The document outlines a 29-week construction schedule for a building project. It details the various construction activities that will take place each week, including earthworks, piling, formwork, concrete works, services installation, and brickwork. Key activities involve site clearing, excavation, piling, pile caps and foundations, ground beams and slabs on the ground floor, first floor and second floor, with columns and staircases also constructed. The schedule provides information on duration, materials, equipment, workers and technical details for each construction activity across the 29 weeks.
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
Post tensioning company method statement | shivforce.in Sathish Kumar
Shivforce is an expert in post tensioned and pre tensioned system contractors in chennai, TN, India. This PT slab Company helps its partners design and build more imaginative, efficient and durable post tensioned structures in chennai, Coimbatore,TN, India.
SF ENGINEERING SYSTEMS (INDIA) PVT LTD was established by a team of Singapore and Indian experienced professionals in the year of 2013 with the aim to provide value added engineering solutions to our clients using post tensioning technology.
We as a specialist agency in post tensioning, offer efficient structural solution to building and infrastructure works.
For innovation in construction, use video presentations with 3D animations to plan and communicate how a project will be carried out and the timeline. This presentation can be used to communicate with the Client, Stakeholders and Site Team.
Post tensioning company method statement | shivforce.in Sathish Kumar
Shivforce is an expert in post tensioned and pre tensioned system contractors in chennai, TN, India. This PT slab Company helps its partners design and build more imaginative, efficient and durable post tensioned structures in chennai, Coimbatore,TN, India.
SF ENGINEERING SYSTEMS (INDIA) PVT LTD was established by a team of Singapore and Indian experienced professionals in the year of 2013 with the aim to provide value added engineering solutions to our clients using post tensioning technology.
We as a specialist agency in post tensioning, offer efficient structural solution to building and infrastructure works.
Make a Gantt Chart from the activities and tasks - Case Descriptio.pdfPierschdJohnstonb
Make a Gantt Chart from the activities and tasks :
Case Description
The City of Toronto has progressed on so many fronts since the October 2019 municipal election
saw a liberal-minded mayor elected to office. The dark, backward days of former Mayor Bobby
Bored and his conservative, hawkish brother are a distant memory.
In addition to new public transit plans, the city moved quickly to initiate a project to replace its
professional baseball stadium. The current stadium, built in the late 1980s is outdated and
generally recognized as the worst professional stadium in North America.
The G&E Company is preparing a bid to build the new 74,000 seat Avignon Stadium (named
after a beautiful town in southern France). The construction must start June 1 2020, and be
completed in time for the start of the 2024 season. A penalty clause of $100,000 per day of delay
beyond April 20, 2024, is written into the contract.
Ben Keith, the president of the company, expressed optimism at obtaining the contract and
revealed that the company could net as much as $5 million on the project. He also said if they are
successful, the prospects for future projects are quite good since there is a projected renaissance
in building classic baseball parks with modern luxury boxes.
Activity Table
ID Activity
1 Baseball Stadium
2 Clear stadium site
3 Demolish building
4 Set up construction site
5 Drive support piling
6 Pour lower concrete bowl
7 Pour main concourse
8 Install playing field
9 Construct upper steel bowl
10 Install seats
11 Build luxury boxes
12 Install electronic
scoreboards
13 Stadium infrastructure
14 Construct steel canopy
Duration
Predecessor(s)
70 days --- 30 days 2 ___ days 3 120 days 2 ___ days 5 120 days 3,6 90 days 3,6 120 days 3,6
140 days 7,9 90 days 7,9 30 days 7,9
120 days 7,9 75 days 10
15 Light installation
16 Build roof supports
17 Construct roof
18 Install roof tracks
19 Install roof
20 Inspection
30 days 14 90 days 6 ___ days 16 90 days 16
Case Description - Avignon Baseball Stadium
90 days ___ days
17,18 8,11,13,15,19
The baseball stadium is an outdoor structure with a retractable roof. The project begins with
clearing the site (activity 2). Once the site is clear, work can start simultaneously on the structure
itself and demolishing an adjacent building site (activity 3). This demolition is necessary to
create a construction stage for storing materials and equipment (activity 4).
