International Journal of Trend in Scientific Research and Development (IJTSRD)
Volume 7 Issue 2, March-April 2023 Available Online: www.ijtsrd.com e-ISSN: 2456 – 6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1173
Systematic Study of Factors Causing Cost Overrun
and Delay in Pune Metro Line Project by using
Relative Importance Index (RII) Method
Ramkrushn Kalbaji Shinde1
, Dr. Sandhya Kashinath Swami2
1
PG Student, 2
Associate Professor,
1,2
Padmabhooshan Vasantdada Patil Institute of Technology, Bavdhan, Pune, Maharashtra, India
ABSTRACT
To sketchily identify the major causes of delays on construction of
Pune metro line I project; the major causes of delays from this
research study were investigated following data collection carried out
through a questionnaire survey with a wide range of construction
professionals based in Metro Projects. The findings from this
research determined the major causes of delays based on an relative
importance index, and the main conclusions from output of the data
could help the construction sector to better assess not only the major
causes of delays on construction of metro projects but also how to
minimize and mitigate the risks involved. The construction industry
which supplements the second largest job in India after agriculture
industry is also generates construction waste which impacts
environment in the form of soil contamination, water contamination,
and deterioration of landscape. It is well well-known fact that most
railway construction projects showing the delay in timeline or cost
overrun or both of them. This phenomenon may distress the progress
of infrastructure in the country as well as may risk many contracting
firms profit margin. This study was supported out based on literature
review and a semi-structured survey that was acquired from
competent people from contracting companies, consultants and
stakeholders of Pune metro project, and to understand the top factors
delaying the time line of railway metro projects analysis has been
carried out by RII method. By analysis it has been find out that top
three factors responsible for delay are Land Acquisition, Covid 19
pandemic and Shortage of skilled workforce which clearly represent
the importance of land acquisition role in infrastructure projects like
metro projects and the scarcity of skilled workforce also plays a
substantial role in delay of project.
How to cite this paper: Ramkrushn
Kalbaji Shinde | Dr. Sandhya Kashinath
Swami "Systematic Study of Factors
Causing Cost Overrun and Delay in
Pune Metro Line Project by using
Relative Importance Index (RII)
Method" Published
in International
Journal of Trend in
Scientific Research
and Development
(ijtsrd), ISSN: 2456-
6470, Volume-7 |
Issue-2, April 2023,
pp.1173-1179, URL:
www.ijtsrd.com/papers/ijtsrd56256.pdf
Copyright © 2023 by author (s) and
International Journal of Trend in
Scientific Research and Development
Journal. This is an
Open Access article
distributed under the
terms of the Creative Commons
Attribution License (CC BY 4.0)
(http://creativecommons.org/licenses/by/4.0)
KEYWORDS: Railway project, Pune
Metro, Material Wastage, Relative
Importance Index
1. INTRODUCTION
1.1. General
The construction industry in India is growing with
rapid speed and investment which accounts for nearly
8% of India’s GDP in 2021. The construction
industry is one of the industries through which the
physical expansion of the nation is accomplished. It is
truly the locomotive of the national economy, at the
same time the impact due to construction activities on
the natural environment is immeasurable.
The construction industry is considered as one of the
most important industries in India. It is well known
fact that most construction projects in India are
getting delayed or cost overrun. The study area of
Pune metro phase I project is one of the prominent
projects of the country which make this ideal to
understand the time delay and cost overrun. The study
carried out in this research paper will be beneficial for
other metro line construction projects as well as give
enrich exposure to the various factors influence the
timeline in construction of metro line projects.[1]
1.2. Problem Statement
Management of construction and demolition waste is
a serious concern in the country given the high
phenomenal growth in the construction industry; the
market size is expected to increase at a Compound
IJTSRD56256
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1174
Annual Growth Rate (CAGR) of about11 percent
considering 2020-21.
Transportation infrastructure projects like metro
projects which will be nerve for many cities of India
faces delays in construction. This study is carried out
with an objective to specifically identify the critical
delay factors in the commissioning of Pune metro line
I project.
2. LITERATURE REVIEW
Investigation of Pune strip development projects
presented to time invades and material wastage or
both. This wonder may influence the advancement of
the development business just as may uncover
numerous organizations of development to be
destroyed.[2]
The charging which is determined in super ventures
can be co-related with uses of CAD utilizing 5
measurements and a geographic data system.[3]
The creator in this exploration accentuation
