SlideShare a Scribd company logo
1 of 33
CHAPTER 07:
PROJECT COST
MANAGEMENT
Giovanni Bambaren
7.1 PLAN COST MANAGEMENT
7.1.1 PLAN COST
MANAGEMENT:
INPUTS
1. Project Charter
2. Project Management
Plan (PMP)
Schedule Management
Plan.
Risk Management Plan
3. Enterprise Environmental Factors (EEFs)
4. Organizational Process Assets (OPAs)
7.1.2 PLAN COST
MANAGEMENT:
TOOLS AND
TECHNIQUES
1. Expert Judgement
2. Data Analysis
 A data analysis technique that can be used for this
process includes but is not limited to alternatives
analysis. Alternatives analysis can include reviewing
strategic funding options such as: self-funding,
funding with equity, or funding with debt. It can
also include consideration of ways to acquire
project resources such as making, purchasing,
renting, or leasing.
3. Meetings
7.1.3 PLAN COST
MANAGEMENT:
OUTPUTS
1. Cost
Management Plan
The cost management plan is a component of the project
management plan and describes how the project costs
be planned, structured, and controlled. The cost
management processes and their associated tools and
techniques are documented in the cost management
7.1.4 PLAN COST
MANAGEMENT:
QUESTIONS
Which process provides direction on how
the project costs will be managed
throughout the project?
Which document describes how costs will
be estimated, structured, and controlled?
7.2 ESTIMATE COSTS
7.2.1
ESTIMATE
COSTS:
INPUTS
1. Project Management Plan (Cost Management Plan,
Quality Management Plan, Scope Baseline)
2. Project Documents (Lessons Learned Register, Project
Schedule, Resources Requirements, Risk Register)
3. Enterprise Environmental Factors (EEFs)
4. Organizational Process Assets (OPAs)
7.2.2 ESTIMATE COSTS: TOOLS AND
TECHNIQUES
1. Expert Judgment
2. Analogous
Estimating
3. Parametric
Estimating
4. Bottom-Up
Estimating
5. Three-Point
Estimating
6. Data Analysis
(Alternative, Reserve,
Cost of Quality (COQ))
7. PMIS
8. Decision Making
(Voting)
7.2.3 ESTIMATE COSTS: OUTPUTS
1. Cost Estimates
 Cost estimates include quantitative assessments of the probable costs
required to complete project work, as well as contingency amounts to
account for identified risks, and management reserve to cover
unplanned work. Cost estimates can be presented in summary form
or in detail. Costs are estimated for all resources that are applied to
the cost estimate. This includes but is not limited to direct labor,
materials, equipment, services, facilities, information technology, and
special categories such as cost of financing (including interest
charges), an inflation allowance, exchange rates, or a cost contingency
reserve.
7.2.3 ESTIMATE COSTS: OUTPUTS
2. Basis of Estimates
 Documentation of the basis of the estimate (i.e., how it was developed),
 Documentation of all assumptions made,
 Documentation of any known constraints,
 Indication of the range of possible estimates (e.g., €10,000 (―10%) to
indicate that the item is expected to cost between a range of values), and
 Indication of the confidence level of the final estimate.
3. Project Documents Updates
7.2.4 ESTIMATE COSTS: QUESTIONS
The organization always estimates the
development of each web page for all
projects at $100. Therefore, you estimate
4000 pages will cost $400,000 . This is an
example of:
The work required to develop some of the
web pages is complex, so you are uncertain
about how much those pages will cost to
develop. You decide to calculate an estimate
averaging three different costs that
the best case, worse case, and realistic
estimates. This is an example of:
7.2.4 ESTIMATE COSTS: QUESTIONS
Earlier in the project, you had
estimated the project would cost
$400,000 because that was the cost
for another similar project in the
company. This is an example of:
The team has helped you break
the specific work involved, so you
estimate at this lower level of work,
then sum up the costs to get cost
estimates for developing the website.
This is an example of:
7.3 DETERMINE BUDGET
7.3.1
DETERMINE
BUDGET:
INPUTS
1. Project Management Plan (Cost Management Plan, Resource Management
Scope Baseline)
2. Project Documents (Basis of Estimates, Cost Estimates, Project Schedule, Risk
Register)
3. Business Documents (Business Case, Benefits Management Plan)
4. Agreements
5. EEFs
6. OPAs
7.3.2 DETERMINE BUDGET: TOOLS
AND TECHNIQUES
1. Expert Judgment
2. Cost Aggregation
 It is the process of collecting individual cost estimates into a whole. Specifically, cost estimates are aggregated by
work packages, then into higher components (typically monitored by control accounts) of the work break down
structure (WBS), and then for the entire project.
3. Data Analysis (Reserve Analysis: Contingency and Management Reserves)
4. Historical Information Review: Review of historical information can be used to develop parametric or
analogous estimates. Historical information my include project characteristics to evolve mathematical
models to forecast the total project cost.
