CHAPTER 7
Fourth Knowledge Area:
Project Cost Management
1
PLAN
COST
MGMT
2
ESTIMATE
COST
3
DETERMINE
BUDGET
4
CONTROL
COSTS
Project Cost Management includes the processes involved in Planning,
Estimating, Budgeting, Financing, Funding, Managing, and Controlling
costs so that projects can be completed within budget
1. Plan Cost Management (Planning Process Group)
The process that establishes the policies, procedures, and documentation for planning, managing, expending, and
controlling project costs.
2. Estimate Cost (Planning Process Group)
The process of developing an approximation of the monetary resources needed to complete project activities
3. Determine Budget (Planning Process Group)
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost
baseline
4. Control Costs (Monitoring & Controlling Process Group)
The process of monitoring the status of the project to update the project costs & managing changes to the cost baseline.
Project Cost Management must consider stakeholder’s requirements for
managing costs – each stakeholder will measure costs differently.
Project Cost Management is primarily concerned with the cost of the
resources needed to complete project activities & the subsequent costs in
using and supporting the deliverables.
The cost management planning effort occurs early in the project & sets the
framework for each of the cost management processes so that
performance will be efficient.
INPUTS TOOLS & TECHNIQUES OUTPUTS
Plan Cost Management: Inputs, Tools & Techniques, & Outputs
1. Project Management
Plan
2. Project Charter
3. Enterprise Environmental
Factors (EEFs)
4. Organizational Process
Assets (OPAs)
1. Expert Judgment
2. Analytical Techniques
3. Meeting
1. Schedule Management
Plan
• Plan Cost Management is the process of establishing the policies, procedures, and
documentations for planning, managing, expending & controlling project cost.
• It’s key benefit is it provides guidance & directions on how the project costs will be
managed throughout the project
OUTPU
T
1
PROJECT
MANAGEMEN
T
PLAN
4
ORGANIZATION
AL
PROCESS
ASSETS
(OPA)
TOOLS &
TECHNIQUE
S
COST
MANAGEMENT
PLAN
3
ENTERPRISE
ENVIRONME
NT
FACTORS
(EEF)
2
PROJECT
CHARTER
OUTPUT
1. EXPERT JUDGMENT
2. ANALYTICAL TECHNIQUES
3. MEETINGS
Other Information
1. Org. Culture & Structure that influences
cost
2. Market Conditions
3. Currency exchange for international
projects
4. Published & Commercially Available Info
5. Project Management Information System
• Financial controls procedures
• Historical information & lessons learned
• Financial databases; and
• Existing formal & informal cost estimating &
budgeting policies
Describes how the project costs will be planned, structured & controlled.
Cost management plan can establish:
• Units of Measure
• Level of Precision
• Level of Accuracy
• Organizational Procedures Links
• Control Thresholds
• Rules of Performance Measurement
• Reporting Formats
• Process Descriptions
• Additional details such as description of strategic funding choices, procedure to
account for fluctuation in currency exchange & cost reporting
INPUTS TOOLS & TECHNIQUES OUTPUTS
Plan Cost Management: Inputs, Tools & Techniques, & Outputs
1. Cost Management Plan
2. Human Resource
Management Plan
3. Scope Baseline
4. Project Schedule
5. Risk Register
6. Enterprise Environmental
Factors
7. Organizational Process
Assets (OPAs)
1. Expert Judgment
2. Analogous Estimating
3. Parametric Estimating
4. Bottom-up Estimating
5. Three-points Estimating
6. Reserve Analysis
7. Cost of Quality
8. Project Management
Software
9. Vendor Bid Analysis
10. Group Decision Making
Techniques
1. Activity Cost Estimates
2. Basic of Estimates
3. Project Documents
Updates
• Estimate Cost is the process of developing an approximation of the monetary
resources needed to complete project activities.
• It’s key benefit is it determines the amount of cost required to complete project work.
3
SCOPE
BASELINE
5
RISK
REGISTER
4
PROJECT
SCHEDUL
E
OUTPU
T
1
COST
MANAGEMEN
T
PLAN
7
ORGANIZATION
AL
PROCESS
ASSETS
(OPA)
TOOLS &
TECHNIQUE
S
BASIS OF
ESTIMATES
6
ENTERPRISE
ENVIRONME
NT
FACTORS
(EEF)
2
H.R.
MGMT
PLAN
OUTPUT
1. EXPERT JUDGMENT
2. ANALOGOUS ESTIMATING
3. PARAMETRIC ESTIMATING
4. THREE-POINT ESTIMATING
5. BOTTOM-UP ESTIMATING
6. RESERVE ANALYSIS
7. COST OF QUALITY
8. PROJECT MANAGEMENT
SOFTWARE
9. VENDOR BID ANALYSIS
10. GROUP DECISION MAKING
TECHNIQUES
1. Market Conditions
2. Published Commercially Info
• Cost Estimating Policies
• Cost Estimating Templates
• Historical Information, and
• Lessons Learned
PROJECT
DOCUMENTS
UPDATES
ACTIVITY
COST ESTIMATES
WBS Dictionary
1. Expert Judgment
