SlideShare a Scribd company logo
1 of 8
Download to read offline
Unit Qty
Operator Helper Labour Mason Shovel Digger Roller Compactor
1 Excavation for foundation pits in normal ground m3 150 1 1 1
2 Excavation for foundations in strips/trenches in normal ground m3 130 1 1 1
3 Hand excavation in normal ground upto 1.5m lift m3 3 1
4 Foundation bed levelling & compaction m2 90 2 1
5 Backfilling in 150mm layers in buildings below slab on grade m3 180 2 1 0.75 1
6 Backfilling around building in 150mm layers m3 200 2 1 0.75 1
1 Plain concrete / Block walls m3 5
2 Hard Rock/ Reinforced concrete m3 2
3 Concrete paving m2 100
4 Asphalt & Subase m2 16
5 Pile Head Cutting - 300 mm Dia No 5
6 Pile Head Cutting - 600 mm Dia No 5
Labour Mason
1 Waterproofing Membrane m2
2 Polythene Sheets m2
3 Protection Screed m2
4 Tower Crane Erection No
1 Columns (Square or Rectangular) m2 14
2 Wall shutter m2 22
3 Beam Bottom m2 14
4 Beam Sides m2 20
5 Stair case /steps m2 8
Concrete Breaker
LABOR EQUIPMENT
RESOURCES - LABOR AND EQUIPMENT
1
LABOR AND EQUIPMENT PRODUCTIVITY
Rapid Breaker
Sr. No. ITEM
8 HRS
PRODUCTIVITY
EXCAVATION & EARTHWORKS
DISMANTLING & DISPOSAL (Manual)
1
1
1
1
2
Waterproofer
Wood Cutting Machine
1
1
2
1
Shutter Making Carpenter Helper
MISCELLANEOUS
1
1
1
1
1
1
1
1
1
1
1
Labour
2
2
2
1
1
1
Page 1 of 1
Unit Qty
1 Water Supply Pipes (PEX) LM
2 Water Supply Pipes (PRP) LM
3 Valves & Accessories of varying diameter No
4 Water Booster Pumpset No 2
5 Water Transfer Pumpset No
6 Water Treatment with Accessories No
7 Storage Tank No
8 Water Heater No 3
9 Water Meter No
10 Waste Water Drainage Pipes & Fittings below grade LM
11 Waste Water Drainage Pipes & Fittings above grade LM
12 Sump Pumpset No
13 Drains & Grating No
14 W/C - Asian No 2
15 W/C - Western No 3
16 Shower set No
17 Urinal No
18 MOP sink No
19 Bidet No 3
1 Chilled water Piping LM 25
2 Chilled water Pipes Insulation with Canvase Cloth LM 20
3 Duct Work with Insulation m2
10
4 Fresh Air Handling Units (FAHU) Installation No 1
5 Fan Coil Units (FCU) Installation No 2
6 Exhaust Fan Installaion No 2
7 Dampers & Control No
8 Grills & Diffusers Installation No 8
9 Closed Control Units No
10 Chemical Dosing No
11 Chilled Water Pump No
12 BMS No
PLUMBING & DRAINAGE Plumber Helper
MEP LABOR PRODUCTIVITY
Sr. No. ITEM
8 HRS
PRODUCTIVITY LABOR
1 1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
HVAC WORKS AC Technician Helper
Page 1 of 2
Unit Qty
MEP LABOR PRODUCTIVITY
Sr. No. ITEM
8 HRS
PRODUCTIVITY LABOR
1 Duct Laying LM 50
2 P.V.C Conduits Layings LM 200
3 G.I Conduits Layings LM 50
4 Cable Pulling ( 10 to 50 Sq mm ) LM 100
5 Cable Pulling ( 50 to 90 Sq mm ) LM 50
6 Cable Pulling ( 100 to 200 Sq mm ) LM 30
7 Cable Pulling ( 200 Sq mm and Above ) LM 30
8 Cable Trays (100mm-300mm ) i/c Support System LM 50
9 Cable Trays (300mm-600mm) i/c Support System LM 40
10 Cable Trays (600mm-900mm) i/c Support System LM 30
11 Wiring LM 300
12 Termination No 50
13 DB Installation No 2
14 MDB/SMDB Installation No 1
15 LV Panels Installation No
16 Motor Control Centres No
17 Sockets Installation No 80
18 Switches Installation No 80
19 Light Fixtures Installation No 50
20 Earthing System No
21 Generator set No
22 Main Cable Laying LM
22 CCTV System No
23 Telephone Equipment Installation No 5