5. Funding Limit Reconciliation: Funding limit reconciliation consists of accommodating the expenditure
of funds to established funding limits for a specific period of time. Any variances between expenditures
and funding limits can result in rescheduling work. To prevent this, any date constraints for work
should be included in the work schedule.
6. Financing
7.3.3
DETERMINE
BUDGET:
OUTPUTS
1. Cost Baseline
2. Project Funding Requirements
3. Project Documents Updates (Cost
Estimates, Project Schedule, Risk Register)
7.3.3 DETERMINE BUDGET: OUTPUTS
7.3.4 DETERMINE BUDGET:
QUESTIONS
1. An important technique used in Determine Budget process is:
2. Which type of reserve is included in the Cost Baseline?
a) Management Reserve
b) Contingeny Reserve
3. Which reserves is attributed to unforeseen risks that have not been
identified?
4. An important output of the Determine Budget process is the:
7.4 CONTROL COSTS
7.4.1
CONTROL
COSTS:
INPUTS
1. Project Management Plan (Cost Management Plan, Cost
Baseline, Performance Measurement baseline)
2. Project Documents (Lessons Learned Register)
3. Project Funding Requirements
4. Work Performance Data
5. OPAs
7.4.2 CONTROL COSTS: TOOLS
AND TECHNIQUES
1. Expert Judgment
2. Data Analysis: Earned Value Analysis
 Planned Value (PV)
 Earned Value (EV)
 Actual Cost (AC)
 Schedule Variance (SV) = EV - PV
 Cost Variance (CV) = EV - AC
 Schedule Performance Index (SPI) = EV / PV
 Cost Performance Index (CPI) = EV / AC
7.4.2 CONTROL COSTS: TOOLS
AND TECHNIQUES
2. Data Analysis: Variance analysis. Variance analysis, as used in EVA, is
the explanation (cause, impact, and corrective actions) for cost (CV = EV
– AC), schedule (SV = EV – PV), and variance at completion (VAC = BAC
– EAC) variances. Cost and schedule variances are the most frequently
analyzed measurements.
7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES
7.4.2 CONTROL COSTS: TOOLS
AND TECHNIQUES
2. Data Analysis: Forecasting
 EAC forecast for ETC work performed at the budgeted rate.
 Equation: EAC = AC + (BAC – EV)
 EAC forecast for ETC work performed at the present CPI.
 Equation: EAC = BAC / CPI
 EAC forecast for ETC work considering both SPI and CPI factors.
 Equation: EAC = AC + [(BAC – EV) / (CPI × SPI)]
7.4.2 CONTROL COSTS: TOOLS
AND TECHNIQUES
2. Data Analysis: Reserve Analysis
 During cost control, reserve analysis is used to monitor the status of
contingency and management reserves for the project to determine if
these reserves are still needed or if additional reserves need to be
requested.
7.4.2 CONTROL COSTS: TOOLS
AND TECHNIQUES
3. To-Complete Performance Index (TCPI)
The equation for the TCPI based on the BAC:
• (BAC – EV) / (BAC – AC).
The equation for the TCPI based on the EAC:
 (BAC – EV) / (EAC – AC).
7.4.3
CONTROL
COSTS:
OUTPUTS
1. Work Performance Information
2. Cost Forecast
3. Change Requests
4. Project Management Plan Updates (Cost Management Plan, Cost
baseline, Performance measurement baseline)
5. Project Documents Updates (Assumption Log, Basis of Estimates,
Cost estimates, Lessons Learned Register, Risk Register)
7.4.4
CONTROL
COSTS:
QUESTIONS
Any increase to the authorized budget can only be
approved through ____________
In a project if we have a negative cost variance, it
means we are ____________
SPI < 1 means that the project is ______________
What’s the name of the output that includes calculated
project performance measures?
SUMMARY
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
Cost Mind Map
7.1
Plan Cost
Management
- Exp. Judg.
- Data Analysis
- Meetings
Project
Documents
PMP
Project
Charter
Cost Mgmt.
Plan
7.2
Estimate
Costs
- Exp. Judg.
- Analogous
- Parametric
- Bottom-Up
- Three-points
- Data Analysis
- PMIS
- Decision Making
Cost Estimates
Basis of
estimates
7.3
Determine
Budget
Agreements
Business docs
- Exp. Judg.
- Cost Aggregation
- Data Analysis
- Historical Info.
- Funding Limit
Rec.
- Financing
Cost Baseline
Project Funding
Requirements
7.4
Control
Costs
WPI
WPD
- Exp. Judg.
- Data Analysis (EVA)
- TCPI
- PMIS
Change
Requests
Cost forecasts
CASE STUDY 1
 You’re a subcontractor responsible for refurbishment of an automobile
showroom. The estimated refurbishment cost is $500 per square feet.
The total showroom area that needs to be refurbished is 1,000 square
feet. Based on your past experience, you know your team can
refurbish 100 square feet per week. After 4 weeks, you have 45% of
the job complete and you have spent $250,000.
 Determine PV, EV, and AC.
 Calculate CV, SV, CPI, and SPI to determine the performance of the
project in terms of Cost and Schedule
CASE STUDY 2
 Your project is required to install lighting fixtures in a 200 room hotel.
You have to install 5 lighting fixtures in each room. Your project’s
approved budget is $500,000 and the approved schedule is 14 weeks.
After 8 weeks, you have 110 of the rooms completed and you have
spent $250,000.
 Determine BAC, PV, EV, and AC.
 Calculate CV, SV, CPI, and SPI to determine the performance of the
project in terms of Cost and Schedule

