the company are analysed individually and key stake
holders have been indicated on the basis of Probability
Impact method. The factors that lead to delay in this project
are studied using Pareto Analysis.
The study has examined factors leading to project success,
and project participants‟ satisfaction on project
performance.
2. CASE STUDY: KOCHI METRO
Considering the influence of external stakeholders on Kochi
Metro Project a case study has been conducted at Kochi,
under the company “KMRL”.
Fig.1 Representation of Stakeholders
For the conducting the analysis the factors were identified
and the external stakeholders were also identified and were
grouped into four different groups.Concernsofstakeholders
are generally different and requirements of different
stakeholders are as a rule always diverse. Hence first
various stakeholders with common need were categorized
into four different groups:LandOwnersandLocal Residents,
Regulatory Agencies (Special Tahasildar Office &
Choornikara Panchayat), Political Parties &
Environmentalists Public Works Department Ernakulam &
Contractors.Separate questionnaireswerepreparedfor each
group of stakeholders and each of them were analysed
separately to get more clarity of the factors that actually
effect the project time. Stakeholders views about the project
was evaluated on a five point Likert scale (1 = Very slight
impact and 5 = Very high impact).
Fig.2 Newspaper clippings on Kochi Metro (Courtesy:
The Hindu)
3. ANALYSIS
A Pareto Chart is a widely used to obtain frequency or
impact of problems .These charts are based on the Pareto
Principle which states that 20% of the causes may lead to
80% of the problems. A scale from 1 to 5 was used to obtain
the parameters vested interest level and influence of impact
level. Level of impact of each group is identified by finding
the average of impact ratings of each group and probability
of impact is the ratio number ofstakeholderswhohaverated
high level of impact for the factors listed to the total number
of stakeholders.
By identifying external stakeholders in the power/interest
matrix, it is possible to understand how the influence of
external stakeholders has developed in the course ofproject
implementation. Despite this being a useful model there are
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2569
certain problems connected with it. Instead of assessing
power and interest it can be more relevanttoassessthelevel
of the potential impact that external stakeholders have and
the probability that impact of a given level will occur. Thus,
the power/interest matrix could be translated into the
impact/probability matrix. The parameters „vested interest
levels‟ (probability of impact) and influence impact levels‟
(level of impact) are assessed on a scale from 1 to 5. Level of
impact of each group is obtained by finding the average of
impact ratings of each group and probability of impact is the
ratio number of stakeholders who have rated high level of
impact for the factors listed to the total number of
stakeholders.
Table 1: Stakeholder Analysis
Fig.3 Impact/Probability Matrix
Fig.4 Level of Impact
4. CONCLUSION
The main findings from this research study shows that
clashes between external stakeholders and the developer of
a facility is mostly depend on their views of each other. Ifthe
developer is not able to understand the problemsofexternal
stakeholders, it results in an environment of distrust
between the two parties. An effective external stakeholder
analysis should identify the possible trade-offs that can be
made without adjusting the aspirations of the project. An
external stakeholder analysisshouldbeseenasanimportant
component of the decision-making process required in any
construction project and as a key input to the external
stakeholder management procedure.
Table 2: Critical Factors Affecting the Project
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2570
REFERENCES
1. Aapaoja and Harri Haapasalo (2014) A Framework
for Stakeholder Identification and Classification in
Construction Projects, OpenJournal ofBusinessand
Management, 02, 43-55.
2. Andrea Caputo (2013) Systemic Stakeholders’
Management for Real Estate Development Projects,
Global Business and Management Research: An
International Journal, 05, 66-82.
3. Ashwini Arun Salunkhe and Rahul S. Patil (2014)
Effect of construction delays on project time
overrun: Indian scenario, International Journal of
Research in Engineering and Technology, 03, 543-
547.
4. Chan, D.W. and M.M. Kumaraswamy (1997) A
comparative study of causes of time overruns in
Hong Kong construction projects, International
Journal of Project Management, 15, 55–63.
5. Doloi, H. (2008) Analysing the novated design and
construct contract from the client's, design teams
and contractors perspectives, Construction
Management and Economics, 26, 1181–1196.
6. Doloi, H. (2009) Analysis of pre-qualification
criteria in contractor selection and their impactson
project success, Construction Management and
Economics, 27, 1245–1263.
7. Hemanta Doloi (2012) Cost overruns and failure in
project management – understanding the roles of
key stakeholders in constructionprojects,Journal of
Construction Engineering and Management, 28, 1-
44.
8. Hemanta Doloi, Anil Sawhney, K.C. Iyer and Sameer
Rentala (2012) Analysing factors affectingdelaysin
Indian construction projects, International Journal
of Project Management, 30, 481-489.
9. Iyer, K.C. and K.N. Jha (2005) Factors affecting cost
performance: evidence from Indian construction
projects, International Journal of Project
Management, 23, 283-295.
10. Iyer, K.C. and K.N. Jha (2006) Critical Factors
Affecting Schedule Performance: Evidence from
Indian Construction Projects, Journal of
Construction Engineering and Management, 08,
871-881.
11. Jing Yang (2009) Exploring critical success factors
for stake holders management in construction
project, Journal of Civil Engineering and
Management, 04, 337-348.