The work on the stadium begins by driving 160 support pilings (activity
5). Next comes the pouring of the lower concrete bowl (activity 6). Once this is done and the
construction site has been set up, then the pouring of the main concourse (activity 7)), the
installation of the playing field (activity 8), and the construction of the upper steel bowl can
occur (activity 9).
Once the concourse and upper bowl are completed, work can start simultaneously on building
the luxury boxes (activity 11), installing the seats (activity 10), installing the electronic
scoreboards (ac.
Company Valuation webinar series - Tuesday, 4 June 2024FelixPerez547899
This session provided an update as to the latest valuation data in the UK and then delved into a discussion on the upcoming election and the impacts on valuation. We finished, as always with a Q&A
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
The world of search engine optimization (SEO) is buzzing with discussions after Google confirmed that around 2,500 leaked internal documents related to its Search feature are indeed authentic. The revelation has sparked significant concerns within the SEO community. The leaked documents were initially reported by SEO experts Rand Fishkin and Mike King, igniting widespread analysis and discourse. For More Info:- https://news.arihantwebtech.com/search-disrupted-googles-leaked-documents-rock-the-seo-world/
Recruiting in the Digital Age: A Social Media MasterclassLuanWise
In this masterclass, presented at the Global HR Summit on 5th June 2024, Luan Wise explored the essential features of social media platforms that support talent acquisition, including LinkedIn, Facebook, Instagram, X (formerly Twitter) and TikTok.
Cracking the Workplace Discipline Code Main.pptxWorkforce Group
Cultivating and maintaining discipline within teams is a critical differentiator for successful organisations.
Forward-thinking leaders and business managers understand the impact that discipline has on organisational success. A disciplined workforce operates with clarity, focus, and a shared understanding of expectations, ultimately driving better results, optimising productivity, and facilitating seamless collaboration.
Although discipline is not a one-size-fits-all approach, it can help create a work environment that encourages personal growth and accountability rather than solely relying on punitive measures.
In this deck, you will learn the significance of workplace discipline for organisational success. You’ll also learn
• Four (4) workplace discipline methods you should consider
• The best and most practical approach to implementing workplace discipline.
• Three (3) key tips to maintain a disciplined workplace.
Premium MEAN Stack Development Solutions for Modern BusinessesSynapseIndia
Stay ahead of the curve with our premium MEAN Stack Development Solutions. Our expert developers utilize MongoDB, Express.js, AngularJS, and Node.js to create modern and responsive web applications. Trust us for cutting-edge solutions that drive your business growth and success.
Know more: https://www.synapseindia.com/technology/mean-stack-development-company.html
Kseniya Leshchenko: Shared development support service model as the way to ma...Lviv Startup Club
Kseniya Leshchenko: Shared development support service model as the way to make small projects with small budgets profitable for the company (UA)
Kyiv PMDay 2024 Summer
Website – www.pmday.org
Youtube – https://www.youtube.com/startuplviv
FB – https://www.facebook.com/pmdayconference
Affordable Stationery Printing Services in Jaipur | Navpack n PrintNavpack & Print
Looking for professional printing services in Jaipur? Navpack n Print offers high-quality and affordable stationery printing for all your business needs. Stand out with custom stationery designs and fast turnaround times. Contact us today for a quote!
Digital Transformation and IT Strategy Toolkit and TemplatesAurelien Domont, MBA
This Digital Transformation and IT Strategy Toolkit was created by ex-McKinsey, Deloitte and BCG Management Consultants, after more than 5,000 hours of work. It is considered the world's best & most comprehensive Digital Transformation and IT Strategy Toolkit. It includes all the Frameworks, Best Practices & Templates required to successfully undertake the Digital Transformation of your organization and define a robust IT Strategy.
Editable Toolkit to help you reuse our content: 700 Powerpoint slides | 35 Excel sheets | 84 minutes of Video training
This PowerPoint presentation is only a small preview of our Toolkits. For more details, visit www.domontconsulting.com
Digital Transformation and IT Strategy Toolkit and Templates
Bungalow
1. BUILDING CONSTRUCTION 1 (ARC 1523)
DEGREE YEAR 1 SEM 2 (MAR 14)
PROJECT 2: Construction Activities and Process
YAP ZHI JUN 0310738
2. Week 1
Construction Activity 1: Earthwork
Duration: 6 Days
Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer
assistant (1)
Technical information: Survey topography for measurement of earthwork quantities.
