IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. VI (Mar - Apr. 2015), PP 15-21
www.iosrjournals.org
DOI: 10.9790/1684-12261521 www.iosrjournals.org 15 | Page
Study on Construction Sequence Delay for Road Infrastructure
Projects
Asish Ram1
, Dr. Pratheeba Paul2
1
(M.Tech, Department of Civil Engineering, Hindustan Institute of Technology and Science, Chennai, India)
2
(Professor, Department of Civil Engineering, Hindustan Institute of Technology and Science, Chennai, India)
Abstract:Due to the inherent risks and increasing complexity of modern infrastructure construction projects,
delays and cost overruns have become common facts in the construction industry. Delays can lead to many
negative effects such as lawsuits between owners and contractors, increased costs, loss of productivity and
revenue, and contract termination. This paper articulates to study about the delay causes and factors that
contribute to the construction sequence delay for the road infrastructure projects and how one can predict the
future completion date for the delayed project using earned value management. In this context, a literature
review conducted thoroughly to know about the causes and factors contributing to delays.From the intricate
analysis of the reviewed literatures, it showed that questionnaire survey is the best and reliable methodology to
gather the data about the causes and quantification of delay factors. The gathered data are analyzed through
Relative Importance Index (RII) and the delay causes are ranked as per their significance. To validate the
findings of questionnaire survey, a case study on road construction was considered and analyzed based on
earned value management (EVM).
Keywords: Delay Causes and factors, Earned Value Management (EVM), Literature Review, Questionnaire
Survey, Relative Importance Index (RII).
I. Introduction
“DELAY IS THE ENEMY OF PROGRESS” – Eliot Spitzer.
Delay is one of the biggest problems construction firms face. Delays can lead to many negative effects
such as lawsuits between owners and contractors, increased costs, loss of productivity and revenue, and contract
termination. The construction companies in many countries around the world experience significant delays. So
what is construction delay? Construction delay can be defined as time overrun or extension of time to complete
the project. It is a situation when the actual progress of a construction project is slower than the planned
schedule or late completion of the project. However, delay situations are complex in nature because multiple
delays can occur concurrently and because they can be caused by more than one party, or by none of the
principal parties. One delay may contribute to the formation of other delays. In complex and big projects having
many activities, delays are analyzed only based on the two major parameters i.e. time and cost because
recording each activity schedules is difficult. Since the delay in infrastructure projects affects the economy of
the country, it is important for the projects to be completed within the budgeted cost and time.
II. Importance Of The Study
The timely completion of road infrastructure projects is an important objective. A significant
annoyance to the public occurs when projects are not completed in a timely manner and when actual progress of
the construction work is longer than necessary, thereby prolonging the inconvenience and disrupted business
access. Economic & social welfare, and safety are all related to timely completion. In spite of the importance of
timely completion, construction delays remain a common occurrence. This paperaddresses the significant causes
and factors of delays in road infrastructure projects and how one can predict the completion date for the project
using earned value management.
III. Literature Review
Agata Czarnigowska (2008) studied on earned value method as a tool for project control that uses
information on cost, schedule and work performance to establish the current status of the project. By means of a
few simple rates, it allowed the manager to extrapolate current trends to predict their likely final effect. The
method based on a simplified model of a project, but proved to be useful in practice of cost control. It’s being
developed to account better for schedule and time aspects. The paper outlines the basic principles of the method
and its recent extension, the Earned Schedule method, and, with help of a few examples, investigates into
assumptions that affect their diagnostic and predictive accuracy.
Hamzah.N et al (2011)constructed a theoretical framework that causes construction delay by doing a
literature review from previous international journal papers and future study about the causes of delay. The
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 16 | Page
study concluded that improvement of delays are not only limited to technical factors, but also factors in project
management perspective, both from the aspect of processes involve and the influence of human attitudes,
mentality, skills and behavior. The theoretical framework is categorized into: (i) Excusable delay - caused by
owner/consultant; (ii) Concurrent delay – caused by the third party @ acts of god: and (iii) Non-Excusable
delay.
Remon Fayek Aziz (2013)ranked the delay factorsin the construction projects after Egyptian
revolution, especially after 25/1/2011 (Egyptian revolution. The research methodology was based on
questionnaire survey. Ninety-nine factors are identified, that are grouped into 9 major categories: (i) Consultant
Related; (ii) Contractor Related; (iii) Design Related; (iv) Equipment Related; (v) External Related; (vi) Labors
Related; (vii) Materials Related; (viii) Owner Related; and (ix) Project Related. Recommendations to minimize
the delays are too being laid down.
Enas Fathi Taher and Pandey (2013)studied delay in project planning and design stage by identifying
and ranking delay causes in the planning & design phases. A structured questionnaire was sent to engineers at
the A/E companies for public construction projects in India. Based on ninety-five valid responses, study
identified the delay causes and analyzed the importance and frequency of delays using relative importance
index. A third-round Delphi form survey was applied as analysis techniques. The Analytical results revealed that
“changes in client’s requirement” are main cause of delay in both planning & design phases. The finding
became good justification for many public clients who usually change their requirement during planning and
design stage.
Patil et al (2013)researched on the causes of delay in Indian transportation infrastructure projects to
identify the causes and to test the importance of causes of delay between parties involved in the projects and
study of difference between their perceptions. The literatures were reviewed thoroughly and a questionnaire
containing sixty-four possible causes was formed. The results revealed that the problem of construction delays
in transportation infrastructure projects is frequent and notable. The top five important causes of construction
delays in transportation infrastructure projects are mainly: (i) Land Acquisition; (ii) Environmental Impact of
the project; (iii) Financial closure; (iv) Change orders by the client; and (v) Poor site management and
supervision by contractor. The study also revealed that consultant as a mediator has less responsibility in
construction delays.
Ravisankar et al (2014)studied on the quantification of delay factors in construction industry. The
objective of the study was to identify major causes of construction delay and their effects. The scope of the
research mainly focused on literature review and a questionnaire survey. Using the SPSS software, survey data’s
are analyzed to find out the major causes of delay. The mean score value and ranking are assigned for
corresponding delay factors. The overall results indicated top five most important causes are: (i) Shortage of
unskilled/skilled labors; (ii) Design changes by owner or his agent during construction; (iii) Fluctuations of
prices; (iv) High waiting time for availability of work teams; and (v) Rework due to errors.
