SlideShare a Scribd company logo
Scope Management
Chapter 5
“Is the process of defining what work is required and making sure all of that work &
only that work is done successfully.”
• “Completion of the project scope is measured against the PMP.”
• “Completion of the product scope is measured against the product requirements.”
Process Process Group Key Deliverables
5.1 Plan Scope Management Planning Scope Management Plan
5.2 Collect Requirements Planning Requirements Document
5.3 Define Scope Planning Project Scope Statement
5.4 Create WBS Planning WBS, WBS Dictionary
5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables
5.6 Control Scope Monitoring & Controlling Change Requests
Scope Management
Chapter 5
Plan Scope Management
Process 1
Key Points
 “Documents how the project scope is defined, validated, controlled & managed throughout the project”
 Process generates 2 management plans that both become part of the PMP
 “The plan helps to reduce the risk of project scope creep”
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Is the process of determining & documenting stakeholder’s needs & requirements in detail
 Critical to project’s success as missed requirements could mean major changes & conflicts
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Project manager chooses the best Tools & Techniques to gather info:
 Interviews, Focus Groups, Facilitated Workshops,
 Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps
 Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus
 Questionnaires, Surveys, Observations, Prototypes, Benchmarking
 Context Diagrams, Document Analysis
 Requirements Documentation: Acceptance Criteria used to set Scope Baseline
 Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a
project objective”
Scope Management
Chapter 5
Define Scope
Process 3
Key Points
 The process of developing a detailed description of the project & product/deliverable
 Defines requirement boundaries – of those collected included or excluded from project scope
 Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 “Is the hierarchical decomposition of the total scope of the work to be done by the project…
into smaller more manageable parts/deliverables.”
 Is the process of subdividing, breaking down, decomposing the project scope into
manageable work packages that is a visual to the entire team.
 Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 WBS is the most important process in Scope Management & foundation of the project
 must be graphical & can be organized by Phase or Category
 used as a basis to estimate costs & time at the work package level
 The entire project is represented in the WBS, if not, then it’s not part of the project
 Control Accounts: Unique accounting codes assigned to track completion of work
 Created with help of the team’s experience to be realistic
 Helps gain the team’s buy-in & builds the team
 Keeps up team momentum by letting ppl see their importance to complete their work
 Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
Scope Management
Chapter 5
Validate Scope
Process 5
Key Points
 “Is the process of formalizing acceptance of completed project deliverables.”
 Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables
 Recommended to validate scope at the end of each phase and/or multiple times in a project
 Validate Scope process: the customer checks & approves deliverables
 Control Quality process: the QC dept checks deliverables to see that requirements are met.
Scope Management
Chapter 5
Control Scope
Process 6
Key Points
 “Is the process of monitoring the project status (scope performance aka work completed) by managing
changes between the work performance data against the scope baseline.”
 Is a proactive process lead by the Project Manager to prevent project changes
 Incontrolled adjustments to project constraints lead to Scope Creep
Scope Management
Chapter 5

More Related Content

What's hot

CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
Muzette Charles, PMP
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
AnAr project management overview
AnAr project management overviewAnAr project management overview
AnAr project management overview
AnAr Solutions Pvt. Ltd.
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
Joshua Render
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
IIT delhi
 
An Introduction to Agile
An Introduction to AgileAn Introduction to Agile
An Introduction to Agile
DavidMcLachlan1
 
3 Steps to Optimize Project Reporting using SharePoint
3 Steps to Optimize Project Reporting using SharePoint3 Steps to Optimize Project Reporting using SharePoint
3 Steps to Optimize Project Reporting using SharePoint
BrightWork
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
rajat898
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing management
Dhamo daran
 
Project Management 3 Scope Management
Project Management 3 Scope ManagementProject Management 3 Scope Management
Project Management 3 Scope Management
grmkslideshare
 
Scala signature introduction
Scala signature introductionScala signature introduction
Scala signature introduction
Boyan Yordanov
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
danieljohn810
 
Proposal to revise documentation
Proposal to revise documentationProposal to revise documentation
Proposal to revise documentation
rgroup99
 
CEM AX ProjectPro
CEM AX ProjectProCEM AX ProjectPro
CEM AX ProjectPro
CEM Business Solutions
 
Factors for Successful Projects
Factors for Successful ProjectsFactors for Successful Projects
Factors for Successful Projects
Trevor Roberts
 
