SlideShare a Scribd company logo
RICS SCHOOL OF BUILT ENVIRONMENT, Amity University
Submitted By : AYUSH KHANDELWAL
: KARAN SONI
: UTKARSH MITTAL
: RAJAT BHARDAWAJ
SECTION : “B”
Group : 2
Sub Group : 5
Taught By:
Mrs. Susan George
Adjunct Associate Professor
INDEX
1. List of activities for the work packages
2. Network linking the activities and incorporating activity durations
3. Critical path calculation and duration of project
4. Calculation of total and free floats
5. Milestone chart showing information requirement and ordering of major items
6. Resource sheet with list of resource needs
7. Crashing of activity to reduce project time by at least 10 days (2 Marks)
Lower Ground Drawing
First Floor Drawing
Underground Plan Drawing
Terrace Plan Drawing
LIST OF ACTIVITIES
Activity No. Work Description Duration
Earthwork
1 Excavation for Foundation 30
2 Refilling of Foundation 8
Civil Works
3 Raft Foundation 8
4 Lower Ground-Column 2
5 Lower Ground-Slab & Beam 4
6 Upper Ground-Column 2
7 Upper Ground-Slab & Beam 4
8 First Floor-Column 2
9 First Floor-Slab & Beam 6
10 Terrce Column (Mumty) 2
11 Terrace Slab & Beam (Mumty) 6
Brickwork
12 Lower Ground 4
13 Upper Ground 14
14 First Floor 6
15 Terrace 2
Electrical Wiring
16 Lower Ground 6
17 Upper Ground 4
18 First Floor 5
19 Terrace 1
Plaster Work
20 Lower Ground 16
21 Upper Ground 16
22 First Floor 17
23 Terrace 3
24 External 17
25 Project Inspection 1
NETWORK
DIAGRAM
(PDF)
Milestone Table & Chart
S.no Start Date Activity Description Days
1.1 Friday, January 5, 2018 Concept 0
1.2 Monday, January 15, 2018 Design Development 10
1.3 Thursday, February 1, 2018 Architectural Drawing Package 27
1.4 Saturday, February 10, 2018 Structural Drawing Package 36
1.5
Thursday, February 15,
2018
Plumbing Drawing Package 41
1.6 Tuesday, February 20, 2018 Electrical Drawing Package 46
1.7 Tuesday, February 27, 2018 HVAC Drawing Package 53
1.8 Saturday, March 3, 2018 Landscape Drawing Package 57
1.9 Sunday, March 4, 2018 Drawing Review 58
2 Monday, March 5, 2018 Sanctioning 59
2.1 Saturday, March 10, 2018 Sanction Drawing Package 64
2.2 Monday, March 12, 2018 Submission of Sanction Drawing 66
2.3 Thursday, March 15, 2018 Working Drawing Package (GFC) 69
2.4 Friday, March 16, 2018 Shop Drawings 70
2.5 Saturday, March 17, 2018 Elevator + Start Procurement 71
2.6
Monday, March 19, 2018
Doors & Windows + Start Procurement 73
2.7 Wednesday, March 21,
2018
Conference/ Meeting before Construction
Stage
75
2.8 Saturday, March 24, 2018 Construction Stage 78
2.9 Sunday, March 25, 2018 Site Clearance and Fencing 79
3 Thursday, March 29, 2018 Excavation for foundation 83
3.1 Monday, April 30, 2018 Raft Foundation 115
3.2 Thursday, May 10, 2018 Civil Work Super Structure 125
3.3 Thursday, May 17, 2018 Brickwork 132
3.4 Thursday, May 31, 2018 Electrical Wiring 146
3.5 Monday, June 18, 2018 Plaster Work 164
RESOURCE SHEET (PDF)
Crashing of Activities
ORIGINAL CRASHED
Activity
No.
Work
Description
Duration IPA Start finish Duration Start Finish Remark
Earthwork
1 Excavation
for
Foundation
30 Start 0 30 30 0 20 REDUCE
BY 10
DAYS
2 Refilling of
Foundation
8 SS4 8 16 8 8 16
Civil Works
3 Raft
Foundation
8 FS1 30 38 8 20 28
4 Lower
Ground-
Column
2 FS3 38 40 2 28 30
5 Lower
Ground-
Slab &
Beam
4 FS4 40 44 2 30 34 REDUCE
BY 2
DAYS
6 Upper
Ground-
Column
2 FS5 44 46 2 34 46
7 Upper
Ground-
Slab &
Beam
4 FS6 46 50 2 46 48 REDUCE
BY 2
DAYS
8 First Floor-
Column
2 FS7 50 52 2 48 52
9 First Floor-
Slab &
Beam
6 FS8 52 58 4 52 56 REDUCE
BY 2
DAYS
10 Terrce
Column
(Mumty)
2 FS9 58 60 2 56 60
11 Terrace
Slab &
Beam
(Mumty)
6 FS10 60 66 4 60 64 REDUCE
BY 2
DAYS
Brickwork
12 Lower
Ground
4 FS5 44 48 4 34 48
13 Upper
Ground
14 FS7 50 64 12 48 62 REDUCE
BY 2
DAYS
14 First Floor 6 FS9 58 64 6 56 62
15 Terrace 2 FS11 66 68 2 64 66
ORIGINAL CRASHED
Electrical
Wiring
16 Lower
Ground
6 FS12 48 54 6 48 54
17 Upper
Ground
4 FS13 64 68 4 62 66
18 First Floor 5 FS14 64 69 5 62 67
19 Terrace 1 FS15 68 69 1 66 67
Plaster
Work
20 Lower
Ground
16 FS16 54 70 16 54 70
21 Upper
Ground
16 FS17 68 84 16 54 70
22 First Floor 17 FS18 69 86 17 67 84
23 Terrace 3 FS19 69 72 3 67 70
24 External 17 FS15 68 85 17 66 83
25 Project
Inspection
1 FS2,FS20,FS21,FS22,FS23,FS24 86 87 1 70 71