Ashwin Arun Salunkhe and Rahul S. Patil (2014)logically explored the delay factors of project and
how it can be avoided or controlled. With the help of detailed literature review and interview, delay factors are
grouped into seven categories, which give the parameters that could have direct effect on success of projects.
The seven categories of critical delay factors are: (i) Owner related; (ii) Consultant related; (iii) Contractor
related; (iv) Material related; (v) Labor & Equipment related; (vi) Project related; and (vii) External related.
Amrita Jhawar and Purnima Bajpai (2014)investigated the cause of construction delays and found out
critical relationship between various critical delay parameters. The top ten factors having highest risk priority
number (RPN) are identified from FMEA and structured into comprehensive systematic model portraying this
complex issues which identifies crux of the problem. The major drivers for delay are: (i) Revision in design; (ii)
Delay in approvals; and (iii) Bureaucracy and organizational gaps which ultimately influence the delay in land
acquisition and environment clearances. The study revealed that stringent departmentization and bureaucratic
environment should be minimized so as to improve the decision-making policies.
Khaled Ahmed Ali Alnaas et al (2014)proposed a practical approach that enables the contractor toprove
the delays & build a well-supported claim for extension of time based on combination between theoretical
information and practical experiences. The approach consist of (i) Preparing baseline programme; (ii) Proper
programme updates; (iii) Accurate programme revisions; (iv) Defining and introducing the delays to the
programme updates; (v) identifying the concurrent delays and splitting between the contractor and employer
delays; and (vi) Preparing the evidences of delay. The contractor is requested to submit EoT claim whenever he
believes that the delay event will delay the project completion date and the delay event is excusable and
compensable.
IV. Objective Of The Study
To find and rank the top ten causes of delay in road infrastructure projects based on their significance.
To validate the significant causes of delay through a case study.
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 17 | Page
V. Methodology For The Study
Questionnaire survey is adopted as a methodology in accordance with the fulfillment of the objective of
the study. The questionnaire believed to be the best techniques for gathering the required data as it can be
analyzed scientifically and objectively.
VI. Questionnaire Survey
6.1 Questionnaire Design
Based on the literature review, a closed ended questionnaire was designed considering the objective of
the study. The questionnaire consists of thee parts: The part A consist of general information of the respondent
while part B consist of 9 delay related factors consisting a of total 101 delay causes where respondent have to
rate each cause as per their significance and part C consist of respondent own opinion.
6.2 Rating Criteria
To identify the degree to how much respondents agree or disagree on the severity of these causes based on their
experience and knowledge, a 5-point Likert Scale is designed.
The ratings of scale from 1 to 5 are:
1 - Not Significant: 0% delay contributing factors;
2 - Slightly Significant: < 35 % delay contributing factors;
3 - Moderately Significant: 35 – 60% delay contributing factors;
4 - Very Significant: 60 – 75 % delay contributing factors; and
5 - Extremely Significant: > 75 % delay contributing factors.
The respondent have to rate a particular cause based upon the above scale.Thereasons for using Likert
Scale are: it is most universal method and is easily understood; response is easily quantifiable; makes question
answering easier on the respondent; quick, efficient and inexpensive method; and high versatility.
6.3 Data Gathering
The questionnaire believed to be the best technique for gathering the required data. As far as possible,
the responses have been taken from respondents of designation who are competent of serving the best for
purpose and answering the survey in the most appropriate way. The questionnaire was distributed to the
respondents by visiting their firms personally. Questionnaire from 43 respondents are analyzed. The respondents
experience are depicted in table 1.
Table 2: Respondent Experience
6.4 Data Analysis
Relative Importance Index (RII) is adopted for ranking the delay causes as per their significance as it is
simple and most widely used for finding the significant factors and ranking of the same. It is a regression based
statistical tools.The formulae used for calculating RII is:
RII = Σ W ⁄ (A × N); (1)
where, 0 ≤ RII ≤ 1
Here, W = Weight given to each cause by respondent, ranges from 1 to 5;
A = Highest weight i.e. =5 (in this case); and
N = Total number of respondent.
VII. Findings
The top ten significant causes of construction delays regarding road infrastructure projects are: (i)
Delay due to land acquisition; (ii) Environmental issues; (iii) Delay in progress payment; (iv) Ineffective project
planning and scheduling; (v) Poor site management and supervision; (vi) Rework due to errors; (vii) Delay in
approving design documents; (viii) Poor coordination between owner and other parties; (ix) Financial closure;
and (x) Change order by clients. Table 2 shows the ranking of top ten significant causes of delay as per delay
related factor; type of delay and RII value.
S. No. Respondents Experience Percentage
1 0 - 5 Years 7%
2 5 - 10 Years 14%
3 10 - 15 Years 23.20%
4 15 - 20 Years 18.60%
5 > 20 Years 37.20%
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 18 | Page
Table 2:Top Ten Significant Delay Causes
S. No. Delay Causes Related Factor RII Value Type of Delay
1 Delay due to land acquisition Owner 0.851 Excusable
2 Environmental Issues External 0.841 Excusable
3 Delay in progress payment Owner 0.837 Excusable
4 Ineffective project planning and scheduling Contractor 0.823 Non-Excusable
5 Poor site management and supervision Contractor 0.813 Non-Excusable
6 Rework due to errors Contractor 0.809 Non-Excusable
7 Delay in approving design documents Owner 0.795 Excusable
8 Poor coordination between owner and the other
parties
Owner 0.795 Excusable
9 Financial Closure Owner 0.790 Excusable
10 Change order Owner 0.781 Excusable
All the delay causes will affect the progress of the project as per their significance and occurrence. As
per the parties involved in the project, consultant as a mediator has a lesser role in construction delay. Excusable
delay can be compensated as per the contract terms and condition and the extension of time (EoT) can be
granted for the projects. To validate the findings of questionnaire survey, a case study on road construction was
considered and analyzed based on earned value management (EVM).
VIII. Case Study
The case study on Chennai – Ennore Port Road Connectivity Project was done to validate the questionnaire
survey. The project involves adequate improvement on four major roads connecting the Chennai – Ennore port
involving total of 30.1 kilometers. The contract value was Rs. 258.78 Crores and the actual duration of the
project was 24 months. The project commences on 03-06-2011 and the completion period was 02-06-2013.
Special Purpose Vehicle (SPV) was formed comprising of NHAI (National Highway Authority of India),
Chennai Port Trust, Ennore Port Limited and Govt. of Tamil Nadu for looking after and funding the projects.
But only 55.99% of work was accomplished in the contract period with 55.87% of total budgeted amount.
Special Purpose Vehicle (SPV) was formed comprising of NHAI (National Highway Authority of India),
Chennai Port Trust, Ennore Port Limited and Govt. of Tamil Nadu for looking after and funding the projects.
The project was given four extension of time by NHAI itself and the fifth extension was recommended by the
contractor. Even after the fifth extension of time (EoT) being granted, the project was just 91% completed till
Jan 2015.Since it’s a vast project consisting of four major roads, the works was carried out parallely.