Lunch time presentation scope management
Lunch time presentation scope managementLunch time presentation scope management
Lunch time presentation scope management
AHMED NADIM JILANI
 
PMP CAPM study guide Scope
PMP CAPM study guide ScopePMP CAPM study guide Scope
PMP CAPM study guide Scope
Ahmed Higazi, PMP CSM
 
ProofHQ and DAM
ProofHQ and DAMProofHQ and DAM
ProofHQ and DAM
ProofHQ
 
Introduction to Scrum
Introduction to ScrumIntroduction to Scrum
Introduction to Scrum
Balavignesh Kasinathan
 
Rising from projects to programs and improve accountability - Oracle Primaver...
Rising from projects to programs and improve accountability - Oracle Primaver...Rising from projects to programs and improve accountability - Oracle Primaver...
Rising from projects to programs and improve accountability - Oracle Primaver...
p6academy
 

What's hot (20)

CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
AnAr project management overview
AnAr project management overviewAnAr project management overview
AnAr project management overview
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
An Introduction to Agile
An Introduction to AgileAn Introduction to Agile
An Introduction to Agile
 
3 Steps to Optimize Project Reporting using SharePoint
3 Steps to Optimize Project Reporting using SharePoint3 Steps to Optimize Project Reporting using SharePoint
3 Steps to Optimize Project Reporting using SharePoint
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
 
13 project control & closing management
13 project control & closing management13 project control & closing management
13 project control & closing management
 
Project Management 3 Scope Management
Project Management 3 Scope ManagementProject Management 3 Scope Management
Project Management 3 Scope Management
 
Scala signature introduction
Scala signature introductionScala signature introduction
Scala signature introduction
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
 
Proposal to revise documentation
Proposal to revise documentationProposal to revise documentation
Proposal to revise documentation
 
CEM AX ProjectPro
CEM AX ProjectProCEM AX ProjectPro
CEM AX ProjectPro
 
Factors for Successful Projects
Factors for Successful ProjectsFactors for Successful Projects
Factors for Successful Projects
 
Lunch time presentation scope management
Lunch time presentation scope managementLunch time presentation scope management
Lunch time presentation scope management
 
PMP CAPM study guide Scope
PMP CAPM study guide ScopePMP CAPM study guide Scope
PMP CAPM study guide Scope
 
ProofHQ and DAM
ProofHQ and DAMProofHQ and DAM
ProofHQ and DAM
 
Introduction to Scrum
Introduction to ScrumIntroduction to Scrum
Introduction to Scrum
 
Rising from projects to programs and improve accountability - Oracle Primaver...
Rising from projects to programs and improve accountability - Oracle Primaver...Rising from projects to programs and improve accountability - Oracle Primaver...
Rising from projects to programs and improve accountability - Oracle Primaver...
 

Similar to CAPM Week 2 Chapter 5

Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
Hisham Ali,PMP
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
ejlp12
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
Joshua Render
 
Project scope management 2
Project scope management 2Project scope management 2
Project scope management 2
Mohammad Ashraf Khan, PMP
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
MohamadAGhareb
 
5 scope
5 scope5 scope
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
GoharSaeed6
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
Qussay Karam
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
Omer Alsayed PhD,MBA, PMP®
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
MUST
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
GlobalSkillup
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
MUST
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
Dhamo daran
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
Omer Alsayed PhD,MBA, PMP®
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
Mohammad Ashraf Khan, PMP
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
Arlene Smith
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
Agus Suhanto
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptx
KareemBullard1
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
Ready to Train
 
Chapter 5- Project mgt.pptx
Chapter 5- Project  mgt.pptxChapter 5- Project  mgt.pptx
Chapter 5- Project mgt.pptx
teshome eshetu
 

Similar to CAPM Week 2 Chapter 5 (20)

Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
Project scope management 2
Project scope management 2Project scope management 2
Project scope management 2
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
 
5 scope
5 scope5 scope
5 scope
 
3&4. project scope management at project.ppt
3&4. project scope management at project.ppt3&4. project scope management at project.ppt
3&4. project scope management at project.ppt
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
 
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge AreaOnline PMP Training Material for PMP Exam - Scope Management Knowledge Area
Online PMP Training Material for PMP Exam - Scope Management Knowledge Area
 