More Related Content

Similar to Chapter 07

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع Mohamed Dahi
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
7.project costmanagement
7.project costmanagement7.project costmanagement
7.project costmanagementNiranjana K.R.
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxvanna37
 
Cost management
Cost managementCost management
Cost managementshkadry
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdfzohir khellouf
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 

Similar to Chapter 07 (20)

Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
7.project costmanagement
7.project costmanagement7.project costmanagement
7.project costmanagement
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptx
 
Cost management
Cost managementCost management
Cost management
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Cost managment
Cost managmentCost managment
Cost managment
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 

More from KareemBullard1

Azure-Interview-Questions.pptx
Azure-Interview-Questions.pptxAzure-Interview-Questions.pptx
Azure-Interview-Questions.pptxKareemBullard1
 
Azure_DP_300_Vocabulary_Cards.pptx
Azure_DP_300_Vocabulary_Cards.pptxAzure_DP_300_Vocabulary_Cards.pptx
Azure_DP_300_Vocabulary_Cards.pptxKareemBullard1
 
Azure-Interview-Questions-Slides.pptx
Azure-Interview-Questions-Slides.pptxAzure-Interview-Questions-Slides.pptx
Azure-Interview-Questions-Slides.pptxKareemBullard1
 
01_DP-300T00A-Intro.pptx
01_DP-300T00A-Intro.pptx01_DP-300T00A-Intro.pptx
01_DP-300T00A-Intro.pptxKareemBullard1
 
02_DP_300T00A_Plan_implement.pptx
02_DP_300T00A_Plan_implement.pptx02_DP_300T00A_Plan_implement.pptx
02_DP_300T00A_Plan_implement.pptxKareemBullard1
 
07_DP_300T00A_HA_Disaster_Recovery.pptx
07_DP_300T00A_HA_Disaster_Recovery.pptx07_DP_300T00A_HA_Disaster_Recovery.pptx
07_DP_300T00A_HA_Disaster_Recovery.pptxKareemBullard1
 