The major causes and factors that delay the project to this extent are found out to be: (i) The delay and
litigation in land acquisition process; (ii) Delay due to non-shifting of Project Affected Families (PAF’s), around
540 families as well as fishing stalls in front of gate no. 1 of Chennai port, from the allignment of road in two
small stretches by Govt. of Tamil Nadu, for which Chennai Port and NHAI is pursuing for early completion;
(iii) Even the obstructions like encroachment, temples, sewage pipes affected the progress of the project. (iv)
Sea erosion is one of the environmental factors that too causes the delay in this particular project in one of the
four roads that runs along the sea coast; and (v) Delay occurred also due to the several bottlenecks including
non-cooperation from the Tamil Nadu govt. with NHAI.
As per Feb 2105, a meeting was conducted involving all the parties involved in the project to discuss
about the faster completion of the project as the project got halted due to resettlement of fishing hamlet in the
1.6 Km stretch. Once the hamlet being resettled, the project can be executed further for completion as only work
on this 1.6 km stretch is being pending.
The earned value management is applied on the project at the end of original two-year contract period.
The reasons for using EVM is because it relate time phase budgets to specific contract task or statements of
work, provide the basis to capture work progress assessments against the base line plan and provide valid,
timely, and auditable data/information for proactive management action. After applying the EVM, the following
parameters are being found out:
(a) Earned Value (EV): The earned value was found to be 144.89 as compare to the actual cost (AC) of Rs.
144.59 Crores.
EV = (Actual % complete/100)*Budget At Completion (BAC) (2)
Here, BAC is Rs. 258.78 Crores.
(b) The project has unfavorable schedule variance (SV) of -113.89 and schedule variance % of -44.01 %. So,
the project was 44.01% behind schedule.
The project has a cost variance (CV) of 0.3 and cost variance % of 0.21 %. So, the project is 0.21 % under
budget for the work performed.
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 19 | Page
SV = EV – PV; SV% = (SV/PV)*100 (3)
CV = EV – AC; CV% = (CV/EV)*100 (4)
Here, PV is the planned value of the project.
Fig. 1: Schedule Variance %
Fig. 2: Cost Variance%
(c) In the two-year contract period, Cost Performance Index (CPI) value is 1. This implies that for every project
rupee spent, 1 rupee is in earned value is accomplished.
And in the same two-year contract period, Schedule Performance Index (SPI) value is 0.56.This implies that for
every Rupee of work the project had planned to accomplish at this point in time, 0.56 rupee worth of work was
actually done. As the cost ratio (CR) is 0.56, the overall performance is POOR.
CPI = EV/AC (5)
SPI = EV/PV (6)
CR = SPI x CPI (7)
Fig. 3: SPI, CPI and CR
VARIANCE
%
-44.01
-50
-40
-30
-20
-10
0
10
20
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
SCHEDULE VARIANCE %
SCHEDULE VARIANCE %
0.21
-1
-0.5
0
0.5
1
1.5
2
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
COST VARIANCE %
COST VARIANCE %
VARIANCE
%
0.56
1
0.56
0
0.2
0.4
0.6
0.8
1
1.2
1.4
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
SPI
CPI
CR
SCHEDULE PERFORMANCE INDEX (SPI); COST
PERFORMANCE INDEX (CPI); and COST RATIO (CR)
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 20 | Page
(d) Additional Time to Complete: The additional time to complete the project was found to be 18.87 months i.e.
approximately 19 months.
Additional Time to Complete = EACt – 24 (Duration) (8)
Here, EACt is Estimate At Completion time and is given by:
EACt = (BAC/SPI)/(BAC/Duration) (9)
Where, duration is 24 months.
Fig. 4: Additional Time To Complete
(e) Estimate At Completion (EAC): It is manager’s projection of total cost of the project at completion. The
EAC was found out to be Rs. 258.78; same as that of BAC as CPI is 1.
EAC = BAC/CPI (10)
(f) Variance At Completion (VAC): VAC was found out to be zero.
VAC = BAC – EAC (11)
(g) To Complete Performance Index (TCPI): The TCPI for the project was 1. TCPI greater than 1 implies
performance must be increased and less than or equal to 1 implies that it should be maintained. Performance in
terms of cost.
TCPI = (BAC – EV)/(BAC – AC) (12)
IX. Conclusion
Most of the government initiated infrastructure projects are delayed and get finished years after there
scheduled completion. From the intricate analysis of the questionnaire survey and the case study, it has been
found that delay in land acquisition is the major cause for the delay in the road infrastructure projects. The delay
in land acquisition is an owner or client related delay factor that is an excusable type of delay. The two major
parameters that determine the success of the project is overall project cost and time. In the case study project, it
has been found that there is an unfavourable schedule variance while the cost variance is favorable. By looking
through all the parameters of the earned value management that is applied in the case study, it has been found
that the root cause for the delay in the road infrastructure projects are delay in land acquisition which is an
owner/client related factor and excusable type of delay. So, the contractor can claim for extension of time (EoT)
if the delay is excusable. Since for executing any road projects, the client should provide the necessary land
acquisition and sort out any other disputes related to land acquisition before the beginning of the project. Even
the removing of all encroachment in the project area i.e. in the land acquired for the project should be sorted out
well ahead to avoid delays. There should not be any bottlenecks between the state and the central government
for any infrastructure projects. Since infrastructure brings economy to the country, any delays have to be
avoided by clients and the contractors. In case of any delays, EVM is found to be helpful in finding out the
probable completion time for the projects.
18.87
-5
0
5
10
15
20
25
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M13
M14
M15
M16
M17
M18
M19
M20
M21
M22
M23
M24
ADDITIONAL TIME TO COMPLETE
ADDITIONAL TIME TO COMPLETE
MONTHS
ADDITIONAL TIME TO COMPLETE
Study on Construction Sequence Delay for Road Infrastructure Projects
DOI: 10.9790/1684-12261521 www.iosrjournals.org 21 | Page
References
[1]. AgataCzarnigowska, Earned value method as a tool for project control, Budownictwo i Architekutra, 3, 2008, 15-32.
[2]. N. Hamzah, M.A. Khoiry, I. Arshad, N.M. Tawil and A.I. Che Ani, Cause of construction delay – Theoretical framework, Procedia
Engineering, 20, 2011, 490-495.
[3]. RemonFayak Aziz, Ranking of delay factors in construction projects after Egyptian revolution, Alexandria Engineering Journal, 52,
2013, 387-406.
[4]. EnasFathi Taher and R.K. Pandey, Study of delay in project planning and design stages of civil engineering projects, international
Journal of Engineering and Advanced Technology (IJEAT), 2(3), 2013, 456-461.
[5]. S.K. Patil, A.K. Gupta, D.B. Desai, A.S. Sajane, Causes of delay in Indian transportation infrastructure projects, International
Journal of Research in Engineering and Technology (IJRET), 2(11), 2013, 71-80.
[6]. K.L. Ravisankar, Dr. S. Anand Kumar, V. Krishnamoorthy, Study on the quantification of delay factors in construction industry,
International Journal of Emerging Technology and Advanced Engineering (IJETAE), 4(1), 2014, 105-113.
[7]. AshwinArunSalunkhe and Rahul S. Patil, Identification of critical construction delay factors, International Journal of Latest Trends
in Enginnering and Technology (IJLTET), 3(4), 2014, 256-261.
[8]. Amrita Jhawar and Purnima Bajpai, Applying FMEA and ISM technique to identify factors causing delay in road construction
projects, International Journal of Applied Engineering Research, 9(5), 2014, 517-524.
[9]. Khaled Ahmed Ali Alnaas, Ayman Hussein Hosny Khalil, Gamal Eldin Nassar, Guidelines for preparing comprehensive extension
of time (EoT) claim, Housing and Building National Research Centre (HBRC) Journal, 2014, 1-9.