1 Piping Network LM
2 Fire Hose Cabinets No
3 Fire Extinguishers and Cabinets No
4 Sprinklers No
5 Valves & Accessories No
6 Fire Protection Pumpset No
7 Fire gas Suppression System No
8 Fire Alarm Control Panel No
9 Smoke & Heat Detectors No
10 Monitor Module No
11 Control Module No
12 Voice Evacuation System No
1 1
1 1
1 1
1
1 1
1
ELECTRICAL WORKS Electrician Helper
1 1
3 5
3 5
4 2
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
FIRE FIGHTING & FIRE ALARM SYSTEM Fire Fighters Helper
Page 2 of 2
Unit Qty
Carpenter Steel Fixer Con Mason Helper
1
a Formwork m
2
40 1 1
b Concrete m
3
20 2 3
2
a Formwork m
2
25 1 1
b Concrete m
3
40 2 3
3
a Formwork m
2
30 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m
3
55 2 2
4
a Formwork m
2
25 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m
3
55 2 2
5
a Formwork m
2
25 2 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m
3
20 1 2
6
a Formwork m
2
30 2 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m
3
20 2 2
7
a Formwork & Joints m
2
of slab 200 2 1
b Mesh Reinforcement m
2
300 2
c Bar Reinforcement (fabrication & fix) kg 250 1
d Concrete - Trowel finished m
3
40 2 3
8
a Formwork m
2
30 3 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m
3
18 1 2
d De-Shuttering m
2
9
a Formwork m
2
b Reinforcement (fabrication & fix) kg
c Concrete m
3
d De-Shuttering m
2
10
a Formwork m
2
14 2 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m
3
9 1 2
d De-Shuttering m
2
8 HRS
PRODUCTIVITY
Slab on grade
CONCRETE WORKS
Strip footings
Tie Beams
Pedestals (Neck Columns)
LABOR PRODUCTIVITY
LABOR
PCC below footings
Column footings / Pile Caps
PCC below slab on grade
Sr. No. ITEM
Shear Walls
Retaining Walls
Columns upto 0.5 sqm in area (using fabricated forms)
Page 1 of 5
Unit Qty
8 HRS
PRODUCTIVITY
LABOR PRODUCTIVITY
LABOR
Sr. No. ITEM
Carpenter Steel Fixer Con Mason Helper
11
a Formwork m
2
20 2 2
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m
3
15 1 2
d De-Shuttering m
2
12
a Formwork m
2
15 1 1
b Reinforcement (fabrication & fix) kg 200 1
c Concrete m
3
75 3 3
d De-Shuttering m
2
13
a Formwork m
2
b Reinforcement (fabrication & fix) kg
c Concrete m
3
d De-Shuttering m
2
14
a Formwork m
2
20 2 2
b Reinforcement (fabrication & fix) kg 175 1
c Concrete m
3
12 1 1
15
a Formwork m
2
12 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m
3
50 3 3
16
a Formwork m
2
15 1 1
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m
3
20 1 1
17
a Formwork m
2
b Reinforcement (fabrication & fix) kg
c Concrete m
3
18
a Formwork m
2
8 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m
3
5 1 1
Parapets
Cantilevers
Ramps
Stairs
Lintels
Slabs (Hourdy)
Beams
Slabs (Solid)
CONCRETE WORKS
Page 2 of 5
Unit Qty
8 HRS
PRODUCTIVITY
LABOR PRODUCTIVITY
LABOR
Sr. No. ITEM
1 200 mm Blockwork m
2
12
1 100 mm Blockwork with pointing m
2
15
2 150 mm Blockwork with pointing m
2
3 200 mm Blockwork with pointing m
2
10
4 250 mm Blockwork with pointing m
2
1 250 mm Blockwork with pointing m
2
2 200 mm Blockwork with pointing m
2
16
3 200 mm blockwork in non-straight walls with pointing m
2
12
4 150 mm Blockwork with pointing m
2
5 150 mm blockwork in non-straight walls with pointing m
2
6 100 mm blockwork in straight walls with pointing m
2
18