2. Analogous Estimating – compare with similar past projects when limited amount of detailed info
available
3. Parametric Estimating – uses statistical relationship relevant historical data & other variable
(like square footage) to calculate a cost estimate for project work. It provides higher level of accuracy
depending on past data
4. Bottom Up Estimating – cost of individual work packages are estimated to the greatest level for
detail. Its accuracy is influenced by the size & complexity of the individual activity or work package.
5. Three-Point Estimating
• Most Likely (cM) based on realistic effort assessment
• Optimistic (cO) based on best case scenario
• Pessimistic (cP) based on worst case scenario
Depending on the assumed distribution of value within the range, there are 2
formulas:
• Triangular Distribution. cE = (cO + cM + cP) /3
• Beta Distribution (from PERT analysis) cE = (cO + 4cM + cP) / 6
6. Reserve Analysis
Contingency Reserves are the budget within cost baseline that is allocated for identified risks. It is often
viewed as part of the budget to address the “known-unknowns” that can affect a project. It may be a
percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis
methods.
7. Cost of Quality (COQ) – it cost less to prevent quality issue than to fix it
8. Project Management Software – Computerized spreadsheets, simulation, and statistical
tools are used to assist with cost estimating.
9. Vendor Bid Analysis – Cost estimates can be based on the responsive bids from qualified
vendors
10.Group Decision-Making Techniques
Team based approaches, such as brainstorming, the Delphi or Nominal Group Techniques are useful for
engaging team members to improve estimate accuracy & commitment to the estimates.
BASIS OF
ESTIMATES
PROJECT
DOCUMENTS
UPDATES
ACTIVITY
COST ESTIMATES
Quantitative assessment of the probable costs required to complete project work. It can be
presented in summary form or in detail. Cost are estimated for ALL resources that are applied
to the activity cost estimate
The amount and type of additional details supporting the cost estimates vary by application
area.
Supporting detail may include:
• Documentation of the basis of the estimate (how it was developed),
• Documentation of all assumptions made,
• Documentation of any known constraints,
• Indication of the range of possible estimates (like +/- 10%) to indicate that the item is
expected to cost between a range of values, and
• Indication of the confidence level of the final estimate.
Project Documents that may be updated include, but not limited to, the risk register.
INPUTS TOOLS & TECHNIQUES OUTPUTS
Determine Budget: Inputs, Tools & Techniques, & Outputs
1. Cost Management Plan
2. Scope Baseline
3. Activity Cost Estimates
4. Basis of Estimates
5. Project Schedule
6. Resource Calendars
7. Risk Register
8. Agreements
9. Organizational Process
Assets (OPAs)
1. Cost Aggregation
2. Reserve Analysis
3. Expert Judgment
4. Historical Relationship
5. Funding Limit
Reconciliation
1. Cost Baseline
2. Project Funding
3. Project Documents
Updates
• Determine Budget is the process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline
• It’s key benefit is it determines the cost baseline against which project performance
can be monitored & controlled.
6
RESOURC
E
CALENDA
RS
2
SCOPE
BASELINE
7
RISK
REGISTER
3
ACTIVITY
COST
ESTIMATE
S
OUTPU
T
1
COST
MANAGEMEN
T
PLAN
9
ORGANIZATION
AL
PROCESS
ASSETS
(OPA)
TOOLS &
TECHNIQUE
S
PROJECT
FUNDING
REQUIREMENTS
5
PROJECT
SCHEDULE
4
BASIS
OF
ESTIMATE
S
OUTPUT
1. COST AGGREGRATION
2. RESERVE ANALYSIS
3. EXPERT JUDGMENT
4. HISTORICAL RELATIONSHIPS
5. FUNDING LIMIT RECONCILIATION
• Existing formal & informal cost budgeting-
related policies, procedures and guidelines;
• Cost budgeting tools; and
• Reporting methods
PROJECT
DOCUMENTS
UPDATES
COST
BASELINE
WBS Dictionary
8
AGREEMEN
TS
Info on which resources are
assigned
and when they are assigned
1. Cost Management Plan – describes how project costs are managed & controlled
2. Scope Baseline:
Project Scope Statement; WBS; & WBS Dictionary.
3. Activity Cost Estimates – each activity in a work package are aggregated to get the cost estimate
4. Basis of Estimates – must specify basic assumptions related to inclusion, exclusion of indirect or other costs
5. Project Schedule – planned start & finish dates of activities, milestones, work packages & control accounts
6. Resource Calendars * – provide info on which resources are assigned and when they are assigned
7. Risk Register * – must be reviewed to consider how to aggregate the risk response cost.
8. Agreements *
Applicable agreement information and cost relating to products, services, or results that have been or will be purchased are