discovering the most ideal course for transportation
lines regarding streets and rail routes, and this paper
have helped in the metro passage course examination
[4]
. The creator has zeroed in on the appraisal of
Mumbai city which falls under metropolitan region
by utilizing 3D demonstrating methods [5]
This examination has utilized a fluffy characterization
approach utilizing high-goal satellite pictures which
have helped the creator for programmed street
extraction.[6]
In this venture for quick development and limiting
waste the creator has utilized E-squander as a
fractional substitution in some rate, obviously, total to
go after the material utilization.[7]
The creator do explore and has utilized 4D GIS
during the time spent different development exercises
alongside the quality, amount, and gauge of different
underlying individuals like chunks, radiates sections,
etc.[8]
The very much dissected exploration including
the labor regarding work and material administration
is considered by the creator utilizing the RII
technique by with the material administration is
controlled.[9]
The creator has applied the RMMM
strategy for infrastructural projects for different asset
management. [10]
The task accentuates discovering the best shorted
conceivable course for RMC vehicles to move the
solid to the site from different RMC plants.[11]
The
creator has taken Akola taluka as the examination
territory wherein utilizing geological information
alongside land drafting maps are utilized for the
improvement of open or empty land space for endless
suburbia. [12]
The creator has utilized the open patio territory for
water assortment by with the water waste isn't
captured with the Mumbai transportation frameworks
and subsequently a turnpike is kept up.[13]
The creator
has worked out the development of the material and
primary components utilizing Etabs and Staad to
actualize the time and cost factors with the pre- and
post-development of intercultural projects. [14]
This investigation was done dependent on writing
audit and a poll review that was acquired from
contracting organizations, specialists and proprietors
in Pune Strip. The examination explained that "late in
modifying and supporting plan reports "was the most
basic factor that impacts project length. The study
demonstrates that "material - related components
"involved the second position in significance”. The
absence of materials on the lookout" and
"postponement in material conveyance to the site" is
likewise the main components influencing project
duration. [15]
According to the investigation by creator, cost
overwhelm is a difficult which influences 90% of
finished tasks on the planet. In this paper creator,
embraced the work area methodological methodology
which includes contrasting the reasons for material
waste and those of cost invades from the writing to
decide the conceivable relationship.[16]
According to the aftereffect of examination paper,
96.88% and 81.81% of the reasons for cost
overwhelm likewise because material waste at the
pre-agreement and post-contract organizes
individually. There is a 86.74% cover between the
reasons for material waste and those of cost
overwhelms at all phases of a project.[17]
The investigation suggests that development project
administrators, just as the development specialists,
ought to empower the administration of material-
squander causes, as it can possibly limit the reasons
for cost invade for a project.[17]
Creator has conveyed the examination included
progressing building development projects inside
Abuja, Nigeria, from which an example of 31 public
and private activities was intentionally chosen. The
creator utilized Pearson second connection and the
engaging technique to dissect the gathered
information and the outcomes uncovered a
measurably critical connection between material
waste and cost overrun.[18]
The outcomes showed material waste to project-cost
overwhelm goes from 1.96% to 8.01%, with a normal
commitment of 4.0% to project-cost overruns.[18]
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1175
In this paper, the creator contemplated five limited
scope private development projects in Nasik where
odds of waste age are more because of absence of
appropriate administration. [19]
The development material waste situation of every
one of the 5 private, medium to little building locales
discovered to be significant in cost-adequacy and
necessities the executives. The increasing expense on
development project emerging because of
development material wastage which is in the middle
of 5% to 10 % of task according to the examination
and investigation by author. [19]
In this investigation, the creator intends to set up
connection between times invade and work
profitability on building site in India. The information
result show that deficient asset for the venture,
lacking arranging before project departure,
insufficient devices and gear and postponement in
conveyance material are the rundown of the
significant reasons for time invade while the
utilization of wrong development strategy, deficient
development material, and off base drawing particular
are the key factor causing low work profitability
building site. The huge negative relationship figured
out between time invade and work profitability at