7 100 mm blockwork in non-straight walls with pointing m
2
14
1 Cover Block m
2
9
2 Cutting & Chasing m
2
2 Block shifting GF to 3rd Floor No 240
1 Plastering Accessories fixing m
2
60
2 Internal Plaster 12mm thick on walls m
2
16
3 Internal Plaster 12mm thick on ceilings m
2
12
4 External Plaster 16mm thick (upto 3m high) m
2
5 External Plaster 16mm thick (over 3m high) m
2
6 External Plaster 19mm thick (upto 3m high) m
2
20
7 External Plaster 19mm thick (over 3m high) m
2
18
8 External plaster -Rush coat m
2
100
9 Compressed Plaster m
2
60
10 Sub frame fixing No 5
11 Tyroline over plastered or fare face concrete surface m
2
175
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1 1
PLASTER Plaster Mason Helper
1 1
1
BLOCK WORK Block Mason Helper
1
1
1
1
2
2
2
2
Sub-Structure - Solid Blocks
Super-Structure (upto 3m height) - Solid Blocks
Super-Structure (upto 3m height) - Hollow Blocks
Miscellaneous
1 1
1
1
2
2
Page 3 of 5
Unit Qty
8 HRS
PRODUCTIVITY
LABOR PRODUCTIVITY
LABOR
Sr. No. ITEM
1 Ceramic Floor Tiles m
2
20
2 Ceramic Wall Tiles m
2
18
3 Ceramic Tile Skirting LM 40
4 Ceramic floor / wall tiles grouting m
2
32
5 Ceramic claustra work m
2
6
6 Granite/Marble threshold No 10
7 Granite/Marble Floor Tiles m
2
10
8 Granite/Marble Wall Tiles m
2
9 Terrazzo Tiles m
2
20
10 Terrazzo Skirting LM 40
11 Terrazzo Treads & Risers LM 30
12 Floor Screed 50mm thick m
2
27
13 Interlocking Pavers m
2
48
14 Kerbstone m 56
1 Suspension System m
2
35
2 Ceiling Tiles m
2
60
3 Gypsum Ceiling & Cornish (i/c Suspension System) m
2
2.5
4 Dry wall partition m
2
20
1 Prime Coat m
2
200
2 Surface preparation for paint m
2
80
3 Paint 1st Coat - brush application (Emulsion Paint) m
2
100
4 Paint 2nd Coat - brush application (Emulsion Paint) m
2
100
5 Paint 1st Coat - roller application (Emulsion paint) m
2
125
6 Paint 2nd Coat - roller application (Emulsion Paint) m
2
125
7 Paint 1st Coat - brush application (Enamel Paint) m
2
60
8 Paint 2nd Coat - brush application (Enamel Paint) m
2
60
9 Paint 1st Coat - roller application (Enamel Paint) m
2
95
10 Paint 2nd Coat - roller application (Enamel Paint) m
2
70
11 Epoxy Paint on Floors per coat m
2
50
12 Bitumen paint for waterpoofing single coat m
2
50
13 Stucco Paint m
2
TILING WORK Tiler Helper
FALSE CEILING Ceiler Helper
1 1
1 1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1 1
1
1
1
1 1
1 1
1 1
1 1
1
1
PAINT WORK Painter Helper
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
Page 4 of 5
Unit Qty
8 HRS
PRODUCTIVITY
LABOR PRODUCTIVITY
LABOR
Sr. No. ITEM
1 Wooden frames fixing for openings upto 5 m
2
nos 8
2 Wooden door shutters fixing (incl hardware) nos 5
3 Wooden Pergola m
2
4 Wooden Vanities nos
5 Kitchen Cabinets nos
6 Wardrobes nos
7 Handrail LM
1 Steel Frames fixing for openings upto 5 m
2
nos 8
2 Steel Shutter fixing nos 5
3 Handrail and Balustrade LM 8
4 Glazed Balustrade with Stainless steel handrail LM 6
5 Structural Steel Columns and Beams kg
6 Wardrobes nos
7 Passanger Lifts nos
1 Aluminium doors for openings upto 5 m
2
nos 8
2 Aluminium windows (glazed) nos 6
3 Glazed Curtain Walling m
2
4 Aluminium Louvers nos
5 Aluminium Cladding m
2
6 Skylights m
2
WOOD WORKS
METAL WORKS
ALUMINIUM WORKS
Joiner Helper
Metal Workers Helper
Aluminium Workers
1 1
1 2
2
2
1
1
2
2
Page 5 of 5