included when determining the budget.
9. Organizational Process Assets
such as Existing formal/informal cost-budgeting policies, procedures & guidelines; Cost budgeting tools; and Reporting
methods.
1. Cost Aggregation *
costs are aggregated by work packages rolling up to the entire project
2. Reserve Analysis
can establish both contingency reserves & management reserves for the project
3. Expert Judgment
such as from Other departments, consultants, stakeholders (including the customers), professional & technical associations;
and industry groups.
4. Historical Relationships *
that result in parametric or analogous estimates to develop mathematical model to predict total project cost. The accuracy
depends on if the:
• Historical information used to develop the model is accurate.
• Parameters used are readily quantifiable; and
• Models are scalable
5. Funding Limit Reconciliation
Expenditures must be reconciled with any funding limit. A variance may necessitate a rescheduling to level out the rate of
expenditures by placing date constraints on the schedule.
PROJECT
DOCUMENTS
UPDATES
PROJECT
FUNDING
REQUIREMENTS
COST
BASELINE
Approved version of the time-phased project budget (excluding any management reserves)
that can only be changed via formal change control procedures. It is used as a basis for
comparison to actual results.
Project Documents that may be updated include, but not limited to:
Risk Register, Activity Cost Estimate, and Project Schedule
Derived from the cost baseline that include projected expenditures plus anticipated liabilities.
Funding are incremental, not continuous and may not be distributed evenly
Project
Budget
Cost
Baselin
e
Control
Accounts
WorkPackage
CostEstimates
Activity
Cost
Estimates
Manage
ment
Reserve
s
Contingen
cy
Reserves
Activity
Contingency
Reserves
TotalAmount
Project Budget Component
INPUTS TOOLS & TECHNIQUES OUTPUTS
Control Costs: Inputs, Tools & Techniques, & Outputs
1. Project Management Plan
2. Project Funding
Requirements
3. Work Performance Data
4. Organization Process Assets
(OPAs)
1. Earned Value
Management
2. Forecasting
3. To Complete Performance
Index (TCPI)
4. Performance Reviews
5. Project Management
Software
6. Reserve Analysis
1. Work Performance Info
2. Cost Forecasts
3. Change Requests
4. Project Management
Plan Updates
5. Projects Documents
Updates
6. Organizational Process
Assets Updates
• Control Costs is the process of monitoring the status of the project to update the project
costs and managing changes to the cost baseline.
• It’s key benefit is it provides means to recognize variance from the plan in order to take
corrective action & minimize risk.
Much of the effort of cost control involves analyzing the relationship between the consumption of
project funds to the physical work being accomplish for such expenditures that includes:
• Influencing the factors that created changes to the authorized cost baseline;
• Ensuring that all change requests are acted on a timely manner;
• Managing the actual changes when they occur;
• Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS
component, by activity, and in total for the project;
• Monitoring cost performance to isolate and understand variances from the approved cost
baseline;
• Monitoring work performance against funds expended;
• Preventing unapproved changes from being included in the reported cost of resource usage;
• Informing appropriate stakeholders of all approved changes and associated costs; and
• Bringing expected cost overruns within acceptable limits.
OUTPU
T
1
PROJECT
MANAGEMEN
T
PLAN
4
ORGANIZATION
AL
PROCESS
ASSETS
(OPA)
TOOLS &
TECHNIQUE
S
COST
FORECASTS
3
WORK
PERFORMAN
CE
DATA
2
PROJECT
FUNDING
REQUIREMEN
TS
OUTPUT
1. EARNED VALUE MANAGEMENT
2. FORECASTING
3. TO COMPLETE PERFORMANCE
INDEX (TCPI)
4. PERFORMANCE REVIEWS
5. PROJECT MANAGEMENT
SOFTWARE
6. RESERVE ANALYIS
• Existing formal & informal cost budgeting-
related policies, procedures and guidelines;
• Cost control tools; and
• Monitoring & Reporting methods to be used
CHANGE
REQUESTS
WORK
PERFORMANCE
INFORMATION
PROJECT
DOCUMENT
UPDATES
ORGANIZATIONAL
PROCESS ASSETS
UPDATES
PROJECT
MANAGEMENT PLAN
UPDATES
1. Earned Value Management (EVM)
A methodology that combines scope, schedule, and resource measurements to asses project performance & progress to
form performance baseline. It is a technique that requires the formation of an integrated baseline to measure performance
of the project.
EVM develops and monitor three key dimensions for each work package & control account:
• Planned Value (PV). Authorized budget assigned to scheduled work for an activity or WBS component (not
including management reserve). It is allocated by phase over the life of the project, but at a given moment, PV
defines the physical work that should have been accomplished. The total of the PV is sometimes referred to as the
Performance Measurement Baseline (PMB). Total PV for the project is also known at Budget At Completion (BAC)
• Earned Value (EV). A measure of work performed expressed in terms on the budget authorized for that work. EV
measured needs to be related to the PMB and it cannot be greater than the authorized PV budget for a component.
It’s often used to calculate the percent complete of a project.
• Actual Cost (AC). The realized cost incurred for work performed on an activity during a specific time period. It is
the total cost incurred in accomplishing the work that the EV measured. The AC needs to correspond in definition to
what was budgeted in the PV and measured in the EV. AC has no upper limit; whatever spent to achieve EV will be
measured.
Variances from the approved baseline will also be monitored:
• Schedule Variance (SV). – SV = EV – PV
A measure of schedule performance expressed as the difference between the Earned Value (EV) and the Planned
Value (PV)
EVM (Earned Value Methodology) is a useful metric that can indicate when a project is falling behind or is ahead of
its baseline schedule. The EVM schedule variance will ultimately equal zero when the project is completed because
ALL the Planned Value will have been Earned. It is best used in conjunction with Critical Path Methodology (CPM)
• Cost Variance (CV). – CV = EV – AC
The amount of budget deficit or surplus at a given point in time, expressed as the difference between Earned Value
(EV) and the Actual Cost (AC)
The cost variance at the end of the project will be the difference between the Budget At Completion (BAC) and the
Actual amount spent. The CV is very critical because it indicates the relationship of physical performance to the cost
spent. A Negative CV is often difficult for the project to recover.
• Schedule Performance Index (SPI) – SPI = EV/PV
A measure of efficiency expressed as the ratio on Earned Value to Planned Value. An SPI value of LESS than 1.0
means that it is behind schedule and GREATER than 1.0 means that it’s ahead of the schedule
• Cost Performance Index (CPI) – CPI = EV/AC
A measure of cost efficiency of budgeted resources, expressed as ratio between Earned Value to Actual Cost. A CPI
value of LESS than 1.0 means that it is Over Budget and GREATER than 1.0 means that it’s Under Budget
2. Forecasting
As the project progresses, the PM may develop a forecast for the Estimate At Completion (EAC) that may differ from the
Budget At Completion (BAC) based on performance. If the BAC is deemed no longer viable, the forecasted EAC will be
used.
EACs are typically based on actual cost incurred, plus an Estimate to Complete (ETC) the remaining work.
The most common EAC forecasting approach is a manual bottom-up summation by the PM & the project team.
EAC = AC + Bottom-Up ETC
Three common methods of calculating EAC are:
• EAC forecast for ETC work performed at the budgeted rate: Accepts the actual project performance to date as
represented by the actual costs & predicts that ALL future ETC work will be accomplished at the budgeted rate.
When actual performance is unfavorable, the assumption that future performance will improve should be accepted
only when supported by risk analysis.
EAC = AC + (BAC – EV)
• EAC forecast for ETC work performed at the present CPI: Assumes what the project has experienced to date can be
expected to continue in the future.
EAC = BAC / CPI
2. Forecasting
3. To Complete Performance Index (TCPI)
4. Performance Reviews
5. Project Management Software
6. Reserve Analysis
PROJECT
DOCUMENTS
UPDATES
PROJECT
FUNDING
REQUIREMENTS
COST
BASELINE
Approved version of the time-phased project budget (excluding any management reserves)
that can only be changed via formal change control procedures. It is used as a basis for
comparison to actual results.
Project Documents that may be updated include, but not limited to:
Risk Register, Activity Cost Estimate, and Project Schedule
Derived from the cost baseline that include projected expenditures plus anticipated liabilities.
Funding are incremental, not continuous and may not be distributed evenly
Project
Budget
Cost
Baselin
e
Control
Accounts
WorkPackage
CostEstimates
Activity
Cost
Estimates
Manage
ment
Reserve
s
Contingen
cy
Reserves
Activity
Contingency
Reserves
TotalAmount
Project Budget Component
Pmp – pmbok 5th edition chapter7 project cost management