06_DP_300T00A_Automate.pptx
06_DP_300T00A_Automate.pptx06_DP_300T00A_Automate.pptx
06_DP_300T00A_Automate.pptxKareemBullard1
 
05_DP_300T00A_Optimize.pptx
05_DP_300T00A_Optimize.pptx05_DP_300T00A_Optimize.pptx
05_DP_300T00A_Optimize.pptxKareemBullard1
 
04_DP_300T00A_Monitor.pptx
04_DP_300T00A_Monitor.pptx04_DP_300T00A_Monitor.pptx
04_DP_300T00A_Monitor.pptxKareemBullard1
 
03_DP_300T00A_Secure_Environment.pptx
03_DP_300T00A_Secure_Environment.pptx03_DP_300T00A_Secure_Environment.pptx
03_DP_300T00A_Secure_Environment.pptxKareemBullard1
 
DP-300 Administering Relational Databases Azure_Oct2020
DP-300 Administering Relational Databases Azure_Oct2020DP-300 Administering Relational Databases Azure_Oct2020
DP-300 Administering Relational Databases Azure_Oct2020KareemBullard1
 
PMP Mind Maps Complete
PMP Mind Maps CompletePMP Mind Maps Complete
PMP Mind Maps CompleteKareemBullard1
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
Pmp Extrenal Documents
Pmp Extrenal DocumentsPmp Extrenal Documents
Pmp Extrenal DocumentsKareemBullard1
 

More from KareemBullard1 (20)

Azure-Interview-Questions.pptx
Azure-Interview-Questions.pptxAzure-Interview-Questions.pptx
Azure-Interview-Questions.pptx
 
Azure_DP_300_Vocabulary_Cards.pptx
Azure_DP_300_Vocabulary_Cards.pptxAzure_DP_300_Vocabulary_Cards.pptx
Azure_DP_300_Vocabulary_Cards.pptx
 
Azure-Interview-Questions-Slides.pptx
Azure-Interview-Questions-Slides.pptxAzure-Interview-Questions-Slides.pptx
Azure-Interview-Questions-Slides.pptx
 
01_DP-300T00A-Intro.pptx
01_DP-300T00A-Intro.pptx01_DP-300T00A-Intro.pptx
01_DP-300T00A-Intro.pptx
 
02_DP_300T00A_Plan_implement.pptx
02_DP_300T00A_Plan_implement.pptx02_DP_300T00A_Plan_implement.pptx
02_DP_300T00A_Plan_implement.pptx
 
07_DP_300T00A_HA_Disaster_Recovery.pptx
07_DP_300T00A_HA_Disaster_Recovery.pptx07_DP_300T00A_HA_Disaster_Recovery.pptx
07_DP_300T00A_HA_Disaster_Recovery.pptx
 
06_DP_300T00A_Automate.pptx
06_DP_300T00A_Automate.pptx06_DP_300T00A_Automate.pptx
06_DP_300T00A_Automate.pptx
 
05_DP_300T00A_Optimize.pptx
05_DP_300T00A_Optimize.pptx05_DP_300T00A_Optimize.pptx
05_DP_300T00A_Optimize.pptx
 
04_DP_300T00A_Monitor.pptx
04_DP_300T00A_Monitor.pptx04_DP_300T00A_Monitor.pptx
04_DP_300T00A_Monitor.pptx
 
03_DP_300T00A_Secure_Environment.pptx
03_DP_300T00A_Secure_Environment.pptx03_DP_300T00A_Secure_Environment.pptx
03_DP_300T00A_Secure_Environment.pptx
 
DP-300 Administering Relational Databases Azure_Oct2020
DP-300 Administering Relational Databases Azure_Oct2020DP-300 Administering Relational Databases Azure_Oct2020
DP-300 Administering Relational Databases Azure_Oct2020
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
Pmp Complete Diagrams
Pmp Complete DiagramsPmp Complete Diagrams
Pmp Complete Diagrams
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
Pmp Complete Diagrams
Pmp Complete DiagramsPmp Complete Diagrams
Pmp Complete Diagrams
 