Week 2
Construction Activity 1: Earthwork
Duration: 6 Days
Equipment: Backhoe (1), excavator (1), dumper (1)
Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1)
Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.
3. Week 3 & 4
Construction Activity 1: Earthwork
Duration: 12 Days
Equipment: Portable penetrometer (1)
Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil
engineer (1), civil engineer assistant (1)
Technical information: Mackintosh Probe (MP) test carried out for testing soft soils
and determining suitable materials.
4. Week 5
Construction Activity 1: Earthwork
Duration: 6 Days
Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1)
Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1),
general worker (1), grader (1), rollers (1)
Technical information: Site is excavated to required lengths, depths, breadths, inclinations
and curvatures
Week 6
Construction Activity 1: Earthwork
Duration: 6 Days
Materials: Timber formwork, gravel
Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire
nails, theodolite, wooden pegs, drill hammer
Skilled worker: Carpenter (2), general worker (1)
Technical information: Filling materials to lines, levels and grades required to complete
permanent construction.
5. Week 7
Construction activity 1: Transporting piles
Duration: 2 days
Materials: piles
Equipment: Lorry (2), Crane (1)
Skilled worker: Lorry driver (4), Crane Operator (1)
Technical information: Transporting piles from factory, lift the piles by using crane from lorry
after reaching the site.
Week 8
Construction activity 1: Pile driving process
Duration: 12 days
Materials: piles, pile cushion, bituminous paint
Equipment: Hydraulic drop hammer (1)
Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3)
Technical information: Mobilize the hydraulic drop hammer to the intended pile position
after marking penetration of the piles, set out the position of drop hammer above the pile
point, pile driving, weld the joints between the piles, and apply bituminous paint around the
joints of welded piles to prevent rusting.
6. Week 9
Construction activity 1: Cut off process
Duration: 3 days
Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1)
Skilled worker: Excavator operator (1), General worker (2)
Technical information: Excavate 1m to 1.5m depth by using multipurpose excavator, cut the
piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in
the pile is cut by oxy-cutter.
Week 10
Construction activity 1: Set up formwork for pile cap
Duration: 5 days
Material: Plywood, nails, reinforcement
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general worker (3)
Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and
set up the reinforcement for column stump before pouring the concrete.
7. Week 11
Construction activity 1: Pour concrete into the formwork
Duration: 2 days
Material: Concrete
Equipment: Concrete mixer truck, Skip, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (3)
Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its
strength by preventing air pockets.
Construction activity 2: Pile cap harden process
Duration: 7 days
Technical information: Let the concrete pile cap harden for 7 days to wait it mature and
sufficient strength, open formwork after completed.
8. Week 12
Construction activity 1: Set up formwork for column stump
Duration: 2 days
Material: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: General worker (2)
Technical information: Set up formwork for column stump before pouring the concrete.
Construction activity 2: Underground services
Duration: 6 days
Material: Metal conduit, steel/ aluminium tubing or PVC tubing, hexagonal plumbing fitting,
plumbing sealant
Equipment: Plow chute, winch
Skilled worker: Electrician (1), general worker (2), plumber (1)
Technical information: Bury cable preinstalled in cable-in-conduit (CIC) and main plumbing
pipes at excavated level.
9. Week 13
Construction activity 1: Pour concrete into the formwork
Duration: 2 days
Material: Concrete
Equipment: Concrete mixer truck, Skip, Concrete vibrator
Skilled worker:
Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate the concrete to increase its strength.
Construction activity 2: Column stump harden process
Duration: 7 days
Technical information: Let the concrete column stump harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
10. Week 14
Construction activity 1: Back filling the pile foundation
Duration: 1 day
Material: soil
Equipment: Multipurpose excavator (1)
Skilled worker: Multipurpose excavator Operator
Technical information: After the harden process, fill up the excavated part around the
foundation to move on to the next process.
11. Week 15
Construction Activity 1: Construction of ground beam (Ground floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
12. Week 16
Construction Activity 1: Slab (Ground floor)
Duration: 6 Days
Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck,
concrete vibrator, tipper, wheelbarrow.
Skilled worker: General worker (2), carpenter (1), bar bender (2)
Technical information: build formwork with plywood, fix reinforced steel, construction
slab formwork, slump test and pour concrete.