More Related Content

What's hot

Pmo Why?
Pmo Why?Pmo Why?
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
DavidMcLachlan1
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
Dilawar Abbas
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptx
AmjadAlk
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 
eCIO PPT What is a PMO
eCIO PPT What is a PMOeCIO PPT What is a PMO
eCIO PPT What is a PMODavid Niles
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavor
Imad Alsadeq
 
Project management
Project managementProject management
Project management
Jaya Velagapudi
 
CPM ORNEK CALISMA
CPM ORNEK CALISMACPM ORNEK CALISMA
CPM ORNEK CALISMA
Safak EBESEK
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
crmackenzie
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
pankajsh10
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
Project Management Solutions
 
Project scope management
Project scope managementProject scope management
Project scope management
Jody R Flower
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls FrameworkReuben Gonzales
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
PMP Mind Maps Complete
PMP Mind Maps CompletePMP Mind Maps Complete
PMP Mind Maps Complete
KareemBullard1
 
Project integration management
Project integration managementProject integration management
Project integration management
Prabudh Dhingra
 

What's hot (20)

Pmo final 1
Pmo final 1Pmo final 1
Pmo final 1
 
Pmo Why?
Pmo Why?Pmo Why?
Pmo Why?
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
PMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptxPMP Exam Prep Module 1.pptx
PMP Exam Prep Module 1.pptx
 
Project Control
Project ControlProject Control
Project Control
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
eCIO PPT What is a PMO
eCIO PPT What is a PMOeCIO PPT What is a PMO
eCIO PPT What is a PMO
 
Having a PMO with agile flavor
Having a PMO with agile flavorHaving a PMO with agile flavor
Having a PMO with agile flavor
 
Project management
Project managementProject management
Project management
 
CPM ORNEK CALISMA
CPM ORNEK CALISMACPM ORNEK CALISMA
CPM ORNEK CALISMA
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls Framework
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
PMP Mind Maps Complete
PMP Mind Maps CompletePMP Mind Maps Complete
PMP Mind Maps Complete
 
Project integration management
Project integration managementProject integration management
Project integration management
 

Similar to Pmp – pmbok 5th edition chapter7 project cost management

7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
Ala Ibrahim
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
Zaur Ahmadov, PMP
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
DavidMcLachlan1
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
Qussay Karam
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
ssuser9d62d6
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen657394
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Andersson Lujan Ojeda
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
Wasis Witjaksono
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
InayatSheikh1
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
KareemBullard1
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
Hossam Maghrabi
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
Cost management
Cost managementCost management
Cost management
Suranji Kannangara
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
HuyNguyen657394
 
Cost management
Cost managementCost management
Cost managementshkadry
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectSharad Srivastava
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
Glen Alleman
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
ArvinThamsir1
 

Similar to Pmp – pmbok 5th edition chapter7 project cost management (20)

7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Cost Management PMBOK
Cost Management PMBOKCost Management PMBOK
Cost Management PMBOK
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Cost management
Cost managementCost management
Cost management
 
Project managment 6
Project managment 6Project managment 6
Project managment 6
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Cost management
Cost managementCost management
Cost management
 
Presentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics ProjectPresentation - Scope and Schedule Management of Business Analytics Project
Presentation - Scope and Schedule Management of Business Analytics Project
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 

Recently uploaded

How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 

Recently uploaded (20)