More Related Content

What's hot

A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Associate Professor in VSB Coimbatore
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 

What's hot (20)

A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
20320140503023
2032014050302320320140503023
20320140503023
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 

Viewers also liked

Comparative Study on Self Confidence among University Level Football, Kho-Kho...
Comparative Study on Self Confidence among University Level Football, Kho-Kho...Comparative Study on Self Confidence among University Level Football, Kho-Kho...
Comparative Study on Self Confidence among University Level Football, Kho-Kho...IOSR Journals
 
H012645760.iosr jmce p2
H012645760.iosr jmce p2H012645760.iosr jmce p2
H012645760.iosr jmce p2IOSR Journals
 

Viewers also liked (9)

K1303058689
K1303058689K1303058689
K1303058689
 
J010515361
J010515361J010515361
J010515361
 
H012466575
H012466575H012466575
H012466575
 
P01052131135
P01052131135P01052131135
P01052131135
 
G017133033
G017133033G017133033
G017133033
 
M017127578
M017127578M017127578
M017127578
 
Comparative Study on Self Confidence among University Level Football, Kho-Kho...
Comparative Study on Self Confidence among University Level Football, Kho-Kho...Comparative Study on Self Confidence among University Level Football, Kho-Kho...
Comparative Study on Self Confidence among University Level Football, Kho-Kho...
 