building site.
The creator closed by suggesting that the early
arrangement of the venture chief could guarantee
appropriate administration of both human and
material assets that could ensure improved
profitability and eventually save project from time
overcome.[20]
3. AIM AND OBJECTIVE
“The eventual aim of this research paper is, to
systematically identify the various factors influence
the cost and time overrun of Pune metro project”.
1. To study various factors causing delay of Pune
metro Line I project.
2. To study various factors causing cost overrun of
Pune metro Line I project.
4. METHODOLOGY
Initially, the data will be collected from literature
review and Pune metro line I project and a roadmap
of research work will be prepared in form of various
factors may influence the time and cost overrun of
metro project and evaluate the factors by RII method.
Figure No. 1: Research Methodology
5. DATA COLLECTION AND ANALYSIS
5.1. Survey
a. Type of Survey: Close-ended Question and using
Likert Scale.
b. Participants
A. Nature of Organization: In this study, the
participants that is contractor, consultant and
owner are 60%, 23% and 17% respectively.
Figure No. 2: Types of Participants Nature of
Organization
B. Types of Projects handled by Participants:
Figure No. 3: Type of Projects Handled by
Participants
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1176
C. Participants Designation:
Figure No. 4: Participants Designation
D. Participants Professional Trades:
Figure No. 5: Participants Professional Trades
5.2. Relative Importance Index
The process used in examining of data was aimed at
forming the relative importance of the various factors
that contribute to causes of delays in metro line
construction project particularly in Pune Metro.
The contribution of each of the factors to overall
delays was examined and the ranking of the attributes
in terms of their criticality as perceived by the
respondents was done by use of Relative Importance
Index (RII) which was computed using equation and
the results of the analysis are presented in following
section.
Simply for understanding, formula can be written in
the following way
Where, N5 = Nos. of respondents for great impact
N4 = Nos. of respondents for considerable impact
N3 = Nos. of respondents for average impact
N2 = Nos. of respondents for slight impact
N1 = Nos. of respondents for least impact
5.3. Skewness and Kurtosis of Survey
The summary of the collected data from survey is
given below. In this datasheet, total sixty respondents
have given their ratings on all thirty factors by using
Likert’s scale of 5 points. The data has been collected
in form of physical sheets and all the respondents are
the competent persons to avoid error in result
analysis.
Table No. 1: Skewness and Kurtosis of Survey
Sr. No Factors Skewness Kurtosis
1 Effects of subsurface and ground conditions 0.5 -0.7
2 Poor site management -0.6 -0.5
3 Poor site layout -0.3 -1.0
4 Delay of materials approved by a consultant 0.0 -0.8
5 Escalation of material prices 0.3 -0.7
6 Low Productivity level of labor -0.5 -0.8
7 Shortage of skilled workforce -0.1 0.9
8 Insufficient number of staffs -1.0 -1.1
9 Frequent change in Contractor 0.5 0.4
10 Low level of equipment operator skills 0.1 -0.9
11 Labor injuries on site 0.4 0.6
12 Insufficient number of Equipment 0.5 0.4
13 Shortage of good conditioned equipment at a site -0.1 -0.6
14 Inadequate contractor work experience -0.5 -0.7
15 Delay of material delivery to site 0.1 -0.7
16 Complexity of the project 0.5 0.4
17 Suspension of work by owner or contractor 0.8 -1.4
18 Poor communication and coordination by owner -0.4 -1.0
19 Poor communication& coordination by contractor 0.0 0.5
20 Slowness in decision making process by owner -1.0 0.8
21 Original contract duration is too short 0.3 -1.0
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1177
22 Delay in Payment 0.1 0.9
23 Shortage of construction material at the site 0.3 1.0
24 Disputes between the parties regarding legal issues 0.5 -0.7
25 Changes in government regulation and laws -1.0 -0.1
26 National or Global Pandemic (Covid 19) -1.0 0.1
27 Ineffective planning & scheduling of project 0.2 -1.0
28 Ineffective planning and scheduling by Agency -0.6 -0.5
29 Land Acquisition -1.0 -0.7
30 Local issues -0.5 -0.7
First the data collected from the semi-structured survey, will be checked by Skewness and Kurtosis method of
analysis to validate the collected data.
Figure No. 6: Graphical Representation of Skewness Value of Survey Data
Figure No. 7: Graphical Representation of Kurtosis Value of Survey Data
5.4. Analysis of Survey
RII Technique is used in dissertation to determine the relative importance of the various causes of delays in
railway project. The same method is going to be adopted in this study within various groups (i.e. contractors,
consultants and clients). The five-point scale ranged from 1 (least impact) to 5 (great impact) is adopted and
transformed to RII for each factor by using the formula specified in previous section.
Table No. 2: Critical Causes of delay to railway project by RII Method
Weighting given by each respondent
∑W A N RII
5 4 3 2 1
0 0 18 41 1 137 5 60 0.46
0 1 42 17 0 164 5 60 0.55
0 1 38 21 0 160 5 60 0.53
23 35 2 0 0 261 5 60 0.87
7 30 23 0 0 224 5 60 0.75