How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 

Pmp – pmbok 5th edition chapter7 project cost management

  • 1. CHAPTER 7 Fourth Knowledge Area: Project Cost Management 1 PLAN COST MGMT 2 ESTIMATE COST 3 DETERMINE BUDGET 4 CONTROL COSTS
  • 2. Project Cost Management includes the processes involved in Planning, Estimating, Budgeting, Financing, Funding, Managing, and Controlling costs so that projects can be completed within budget 1. Plan Cost Management (Planning Process Group) The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. 2. Estimate Cost (Planning Process Group) The process of developing an approximation of the monetary resources needed to complete project activities 3. Determine Budget (Planning Process Group) The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline 4. Control Costs (Monitoring & Controlling Process Group) The process of monitoring the status of the project to update the project costs & managing changes to the cost baseline.
  • 3. Project Cost Management must consider stakeholder’s requirements for managing costs – each stakeholder will measure costs differently. Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities & the subsequent costs in using and supporting the deliverables. The cost management planning effort occurs early in the project & sets the framework for each of the cost management processes so that performance will be efficient.
  • 4. INPUTS TOOLS & TECHNIQUES OUTPUTS Plan Cost Management: Inputs, Tools & Techniques, & Outputs 1. Project Management Plan 2. Project Charter 3. Enterprise Environmental Factors (EEFs) 4. Organizational Process Assets (OPAs) 1. Expert Judgment 2. Analytical Techniques 3. Meeting 1. Schedule Management Plan • Plan Cost Management is the process of establishing the policies, procedures, and documentations for planning, managing, expending & controlling project cost. • It’s key benefit is it provides guidance & directions on how the project costs will be managed throughout the project
  • 5. OUTPU T 1 PROJECT MANAGEMEN T PLAN 4 ORGANIZATION AL PROCESS ASSETS (OPA) TOOLS & TECHNIQUE S COST MANAGEMENT PLAN 3 ENTERPRISE ENVIRONME NT FACTORS (EEF) 2 PROJECT CHARTER OUTPUT 1. EXPERT JUDGMENT 2. ANALYTICAL TECHNIQUES 3. MEETINGS Other Information 1. Org. Culture & Structure that influences cost 2. Market Conditions 3. Currency exchange for international projects 4. Published & Commercially Available Info 5. Project Management Information System • Financial controls procedures • Historical information & lessons learned • Financial databases; and • Existing formal & informal cost estimating & budgeting policies
  • 6. Describes how the project costs will be planned, structured & controlled. Cost management plan can establish: • Units of Measure • Level of Precision • Level of Accuracy • Organizational Procedures Links • Control Thresholds • Rules of Performance Measurement • Reporting Formats • Process Descriptions • Additional details such as description of strategic funding choices, procedure to account for fluctuation in currency exchange & cost reporting
  • 7. INPUTS TOOLS & TECHNIQUES OUTPUTS Plan Cost Management: Inputs, Tools & Techniques, & Outputs 1. Cost Management Plan 2. Human Resource Management Plan 3. Scope Baseline 4. Project Schedule 5. Risk Register 6. Enterprise Environmental Factors 7. Organizational Process Assets (OPAs) 1. Expert Judgment 2. Analogous Estimating 3. Parametric Estimating 4. Bottom-up Estimating 5. Three-points Estimating 6. Reserve Analysis 7. Cost of Quality 8. Project Management Software 9. Vendor Bid Analysis 10. Group Decision Making Techniques 1. Activity Cost Estimates 2. Basic of Estimates 3. Project Documents Updates • Estimate Cost is the process of developing an approximation of the monetary resources needed to complete project activities. • It’s key benefit is it determines the amount of cost required to complete project work.
  • 8. 3 SCOPE BASELINE 5 RISK REGISTER 4 PROJECT SCHEDUL E OUTPU T 1 COST MANAGEMEN T PLAN 7 ORGANIZATION AL PROCESS ASSETS (OPA) TOOLS & TECHNIQUE S BASIS OF ESTIMATES 6 ENTERPRISE ENVIRONME NT FACTORS (EEF) 2 H.R. MGMT PLAN OUTPUT 1. EXPERT JUDGMENT 2. ANALOGOUS ESTIMATING 3. PARAMETRIC ESTIMATING 4. THREE-POINT ESTIMATING 5. BOTTOM-UP ESTIMATING 6. RESERVE ANALYSIS 7. COST OF QUALITY 8. PROJECT MANAGEMENT SOFTWARE 9. VENDOR BID ANALYSIS 10. GROUP DECISION MAKING TECHNIQUES 1. Market Conditions 2. Published Commercially Info • Cost Estimating Policies • Cost Estimating Templates • Historical Information, and • Lessons Learned PROJECT DOCUMENTS UPDATES ACTIVITY COST ESTIMATES WBS Dictionary
  • 9. 1. Expert Judgment 2. Analogous Estimating – compare with similar past projects when limited amount of detailed info available 3. Parametric Estimating – uses statistical relationship relevant historical data & other variable (like square footage) to calculate a cost estimate for project work. It provides higher level of accuracy depending on past data 4. Bottom Up Estimating – cost of individual work packages are estimated to the greatest level for detail. Its accuracy is influenced by the size & complexity of the individual activity or work package. 5. Three-Point Estimating • Most Likely (cM) based on realistic effort assessment • Optimistic (cO) based on best case scenario • Pessimistic (cP) based on worst case scenario Depending on the assumed distribution of value within the range, there are 2 formulas: • Triangular Distribution. cE = (cO + cM + cP) /3 • Beta Distribution (from PERT analysis) cE = (cO + 4cM + cP) / 6
  • 10. 6. Reserve Analysis Contingency Reserves are the budget within cost baseline that is allocated for identified risks. It is often viewed as part of the budget to address the “known-unknowns” that can affect a project. It may be a percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis methods. 7. Cost of Quality (COQ) – it cost less to prevent quality issue than to fix it 8. Project Management Software – Computerized spreadsheets, simulation, and statistical tools are used to assist with cost estimating. 9. Vendor Bid Analysis – Cost estimates can be based on the responsive bids from qualified vendors 10.Group Decision-Making Techniques Team based approaches, such as brainstorming, the Delphi or Nominal Group Techniques are useful for engaging team members to improve estimate accuracy & commitment to the estimates.