H012645760.iosr jmce p2
H012645760.iosr jmce p2H012645760.iosr jmce p2
H012645760.iosr jmce p2
 
La Silvicutura de la guadua en países latinoamericanos"
La Silvicutura de la guadua en países latinoamericanos" La Silvicutura de la guadua en países latinoamericanos"
La Silvicutura de la guadua en países latinoamericanos"
 

Similar to D012261521

IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainIJRES Journal
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docxEbrahimJemal4
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction worksvivatechijri
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxsaeedahmed433704
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple ProjectsIRJET Journal
 

Similar to D012261521 (20)

IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
IRJET- 	  Review: Factors Affecting Scheduling of Multiple ProjectsIRJET- 	  Review: Factors Affecting Scheduling of Multiple Projects
IRJET- Review: Factors Affecting Scheduling of Multiple Projects
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdfChristopherTHyatt
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 

Recently uploaded (20)

Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 

D012261521

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. VI (Mar - Apr. 2015), PP 15-21 www.iosrjournals.org DOI: 10.9790/1684-12261521 www.iosrjournals.org 15 | Page Study on Construction Sequence Delay for Road Infrastructure Projects Asish Ram1 , Dr. Pratheeba Paul2 1 (M.Tech, Department of Civil Engineering, Hindustan Institute of Technology and Science, Chennai, India) 2 (Professor, Department of Civil Engineering, Hindustan Institute of Technology and Science, Chennai, India) Abstract:Due to the inherent risks and increasing complexity of modern infrastructure construction projects, delays and cost overruns have become common facts in the construction industry. Delays can lead to many negative effects such as lawsuits between owners and contractors, increased costs, loss of productivity and revenue, and contract termination. This paper articulates to study about the delay causes and factors that contribute to the construction sequence delay for the road infrastructure projects and how one can predict the future completion date for the delayed project using earned value management. In this context, a literature review conducted thoroughly to know about the causes and factors contributing to delays.From the intricate analysis of the reviewed literatures, it showed that questionnaire survey is the best and reliable methodology to gather the data about the causes and quantification of delay factors. The gathered data are analyzed through Relative Importance Index (RII) and the delay causes are ranked as per their significance. To validate the findings of questionnaire survey, a case study on road construction was considered and analyzed based on earned value management (EVM). Keywords: Delay Causes and factors, Earned Value Management (EVM), Literature Review, Questionnaire Survey, Relative Importance Index (RII). I. Introduction “DELAY IS THE ENEMY OF PROGRESS” – Eliot Spitzer. Delay is one of the biggest problems construction firms face. Delays can lead to many negative effects such as lawsuits between owners and contractors, increased costs, loss of productivity and revenue, and contract termination. The construction companies in many countries around the world experience significant delays. So what is construction delay? Construction delay can be defined as time overrun or extension of time to complete the project. It is a situation when the actual progress of a construction project is slower than the planned schedule or late completion of the project. However, delay situations are complex in nature because multiple delays can occur concurrently and because they can be caused by more than one party, or by none of the principal parties. One delay may contribute to the formation of other delays. In complex and big projects having many activities, delays are analyzed only based on the two major parameters i.e. time and cost because recording each activity schedules is difficult. Since the delay in infrastructure projects affects the economy of the country, it is important for the projects to be completed within the budgeted cost and time. II. Importance Of The Study The timely completion of road infrastructure projects is an important objective. A significant annoyance to the public occurs when projects are not completed in a timely manner and when actual progress of the construction work is longer than necessary, thereby prolonging the inconvenience and disrupted business access. Economic & social welfare, and safety are all related to timely completion. In spite of the importance of timely completion, construction delays remain a common occurrence. This paperaddresses the significant causes and factors of delays in road infrastructure projects and how one can predict the completion date for the project using earned value management. III. Literature Review Agata Czarnigowska (2008) studied on earned value method as a tool for project control that uses information on cost, schedule and work performance to establish the current status of the project. By means of a few simple rates, it allowed the manager to extrapolate current trends to predict their likely final effect. The method based on a simplified model of a project, but proved to be useful in practice of cost control. It’s being developed to account better for schedule and time aspects. The paper outlines the basic principles of the method and its recent extension, the Earned Schedule method, and, with help of a few examples, investigates into assumptions that affect their diagnostic and predictive accuracy. Hamzah.N et al (2011)constructed a theoretical framework that causes construction delay by doing a literature review from previous international journal papers and future study about the causes of delay. The