More Related Content

What's hot

Force structural engineers - Company profile
Force structural engineers - Company profileForce structural engineers - Company profile
Force structural engineers - Company profilePrateek Jain
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered BuildingsIRJET Journal
 
Project report on multi storied building expertcivil
Project report on multi storied building expertcivilProject report on multi storied building expertcivil
Project report on multi storied building expertcivilMumairbuttg
 
Civil Engineering Project Presentation
Civil Engineering Project PresentationCivil Engineering Project Presentation
Civil Engineering Project PresentationIbrahim Ali
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian uitm pulau pinang
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
 
Civil Technical questions word presentation
Civil Technical questions word presentationCivil Technical questions word presentation
Civil Technical questions word presentationpremsai05
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.Gebeyehu Worku
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGAtiq Iqbal
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and paymentsHafizul Mukhlis
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yardRavinder Singh
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 

What's hot (20)

Force structural engineers - Company profile
Force structural engineers - Company profileForce structural engineers - Company profile
Force structural engineers - Company profile
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered Buildings
 
Project report on multi storied building expertcivil
Project report on multi storied building expertcivilProject report on multi storied building expertcivil
Project report on multi storied building expertcivil
 
Civil Engineering Project Presentation
Civil Engineering Project PresentationCivil Engineering Project Presentation
Civil Engineering Project Presentation
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian
 
Fidic
FidicFidic
Fidic
 
Tremie
TremieTremie
Tremie
 
Road machinery
Road machineryRoad machinery
Road machinery
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Civil Technical questions word presentation
Civil Technical questions word presentationCivil Technical questions word presentation
Civil Technical questions word presentation
 
Construction site supervision aalecture one.
Construction site supervision aalecture one.Construction site supervision aalecture one.
Construction site supervision aalecture one.
 
CONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERINGCONSTRUCTION ENGINEERING
CONSTRUCTION ENGINEERING
 
Underwater concrete
Underwater concreteUnderwater concrete
Underwater concrete
 
Certificates and payments
Certificates and paymentsCertificates and payments
Certificates and payments
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 

Similar to Labour-and-Equipment-Productivity.pdf

Similar to Labour-and-Equipment-Productivity.pdf (20)

ALYSSA MASON - PORTFOLIO - SCDC
ALYSSA MASON - PORTFOLIO - SCDCALYSSA MASON - PORTFOLIO - SCDC
ALYSSA MASON - PORTFOLIO - SCDC
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
Tuladhar
TuladharTuladhar
Tuladhar
 
dan palmer
dan palmerdan palmer
dan palmer
 
SL020 & SL022 - sections
SL020 & SL022 - sectionsSL020 & SL022 - sections
SL020 & SL022 - sections
 
3. Hansons lodge.pdf
3. Hansons lodge.pdf3. Hansons lodge.pdf
3. Hansons lodge.pdf
 
Arki tabulated-reviewer
Arki tabulated-reviewerArki tabulated-reviewer
Arki tabulated-reviewer
 
Bo q for shelter
Bo q  for shelterBo q  for shelter
Bo q for shelter
 
HRP Manchester Square Court Office_Acoustic_firescreen
HRP Manchester Square Court Office_Acoustic_firescreenHRP Manchester Square Court Office_Acoustic_firescreen
HRP Manchester Square Court Office_Acoustic_firescreen
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Roof structure
Roof structureRoof structure
Roof structure
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Ceramic Liners brochure
Ceramic Liners brochureCeramic Liners brochure
Ceramic Liners brochure
 
section and detail sheet1
section and detail sheet1section and detail sheet1
section and detail sheet1
 
Schiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue systemSchiedel Metaloterm MFflue system
Schiedel Metaloterm MFflue system
 
Versaloc - very easy, very quick
Versaloc - very easy, very quickVersaloc - very easy, very quick
Versaloc - very easy, very quick
 
Versaloc
VersalocVersaloc
Versaloc
 
Jack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack_Lambourne - Portfolio
Jack_Lambourne - Portfolio
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 