More Related Content

What's hot

tunnel farming project
tunnel farming projecttunnel farming project
tunnel farming project
umair mohsin
 
Landscape architecture & water management_ Mohan Subramaniam_2013
Landscape architecture & water management_ Mohan Subramaniam_2013Landscape architecture & water management_ Mohan Subramaniam_2013
Landscape architecture & water management_ Mohan Subramaniam_2013
India Water Portal
 
Appropriate material for sustainable building
Appropriate material for sustainable building Appropriate material for sustainable building
Appropriate material for sustainable building
Biya Girma Hirpo
 
Ecbc ppt mk
Ecbc ppt   mkEcbc ppt   mk
Impurities in wastewater & problems caused by it
Impurities in wastewater & problems caused by itImpurities in wastewater & problems caused by it
Impurities in wastewater & problems caused by it
Nikhil Sharma
 
Indoor environment
Indoor environmentIndoor environment
Indoor environment
Sakshi Mishra
 
Alternative Water Supply Technologies.
Alternative Water Supply  Technologies.Alternative Water Supply  Technologies.
Alternative Water Supply Technologies.
Shariful Haque Robin
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
Intaver Insititute
 
Aerobic Biotoilet technology
Aerobic Biotoilet technology   Aerobic Biotoilet technology
Aerobic Biotoilet technology
moumita karmakar
 
BWSSB presentation - Water Supply Realities Bnagalore
BWSSB presentation - Water Supply Realities BnagaloreBWSSB presentation - Water Supply Realities Bnagalore
BWSSB presentation - Water Supply Realities Bnagalore
ADDA
 
RO
RORO
DRDO APPROVED AOV BIO TOILET PRESENTATION
DRDO APPROVED AOV BIO TOILET PRESENTATIONDRDO APPROVED AOV BIO TOILET PRESENTATION
DRDO APPROVED AOV BIO TOILET PRESENTATION
AOV INTERNATIONAL
 
Energy Efficiency Methods And Techniques V.2
Energy Efficiency Methods And Techniques V.2Energy Efficiency Methods And Techniques V.2
Energy Efficiency Methods And Techniques V.2
patmcmmc
 
Hydroponic Green House Farming
Hydroponic Green House FarmingHydroponic Green House Farming
Hydroponic Green House Farming
Ajjay Kumar Gupta
 