  • 2. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 16 | Page study concluded that improvement of delays are not only limited to technical factors, but also factors in project management perspective, both from the aspect of processes involve and the influence of human attitudes, mentality, skills and behavior. The theoretical framework is categorized into: (i) Excusable delay - caused by owner/consultant; (ii) Concurrent delay – caused by the third party @ acts of god: and (iii) Non-Excusable delay. Remon Fayek Aziz (2013)ranked the delay factorsin the construction projects after Egyptian revolution, especially after 25/1/2011 (Egyptian revolution. The research methodology was based on questionnaire survey. Ninety-nine factors are identified, that are grouped into 9 major categories: (i) Consultant Related; (ii) Contractor Related; (iii) Design Related; (iv) Equipment Related; (v) External Related; (vi) Labors Related; (vii) Materials Related; (viii) Owner Related; and (ix) Project Related. Recommendations to minimize the delays are too being laid down. Enas Fathi Taher and Pandey (2013)studied delay in project planning and design stage by identifying and ranking delay causes in the planning & design phases. A structured questionnaire was sent to engineers at the A/E companies for public construction projects in India. Based on ninety-five valid responses, study identified the delay causes and analyzed the importance and frequency of delays using relative importance index. A third-round Delphi form survey was applied as analysis techniques. The Analytical results revealed that “changes in client’s requirement” are main cause of delay in both planning & design phases. The finding became good justification for many public clients who usually change their requirement during planning and design stage. Patil et al (2013)researched on the causes of delay in Indian transportation infrastructure projects to identify the causes and to test the importance of causes of delay between parties involved in the projects and study of difference between their perceptions. The literatures were reviewed thoroughly and a questionnaire containing sixty-four possible causes was formed. The results revealed that the problem of construction delays in transportation infrastructure projects is frequent and notable. The top five important causes of construction delays in transportation infrastructure projects are mainly: (i) Land Acquisition; (ii) Environmental Impact of the project; (iii) Financial closure; (iv) Change orders by the client; and (v) Poor site management and supervision by contractor. The study also revealed that consultant as a mediator has less responsibility in construction delays. Ravisankar et al (2014)studied on the quantification of delay factors in construction industry. The objective of the study was to identify major causes of construction delay and their effects. The scope of the research mainly focused on literature review and a questionnaire survey. Using the SPSS software, survey data’s are analyzed to find out the major causes of delay. The mean score value and ranking are assigned for corresponding delay factors. The overall results indicated top five most important causes are: (i) Shortage of unskilled/skilled labors; (ii) Design changes by owner or his agent during construction; (iii) Fluctuations of prices; (iv) High waiting time for availability of work teams; and (v) Rework due to errors. Ashwin Arun Salunkhe and Rahul S. Patil (2014)logically explored the delay factors of project and how it can be avoided or controlled. With the help of detailed literature review and interview, delay factors are grouped into seven categories, which give the parameters that could have direct effect on success of projects. The seven categories of critical delay factors are: (i) Owner related; (ii) Consultant related; (iii) Contractor related; (iv) Material related; (v) Labor & Equipment related; (vi) Project related; and (vii) External related. Amrita Jhawar and Purnima Bajpai (2014)investigated the cause of construction delays and found out critical relationship between various critical delay parameters. The top ten factors having highest risk priority number (RPN) are identified from FMEA and structured into comprehensive systematic model portraying this complex issues which identifies crux of the problem. The major drivers for delay are: (i) Revision in design; (ii) Delay in approvals; and (iii) Bureaucracy and organizational gaps which ultimately influence the delay in land acquisition and environment clearances. The study revealed that stringent departmentization and bureaucratic environment should be minimized so as to improve the decision-making policies. Khaled Ahmed Ali Alnaas et al (2014)proposed a practical approach that enables the contractor toprove the delays & build a well-supported claim for extension of time based on combination between theoretical information and practical experiences. The approach consist of (i) Preparing baseline programme; (ii) Proper programme updates; (iii) Accurate programme revisions; (iv) Defining and introducing the delays to the programme updates; (v) identifying the concurrent delays and splitting between the contractor and employer delays; and (vi) Preparing the evidences of delay. The contractor is requested to submit EoT claim whenever he believes that the delay event will delay the project completion date and the delay event is excusable and compensable. IV. Objective Of The Study To find and rank the top ten causes of delay in road infrastructure projects based on their significance. To validate the significant causes of delay through a case study.
  • 3. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 17 | Page V. Methodology For The Study Questionnaire survey is adopted as a methodology in accordance with the fulfillment of the objective of the study. The questionnaire believed to be the best techniques for gathering the required data as it can be analyzed scientifically and objectively. VI. Questionnaire Survey 6.1 Questionnaire Design Based on the literature review, a closed ended questionnaire was designed considering the objective of the study. The questionnaire consists of thee parts: The part A consist of general information of the respondent while part B consist of 9 delay related factors consisting a of total 101 delay causes where respondent have to rate each cause as per their significance and part C consist of respondent own opinion. 