L2_Scope Management.ppt
L2_Scope Management.pptL2_Scope Management.ppt
L2_Scope Management.ppt
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Project Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptxProject Scope Management Chapter 05.pptx
Project Scope Management Chapter 05.pptx
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 
Chapter 5- Project mgt.pptx
Chapter 5- Project  mgt.pptxChapter 5- Project  mgt.pptx
Chapter 5- Project mgt.pptx
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
Muzette Charles, PMP
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
Muzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
Muzette Charles, PMP
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
Muzette Charles, PMP
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
Muzette Charles, PMP
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
Muzette Charles, PMP
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
Muzette Charles, PMP
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
Muzette Charles, PMP
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 

Recently uploaded

PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
สมใจ จันสุกสี
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
Celine George
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
paigestewart1632
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
Katrina Pritchard
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 

Recently uploaded (20)

PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
คำศัพท์ คำพื้นฐานการอ่าน ภาษาอังกฤษ ระดับชั้น ม.1
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17How to Fix the Import Error in the Odoo 17
How to Fix the Import Error in the Odoo 17
 
Cognitive Development Adolescence Psychology
Cognitive Development Adolescence PsychologyCognitive Development Adolescence Psychology
Cognitive Development Adolescence Psychology
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 

CAPM Week 2 Chapter 5

  • 1. Scope Management Chapter 5 “Is the process of defining what work is required and making sure all of that work & only that work is done successfully.” • “Completion of the project scope is measured against the PMP.” • “Completion of the product scope is measured against the product requirements.” Process Process Group Key Deliverables 5.1 Plan Scope Management Planning Scope Management Plan 5.2 Collect Requirements Planning Requirements Document 5.3 Define Scope Planning Project Scope Statement 5.4 Create WBS Planning WBS, WBS Dictionary 5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables 5.6 Control Scope Monitoring & Controlling Change Requests
  • 2. Scope Management Chapter 5 Plan Scope Management Process 1 Key Points  “Documents how the project scope is defined, validated, controlled & managed throughout the project”  Process generates 2 management plans that both become part of the PMP  “The plan helps to reduce the risk of project scope creep”
  • 3. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Is the process of determining & documenting stakeholder’s needs & requirements in detail  Critical to project’s success as missed requirements could mean major changes & conflicts
  • 4. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Project manager chooses the best Tools & Techniques to gather info:  Interviews, Focus Groups, Facilitated Workshops,  Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps  Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus  Questionnaires, Surveys, Observations, Prototypes, Benchmarking  Context Diagrams, Document Analysis  Requirements Documentation: Acceptance Criteria used to set Scope Baseline  Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a project objective”
  • 5. Scope Management Chapter 5 Define Scope Process 3 Key Points  The process of developing a detailed description of the project & product/deliverable  Defines requirement boundaries – of those collected included or excluded from project scope  Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
  • 6. Scope Management Chapter 5 Create WBS Process 4 Key Points  “Is the hierarchical decomposition of the total scope of the work to be done by the project… into smaller more manageable parts/deliverables.”  Is the process of subdividing, breaking down, decomposing the project scope into manageable work packages that is a visual to the entire team.  Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
  • 7. Scope Management Chapter 5 Create WBS Process 4 Key Points  WBS is the most important process in Scope Management & foundation of the project  must be graphical & can be organized by Phase or Category  used as a basis to estimate costs & time at the work package level  The entire project is represented in the WBS, if not, then it’s not part of the project  Control Accounts: Unique accounting codes assigned to track completion of work  Created with help of the team’s experience to be realistic  Helps gain the team’s buy-in & builds the team  Keeps up team momentum by letting ppl see their importance to complete their work  Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
  • 8. Scope Management Chapter 5 Validate Scope Process 5 Key Points  “Is the process of formalizing acceptance of completed project deliverables.”  Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables  Recommended to validate scope at the end of each phase and/or multiple times in a project  Validate Scope process: the customer checks & approves deliverables  Control Quality process: the QC dept checks deliverables to see that requirements are met.
  • 9. Scope Management Chapter 5 Control Scope Process 6 Key Points  “Is the process of monitoring the project status (scope performance aka work completed) by managing changes between the work performance data against the scope baseline.”  Is a proactive process lead by the Project Manager to prevent project changes  Incontrolled adjustments to project constraints lead to Scope Creep