  • 11. BASIS OF ESTIMATES PROJECT DOCUMENTS UPDATES ACTIVITY COST ESTIMATES Quantitative assessment of the probable costs required to complete project work. It can be presented in summary form or in detail. Cost are estimated for ALL resources that are applied to the activity cost estimate The amount and type of additional details supporting the cost estimates vary by application area. Supporting detail may include: • Documentation of the basis of the estimate (how it was developed), • Documentation of all assumptions made, • Documentation of any known constraints, • Indication of the range of possible estimates (like +/- 10%) to indicate that the item is expected to cost between a range of values, and • Indication of the confidence level of the final estimate. Project Documents that may be updated include, but not limited to, the risk register.
  • 12. INPUTS TOOLS & TECHNIQUES OUTPUTS Determine Budget: Inputs, Tools & Techniques, & Outputs 1. Cost Management Plan 2. Scope Baseline 3. Activity Cost Estimates 4. Basis of Estimates 5. Project Schedule 6. Resource Calendars 7. Risk Register 8. Agreements 9. Organizational Process Assets (OPAs) 1. Cost Aggregation 2. Reserve Analysis 3. Expert Judgment 4. Historical Relationship 5. Funding Limit Reconciliation 1. Cost Baseline 2. Project Funding 3. Project Documents Updates • Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline • It’s key benefit is it determines the cost baseline against which project performance can be monitored & controlled.
  • 13. 6 RESOURC E CALENDA RS 2 SCOPE BASELINE 7 RISK REGISTER 3 ACTIVITY COST ESTIMATE S OUTPU T 1 COST MANAGEMEN T PLAN 9 ORGANIZATION AL PROCESS ASSETS (OPA) TOOLS & TECHNIQUE S PROJECT FUNDING REQUIREMENTS 5 PROJECT SCHEDULE 4 BASIS OF ESTIMATE S OUTPUT 1. COST AGGREGRATION 2. RESERVE ANALYSIS 3. EXPERT JUDGMENT 4. HISTORICAL RELATIONSHIPS 5. FUNDING LIMIT RECONCILIATION • Existing formal & informal cost budgeting- related policies, procedures and guidelines; • Cost budgeting tools; and • Reporting methods PROJECT DOCUMENTS UPDATES COST BASELINE WBS Dictionary 8 AGREEMEN TS Info on which resources are assigned and when they are assigned
  • 14. 1. Cost Management Plan – describes how project costs are managed & controlled 2. Scope Baseline: Project Scope Statement; WBS; & WBS Dictionary. 3. Activity Cost Estimates – each activity in a work package are aggregated to get the cost estimate 4. Basis of Estimates – must specify basic assumptions related to inclusion, exclusion of indirect or other costs 5. Project Schedule – planned start & finish dates of activities, milestones, work packages & control accounts 6. Resource Calendars * – provide info on which resources are assigned and when they are assigned 7. Risk Register * – must be reviewed to consider how to aggregate the risk response cost. 8. Agreements * Applicable agreement information and cost relating to products, services, or results that have been or will be purchased are included when determining the budget. 9. Organizational Process Assets such as Existing formal/informal cost-budgeting policies, procedures & guidelines; Cost budgeting tools; and Reporting methods.
  • 15. 1. Cost Aggregation * costs are aggregated by work packages rolling up to the entire project 2. Reserve Analysis can establish both contingency reserves & management reserves for the project 3. Expert Judgment such as from Other departments, consultants, stakeholders (including the customers), professional & technical associations; and industry groups. 4. Historical Relationships * that result in parametric or analogous estimates to develop mathematical model to predict total project cost. The accuracy depends on if the: • Historical information used to develop the model is accurate. • Parameters used are readily quantifiable; and • Models are scalable 5. Funding Limit Reconciliation Expenditures must be reconciled with any funding limit. A variance may necessitate a rescheduling to level out the rate of expenditures by placing date constraints on the schedule.
  • 16. PROJECT DOCUMENTS UPDATES PROJECT FUNDING REQUIREMENTS COST BASELINE Approved version of the time-phased project budget (excluding any management reserves) that can only be changed via formal change control procedures. It is used as a basis for comparison to actual results. Project Documents that may be updated include, but not limited to: Risk Register, Activity Cost Estimate, and Project Schedule Derived from the cost baseline that include projected expenditures plus anticipated liabilities. Funding are incremental, not continuous and may not be distributed evenly Project Budget Cost Baselin e Control Accounts WorkPackage CostEstimates Activity Cost Estimates Manage ment Reserve s Contingen cy Reserves Activity Contingency Reserves TotalAmount Project Budget Component
  • 17. INPUTS TOOLS & TECHNIQUES OUTPUTS Control Costs: Inputs, Tools & Techniques, & Outputs 1. Project Management Plan 2. Project Funding Requirements 3. Work Performance Data 4. Organization Process Assets (OPAs) 1. Earned Value Management 2. Forecasting 3. To Complete Performance Index (TCPI) 4. Performance Reviews 5. Project Management Software 6. Reserve Analysis 1. Work Performance Info 2. Cost Forecasts 3. Change Requests 4. Project Management Plan Updates 5. Projects Documents Updates 6. Organizational Process Assets Updates • Control Costs is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. • It’s key benefit is it provides means to recognize variance from the plan in order to take corrective action & minimize risk.