6.2 Rating Criteria To identify the degree to how much respondents agree or disagree on the severity of these causes based on their experience and knowledge, a 5-point Likert Scale is designed. The ratings of scale from 1 to 5 are: 1 - Not Significant: 0% delay contributing factors; 2 - Slightly Significant: < 35 % delay contributing factors; 3 - Moderately Significant: 35 – 60% delay contributing factors; 4 - Very Significant: 60 – 75 % delay contributing factors; and 5 - Extremely Significant: > 75 % delay contributing factors. The respondent have to rate a particular cause based upon the above scale.Thereasons for using Likert Scale are: it is most universal method and is easily understood; response is easily quantifiable; makes question answering easier on the respondent; quick, efficient and inexpensive method; and high versatility. 6.3 Data Gathering The questionnaire believed to be the best technique for gathering the required data. As far as possible, the responses have been taken from respondents of designation who are competent of serving the best for purpose and answering the survey in the most appropriate way. The questionnaire was distributed to the respondents by visiting their firms personally. Questionnaire from 43 respondents are analyzed. The respondents experience are depicted in table 1. Table 2: Respondent Experience 6.4 Data Analysis Relative Importance Index (RII) is adopted for ranking the delay causes as per their significance as it is simple and most widely used for finding the significant factors and ranking of the same. It is a regression based statistical tools.The formulae used for calculating RII is: RII = Σ W ⁄ (A × N); (1) where, 0 ≤ RII ≤ 1 Here, W = Weight given to each cause by respondent, ranges from 1 to 5; A = Highest weight i.e. =5 (in this case); and N = Total number of respondent. VII. Findings The top ten significant causes of construction delays regarding road infrastructure projects are: (i) Delay due to land acquisition; (ii) Environmental issues; (iii) Delay in progress payment; (iv) Ineffective project planning and scheduling; (v) Poor site management and supervision; (vi) Rework due to errors; (vii) Delay in approving design documents; (viii) Poor coordination between owner and other parties; (ix) Financial closure; and (x) Change order by clients. Table 2 shows the ranking of top ten significant causes of delay as per delay related factor; type of delay and RII value. S. No. Respondents Experience Percentage 1 0 - 5 Years 7% 2 5 - 10 Years 14% 3 10 - 15 Years 23.20% 4 15 - 20 Years 18.60% 5 > 20 Years 37.20%
  • 4. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 18 | Page Table 2:Top Ten Significant Delay Causes S. No. Delay Causes Related Factor RII Value Type of Delay 1 Delay due to land acquisition Owner 0.851 Excusable 2 Environmental Issues External 0.841 Excusable 3 Delay in progress payment Owner 0.837 Excusable 4 Ineffective project planning and scheduling Contractor 0.823 Non-Excusable 5 Poor site management and supervision Contractor 0.813 Non-Excusable 6 Rework due to errors Contractor 0.809 Non-Excusable 7 Delay in approving design documents Owner 0.795 Excusable 8 Poor coordination between owner and the other parties Owner 0.795 Excusable 9 Financial Closure Owner 0.790 Excusable 10 Change order Owner 0.781 Excusable All the delay causes will affect the progress of the project as per their significance and occurrence. As per the parties involved in the project, consultant as a mediator has a lesser role in construction delay. Excusable delay can be compensated as per the contract terms and condition and the extension of time (EoT) can be granted for the projects. To validate the findings of questionnaire survey, a case study on road construction was considered and analyzed based on earned value management (EVM). VIII. Case Study The case study on Chennai – Ennore Port Road Connectivity Project was done to validate the questionnaire survey. The project involves adequate improvement on four major roads connecting the Chennai – Ennore port involving total of 30.1 kilometers. The contract value was Rs. 258.78 Crores and the actual duration of the project was 24 months. The project commences on 03-06-2011 and the completion period was 02-06-2013. Special Purpose Vehicle (SPV) was formed comprising of NHAI (National Highway Authority of India), Chennai Port Trust, Ennore Port Limited and Govt. of Tamil Nadu for looking after and funding the projects. But only 55.99% of work was accomplished in the contract period with 55.87% of total budgeted amount. Special Purpose Vehicle (SPV) was formed comprising of NHAI (National Highway Authority of India), Chennai Port Trust, Ennore Port Limited and Govt. of Tamil Nadu for looking after and funding the projects. The project was given four extension of time by NHAI itself and the fifth extension was recommended by the contractor. Even after the fifth extension of time (EoT) being granted, the project was just 91% completed till Jan 2015.Since it’s a vast project consisting of four major roads, the works was carried out parallely. The major causes and factors that delay the project to this extent are found out to be: (i) The delay and litigation in land acquisition process; (ii) Delay due to non-shifting of Project Affected Families (PAF’s), around 540 families as well as fishing stalls in front of gate no. 1 of Chennai port, from the allignment of road in two small stretches by Govt. of Tamil Nadu, for which Chennai Port and NHAI is pursuing for early completion; (iii) Even the obstructions like encroachment, temples, sewage pipes affected the progress of the project. (iv) Sea erosion is one of the environmental factors that too causes the delay in this particular project in one of the four roads that runs along the sea coast; and (v) Delay occurred also due to the several bottlenecks including non-cooperation from the Tamil Nadu govt. with NHAI. As per Feb 2105, a meeting was conducted involving all the parties involved in the project to discuss about the faster completion of the project as the project got halted due to resettlement of fishing hamlet in the 1.6 Km stretch. Once the hamlet being resettled, the project can be executed further for completion as only work on this 1.6 km stretch is being pending. The earned value management is applied on the project at the end of original two-year contract period. The reasons for using EVM is because it relate time phase budgets to specific contract task or statements of work, provide the basis to capture work progress assessments against the base line plan and provide valid, timely, and auditable data/information for proactive management action. After applying the EVM, the following parameters are being found out: (a) Earned Value (EV): The earned value was found to be 144.89 as compare to the actual cost (AC) of Rs. 144.59 Crores. EV = (Actual % complete/100)*Budget At Completion (BAC) (2) Here, BAC is Rs. 258.78 Crores. (b) The project has unfavorable schedule variance (SV) of -113.89 and schedule variance % of -44.01 %. So, the project was 44.01% behind schedule. The project has a cost variance (CV) of 0.3 and cost variance % of 0.21 %. So, the project is 0.21 % under budget for the work performed.