Pmp ITTO Complete
Pmp ITTO CompletePmp ITTO Complete
Pmp ITTO Complete
 
PMP Mind Maps Complete
PMP Mind Maps CompletePMP Mind Maps Complete
PMP Mind Maps Complete
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Pmp Test Complete
Pmp Test CompletePmp Test Complete
Pmp Test Complete
 
Pmp Extrenal Documents
Pmp Extrenal DocumentsPmp Extrenal Documents
Pmp Extrenal Documents
 

Recently uploaded

Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 

Recently uploaded (20)

Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 

Chapter 07

  • 2. 7.1 PLAN COST MANAGEMENT
  • 3. 7.1.1 PLAN COST MANAGEMENT: INPUTS 1. Project Charter 2. Project Management Plan (PMP) Schedule Management Plan. Risk Management Plan 3. Enterprise Environmental Factors (EEFs) 4. Organizational Process Assets (OPAs)
  • 4. 7.1.2 PLAN COST MANAGEMENT: TOOLS AND TECHNIQUES 1. Expert Judgement 2. Data Analysis  A data analysis technique that can be used for this process includes but is not limited to alternatives analysis. Alternatives analysis can include reviewing strategic funding options such as: self-funding, funding with equity, or funding with debt. It can also include consideration of ways to acquire project resources such as making, purchasing, renting, or leasing. 3. Meetings
  • 5. 7.1.3 PLAN COST MANAGEMENT: OUTPUTS 1. Cost Management Plan The cost management plan is a component of the project management plan and describes how the project costs be planned, structured, and controlled. The cost management processes and their associated tools and techniques are documented in the cost management
  • 6. 7.1.4 PLAN COST MANAGEMENT: QUESTIONS Which process provides direction on how the project costs will be managed throughout the project? Which document describes how costs will be estimated, structured, and controlled?
  • 8. 7.2.1 ESTIMATE COSTS: INPUTS 1. Project Management Plan (Cost Management Plan, Quality Management Plan, Scope Baseline) 2. Project Documents (Lessons Learned Register, Project Schedule, Resources Requirements, Risk Register) 3. Enterprise Environmental Factors (EEFs) 4. Organizational Process Assets (OPAs)
  • 9. 7.2.2 ESTIMATE COSTS: TOOLS AND TECHNIQUES 1. Expert Judgment 2. Analogous Estimating 3. Parametric Estimating 4. Bottom-Up Estimating 5. Three-Point Estimating 6. Data Analysis (Alternative, Reserve, Cost of Quality (COQ)) 7. PMIS 8. Decision Making (Voting)
  • 10. 7.2.3 ESTIMATE COSTS: OUTPUTS 1. Cost Estimates  Cost estimates include quantitative assessments of the probable costs required to complete project work, as well as contingency amounts to account for identified risks, and management reserve to cover unplanned work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the cost estimate. This includes but is not limited to direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve.
  • 11. 7.2.3 ESTIMATE COSTS: OUTPUTS 2. Basis of Estimates  Documentation of the basis of the estimate (i.e., how it was developed),  Documentation of all assumptions made,  Documentation of any known constraints,  Indication of the range of possible estimates (e.g., €10,000 (―10%) to indicate that the item is expected to cost between a range of values), and  Indication of the confidence level of the final estimate. 3. Project Documents Updates
  • 12. 7.2.4 ESTIMATE COSTS: QUESTIONS The organization always estimates the development of each web page for all projects at $100. Therefore, you estimate 4000 pages will cost $400,000 . This is an example of: The work required to develop some of the web pages is complex, so you are uncertain about how much those pages will cost to develop. You decide to calculate an estimate averaging three different costs that the best case, worse case, and realistic estimates. This is an example of:
  • 13. 7.2.4 ESTIMATE COSTS: QUESTIONS Earlier in the project, you had estimated the project would cost $400,000 because that was the cost for another similar project in the company. This is an example of: The team has helped you break the specific work involved, so you estimate at this lower level of work, then sum up the costs to get cost estimates for developing the website. This is an example of:
  • 15. 7.3.1 DETERMINE BUDGET: INPUTS 1. Project Management Plan (Cost Management Plan, Resource Management Scope Baseline) 2. Project Documents (Basis of Estimates, Cost Estimates, Project Schedule, Risk Register) 3. Business Documents (Business Case, Benefits Management Plan) 4. Agreements 5. EEFs 6. OPAs
  • 16. 7.3.2 DETERMINE BUDGET: TOOLS AND TECHNIQUES 1. Expert Judgment 2. Cost Aggregation  It is the process of collecting individual cost estimates into a whole. Specifically, cost estimates are aggregated by work packages, then into higher components (typically monitored by control accounts) of the work break down structure (WBS), and then for the entire project. 3. Data Analysis (Reserve Analysis: Contingency and Management Reserves) 4. Historical Information Review: Review of historical information can be used to develop parametric or analogous estimates. Historical information my include project characteristics to evolve mathematical models to forecast the total project cost. 5. Funding Limit Reconciliation: Funding limit reconciliation consists of accommodating the expenditure of funds to established funding limits for a specific period of time. Any variances between expenditures and funding limits can result in rescheduling work. To prevent this, any date constraints for work should be included in the work schedule. 6. Financing