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1178
0 1 40 19 0 162 5 60 0.54
0 7 44 9 0 178 5 60 0.59
0 0 43 17 0 163 5 60 0.54
0 0 14 44 2 132 5 60 0.44
2 33 25 0 0 217 5 60 0.72
0 0 13 44 3 130 5 60 0.43
0 0 14 44 2 132 5 60 0.44
0 15 34 11 0 184 5 60 0.61
0 1 41 18 0 163 5 60 0.54
1 28 30 1 0 209 5 60 0.70
0 0 14 44 2 132 5 60 0.44
0 19 41 0 0 199 5 60 0.66
0 25 25 10 0 195 5 60 0.65
0 8 42 10 0 178 5 60 0.59
0 1 42 16 1 163 5 60 0.54
0 11 28 21 0 170 5 60 0.57
0 10 44 6 0 184 5 60 0.61
0 11 45 4 0 187 5 60 0.62
0 18 41 1 0 197 5 60 0.66
0 40 19 1 0 219 5 60 0.73
0 38 20 2 0 216 5 60 0.72
0 12 28 20 0 172 5 60 0.57
0 1 42 17 0 164 5 60 0.55
0 39 9 12 0 207 5 60 0.69
0 0 43 17 0 163 5 60 0.54
Base on the ranking, the 10 most important causes of material management by RII were as follows table:
Table No. 3: Rank of Factors Delaying Railway Project as per RII
Rank Factors Delaying Railway Project
1 Land Acquisition
2 National or Global Pandemic (Covid 19)
3 Shortage of skilled workforce
4 Frequent change in Contractor
5 Local issues
6 Delay of material delivery to site
7 Shortage of construction material at the site
8 Inadequate contractor work experience
9 Suspension of work by owner or contractor
10 Ineffective planning & scheduling of project
6. CONCLUSION
As per the ranking on the bases of RII value, it can be
observed that the top three factors responsible for
delay in Pune project are Land Acquisition, Covid 19
pandemic and Shortage of skilled workforce which
clearly represent the importance of land acquisition
role in infrastructure projects like metro projects and
the scarcity of skilled workforce also plays a
substantial role in delay of project. Even in top 10
factors there are two factors related to material
management i.e. delay of material delivery to site and
shortage of construction materials at the site, which
clearly reflects the role played by material in terms of
cost overrun and delay in Pune metro project.
REFERENCE
[1] Agopyan V., Souza, U. E. L., Paliari, J. C., and
Andrade, A. C. (2018). Alternatives for
reducing waste of materials in building sites:
final report, EPUSP/FINEP/ITQC, in
Portuguese.
[2] Bossink, B. A. G., and Brouwers, H. J. H.
(2018). “Construction waste: Quantification
and source evaluation.” Journal Construction
Engineering. and Management., ASCE.
[3] Carlos Torres Formoso and Eduardo luis Isatto
"Method for waste control in building Industry”
University of California, Berkery, CA, USA,
July 2019
International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470
@ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1179
[4] Chandler Ian E; "Material Management On
Construction At Site" Longman Inc; 78 Edition
[5] Gavilan, R. M., and Bernold, L. E. (2018).
‘‘Source evaluation of solid Waste in building
construction.’’ J. Constr. Eng. Manage., 120(3)
[6] Hong Kong Polytechnic and The Hong Kong
Construction Association Ltd. (2020).
Reduction of Construction Waste: Final Report,
Hong Kong.
[7] Indira Gandhi National Open University
(IGNOU) " Materials Management" Part Ms-5,
Unit-6
[8] Shri Rakesh j. Hingu (2010), “Wastage of
building materials during construction of
structure” Sardar Patel University, V.V. Nagar,
Dissertation report, June 2010
[9] Skoyles, E.R., and Skoyles, J.R. (2016). Waste
prevention on site. Mitchell Publishing
Company Limited. London.
[10] Vaid K.N. "Waste Control of Building
Materials' NICMAR Course Materials In
Construction Materials Management, Oct-2018.
[11] C. T. Formoso, E. L. Isatto, and, E. H. Hirota,
“Method for waste control in the building
industry,” Proceedings of the Seventh Annual
Conference of the International Group for Lean
Construction, Berkeley, USA, 2019.
[12] Y. Khairulzan, and A. B. Halim, “Eco-costing
of construction waste,” Journal of Management
of Environmental Quality: An International
Journal, vol 17(1), pp. 6–19, 2016.
[13] M. Osmani, J. Glass, and A.D.F. Price,
“Architects perspectives on construction waste
reduction by design,” Journal of Waste
Management, vol. 28, pp. 1147–1158, 2014.
[14] J. Y. Wang, X. P. Kang, and V. W. Y. Tam,
“An investigation of construction wastes: an
empirical study in Shenzhen,” Journal of
Engineering, Design and Technology, vol. 6(3).
pp. 227–236, 2017.
[15] R. Ndihokubwayo, and T. Haupt, “Variation
orders on construction projects: Value adding
or waste,” International Journal of Construction
Project Management, vol. 1(2), pp. 1– 17, 2019.
[16] H. Yuan, “A model for evaluating the social
performance of construction waste
management,” Waste Management, vol. 32(6),
pp. 1218–1228, 2012.
[17] S. Nagapan, A. R. Ismail, and A. Ade,
“Construction waste and related issues in
Malaysia,” Diges FKAAS, Vol.1, pp. 15–20,
2012.
[18] Department of Environment and Climate
Change (DECC), “Cracking down on illegal
dumping: Handbook for local government,”
Sydney, Australia, pp. 7–15, February 2018.
[19] C. S. Poon, A. T. W. Yu, S. W. Wong, and E.
Cheung “Management of construction waste in
public housing projects in Hong Kong,” Journal
of Construction Management and Economics,
vol. 22, pp. 675-689, 2014.
[20] N. Yahaya, and I. Larsen, “Federalizing solid
waste management in Peninsular Malaysia,”
Proceeding of International Solid Waste
Association (ISWA) World Congress,
Singapore, 2018.