Labour-and-Equipment-Productivity.pdf

  • 1. Unit Qty Operator Helper Labour Mason Shovel Digger Roller Compactor 1 Excavation for foundation pits in normal ground m3 150 1 1 1 2 Excavation for foundations in strips/trenches in normal ground m3 130 1 1 1 3 Hand excavation in normal ground upto 1.5m lift m3 3 1 4 Foundation bed levelling & compaction m2 90 2 1 5 Backfilling in 150mm layers in buildings below slab on grade m3 180 2 1 0.75 1 6 Backfilling around building in 150mm layers m3 200 2 1 0.75 1 1 Plain concrete / Block walls m3 5 2 Hard Rock/ Reinforced concrete m3 2 3 Concrete paving m2 100 4 Asphalt & Subase m2 16 5 Pile Head Cutting - 300 mm Dia No 5 6 Pile Head Cutting - 600 mm Dia No 5 Labour Mason 1 Waterproofing Membrane m2 2 Polythene Sheets m2 3 Protection Screed m2 4 Tower Crane Erection No 1 Columns (Square or Rectangular) m2 14 2 Wall shutter m2 22 3 Beam Bottom m2 14 4 Beam Sides m2 20 5 Stair case /steps m2 8 Concrete Breaker LABOR EQUIPMENT RESOURCES - LABOR AND EQUIPMENT 1 LABOR AND EQUIPMENT PRODUCTIVITY Rapid Breaker Sr. No. ITEM 8 HRS PRODUCTIVITY EXCAVATION & EARTHWORKS DISMANTLING & DISPOSAL (Manual) 1 1 1 1 2 Waterproofer Wood Cutting Machine 1 1 2 1 Shutter Making Carpenter Helper MISCELLANEOUS 1 1 1 1 1 1 1 1 1 1 1 Labour 2 2 2 1 1 1 Page 1 of 1
  • 2. Unit Qty 1 Water Supply Pipes (PEX) LM 2 Water Supply Pipes (PRP) LM 3 Valves & Accessories of varying diameter No 4 Water Booster Pumpset No 2 5 Water Transfer Pumpset No 6 Water Treatment with Accessories No 7 Storage Tank No 8 Water Heater No 3 9 Water Meter No 10 Waste Water Drainage Pipes & Fittings below grade LM 11 Waste Water Drainage Pipes & Fittings above grade LM 12 Sump Pumpset No 13 Drains & Grating No 14 W/C - Asian No 2 15 W/C - Western No 3 16 Shower set No 17 Urinal No 18 MOP sink No 19 Bidet No 3 1 Chilled water Piping LM 25 2 Chilled water Pipes Insulation with Canvase Cloth LM 20 3 Duct Work with Insulation m2 10 4 Fresh Air Handling Units (FAHU) Installation No 1 5 Fan Coil Units (FCU) Installation No 2 6 Exhaust Fan Installaion No 2 7 Dampers & Control No 8 Grills & Diffusers Installation No 8 9 Closed Control Units No 10 Chemical Dosing No 11 Chilled Water Pump No 12 BMS No PLUMBING & DRAINAGE Plumber Helper MEP LABOR PRODUCTIVITY Sr. No. ITEM 8 HRS PRODUCTIVITY LABOR 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 HVAC WORKS AC Technician Helper Page 1 of 2
  • 3. Unit Qty MEP LABOR PRODUCTIVITY Sr. No. ITEM 8 HRS PRODUCTIVITY LABOR 1 Duct Laying LM 50 2 P.V.C Conduits Layings LM 200 3 G.I Conduits Layings LM 50 4 Cable Pulling ( 10 to 50 Sq mm ) LM 100 5 Cable Pulling ( 50 to 90 Sq mm ) LM 50 6 Cable Pulling ( 100 to 200 Sq mm ) LM 30 7 Cable Pulling ( 200 Sq mm and Above ) LM 30 8 Cable Trays (100mm-300mm ) i/c Support System LM 50 9 Cable Trays (300mm-600mm) i/c Support System LM 40 10 Cable Trays (600mm-900mm) i/c Support System LM 30 11 Wiring LM 300 12 Termination No 50 13 DB Installation No 2 14 MDB/SMDB Installation No 1 15 LV Panels Installation No 16 Motor Control Centres No 17 Sockets Installation No 80 18 Switches Installation No 80 19 Light Fixtures Installation No 50 20 Earthing System No 21 Generator set No 22 Main Cable Laying LM 22 CCTV System No 23 Telephone Equipment Installation No 5 1 Piping