Sewage treatment
Sewage treatmentSewage treatment
Sewage treatment
elizashufina99
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvesting
Ayushi Agrawal
 
Managing Water and Agriculture for Sustainable Food Security
Managing Water and Agriculture for Sustainable Food SecurityManaging Water and Agriculture for Sustainable Food Security
Managing Water and Agriculture for Sustainable Food Security
International Food Policy Research Institute (IFPRI)
 
Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
 Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes. Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
Center for Sustainable Energy
 
Solid waste Part-II
Solid waste  Part-IISolid waste  Part-II
Solid waste Part-II
Dr. shrikant jahagirdar
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
constructingexcellence
 

What's hot (20)

tunnel farming project
tunnel farming projecttunnel farming project
tunnel farming project
 
Landscape architecture & water management_ Mohan Subramaniam_2013
Landscape architecture & water management_ Mohan Subramaniam_2013Landscape architecture & water management_ Mohan Subramaniam_2013
Landscape architecture & water management_ Mohan Subramaniam_2013
 
Appropriate material for sustainable building
Appropriate material for sustainable building Appropriate material for sustainable building
Appropriate material for sustainable building
 
Ecbc ppt mk
Ecbc ppt   mkEcbc ppt   mk
Ecbc ppt mk
 
Impurities in wastewater & problems caused by it
Impurities in wastewater & problems caused by itImpurities in wastewater & problems caused by it
Impurities in wastewater & problems caused by it
 
Indoor environment
Indoor environmentIndoor environment
Indoor environment
 
Alternative Water Supply Technologies.
Alternative Water Supply  Technologies.Alternative Water Supply  Technologies.
Alternative Water Supply Technologies.
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Aerobic Biotoilet technology
Aerobic Biotoilet technology   Aerobic Biotoilet technology
Aerobic Biotoilet technology
 
BWSSB presentation - Water Supply Realities Bnagalore
BWSSB presentation - Water Supply Realities BnagaloreBWSSB presentation - Water Supply Realities Bnagalore
BWSSB presentation - Water Supply Realities Bnagalore
 
RO
RORO
RO
 
DRDO APPROVED AOV BIO TOILET PRESENTATION
DRDO APPROVED AOV BIO TOILET PRESENTATIONDRDO APPROVED AOV BIO TOILET PRESENTATION
DRDO APPROVED AOV BIO TOILET PRESENTATION
 
Energy Efficiency Methods And Techniques V.2
Energy Efficiency Methods And Techniques V.2Energy Efficiency Methods And Techniques V.2
Energy Efficiency Methods And Techniques V.2
 
Hydroponic Green House Farming
Hydroponic Green House FarmingHydroponic Green House Farming
Hydroponic Green House Farming
 
Sewage treatment
Sewage treatmentSewage treatment
Sewage treatment
 
Water supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvestingWater supply, sanitation and rainwater harvesting
Water supply, sanitation and rainwater harvesting
 
Managing Water and Agriculture for Sustainable Food Security
Managing Water and Agriculture for Sustainable Food SecurityManaging Water and Agriculture for Sustainable Food Security
Managing Water and Agriculture for Sustainable Food Security
 
Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
 Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes. Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
Residential Title-24 Lighting & ASHRAE 62.2 Ventilation Codes.
 
Solid waste Part-II
Solid waste  Part-IISolid waste  Part-II
Solid waste Part-II
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 

Similar to Project Planning And Control Club house design with MSP

PPT CE DEPT.pptx
PPT CE DEPT.pptxPPT CE DEPT.pptx
PPT CE DEPT.pptx
BOBBY281420
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
abirsengupta9
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
Ahmad Basim Hamza
 
bstrut report
bstrut reportbstrut report
bstrut report
Gary Yeow
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
Yue Yun
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
SolomonTangerine
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
yenweizheng
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
teoh zhe khai
 
Setting BI for ultimate performance for Site
Setting BI for ultimate performance for SiteSetting BI for ultimate performance for Site
Setting BI for ultimate performance for Site
neerajgulab
 
B.E.-third-semester-syllabus.pdf
B.E.-third-semester-syllabus.pdfB.E.-third-semester-syllabus.pdf
B.E.-third-semester-syllabus.pdf
BipinKumarThakur3
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
Wan Nee
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
Sushrut Gautam
 