  • 5. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 19 | Page SV = EV – PV; SV% = (SV/PV)*100 (3) CV = EV – AC; CV% = (CV/EV)*100 (4) Here, PV is the planned value of the project. Fig. 1: Schedule Variance % Fig. 2: Cost Variance% (c) In the two-year contract period, Cost Performance Index (CPI) value is 1. This implies that for every project rupee spent, 1 rupee is in earned value is accomplished. And in the same two-year contract period, Schedule Performance Index (SPI) value is 0.56.This implies that for every Rupee of work the project had planned to accomplish at this point in time, 0.56 rupee worth of work was actually done. As the cost ratio (CR) is 0.56, the overall performance is POOR. CPI = EV/AC (5) SPI = EV/PV (6) CR = SPI x CPI (7) Fig. 3: SPI, CPI and CR VARIANCE % -44.01 -50 -40 -30 -20 -10 0 10 20 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 SCHEDULE VARIANCE % SCHEDULE VARIANCE % 0.21 -1 -0.5 0 0.5 1 1.5 2 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 COST VARIANCE % COST VARIANCE % VARIANCE % 0.56 1 0.56 0 0.2 0.4 0.6 0.8 1 1.2 1.4 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 SPI CPI CR SCHEDULE PERFORMANCE INDEX (SPI); COST PERFORMANCE INDEX (CPI); and COST RATIO (CR)
  • 6. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 20 | Page (d) Additional Time to Complete: The additional time to complete the project was found to be 18.87 months i.e. approximately 19 months. Additional Time to Complete = EACt – 24 (Duration) (8) Here, EACt is Estimate At Completion time and is given by: EACt = (BAC/SPI)/(BAC/Duration) (9) Where, duration is 24 months. Fig. 4: Additional Time To Complete (e) Estimate At Completion (EAC): It is manager’s projection of total cost of the project at completion. The EAC was found out to be Rs. 258.78; same as that of BAC as CPI is 1. EAC = BAC/CPI (10) (f) Variance At Completion (VAC): VAC was found out to be zero. VAC = BAC – EAC (11) (g) To Complete Performance Index (TCPI): The TCPI for the project was 1. TCPI greater than 1 implies performance must be increased and less than or equal to 1 implies that it should be maintained. Performance in terms of cost. TCPI = (BAC – EV)/(BAC – AC) (12) IX. Conclusion Most of the government initiated infrastructure projects are delayed and get finished years after there scheduled completion. From the intricate analysis of the questionnaire survey and the case study, it has been found that delay in land acquisition is the major cause for the delay in the road infrastructure projects. The delay in land acquisition is an owner or client related delay factor that is an excusable type of delay. The two major parameters that determine the success of the project is overall project cost and time. In the case study project, it has been found that there is an unfavourable schedule variance while the cost variance is favorable. By looking through all the parameters of the earned value management that is applied in the case study, it has been found that the root cause for the delay in the road infrastructure projects are delay in land acquisition which is an owner/client related factor and excusable type of delay. So, the contractor can claim for extension of time (EoT) if the delay is excusable. Since for executing any road projects, the client should provide the necessary land acquisition and sort out any other disputes related to land acquisition before the beginning of the project. Even the removing of all encroachment in the project area i.e. in the land acquired for the project should be sorted out well ahead to avoid delays. There should not be any bottlenecks between the state and the central government for any infrastructure projects. Since infrastructure brings economy to the country, any delays have to be avoided by clients and the contractors. In case of any delays, EVM is found to be helpful in finding out the probable completion time for the projects. 18.87 -5 0 5 10 15 20 25 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 ADDITIONAL TIME TO COMPLETE ADDITIONAL TIME TO COMPLETE MONTHS ADDITIONAL TIME TO COMPLETE
  • 7. Study on Construction Sequence Delay for Road Infrastructure Projects DOI: 10.9790/1684-12261521 www.iosrjournals.org 21 | Page References [1]. AgataCzarnigowska, Earned value method as a tool for project control, Budownictwo i Architekutra, 3, 2008, 15-32. [2]. N. Hamzah, M.A. Khoiry, I. Arshad, N.M. Tawil and A.I. Che Ani, Cause of construction delay – Theoretical framework, Procedia Engineering, 20, 2011, 490-495. [3]. RemonFayak Aziz, Ranking of delay factors in construction projects after Egyptian revolution, Alexandria Engineering Journal, 52, 2013, 387-406. [4]. EnasFathi Taher and R.K. Pandey, Study of delay in project planning and design stages of civil engineering projects, international Journal of Engineering and Advanced Technology (IJEAT), 2(3), 2013, 456-461. [5]. S.K. Patil, A.K. Gupta, D.B. Desai, A.S. Sajane, Causes of delay in Indian transportation infrastructure projects, International Journal of Research in Engineering and Technology (IJRET), 2(11), 2013, 71-80. [6]. K.L. Ravisankar, Dr. S. Anand Kumar, V. Krishnamoorthy, Study on the quantification of delay factors in construction industry, International Journal of Emerging Technology and Advanced Engineering (IJETAE), 4(1), 2014, 105-113. [7]. AshwinArunSalunkhe and Rahul S. Patil, Identification of critical construction delay factors, International Journal of Latest Trends in Enginnering and Technology (IJLTET), 3(4), 2014, 256-261. [8]. Amrita Jhawar and Purnima Bajpai, Applying FMEA and ISM technique to identify factors causing delay in road construction projects, International Journal of Applied Engineering Research, 9(5), 2014, 517-524. [9]. Khaled Ahmed Ali Alnaas, Ayman Hussein Hosny Khalil, Gamal Eldin Nassar, Guidelines for preparing comprehensive extension of time (EoT) claim, Housing and Building National Research Centre (HBRC) Journal, 2014, 1-9.