More Related Content

What's hot

IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 
Dibyendu.chakraborty
Dibyendu.chakrabortyDibyendu.chakraborty
Dibyendu.chakrabortyPMI2011
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryeSAT Journals
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewA Makwana
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET Journal
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET Journal
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...eSAT Journals
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
Feasibility Report seminar
Feasibility Report seminarFeasibility Report seminar
Feasibility Report seminarPujaBrahma
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Rizwan Khurram
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Projectcsandit
 
Project Management Notes 2
Project Management Notes 2Project Management Notes 2
Project Management Notes 2Golam Bitonsir
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 

What's hot (19)

IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
D012251726
D012251726D012251726
D012251726
 
Dibyendu.chakraborty
Dibyendu.chakrabortyDibyendu.chakraborty
Dibyendu.chakraborty
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industry
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...IRJET- Decision Making in Construction Management using AHP and Expert Choice...
IRJET- Decision Making in Construction Management using AHP and Expert Choice...
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
Feasibility Report seminar
Feasibility Report seminarFeasibility Report seminar
Feasibility Report seminar
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Analysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software ProjectAnalysing Attrition in Outsourced Software Project
Analysing Attrition in Outsourced Software Project
 
Project Management Notes 2
Project Management Notes 2Project Management Notes 2
Project Management Notes 2
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 

Similar to IRJET- Influence of Stakeholders on Project Time Overrun

IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...IRJET Journal
 
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...
IRJET- Influence of Stakeholder Management on the Success Construction Pr...IRJET Journal
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction ProjectsIRJET Journal
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...IRJET Journal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET Journal
 
IRJET- S.W.O.T Analysis: Current Status of Construction
IRJET-  	  S.W.O.T Analysis: Current Status of ConstructionIRJET-  	  S.W.O.T Analysis: Current Status of Construction
IRJET- S.W.O.T Analysis: Current Status of ConstructionIRJET Journal
 
IRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET Journal
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for ConstructionIRJET Journal
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET Journal
 
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...IRJET Journal
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...IRJET Journal
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET Journal
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 

Similar to IRJET- Influence of Stakeholders on Project Time Overrun (20)

IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
 
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction Projects
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
IRJET- Risk Assessment and Mitigation of International Airport Projects in In...
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
 
IRJET- S.W.O.T Analysis: Current Status of Construction
IRJET-  	  S.W.O.T Analysis: Current Status of ConstructionIRJET-  	  S.W.O.T Analysis: Current Status of Construction
IRJET- S.W.O.T Analysis: Current Status of Construction
 
IRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction Industry
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for Construction
 
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
IRJET- Analysis of Risk Factors Affecting Management and Maintenance of Urban...
 
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure Projects
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