  • 18. Much of the effort of cost control involves analyzing the relationship between the consumption of project funds to the physical work being accomplish for such expenditures that includes: • Influencing the factors that created changes to the authorized cost baseline; • Ensuring that all change requests are acted on a timely manner; • Managing the actual changes when they occur; • Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by activity, and in total for the project; • Monitoring cost performance to isolate and understand variances from the approved cost baseline; • Monitoring work performance against funds expended; • Preventing unapproved changes from being included in the reported cost of resource usage; • Informing appropriate stakeholders of all approved changes and associated costs; and • Bringing expected cost overruns within acceptable limits.
  • 19. OUTPU T 1 PROJECT MANAGEMEN T PLAN 4 ORGANIZATION AL PROCESS ASSETS (OPA) TOOLS & TECHNIQUE S COST FORECASTS 3 WORK PERFORMAN CE DATA 2 PROJECT FUNDING REQUIREMEN TS OUTPUT 1. EARNED VALUE MANAGEMENT 2. FORECASTING 3. TO COMPLETE PERFORMANCE INDEX (TCPI) 4. PERFORMANCE REVIEWS 5. PROJECT MANAGEMENT SOFTWARE 6. RESERVE ANALYIS • Existing formal & informal cost budgeting- related policies, procedures and guidelines; • Cost control tools; and • Monitoring & Reporting methods to be used CHANGE REQUESTS WORK PERFORMANCE INFORMATION PROJECT DOCUMENT UPDATES ORGANIZATIONAL PROCESS ASSETS UPDATES PROJECT MANAGEMENT PLAN UPDATES
  • 20. 1. Earned Value Management (EVM) A methodology that combines scope, schedule, and resource measurements to asses project performance & progress to form performance baseline. It is a technique that requires the formation of an integrated baseline to measure performance of the project. EVM develops and monitor three key dimensions for each work package & control account: • Planned Value (PV). Authorized budget assigned to scheduled work for an activity or WBS component (not including management reserve). It is allocated by phase over the life of the project, but at a given moment, PV defines the physical work that should have been accomplished. The total of the PV is sometimes referred to as the Performance Measurement Baseline (PMB). Total PV for the project is also known at Budget At Completion (BAC) • Earned Value (EV). A measure of work performed expressed in terms on the budget authorized for that work. EV measured needs to be related to the PMB and it cannot be greater than the authorized PV budget for a component. It’s often used to calculate the percent complete of a project. • Actual Cost (AC). The realized cost incurred for work performed on an activity during a specific time period. It is the total cost incurred in accomplishing the work that the EV measured. The AC needs to correspond in definition to what was budgeted in the PV and measured in the EV. AC has no upper limit; whatever spent to achieve EV will be measured.
  • 21. Variances from the approved baseline will also be monitored: • Schedule Variance (SV). – SV = EV – PV A measure of schedule performance expressed as the difference between the Earned Value (EV) and the Planned Value (PV) EVM (Earned Value Methodology) is a useful metric that can indicate when a project is falling behind or is ahead of its baseline schedule. The EVM schedule variance will ultimately equal zero when the project is completed because ALL the Planned Value will have been Earned. It is best used in conjunction with Critical Path Methodology (CPM) • Cost Variance (CV). – CV = EV – AC The amount of budget deficit or surplus at a given point in time, expressed as the difference between Earned Value (EV) and the Actual Cost (AC) The cost variance at the end of the project will be the difference between the Budget At Completion (BAC) and the Actual amount spent. The CV is very critical because it indicates the relationship of physical performance to the cost spent. A Negative CV is often difficult for the project to recover. • Schedule Performance Index (SPI) – SPI = EV/PV A measure of efficiency expressed as the ratio on Earned Value to Planned Value. An SPI value of LESS than 1.0 means that it is behind schedule and GREATER than 1.0 means that it’s ahead of the schedule • Cost Performance Index (CPI) – CPI = EV/AC A measure of cost efficiency of budgeted resources, expressed as ratio between Earned Value to Actual Cost. A CPI value of LESS than 1.0 means that it is Over Budget and GREATER than 1.0 means that it’s Under Budget
  • 22. 2. Forecasting As the project progresses, the PM may develop a forecast for the Estimate At Completion (EAC) that may differ from the Budget At Completion (BAC) based on performance. If the BAC is deemed no longer viable, the forecasted EAC will be used. EACs are typically based on actual cost incurred, plus an Estimate to Complete (ETC) the remaining work. The most common EAC forecasting approach is a manual bottom-up summation by the PM & the project team. EAC = AC + Bottom-Up ETC Three common methods of calculating EAC are: • EAC forecast for ETC work performed at the budgeted rate: Accepts the actual project performance to date as represented by the actual costs & predicts that ALL future ETC work will be accomplished at the budgeted rate. When actual performance is unfavorable, the assumption that future performance will improve should be accepted only when supported by risk analysis. EAC = AC + (BAC – EV) • EAC forecast for ETC work performed at the present CPI: Assumes what the project has experienced to date can be expected to continue in the future. EAC = BAC / CPI
  • 23. 2. Forecasting 3. To Complete Performance Index (TCPI) 4. Performance Reviews 5. Project Management Software 6. Reserve Analysis
  • 24. PROJECT DOCUMENTS UPDATES PROJECT FUNDING REQUIREMENTS COST BASELINE Approved version of the time-phased project budget (excluding any management reserves) that can only be changed via formal change control procedures. It is used as a basis for comparison to actual results. Project Documents that may be updated include, but not limited to: Risk Register, Activity Cost Estimate, and Project Schedule Derived from the cost baseline that include projected expenditures plus anticipated liabilities. Funding are incremental, not continuous and may not be distributed evenly Project Budget Cost Baselin e Control Accounts WorkPackage CostEstimates Activity Cost Estimates Manage ment Reserve s Contingen cy Reserves Activity Contingency Reserves TotalAmount Project Budget Component