  • 17. 7.3.3 DETERMINE BUDGET: OUTPUTS 1. Cost Baseline 2. Project Funding Requirements 3. Project Documents Updates (Cost Estimates, Project Schedule, Risk Register)
  • 19. 7.3.4 DETERMINE BUDGET: QUESTIONS 1. An important technique used in Determine Budget process is: 2. Which type of reserve is included in the Cost Baseline? a) Management Reserve b) Contingeny Reserve 3. Which reserves is attributed to unforeseen risks that have not been identified? 4. An important output of the Determine Budget process is the:
  • 21. 7.4.1 CONTROL COSTS: INPUTS 1. Project Management Plan (Cost Management Plan, Cost Baseline, Performance Measurement baseline) 2. Project Documents (Lessons Learned Register) 3. Project Funding Requirements 4. Work Performance Data 5. OPAs
  • 22. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES 1. Expert Judgment 2. Data Analysis: Earned Value Analysis  Planned Value (PV)  Earned Value (EV)  Actual Cost (AC)  Schedule Variance (SV) = EV - PV  Cost Variance (CV) = EV - AC  Schedule Performance Index (SPI) = EV / PV  Cost Performance Index (CPI) = EV / AC
  • 23. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES 2. Data Analysis: Variance analysis. Variance analysis, as used in EVA, is the explanation (cause, impact, and corrective actions) for cost (CV = EV – AC), schedule (SV = EV – PV), and variance at completion (VAC = BAC – EAC) variances. Cost and schedule variances are the most frequently analyzed measurements.
  • 24. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES
  • 25. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES 2. Data Analysis: Forecasting  EAC forecast for ETC work performed at the budgeted rate.  Equation: EAC = AC + (BAC – EV)  EAC forecast for ETC work performed at the present CPI.  Equation: EAC = BAC / CPI  EAC forecast for ETC work considering both SPI and CPI factors.  Equation: EAC = AC + [(BAC – EV) / (CPI × SPI)]
  • 26. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES 2. Data Analysis: Reserve Analysis  During cost control, reserve analysis is used to monitor the status of contingency and management reserves for the project to determine if these reserves are still needed or if additional reserves need to be requested.
  • 27. 7.4.2 CONTROL COSTS: TOOLS AND TECHNIQUES 3. To-Complete Performance Index (TCPI) The equation for the TCPI based on the BAC: • (BAC – EV) / (BAC – AC). The equation for the TCPI based on the EAC:  (BAC – EV) / (EAC – AC).
  • 28. 7.4.3 CONTROL COSTS: OUTPUTS 1. Work Performance Information 2. Cost Forecast 3. Change Requests 4. Project Management Plan Updates (Cost Management Plan, Cost baseline, Performance measurement baseline) 5. Project Documents Updates (Assumption Log, Basis of Estimates, Cost estimates, Lessons Learned Register, Risk Register)
  • 29. 7.4.4 CONTROL COSTS: QUESTIONS Any increase to the authorized budget can only be approved through ____________ In a project if we have a negative cost variance, it means we are ____________ SPI < 1 means that the project is ______________ What’s the name of the output that includes calculated project performance measures?
  • 30. SUMMARY 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs
  • 31. Cost Mind Map 7.1 Plan Cost Management - Exp. Judg. - Data Analysis - Meetings Project Documents PMP Project Charter Cost Mgmt. Plan 7.2 Estimate Costs - Exp. Judg. - Analogous - Parametric - Bottom-Up - Three-points - Data Analysis - PMIS - Decision Making Cost Estimates Basis of estimates 7.3 Determine Budget Agreements Business docs - Exp. Judg. - Cost Aggregation - Data Analysis - Historical Info. - Funding Limit Rec. - Financing Cost Baseline Project Funding Requirements 7.4 Control Costs WPI WPD - Exp. Judg. - Data Analysis (EVA) - TCPI - PMIS Change Requests Cost forecasts
  • 32. CASE STUDY 1  You’re a subcontractor responsible for refurbishment of an automobile showroom. The estimated refurbishment cost is $500 per square feet. The total showroom area that needs to be refurbished is 1,000 square feet. Based on your past experience, you know your team can refurbish 100 square feet per week. After 4 weeks, you have 45% of the job complete and you have spent $250,000.  Determine PV, EV, and AC.  Calculate CV, SV, CPI, and SPI to determine the performance of the project in terms of Cost and Schedule
  • 33. CASE STUDY 2  Your project is required to install lighting fixtures in a 200 room hotel. You have to install 5 lighting fixtures in each room. Your project’s approved budget is $500,000 and the approved schedule is 14 weeks. After 8 weeks, you have 110 of the rooms completed and you have spent $250,000.  Determine BAC, PV, EV, and AC.  Calculate CV, SV, CPI, and SPI to determine the performance of the project in terms of Cost and Schedule