IRJET- Influence of Stakeholders on Project Time Overrun

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2568 Influence of Stakeholders on Project Time Overrun Sanya Sathyan Chakkalakal Assistant Professor, Dept. of civil Engineering, SSJCET, Maharashtra, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract- The relationship between stakeholders governs the overall performance of a construction project. Under the company “Kochi Metro Rail Limited” a case study has been conducted. The main aim wastoperformExternalStakeholder Analysis, and to find out the key stakeholders who will have influence on the successful outcome of the project and also to find out the stakeholders who can be amenacetothecompany on the basis of their power and influence level and find the various factors that cause delay has been done using pareto analysis. The proposed analysis was able to indicate the factors that causes 80 percentage of the delay and also to find out the stakeholder groups that influencetheprojectschedule. Key Words: Stakeholders Prioritizations, Power Interest Method, Key Stakeholders, Pareto Analysis. 1. INTRODUCTION Individuals or groups that benefit from an organization may be called as stakeholders. A case study at Kochi Metro under the company ―KMRLwasdone.Thestakeholdersassociated with the company are analysed individually and key stake holders have been indicated on the basis of Probability Impact method. The factors that lead to delay in this project are studied using Pareto Analysis. The study has examined factors leading to project success, and project participants‟ satisfaction on project performance. 2. CASE STUDY: KOCHI METRO Considering the influence of external stakeholders on Kochi Metro Project a case study has been conducted at Kochi, under the company “KMRL”. Fig.1 Representation of Stakeholders For the conducting the analysis the factors were identified and the external stakeholders were also identified and were grouped into four different groups.Concernsofstakeholders are generally different and requirements of different stakeholders are as a rule always diverse. Hence first various stakeholders with common need were categorized into four different groups:LandOwnersandLocal Residents, Regulatory Agencies (Special Tahasildar Office & Choornikara Panchayat), Political Parties & Environmentalists Public Works Department Ernakulam & Contractors.Separate questionnaireswerepreparedfor each group of stakeholders and each of them were analysed separately to get more clarity of the factors that actually effect the project time. Stakeholders views about the project was evaluated on a five point Likert scale (1 = Very slight impact and 5 = Very high impact). Fig.2 Newspaper clippings on Kochi Metro (Courtesy: The Hindu) 3. ANALYSIS A Pareto Chart is a widely used to obtain frequency or impact of problems .These charts are based on the Pareto Principle which states that 20% of the causes may lead to 80% of the problems. A scale from 1 to 5 was used to obtain the parameters vested interest level and influence of impact level. Level of impact of each group is identified by finding the average of impact ratings of each group and probability of impact is the ratio number ofstakeholderswhohaverated high level of impact for the factors listed to the total number of stakeholders. By identifying external stakeholders in the power/interest matrix, it is possible to understand how the influence of external stakeholders has developed in the course ofproject implementation. Despite this being a useful model there are
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2569 certain problems connected with it. Instead of assessing power and interest it can be more relevanttoassessthelevel of the potential impact that external stakeholders have and the probability that impact of a given level will occur. Thus, the power/interest matrix could be translated into the impact/probability matrix. The parameters „vested interest levels‟ (probability of impact) and influence impact levels‟ (level of impact) are assessed on a scale from 1 to 5. Level of impact of each group is obtained by finding the average of impact ratings of each group and probability of impact is the ratio number of stakeholders who have rated high level of impact for the factors listed to the total number of stakeholders. Table 1: Stakeholder Analysis Fig.3 Impact/Probability Matrix Fig.4 Level of Impact 4. CONCLUSION The main findings from this research study shows that clashes between external stakeholders and the developer of a facility is mostly depend on their views of each other. Ifthe developer is not able to understand the problemsofexternal stakeholders, it results in an environment of distrust between the two parties. An effective external stakeholder analysis should identify the possible trade-offs that can be made without adjusting the aspirations of the project. An external stakeholder analysisshouldbeseenasanimportant component of the decision-making process required in any construction project and as a key input to the external stakeholder management procedure. Table 2: Critical Factors Affecting the Project
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2570 REFERENCES 1. Aapaoja and Harri Haapasalo (2014) A Framework for Stakeholder Identification and Classification in Construction Projects, OpenJournal ofBusinessand Management, 02, 43-55. 2. Andrea Caputo (2013) Systemic Stakeholders’ Management for Real Estate Development Projects, Global Business and Management Research: An International Journal, 05, 66-82. 3. Ashwini Arun Salunkhe and Rahul S. Patil (2014) Effect of construction delays on project time overrun: Indian scenario, International Journal of Research in Engineering and Technology, 03, 543- 547. 4. Chan, D.W. and M.M. Kumaraswamy (1997) A comparative study of causes of time overruns in Hong Kong construction projects, International Journal of Project Management, 15, 55–63. 5. Doloi, H. (2008) Analysing the novated design and construct contract from the client's, design teams and contractors perspectives, Construction Management and Economics, 26, 1181–1196. 6. Doloi, H. (2009) Analysis of pre-qualification criteria in contractor selection and their impactson project success, Construction Management and Economics, 27, 1245–1263. 7. Hemanta Doloi (2012) Cost overruns and failure in project management – understanding the roles of key stakeholders in constructionprojects,Journal of Construction Engineering and Management, 28, 1- 44. 8. Hemanta Doloi, Anil Sawhney, K.C. Iyer and Sameer Rentala (2012) Analysing factors affectingdelaysin Indian construction projects, International Journal of Project Management, 30, 481-489. 9. Iyer, K.C. and K.N. Jha (2005) Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management, 23, 283-295. 10. Iyer, K.C. and K.N. Jha (2006) Critical Factors Affecting Schedule Performance: Evidence from Indian Construction Projects, Journal of Construction Engineering and Management, 08, 871-881. 11. Jing Yang (2009) Exploring critical success factors for stake holders management in construction project, Journal of Civil Engineering and Management, 04, 337-348.