More Related Content

Similar to Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line Project by using Relative Importance Index RII Method

IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...IRJET Journal
 
Analytical Study between Construction Material Wastage and Time Overrun
Analytical Study between Construction Material Wastage and Time OverrunAnalytical Study between Construction Material Wastage and Time Overrun
Analytical Study between Construction Material Wastage and Time Overrunijtsrd
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction worksvivatechijri
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectseSAT Publishing House
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaAI Publications
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
Feasibility study of_metro_transport_case_study_madurai
Feasibility study of_metro_transport_case_study_maduraiFeasibility study of_metro_transport_case_study_madurai
Feasibility study of_metro_transport_case_study_maduraiDurga Rai
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...IRJET Journal
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 

Similar to Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line Project by using Relative Importance Index RII Method (20)

IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
D012261521
D012261521D012261521
D012261521
 
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...
IRJET- Construction of Flyover Bridge (Grade Separator) at Powai Naka on Maha...
 
B1303020508
B1303020508B1303020508
B1303020508
 
Analytical Study between Construction Material Wastage and Time Overrun
Analytical Study between Construction Material Wastage and Time OverrunAnalytical Study between Construction Material Wastage and Time Overrun
Analytical Study between Construction Material Wastage and Time Overrun
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali IndonesiaValue Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
Value Engineering on Bias Munjul Port Project in Nusa Ceningan Bali Indonesia
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
Feasibility study of_metro_transport_case_study_madurai
Feasibility study of_metro_transport_case_study_maduraiFeasibility study of_metro_transport_case_study_madurai
Feasibility study of_metro_transport_case_study_madurai
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 

More from ijtsrd

‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementationijtsrd
 
Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...ijtsrd
 
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and ProspectsDynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and Prospectsijtsrd
 
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...ijtsrd
 
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...ijtsrd
 
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...ijtsrd
 
Problems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A StudyProblems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A Studyijtsrd
 
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...ijtsrd
 
The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...ijtsrd
 
A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...ijtsrd
 
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...ijtsrd
 
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...ijtsrd
 
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. SadikuSustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadikuijtsrd
 
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...ijtsrd
 
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...ijtsrd
 
Activating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment MapActivating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment Mapijtsrd
 
Educational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger SocietyEducational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger Societyijtsrd
 
Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...ijtsrd
 
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...ijtsrd
 
Streamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine LearningStreamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine Learningijtsrd
 

More from ijtsrd (20)

‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation‘Six Sigma Technique’ A Journey Through its Implementation
‘Six Sigma Technique’ A Journey Through its Implementation
 
Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...Edge Computing in Space Enhancing Data Processing and Communication for Space...
Edge Computing in Space Enhancing Data Processing and Communication for Space...
 
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and ProspectsDynamics of Communal Politics in 21st Century India Challenges and Prospects
Dynamics of Communal Politics in 21st Century India Challenges and Prospects
 
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...
 
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...The Impact of Digital Media on the Decentralization of Power and the Erosion ...
The Impact of Digital Media on the Decentralization of Power and the Erosion ...
 
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...
 
Problems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A StudyProblems and Challenges of Agro Entreprenurship A Study
Problems and Challenges of Agro Entreprenurship A Study
 
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...
 
The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...The Impact of Educational Background and Professional Training on Human Right...
The Impact of Educational Background and Professional Training on Human Right...
 
A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...A Study on the Effective Teaching Learning Process in English Curriculum at t...
A Study on the Effective Teaching Learning Process in English Curriculum at t...
 
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...
 
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...
 
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. SadikuSustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku
 
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...
 
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...
 
Activating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment MapActivating Geospatial Information for Sudans Sustainable Investment Map
Activating Geospatial Information for Sudans Sustainable Investment Map
 
Educational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger SocietyEducational Unity Embracing Diversity for a Stronger Society
Educational Unity Embracing Diversity for a Stronger Society
 
Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...Integration of Indian Indigenous Knowledge System in Management Prospects and...
Integration of Indian Indigenous Knowledge System in Management Prospects and...
 
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...
 
Streamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine LearningStreamlining Data Collection eCRF Design and Machine Learning
Streamlining Data Collection eCRF Design and Machine Learning
 

Recently uploaded

Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 

Recently uploaded (20)

Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 

Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line Project by using Relative Importance Index RII Method