Thickness range of plywood: 7mm - 32mm
13. Week 17
Construction Activity 1: Construction of columns (Ground floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
14. Week 18
Construction Activity 1: Construction of beam (First floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
15. Week 19
Construction Activity 1: Construction of slab (First Floor)
Duration: 6 Days
Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete
vibrator, tipper, wheelbarrow.
Skilled worker: General worker (2), carpenter (1), bar bender (2)
Technical information: build formwork with plywood, fix reinforced steel, construction slab
formwork, slump test and pour concrete.
Thickness range of plywood: 7mm - 32mm
16. Week 20
Construction Activity 1: Staircase (Ground floor)
Duration: 3 Days
Materials: Ply Woods, Timber Battens
Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
Skilled worker: Carpenter (1), Joinery (1)
Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the
side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (Ground floor)
Duration: 3 Days
Materials: Timber, Metal or Prefabricated Formwork
Equipment: Drill, Hammer, Hand Saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Construct formwork by laying out riser heights and tread widths
followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut
and nailed cleats to plank, nail riser form boards to the ends of cleats.
17. Week 21
Construction Activity 1: Staircase (Ground floor)
Duration: 2 Days
Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve
Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Create strong grid of rebar, two or more pieces of rebar cross are
joined together. Secure riser form board with cleats attached about an inch above the stairs
layout to the slide form.
Construction Activity 2: Staircase (Ground floor)
Duration: 4 Days
Materials: Concrete, Long screws, Nails
Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
Skilled worker: Carpenters (2)
Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to
prevent cracks for up to one week while it cures.
18. Week 22
Construction Activity 1: Construction of columns (First floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
19. Week 23
Construction Activity 1: Construction of beam (Second floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
20. Week 24
Construction Activity 1: Slab (Second Floor)
Duration: 6 Days
Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete
vibrator, tipper, wheelbarrow.
Skilled worker: General worker (2), carpenter (1), bar bender (2)
Technical information: build formwork with plywood, fix reinforced steel, construction slab
formwork, slump test and pour concrete.
Thickness range of plywood: 7mm - 32mm
21. Week 25
Construction Activity 1: Staircase (First floor)
Duration: 3 Days
Materials: Ply Woods, Timber Battens
Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
Skilled worker: Carpenter (1), Joinery (1)
Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the
side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (First floor)
Duration: 3 Days
Materials: Timber, Metal or Prefabricated Formwork
Equipment: Drill, Hammer, Hand Saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Construct formwork by laying out riser heights and tread widths
followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut
and nailed cleats to plank, nail riser form boards to the ends of cleats.
22. Week 26
Construction Activity 1: Staircase (First floor)
Duration: 2 Days
Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve
Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
Skilled worker: Bar Benders (1), Formwork Carpenters (1)
Technical information: Create strong grid of rebar, two or more pieces of rebar cross are
joined together. Secure riser form board with cleats attached about an inch above the stairs
layout to the slide form.
Construction Activity 2: Staircase (First floor)
Duration: 4 Days
Materials: Concrete, Long screws, Nails
Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
Skilled worker: Carpenters (2)
Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to
prevent cracks for up to one week while it cures.
23. Week 27
Construction Activity 1: Construction of columns (Second floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1), bar bending machine (1), table saw
Skilled worker: Carpenter (2), bar bender (1), general worker (1)
Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
24. Week 28
Construction Activity 1: Construction of beam (Third floor)
Duration: 6 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete (1)
Skilled worker: Carpenter (2) , bar bender (1), general worker (1)
Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
25. Week 29
Construction Activity 1: Brickwork (Ground floor)
Duration: 5 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Installation of door frame (Ground floor)
Duration: 2 days
Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties,
hinges, spreader bars.
Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
Skilled worker: general worker (1), door and window installer (1)
Technical information: Mark door and bricks area, use timber to prop up door to standing
position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place
mortar into gap of the brick and frame, insert wire brick ties.
26. Week 30
Construction Activity 1: Brickwork (First floor)
Duration: 5 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Brickwork – Rendering (Ground floor)
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
27. Week 31
Construction Activity 1: Brickwork (Second floor)
Duration: 5 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Brickwork – Rendering (First floor)
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
28. Week 32
Construction Activity 2: Brickwork – Rendering (Second floor)
Duration: 3 Days
Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
Technical information:
Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Construction Activity 2: Installation of door frame (First and Second floors)
Duration: 2 days
Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties,
hinges, spreader bars.
Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
Skilled worker: general worker (1), door and window installer (1)
Technical information: Mark door and bricks area, use timber to prop up door to standing
position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place
mortar into gap of the brick and frame, insert wire brick ties.
30. Week 35
Construction Activity 1: Roof
Duration: 6 Days
Materials: Metal trusses
Equipment: Driller, screw driver, spiral screw, measuring tape
Skilled worker: General worker (1), truss erector (1)
Technical information: Fix truss.
Construction Activity 2: Roof
Duration: 6 Days
Materials: Meranti timber formwork
Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails,
measuring tape
Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffold
(1)
Technical information: Progressively install temporary brace as scaffolding is erected.
Construction Activity 3: Roof
Duration: 6 Days
Materials: Metal trusses
Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape
Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)
Technical information: Install permanent lateral bracing to truss.
31. Week 36
Construction Activity 1: Roof
Duration: 6 Days
Materials: Metal trusses
Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape
Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)
Technical information: Install permanent lateral bracing to truss.
Construction Activity 2: Roof
Duration: 6 Days
Materials: Metal anchor sling, roof anchor bracket
Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
Skilled worker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install anchor slings.
Week 37
Construction Activity 1: Roof
Duration: 3 Days
Materials: Chicken netting
Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
Skilled worker: Roofer (1), general worker (1)
Technical information: Install chicken netting.
Construction Activity 2: Roof
Materials: Aluminium sheet
Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
Skilled worker: Roofer (1), general worker (1)
Technical information: Install aluminium sheathing.
32. Week 38
Construction Activity 1: Roof
Duration: 6 Days
Materials: Metal batten strips (aluminium)
Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
Skilled worker: Roofer (1), general worker (1)
Technical information: Install batten.
Week 39
Construction Activity 1: Roof
Duration: 6 Days
Materials: Cement tiles
Equipment: Measuring tape, dip-galvanised nails, hammer
Skilled worker: Roofer (1), general worker (1), roof tiler (1)
Technical information: Place cement tiles and nail every third row
33. Week 40
Construction Activity 1: Roof
Duration: 6 Days
Materials: Ridge metal (aluminium), ridge bracket, ridge vent
Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
Skilled worker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install ridge block.
Construction Activity 2: Roof
Duration: 6 Days
Materials: Fascia board ribbon, fascia board bracket
Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
Skilled worker: Roofer (1), general worker (1), bar bender (1)
Technical information: Install fascia board.
34. Week 41
Construction Activity 1: Wall Finishes – primer (Ground floor and First floors)
Duration: 3 Days
Materials: Primer
Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,
Caulks, Sealants and Caulking Tools
Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)
Technical information: Before applying primer, the wall need to be patched if there is any
holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.
Construction Activity 2: Wall Finishes – 1st
layer painting (Ground floor and first floors)
Duration: 3 Day
Materials: paint
Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: Painter (2)
Technical information: Wall painting with colour chosen.
35. Week 42
Construction Activity 1: Installation of door (Ground floor)
Duration: 3 days
Materials: Required door, door lock, doorknob and screws
Equipment: Screw driver, measuring tape
Skilled worker: general worker (1), window and door installer (2)
Technical information: Install required door types and measurement with door lock and
doorknob
Construction Activity 2: Wall Finishes – primer (Second floor)
Duration: 3 Days
Materials: Primer
Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,
Caulks, Sealants and Caulking Tools
Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)
Technical information: Before applying primer, the wall need to be patched if there is any
holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.
Construction Activity 3: Wall Finishes – 1st
layer painting (Second floor)
Duration: 3 Day
Materials: paint
Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: Painter (2)
Technical information: Wall painting with colour chosen.
36. Week 43
Construction Activity 1: Installation of door (First and Second floors)
Duration: 3 days
Materials: Required door, door lock, doorknob and screws
Equipment: Screw driver, measuring tape
Skilled worker: general worker (1), window and door installer (2)
Technical information: Install required door types and measurement with door lock and
doorknob
Construction Activity 2: Installation of door trim (All floors)
Duration: 3 days
Materials: nails, door trim panels
Equipment: Finish hammer, hand plane, measuring tape, carpenter’s glue, sandpaper, jigsaw,
combination square, compass, pencil, utility knife, putty knife, miter saw, drill with bit
Skilled worker: general worker (1), carpenter (2)
Technical information: Mark the reveals, cut all miters, cut and test-fit side casings, make
adjustments, secure casing, and cross-nail miters.