Network LM 2 Fire Hose Cabinets No 3 Fire Extinguishers and Cabinets No 4 Sprinklers No 5 Valves & Accessories No 6 Fire Protection Pumpset No 7 Fire gas Suppression System No 8 Fire Alarm Control Panel No 9 Smoke & Heat Detectors No 10 Monitor Module No 11 Control Module No 12 Voice Evacuation System No 1 1 1 1 1 1 1 1 1 1 ELECTRICAL WORKS Electrician Helper 1 1 3 5 3 5 4 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 FIRE FIGHTING & FIRE ALARM SYSTEM Fire Fighters Helper Page 2 of 2
  • 4. Unit Qty Carpenter Steel Fixer Con Mason Helper 1 a Formwork m 2 40 1 1 b Concrete m 3 20 2 3 2 a Formwork m 2 25 1 1 b Concrete m 3 40 2 3 3 a Formwork m 2 30 2 2 b Reinforcement (fabrication & fix) kg 170 1 c Concrete m 3 55 2 2 4 a Formwork m 2 25 2 2 b Reinforcement (fabrication & fix) kg 170 1 c Concrete m 3 55 2 2 5 a Formwork m 2 25 2 1 b Reinforcement (fabrication & fix) kg 160 1 c Concrete m 3 20 1 2 6 a Formwork m 2 30 2 1 b Reinforcement (fabrication & fix) kg 180 1 c Concrete m 3 20 2 2 7 a Formwork & Joints m 2 of slab 200 2 1 b Mesh Reinforcement m 2 300 2 c Bar Reinforcement (fabrication & fix) kg 250 1 d Concrete - Trowel finished m 3 40 2 3 8 a Formwork m 2 30 3 1 b Reinforcement (fabrication & fix) kg 160 1 c Concrete m 3 18 1 2 d De-Shuttering m 2 9 a Formwork m 2 b Reinforcement (fabrication & fix) kg c Concrete m 3 d De-Shuttering m 2 10 a Formwork m 2 14 2 1 b Reinforcement (fabrication & fix) kg 160 1 c Concrete m 3 9 1 2 d De-Shuttering m 2 8 HRS PRODUCTIVITY Slab on grade CONCRETE WORKS Strip footings Tie Beams Pedestals (Neck Columns) LABOR PRODUCTIVITY LABOR PCC below footings Column footings / Pile Caps PCC below slab on grade Sr. No. ITEM Shear Walls Retaining Walls Columns upto 0.5 sqm in area (using fabricated forms) Page 1 of 5
  • 5. Unit Qty 8 HRS PRODUCTIVITY LABOR PRODUCTIVITY LABOR Sr. No. ITEM Carpenter Steel Fixer Con Mason Helper 11 a Formwork m 2 20 2 2 b Reinforcement (fabrication & fix) kg 160 1 c Concrete m 3 15 1 2 d De-Shuttering m 2 12 a Formwork m 2 15 1 1 b Reinforcement (fabrication & fix) kg 200 1 c Concrete m 3 75 3 3 d De-Shuttering m 2 13 a Formwork m 2 b Reinforcement (fabrication & fix) kg c Concrete m 3 d De-Shuttering m 2 14 a Formwork m 2 20 2 2 b Reinforcement (fabrication & fix) kg 175 1 c Concrete m 3 12 1 1 15 a Formwork m 2 12 1 1 b Reinforcement (fabrication & fix) kg 180 1 c Concrete m 3 50 3 3 16 a Formwork m 2 15 1 1 b Reinforcement (fabrication & fix) kg 170 1 c Concrete m 3 20 1 1 17 a Formwork m 2 b Reinforcement (fabrication & fix) kg c Concrete m 3 18 a Formwork m 2 8 1 1 b Reinforcement (fabrication & fix) kg 180 1 c Concrete m 3 5 1 1 Parapets Cantilevers Ramps Stairs Lintels Slabs (Hourdy) Beams Slabs (Solid) CONCRETE WORKS Page 2 of 5
  • 6. Unit Qty 8 HRS PRODUCTIVITY LABOR PRODUCTIVITY LABOR Sr. No. ITEM 1 200 mm Blockwork m 2 12 1 100 mm Blockwork with pointing m 2 15 2 150 mm Blockwork with pointing m 2 3 200 mm Blockwork with pointing m 2 10 4 250 mm Blockwork with pointing m 2 1 250 mm Blockwork with pointing m 2 2 200 mm Blockwork with pointing m 2 16 3 200 mm blockwork in non-straight walls with pointing m 2 12 4 150 mm Blockwork with pointing m 2 5 150 mm blockwork in non-straight walls with pointing m 2 6 100 mm blockwork in straight walls