Editor's Notes

  1. Project Charter: High level description of the product. EEF: Culture of Organization, Schedule System Availables, Infrastructure. OPA: Templates, Historical Information, Knowledge base.
  2. Plan Cost Management Cost Management Plan
  3. Risk Register: Cost for mitigate risks.
  4. Reserve Analysis: Cost estimates may include contingency reserves (sometimes called contingency allowances) to account for cost uncertainty. Contingency reserves are the budget within the cost baseline that is allocated for identified risks, which are accepted and for which contingent or mitigating responses are developed. Contingency reserves are often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project.
  5. Parametric Estimating Three-Point Estimating
  6. 3. Analogous Estimating 4. Bottom-up Estimating
  7. Cost Aggregation Cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS (such as control accounts) and, ultimately, for the entire project. Historical INFORMATION REVIEW Reviewing historical information can assist in developing parametric estimates or analogous estimates. Historical information may include project characteristics (parameters) to develop mathematical models to predict total project costs. Such models may be simple (e.g., residential home construction is based on a certain cost per square foot of space) or complex (e.g., one model of software development costing uses multiple separate adjustment factors, each of which has numerous points within it). Financing Financing entails acquiring funding for projects. It is common for long-term infrastructure, industrial, and public services projects to seek external sources of funds. If a project is funded externally, the funding entity may have certain requirements that are required to be met.
  8. Cost Aggregation. Contingency Reserves. Management Reserves. Cost Baseline.
  9. Planned value. Planned value (PV) is the authorized budget assigned to scheduled work. It is the authorized budget planned for the work to be accomplished for an activity or work breakdown structure (WBS) component, not including management reserve. Earned value. Earned value (EV) is a measure of work performed expressed in terms of the budget authorized for that work. It is the budget associated with the authorized work that has been completed Actual cost. Actual cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period. It is the total cost incurred in accomplishing the work that the EV measured.
  10. If the variance is expected to go away(If the variance is not expected to continue), use the formula: AC + BAC – EV If the project will continue to spend at the same current rate, the formula to be used would be: EAC = BAC/CPI If the project will be impacted by the current cost performance and current schedule performance, the formula would be: EAC = AC + [(BAC-EV)/(SPI*CPI)]
  11. Perform Integrated Change Control Over-budget Behind Schedule Work Performance Information
  12. Homework for students.
  13. Solution will be developed in class.
  14. Homework for students.