  • 1. International Journal of Trend in Scientific Research and Development (IJTSRD) Volume 7 Issue 2, March-April 2023 Available Online: www.ijtsrd.com e-ISSN: 2456 – 6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1173 Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line Project by using Relative Importance Index (RII) Method Ramkrushn Kalbaji Shinde1 , Dr. Sandhya Kashinath Swami2 1 PG Student, 2 Associate Professor, 1,2 Padmabhooshan Vasantdada Patil Institute of Technology, Bavdhan, Pune, Maharashtra, India ABSTRACT To sketchily identify the major causes of delays on construction of Pune metro line I project; the major causes of delays from this research study were investigated following data collection carried out through a questionnaire survey with a wide range of construction professionals based in Metro Projects. The findings from this research determined the major causes of delays based on an relative importance index, and the main conclusions from output of the data could help the construction sector to better assess not only the major causes of delays on construction of metro projects but also how to minimize and mitigate the risks involved. The construction industry which supplements the second largest job in India after agriculture industry is also generates construction waste which impacts environment in the form of soil contamination, water contamination, and deterioration of landscape. It is well well-known fact that most railway construction projects showing the delay in timeline or cost overrun or both of them. This phenomenon may distress the progress of infrastructure in the country as well as may risk many contracting firms profit margin. This study was supported out based on literature review and a semi-structured survey that was acquired from competent people from contracting companies, consultants and stakeholders of Pune metro project, and to understand the top factors delaying the time line of railway metro projects analysis has been carried out by RII method. By analysis it has been find out that top three factors responsible for delay are Land Acquisition, Covid 19 pandemic and Shortage of skilled workforce which clearly represent the importance of land acquisition role in infrastructure projects like metro projects and the scarcity of skilled workforce also plays a substantial role in delay of project. How to cite this paper: Ramkrushn Kalbaji Shinde | Dr. Sandhya Kashinath Swami "Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line Project by using Relative Importance Index (RII) Method" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456- 6470, Volume-7 | Issue-2, April 2023, pp.1173-1179, URL: www.ijtsrd.com/papers/ijtsrd56256.pdf Copyright © 2023 by author (s) and International Journal of Trend in Scientific Research and Development Journal. This is an Open Access article distributed under the terms of the Creative Commons Attribution License (CC BY 4.0) (http://creativecommons.org/licenses/by/4.0) KEYWORDS: Railway project, Pune Metro, Material Wastage, Relative Importance Index 1. INTRODUCTION 1.1. General The construction industry in India is growing with rapid speed and investment which accounts for nearly 8% of India’s GDP in 2021. The construction industry is one of the industries through which the physical expansion of the nation is accomplished. It is truly the locomotive of the national economy, at the same time the impact due to construction activities on the natural environment is immeasurable. The construction industry is considered as one of the most important industries in India. It is well known fact that most construction projects in India are getting delayed or cost overrun. The study area of Pune metro phase I project is one of the prominent projects of the country which make this ideal to understand the time delay and cost overrun. The study carried out in this research paper will be beneficial for other metro line construction projects as well as give enrich exposure to the various factors influence the timeline in construction of metro line projects.[1] 1.2. Problem Statement Management of construction and demolition waste is a serious concern in the country given the high phenomenal growth in the construction industry; the market size is expected to increase at a Compound IJTSRD56256
  • 2. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1174 Annual Growth Rate (CAGR) of about11 percent considering 2020-21. Transportation infrastructure projects like metro projects which will be nerve for many cities of India faces delays in construction. This study is carried out with an objective to specifically identify the critical delay factors in the commissioning of Pune metro line I project. 2. LITERATURE REVIEW Investigation of Pune strip development projects presented to time invades and material wastage or both. This wonder may influence the advancement of the development business just as may uncover numerous organizations of development to be destroyed.[2] The charging which is determined in super ventures can be co-related with uses of CAD utilizing 5 measurements and a geographic data system.[3] The creator in this exploration accentuation discovering the most ideal course for transportation lines regarding streets and rail routes, and this paper have helped in the metro passage course examination [4] . The creator has zeroed in on the appraisal of Mumbai city which falls under metropolitan region by utilizing 3D demonstrating methods [5] This examination has utilized a fluffy characterization approach utilizing high-goal satellite pictures which have helped the creator for programmed street extraction.[6] In this venture for quick development and limiting waste the creator has utilized E-squander as a fractional substitution in some rate, obviously, total to go after the material utilization.[7] The creator do explore and has utilized 4D GIS during the time spent different development exercises alongside the quality, amount, and gauge of different underlying individuals like chunks, radiates sections, etc.[8] The very much dissected exploration including the labor regarding work and material administration is considered by the creator utilizing the RII technique by with the material administration is controlled.[9] The creator has applied the RMMM strategy for infrastructural projects for different asset management. [10] The task accentuates discovering the best shorted conceivable course for RMC vehicles to move the solid to the site from different RMC plants.[11] The creator has taken Akola taluka as the examination territory wherein utilizing geological information alongside land drafting maps are utilized for the improvement of open or empty land space for endless suburbia. [12] The creator has utilized the open patio territory for water assortment by with the water waste isn't captured with the Mumbai transportation frameworks and subsequently a turnpike is kept up.