37. Week 44
Construction Activity 1: Installation of windows (All floors)
Duration: 3 days
Materials: Required windows, backer rod, insulation, shims, roofing nails, screws, silicone
sealant, flashing, fastener, corner guard
Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
Skilled worker: general worker (1), door and window installer (2)
Technical information: Verify window opening, apply weather resistant barrier, create
flashing, prepare window for installation, set the unit and secure, apply flashing at jambs
and head, seal and insulate interior cavity, insert backer rod.
38. Week 45
Construction Activity 1: Installation of plumbing
Duration: 4 days
Materials: cast iron pipe, galvanized iron pipe, and galvanized steel pipe, vitrified clay pipe,
PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threaded, steel
pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems are potable
cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface,
and subsurface water drainage, fuel gas piping.
Construction Activity 2: Installation of main electrical panel
Duration: 1 day
Materials: Sheet steel/cold role steel, breakers, plastic
Equipment: Driller, locknut, screw
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: The panel distributes the electricity to all the electrical circuits that
are installed in the house to protect the wiring from damage by “tripping” when an electrical
short or overcurrent occurs.
39. Week 46
Construction Activity 1: Installation of railings
Duration: 3 days
Materials: Ordered glass railing, stainless steel screws
Equipment: level, scaffolding, measuring tape, sealant, gloves and screwdriver
Skilled worker: general worker (1), railing installer (1)
Technical information: Insert measured bottom rail and top plate and insert glass panel, fix
them with sealant or screws.
40. Week 47
Construction Activity 1: Installation of ceiling
Duration: 3 days
Materials: Steel brandering, insulation, jointing strip, drywall screw, plasterboards, Lafarge
access panel
Equipment: ladder, gloves and screwdriver
Skilled worker: ceiling installer (1), general worker (1)
Technical information: Determine amount of steel brandering needed, planning the
direction of plasterboard, calculate number of plasterboard needed, install it on one by one.
Construction Activity 2: Installation of tiles
Duration: 6 days
Materials: Cement board, tiles, thinset mortar, grout
Equipment: Floor cleaner, measuring tape, square, trowel, level and brush
Skilled worker: Tiler (1), general worker (1)
Technical information: Calculate surface area, decide types and size of tiles to use, apply
mortar, install tiles, grout the joints and clean.
41. Week 48
Construction Activity 2: Wall Finishes (Whole house 2nd
layer painting)
Duration: 6 Days
Materials: Selected paints
Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: painters (2)
Technical information: Wall painting with colour chosen.
Week 49
Construction Activity 1: Bathroom Equipment Installation
Duration: 3 days
Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC pipes
Equipment: clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe vice, pipe
bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: Materials are installed at first fix stage as they need to be fitted prior
to the commencement of tiling. This is essential to get professional watertight seals, as
water ingress resulting from doing things in the wrong order can cause massive problems
later on.
Construction Activity 2: Installation of receptacle
Duration: 1 day
Materials: Nickel/silver, beryllium copper, plastic
Equipment: Screw, screwdriver
Skilled worker: Electrician (2)
Technical information: Electrician installs receptacles for outlets, lights and switches and
runs wires from the breaker panel to each receptacle. Wiring for telephones, TV cable and
network cable is included in this work.
Week 50
Construction Activity 1: Landscaping
Duration: 4 days
Materials: Grass, soil, stone, trees, plants
Equipment: wheelbarrow, shovel, hoe, shears
Skilled worker: General worker (1), landscape designer (1)
Technical information: Design of landscaping make the whole house look more attractive
and lively. (Porches, sidewalks, decks, driveways, final grade and seed)
42. Week 51
Construction Activity 1: Final touch up
Duration: 2 days
Technical information: punch out walk-thru list, trim and adjust doors, paint touch-up
Week 52
Construction Activity 1: Cleaning
Duration: 3 days
Equipment: Cleaning tools
Skilled worker: General worker (5)
Technical information: Windows, floors final clean.