Civil course
Civil courseCivil course
Civil course
Olik3
 
Structure report
Structure reportStructure report
Structure report
Elaine Bong
 
Hong Albert Portfolio
Hong Albert PortfolioHong Albert Portfolio
Hong Albert Portfolio
Albert Hong
 
Delhi high court construction
Delhi high court constructionDelhi high court construction
Delhi high court construction
Shubham Singh [NITK]
 
Building Structure Force Analysis
Building Structure Force AnalysisBuilding Structure Force Analysis
Building Structure Force Analysis
shacjhow
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
ayonpal
 
department of mechanical & water resources
department of mechanical & water resourcesdepartment of mechanical & water resources
department of mechanical & water resources
Dimitrios Gkravas
 

Similar to Project Planning And Control Club house design with MSP (20)

PPT CE DEPT.pptx
PPT CE DEPT.pptxPPT CE DEPT.pptx
PPT CE DEPT.pptx
 
Sunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptxSunshine_ W2 Dec'23_09.12.23.pptx
Sunshine_ W2 Dec'23_09.12.23.pptx
 
11 lecture project scheduling 3
11 lecture project scheduling 311 lecture project scheduling 3
11 lecture project scheduling 3
 
bstrut report
bstrut reportbstrut report
bstrut report
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
 
Team bunga raya final report
Team bunga raya final reportTeam bunga raya final report
Team bunga raya final report
 
Setting BI for ultimate performance for Site
Setting BI for ultimate performance for SiteSetting BI for ultimate performance for Site
Setting BI for ultimate performance for Site
 
B.E.-third-semester-syllabus.pdf
B.E.-third-semester-syllabus.pdfB.E.-third-semester-syllabus.pdf
B.E.-third-semester-syllabus.pdf
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
 
FYP Structure.pdf
FYP Structure.pdfFYP Structure.pdf
FYP Structure.pdf
 
Civil course
Civil courseCivil course
Civil course
 
Structure report
Structure reportStructure report
Structure report
 
Hong Albert Portfolio
Hong Albert PortfolioHong Albert Portfolio
Hong Albert Portfolio
 
Delhi high court construction
Delhi high court constructionDelhi high court construction
Delhi high court construction
 
Building Structure Force Analysis
Building Structure Force AnalysisBuilding Structure Force Analysis
Building Structure Force Analysis
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
department of mechanical & water resources
department of mechanical & water resourcesdepartment of mechanical & water resources
department of mechanical & water resources
 

Recently uploaded

Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
bjmsejournal
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 

Recently uploaded (20)

Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 

Project Planning And Control Club house design with MSP

  • 1. RICS SCHOOL OF BUILT ENVIRONMENT, Amity University Submitted By : AYUSH KHANDELWAL : KARAN SONI : UTKARSH MITTAL : RAJAT BHARDAWAJ SECTION : “B” Group : 2 Sub Group : 5 Taught By: Mrs. Susan George Adjunct Associate Professor
  • 2. INDEX 1. List of activities for the work packages 2. Network linking the activities and incorporating activity durations 3. Critical path calculation and duration of project 4. Calculation of total and free floats 5. Milestone chart showing information requirement and ordering of major items 6. Resource sheet with list of resource needs 7. Crashing of activity to reduce project time by at least 10 days (2 Marks)
  • 7. LIST OF ACTIVITIES Activity No. Work Description Duration Earthwork 1 Excavation for Foundation 30 2 Refilling of Foundation 8 Civil Works 3 Raft Foundation 8 4 Lower Ground-Column 2 5 Lower Ground-Slab & Beam 4 6 Upper Ground-Column 2 7 Upper Ground-Slab & Beam 4 8 First Floor-Column 2 9 First Floor-Slab & Beam 6 10 Terrce Column (Mumty) 2 11 Terrace Slab & Beam (Mumty) 6 Brickwork 12 Lower Ground 4 13 Upper Ground 14 14 First Floor 6 15 Terrace 2 Electrical Wiring 16 Lower Ground 6 17 Upper Ground 4 18 First Floor 5 19 Terrace 1 Plaster Work 20 Lower Ground 16 21 Upper Ground 16 22 First Floor 17 23 Terrace 3 24 External 17 25 Project Inspection 1
  • 9. Milestone Table & Chart S.no Start Date Activity Description Days 1.1 Friday, January 5, 2018 Concept 0 1.2 Monday, January 15, 2018 Design Development 10 1.3 Thursday, February 1, 2018 Architectural Drawing Package 27 1.4 Saturday, February 10, 2018 Structural Drawing Package 36 1.5 Thursday, February 15, 2018 Plumbing Drawing Package 41 1.6 Tuesday, February 20, 2018 Electrical Drawing Package 46 1.7 Tuesday, February 27, 2018 HVAC Drawing Package 53 1.8 Saturday, March 3, 2018 Landscape Drawing Package 57 1.9 Sunday, March 4, 2018 Drawing Review 58 2 Monday, March 5, 2018 Sanctioning 59 2.1 Saturday, March 10, 2018 Sanction Drawing Package 64 2.2 Monday, March 12, 2018 Submission of Sanction Drawing 66 2.3 Thursday, March 15, 2018 Working Drawing Package (GFC) 69 2.4 Friday, March 16, 2018 Shop Drawings 70 2.5 Saturday, March 17, 2018 Elevator + Start Procurement 71 2.6 Monday, March 19, 2018 Doors & Windows + Start Procurement 73 2.7 Wednesday, March 21, 2018 Conference/ Meeting before Construction Stage 75 2.8 Saturday, March 24, 2018 Construction Stage 78 2.9 Sunday, March 25, 2018 Site Clearance and Fencing 79 3 Thursday, March 29, 2018 Excavation for foundation 83 3.1 Monday, April 30, 2018 Raft Foundation 115 3.2 Thursday, May 10, 2018 Civil Work Super Structure 125 3.3 Thursday, May 17, 2018 Brickwork 132 3.4 Thursday, May 31, 2018 Electrical Wiring 146 3.5 Monday, June 18, 2018 Plaster Work 164
  • 10.
  • 11.
  • 13. Crashing of Activities ORIGINAL CRASHED Activity No. Work Description Duration IPA Start finish Duration Start Finish Remark Earthwork 1 Excavation for Foundation 30 Start 0 30 30 0 20 REDUCE BY 10 DAYS 2 Refilling of Foundation 8 SS4 8 16 8 8 16 Civil Works 3 Raft Foundation 8 FS1 30 38 8 20 28 4 Lower Ground- Column 2 FS3 38 40 2 28 30 5 Lower Ground- Slab & Beam 4 FS4 40 44 2 30 34 REDUCE BY 2 DAYS 6 Upper Ground- Column 2 FS5 44 46 2 34 46 7 Upper Ground- Slab & Beam 4 FS6 46 50 2 46 48 REDUCE BY 2 DAYS 8 First Floor- Column 2 FS7 50 52 2 48 52 9 First Floor- Slab & Beam 6 FS8 52 58 4 52 56 REDUCE BY 2 DAYS 10 Terrce Column (Mumty) 2 FS9 58 60 2 56 60 11 Terrace Slab & Beam (Mumty) 6 FS10 60 66 4 60 64 REDUCE BY 2 DAYS
  • 14. Brickwork 12 Lower Ground 4 FS5 44 48 4 34 48 13 Upper Ground 14 FS7 50 64 12 48 62 REDUCE BY 2 DAYS 14 First Floor 6 FS9 58 64 6 56 62 15 Terrace 2 FS11 66 68 2 64 66 ORIGINAL CRASHED Electrical Wiring 16 Lower Ground 6 FS12 48 54 6 48 54 17 Upper Ground 4 FS13 64 68 4 62 66 18 First Floor 5 FS14 64 69 5 62 67 19 Terrace 1 FS15 68 69 1 66 67 Plaster Work 20 Lower Ground 16 FS16 54 70 16 54 70 21 Upper Ground 16 FS17 68 84 16 54 70 22 First Floor 17 FS18 69 86 17 67 84 23 Terrace 3 FS19 69 72 3 67 70 24 External 17 FS15 68 85 17 66 83 25 Project Inspection 1 FS2,FS20,FS21,FS22,FS23,FS24 86 87 1 70 71