[13] The creator has worked out the development of the material and primary components utilizing Etabs and Staad to actualize the time and cost factors with the pre- and post-development of intercultural projects. [14] This investigation was done dependent on writing audit and a poll review that was acquired from contracting organizations, specialists and proprietors in Pune Strip. The examination explained that "late in modifying and supporting plan reports "was the most basic factor that impacts project length. The study demonstrates that "material - related components "involved the second position in significance”. The absence of materials on the lookout" and "postponement in material conveyance to the site" is likewise the main components influencing project duration. [15] According to the investigation by creator, cost overwhelm is a difficult which influences 90% of finished tasks on the planet. In this paper creator, embraced the work area methodological methodology which includes contrasting the reasons for material waste and those of cost invades from the writing to decide the conceivable relationship.[16] According to the aftereffect of examination paper, 96.88% and 81.81% of the reasons for cost overwhelm likewise because material waste at the pre-agreement and post-contract organizes individually. There is a 86.74% cover between the reasons for material waste and those of cost overwhelms at all phases of a project.[17] The investigation suggests that development project administrators, just as the development specialists, ought to empower the administration of material- squander causes, as it can possibly limit the reasons for cost invade for a project.[17] Creator has conveyed the examination included progressing building development projects inside Abuja, Nigeria, from which an example of 31 public and private activities was intentionally chosen. The creator utilized Pearson second connection and the engaging technique to dissect the gathered information and the outcomes uncovered a measurably critical connection between material waste and cost overrun.[18] The outcomes showed material waste to project-cost overwhelm goes from 1.96% to 8.01%, with a normal commitment of 4.0% to project-cost overruns.[18]
  • 3. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1175 In this paper, the creator contemplated five limited scope private development projects in Nasik where odds of waste age are more because of absence of appropriate administration. [19] The development material waste situation of every one of the 5 private, medium to little building locales discovered to be significant in cost-adequacy and necessities the executives. The increasing expense on development project emerging because of development material wastage which is in the middle of 5% to 10 % of task according to the examination and investigation by author. [19] In this investigation, the creator intends to set up connection between times invade and work profitability on building site in India. The information result show that deficient asset for the venture, lacking arranging before project departure, insufficient devices and gear and postponement in conveyance material are the rundown of the significant reasons for time invade while the utilization of wrong development strategy, deficient development material, and off base drawing particular are the key factor causing low work profitability building site. The huge negative relationship figured out between time invade and work profitability at building site. The creator closed by suggesting that the early arrangement of the venture chief could guarantee appropriate administration of both human and material assets that could ensure improved profitability and eventually save project from time overcome.[20] 3. AIM AND OBJECTIVE “The eventual aim of this research paper is, to systematically identify the various factors influence the cost and time overrun of Pune metro project”. 1. To study various factors causing delay of Pune metro Line I project. 2. To study various factors causing cost overrun of Pune metro Line I project. 4. METHODOLOGY Initially, the data will be collected from literature review and Pune metro line I project and a roadmap of research work will be prepared in form of various factors may influence the time and cost overrun of metro project and evaluate the factors by RII method. Figure No. 1: Research Methodology 5. DATA COLLECTION AND ANALYSIS 5.1. Survey a. Type of Survey: Close-ended Question and using Likert Scale. b. Participants A. Nature of Organization: In this study, the participants that is contractor, consultant and owner are 60%, 23% and 17% respectively. Figure No. 2: Types of Participants Nature of Organization B. Types of Projects handled by Participants: Figure No. 3: Type of Projects Handled by Participants
  • 4. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1176 C. Participants Designation: Figure No. 4: Participants Designation D. Participants Professional Trades: Figure No. 5: Participants Professional Trades 5.2. Relative Importance Index The process used in examining of data was aimed at forming the relative importance of the various factors that contribute to causes of delays in metro line construction project particularly in Pune Metro. The contribution of each of the factors to overall delays was examined and the ranking of the attributes in terms of their criticality as perceived by the respondents was done by use of Relative Importance Index (RII) which was computed using equation and the results of the analysis are presented in following section. Simply for understanding, formula can be written in the following way Where, N5 = Nos. of respondents for great impact N4 = Nos. of respondents for considerable impact N3 = Nos. of respondents for average impact N2 = Nos. of respondents for slight impact N1 = Nos. of respondents for least impact 5.3. Skewness and Kurtosis of Survey The summary of the collected data from survey is given below. In this datasheet, total sixty respondents have given their ratings on all thirty factors by using Likert’s scale of 5 points. The data has been collected in form of physical sheets and all the respondents are the competent persons to avoid error in result analysis. Table No. 1: Skewness and Kurtosis of Survey Sr. No Factors Skewness Kurtosis 1 Effects of subsurface and ground conditions 0.5 -0.7 2 Poor site management -0.6 -0.5 3 Poor site layout -0.3 -1.0 4 Delay of materials approved by a consultant 0.0 -0.8 5 Escalation of material prices 0.3 -0.7 6 Low Productivity level of labor -0.5 -0.8 7 Shortage of skilled workforce -0.1 0.9 8 Insufficient number of staffs -1.0 -1.1 9 Frequent change in Contractor 0.5 0.4 10 Low level of equipment operator skills 0.1 -0.9 11 Labor injuries on site 0.4 0.6 12 Insufficient number of Equipment 0.5 0.4 13 Shortage of good conditioned equipment at a site -0.1 -0.6 14 Inadequate contractor work experience -0.5 -0.7 15 Delay of material delivery to site 0.1 -0.7 16 Complexity of the project 0.5 0.4 17 Suspension of work by owner or contractor 0.8 -1.4 18 Poor communication and coordination by owner -0.4 -1.0 19 Poor communication& coordination by contractor 0.0 0.5 20 Slowness in decision making process by owner -1.0 0.8 21 Original contract duration is too short 0.3 -1.0