with pointing m 2 18 7 100 mm blockwork in non-straight walls with pointing m 2 14 1 Cover Block m 2 9 2 Cutting & Chasing m 2 2 Block shifting GF to 3rd Floor No 240 1 Plastering Accessories fixing m 2 60 2 Internal Plaster 12mm thick on walls m 2 16 3 Internal Plaster 12mm thick on ceilings m 2 12 4 External Plaster 16mm thick (upto 3m high) m 2 5 External Plaster 16mm thick (over 3m high) m 2 6 External Plaster 19mm thick (upto 3m high) m 2 20 7 External Plaster 19mm thick (over 3m high) m 2 18 8 External plaster -Rush coat m 2 100 9 Compressed Plaster m 2 60 10 Sub frame fixing No 5 11 Tyroline over plastered or fare face concrete surface m 2 175 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 PLASTER Plaster Mason Helper 1 1 1 BLOCK WORK Block Mason Helper 1 1 1 1 2 2 2 2 Sub-Structure - Solid Blocks Super-Structure (upto 3m height) - Solid Blocks Super-Structure (upto 3m height) - Hollow Blocks Miscellaneous 1 1 1 1 2 2 Page 3 of 5
  • 7. Unit Qty 8 HRS PRODUCTIVITY LABOR PRODUCTIVITY LABOR Sr. No. ITEM 1 Ceramic Floor Tiles m 2 20 2 Ceramic Wall Tiles m 2 18 3 Ceramic Tile Skirting LM 40 4 Ceramic floor / wall tiles grouting m 2 32 5 Ceramic claustra work m 2 6 6 Granite/Marble threshold No 10 7 Granite/Marble Floor Tiles m 2 10 8 Granite/Marble Wall Tiles m 2 9 Terrazzo Tiles m 2 20 10 Terrazzo Skirting LM 40 11 Terrazzo Treads & Risers LM 30 12 Floor Screed 50mm thick m 2 27 13 Interlocking Pavers m 2 48 14 Kerbstone m 56 1 Suspension System m 2 35 2 Ceiling Tiles m 2 60 3 Gypsum Ceiling & Cornish (i/c Suspension System) m 2 2.5 4 Dry wall partition m 2 20 1 Prime Coat m 2 200 2 Surface preparation for paint m 2 80 3 Paint 1st Coat - brush application (Emulsion Paint) m 2 100 4 Paint 2nd Coat - brush application (Emulsion Paint) m 2 100 5 Paint 1st Coat - roller application (Emulsion paint) m 2 125 6 Paint 2nd Coat - roller application (Emulsion Paint) m 2 125 7 Paint 1st Coat - brush application (Enamel Paint) m 2 60 8 Paint 2nd Coat - brush application (Enamel Paint) m 2 60 9 Paint 1st Coat - roller application (Enamel Paint) m 2 95 10 Paint 2nd Coat - roller application (Enamel Paint) m 2 70 11 Epoxy Paint on Floors per coat m 2 50 12 Bitumen paint for waterpoofing single coat m 2 50 13 Stucco Paint m 2 TILING WORK Tiler Helper FALSE CEILING Ceiler Helper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 PAINT WORK Painter Helper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Page 4 of 5
  • 8. Unit Qty 8 HRS PRODUCTIVITY LABOR PRODUCTIVITY LABOR Sr. No. ITEM 1 Wooden frames fixing for openings upto 5 m 2 nos 8 2 Wooden door shutters fixing (incl hardware) nos 5 3 Wooden Pergola m 2 4 Wooden Vanities nos 5 Kitchen Cabinets nos 6 Wardrobes nos 7 Handrail LM 1 Steel Frames fixing for openings upto 5 m 2 nos 8 2 Steel Shutter fixing nos 5 3 Handrail and Balustrade LM 8 4 Glazed Balustrade with Stainless steel handrail LM 6 5 Structural Steel Columns and Beams kg 6 Wardrobes nos 7 Passanger Lifts nos 1 Aluminium doors for openings upto 5 m 2 nos 8 2 Aluminium windows (glazed) nos 6 3 Glazed Curtain Walling m 2 4 Aluminium Louvers nos 5 Aluminium Cladding m 2 6 Skylights m 2 WOOD WORKS METAL WORKS ALUMINIUM WORKS Joiner Helper Metal Workers Helper Aluminium Workers 1 1 1 2 2 2 1 1 2 2 Page 5 of 5