  • 5. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1177 22 Delay in Payment 0.1 0.9 23 Shortage of construction material at the site 0.3 1.0 24 Disputes between the parties regarding legal issues 0.5 -0.7 25 Changes in government regulation and laws -1.0 -0.1 26 National or Global Pandemic (Covid 19) -1.0 0.1 27 Ineffective planning & scheduling of project 0.2 -1.0 28 Ineffective planning and scheduling by Agency -0.6 -0.5 29 Land Acquisition -1.0 -0.7 30 Local issues -0.5 -0.7 First the data collected from the semi-structured survey, will be checked by Skewness and Kurtosis method of analysis to validate the collected data. Figure No. 6: Graphical Representation of Skewness Value of Survey Data Figure No. 7: Graphical Representation of Kurtosis Value of Survey Data 5.4. Analysis of Survey RII Technique is used in dissertation to determine the relative importance of the various causes of delays in railway project. The same method is going to be adopted in this study within various groups (i.e. contractors, consultants and clients). The five-point scale ranged from 1 (least impact) to 5 (great impact) is adopted and transformed to RII for each factor by using the formula specified in previous section. Table No. 2: Critical Causes of delay to railway project by RII Method Weighting given by each respondent ∑W A N RII 5 4 3 2 1 0 0 18 41 1 137 5 60 0.46 0 1 42 17 0 164 5 60 0.55 0 1 38 21 0 160 5 60 0.53 23 35 2 0 0 261 5 60 0.87 7 30 23 0 0 224 5 60 0.75
  • 6. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1178 0 1 40 19 0 162 5 60 0.54 0 7 44 9 0 178 5 60 0.59 0 0 43 17 0 163 5 60 0.54 0 0 14 44 2 132 5 60 0.44 2 33 25 0 0 217 5 60 0.72 0 0 13 44 3 130 5 60 0.43 0 0 14 44 2 132 5 60 0.44 0 15 34 11 0 184 5 60 0.61 0 1 41 18 0 163 5 60 0.54 1 28 30 1 0 209 5 60 0.70 0 0 14 44 2 132 5 60 0.44 0 19 41 0 0 199 5 60 0.66 0 25 25 10 0 195 5 60 0.65 0 8 42 10 0 178 5 60 0.59 0 1 42 16 1 163 5 60 0.54 0 11 28 21 0 170 5 60 0.57 0 10 44 6 0 184 5 60 0.61 0 11 45 4 0 187 5 60 0.62 0 18 41 1 0 197 5 60 0.66 0 40 19 1 0 219 5 60 0.73 0 38 20 2 0 216 5 60 0.72 0 12 28 20 0 172 5 60 0.57 0 1 42 17 0 164 5 60 0.55 0 39 9 12 0 207 5 60 0.69 0 0 43 17 0 163 5 60 0.54 Base on the ranking, the 10 most important causes of material management by RII were as follows table: Table No. 3: Rank of Factors Delaying Railway Project as per RII Rank Factors Delaying Railway Project 1 Land Acquisition 2 National or Global Pandemic (Covid 19) 3 Shortage of skilled workforce 4 Frequent change in Contractor 5 Local issues 6 Delay of material delivery to site 7 Shortage of construction material at the site 8 Inadequate contractor work experience 9 Suspension of work by owner or contractor 10 Ineffective planning & scheduling of project 6. CONCLUSION As per the ranking on the bases of RII value, it can be observed that the top three factors responsible for delay in Pune project are Land Acquisition, Covid 19 pandemic and Shortage of skilled workforce which clearly represent the importance of land acquisition role in infrastructure projects like metro projects and the scarcity of skilled workforce also plays a substantial role in delay of project. Even in top 10 factors there are two factors related to material management i.e. delay of material delivery to site and shortage of construction materials at the site, which clearly reflects the role played by material in terms of cost overrun and delay in Pune metro project. REFERENCE [1] Agopyan V., Souza, U. E. L., Paliari, J. C., and Andrade, A. C. (2018). Alternatives for reducing waste of materials in building sites: final report, EPUSP/FINEP/ITQC, in Portuguese. [2] Bossink, B. A. G., and Brouwers, H. J. H. (2018). “Construction waste: Quantification and source evaluation.” Journal Construction Engineering. and Management., ASCE. [3] Carlos Torres Formoso and Eduardo luis Isatto "Method for waste control in building Industry” University of California, Berkery, CA, USA, July 2019
  • 7. International Journal of Trend in Scientific Research and Development @ www.ijtsrd.com eISSN: 2456-6470 @ IJTSRD | Unique Paper ID – IJTSRD56256 | Volume – 7 | Issue – 2 | March-April 2023 Page 1179 [4] Chandler Ian E; "Material Management On Construction At Site" Longman Inc; 78 Edition [5] Gavilan, R. M., and Bernold, L. E. (2018). ‘‘Source evaluation of solid Waste in building construction.’’ J. Constr. Eng. Manage., 120(3) [6] Hong Kong Polytechnic and The Hong Kong Construction Association Ltd. (2020). Reduction of Construction Waste: Final Report, Hong Kong. [7] Indira Gandhi National Open University (IGNOU) " Materials Management" Part Ms-5, Unit-6 [8] Shri Rakesh j. Hingu (2010), “Wastage of building materials during construction of structure” Sardar Patel University, V.V. Nagar, Dissertation report, June 2010 [9] Skoyles, E.R., and Skoyles, J.R. (2016). Waste prevention on site. Mitchell Publishing Company Limited. London. [10] Vaid K.N. "Waste Control of Building Materials' NICMAR Course Materials In Construction Materials Management, Oct-2018. [11] C. T. Formoso, E. L. Isatto, and, E. H. Hirota, “Method for waste control in the building industry,” Proceedings of the Seventh Annual Conference of the International Group for Lean Construction, Berkeley, USA, 2019. [12] Y. Khairulzan, and A. B. Halim, “Eco-costing of construction waste,” Journal of Management of Environmental Quality: An International Journal, vol 17(1), pp. 6–19, 2016. [13] M. Osmani, J. Glass, and A.D.F. Price, “Architects perspectives on construction waste reduction by design,” Journal of Waste Management, vol. 28, pp. 1147–1158, 2014. [14] J. Y. Wang, X. P. Kang, and V. W. Y. Tam, “An investigation of construction wastes: an empirical study in Shenzhen,” Journal of Engineering, Design and Technology, vol. 6(3). pp. 227–236, 2017. [15] R. Ndihokubwayo, and T. Haupt, “Variation orders on construction projects: Value adding or waste,” International Journal of Construction Project Management, vol. 1(2), pp. 1– 17, 2019. [16] H. Yuan, “A model for evaluating the social performance of construction waste management,” Waste Management, vol. 32(6), pp. 1218–1228, 2012. [17] S. Nagapan, A. R. Ismail, and A. Ade, “Construction waste and related issues in Malaysia,” Diges FKAAS, Vol.1, pp. 15–20, 2012. [18] Department of Environment and Climate Change (DECC), “Cracking down on illegal dumping: Handbook for local government,” Sydney, Australia, pp. 7–15, February 2018. [19] C. S. Poon, A. T. W. Yu, S. W. Wong, and E. Cheung “Management of construction waste in public housing projects in Hong Kong,” Journal of Construction Management and Economics, vol. 22, pp. 675-689, 2014. [20] N. Yahaya, and I. Larsen, “Federalizing solid waste management in Peninsular Malaysia,” Proceeding of International Solid Waste Association (ISWA) World Congress, Singapore, 2018.