SlideShare a Scribd company logo
DELAY IN MAJOR CIVIL CONSTRUCTION
PROJECTS:
A CASE STUDY OF MELAMCHI WATER SUPPLY
PROJECT(MWSP)
Presented By:
PROJECT GROUP
School Of Engineering
Pokhara University
067/BCE
GROUP MEMBERS:
MAHESH RAJ BHATT
SUNDAR ADHIKARI
RAJU KHATRI
RAM KRISHNAACHARYA
SANJU SHARMA
SADANA TIWARI
MUKESH KR. SWARNKAR
ABSTRACT
 Nepal is a landlocked country in between
two giant civil developed countries named
China & India.
 As being in developing era , Nepal has
been suffering from delay problem in major
civil construction projects such as
hydroelectric project , water supply project,
irrigation project ,projects related to
transportation and other too.
 Various news articles from online newspaper and documents
of MWSDP were studied and analyzed to collect published
data related to MWSDP in central region of Nepal.
 .Major study is oriented with contracting process, tendering
process, various construction problems, technical and socio-
economical aspects these causes delay in completion.
 Melamchi Khanepani development committee (MKDC)
was established under developing act 2034 has scheduled its
completion date as 2 September 2013.
• Key words:
Delay in major civil engineering projects,
water supply project, technical causes of
delay.
1. INTRODUCTION
• In the moment the country is entering into the
new era of democratic republic and feudal
autocratic kingdom was abolished by the
peoples movement, many horizons of new
opportunities are emerging .
• Investment in civil construction projects
mainly water supply project is very important
for the development of any country .
• As water is not only essential for human being
it is also necessary to all livestock and plants..
• The Melamchi water supply project (MWSP)
is considered to be the most viable long-term
alternative to ease the chronic water shortage
situation within the Kathmandu valley .
• The project is designed to divert about 170
MLD of fresh water to Kathmandu valley
from the Melamchi river in Sindhupalchowk
district . Augmenting this supply by adding
about the further 170 MLD each from the
Yangri and Larke rivers.
• Project is located in Kathmandu and
Sindhupalchowk central development region.
• The intake site is located in the upper part of
the Melamchi river basin about 1 km North
West of Dorin village and about 0.5 km south
east of Ghawakang village at the elevation of
about 1425 m.
• The project area stretches from the intake at
Melamchi River to the outlet at Sundarijal,
about 14 km north east of Kathmandu city.
• The MWSP was projected to cost US $464
million in 2000 A.D .Out of which financial
separation as GON US $118 million and US $
346 million for donor agencies.
• Current financing plan and sources to
respective project is..
1.GON US $118 million
2.ADB US $120 million
3.WB US $80 million
4.JBIC US $52 million
5.NORAD US $28 million
6.SIDA US $25 million
7.JICA US $18 million, and others..
• China Railway 15 Bureau Group Co-
orporation and CMIICJV has selected as
contractor for project in 2008.
• Currently Italian Co-operation Muritorie
cementisti ( CMC ) is constructing tunneling
part with completition schedule targeted as
April 14,2016.
SEE VIDEO CLIP1
2.STUDY AREA OF MWSP
• Located in Kathamandu and Sindhupalchowk
district in Central Development Region of Nepal.
• The intake site is located in the upper part of the
Melamchi river basin about 1 km North West of
Dorin village and about 0.5 km south east of
Ghawakang village at the elevation of about 1425 m.
• The project area stretches from the intake at
Melamchi River to the outlet at Sundarijal, about 14
km north east of Kathmandu city.
3.METHODS AND MATERIALS
• The desk study is followed by the literature
review.
• Scientific literature such as journal , articles ,
books /documents including research/project
reports.
• Study of Progress reports of MWSDB.
• study of online news.
• study of old national newspapers of various
dates.
• 4.SPECIAL FEATURES OF THE PROJECTS
S.N. NAME DIMENSION LOCATION REM.
1 TUNNEL 27.582 k.m.
2 AMBATHAN ADIT 298.3m
3 GYALTHUM AUDIT 330.5 M.
4 SINDHU AUDIT 752 m.
5 TREATMENT PLANT 4 NOS. WITH 85 MLD SUNDARIJAL
6 ACCESS ROAD 6.5 K.M. KATHMANDU
7 ACCESS ROAD 59.5 KM. MELANCHI
8 OUTLET 1.5 K.M. SUNDARIJAL
5.PROBLEMS:
Major problems/ challenges causing delay of project can be
categorized as
A. Technical
• Political situation
aggrement with ADB was done in 2002 for 6 years, but it
completed without any starting of work up to 2008.
• Detail estimate conflict/controversial estimation.
;g @))* df af]nkq cfJxfg ubf{ k]z ePsf af]nkqx? dWo] ;a}eGbf sd
c+s saf]n ug]{af]nkqbftf afx]s cGo af]nkqbftfx?sf] af]nkq tTsflng
cj:Yffdf ;d]t nfut cg'dfg eGbfsl/a #* b]lv &# k|ltzt a9L /x]sf] lyof] .
o;/L tTsflng cj:yfdf g} af]nkqbftfx?sf] cf};tsaf]n c+s Go'gtd saf]n
c+seGbf nueu ?= Ps ca{ krf; s/f]8 al9 /x]sf] b]lvG5 . o;af6tTsflng
cj:yfdf klg o; sfo{sf] k|rlnt ahf/ d"No nfut cg'dfg eGbf a9L /x]sf]
cj:yfb]lvG5 .
•
• Administrative problems
• tendering process/ contracting process.
With first contractor aggrement about Niches and
pregrouting was not done accurately. That causes
serious problem between both parties during
construction.
Termination of first contractor without
completion of work (only 23%) in 25 sep2012.
And rebidding with CMC in 21 June 3013.
this causes hamper of nearly one and half
year.
B.Geographic problems
-landslides
-weak interior geography in tunneling line.
C.Social and environmental
• obstruction of local people.
Because of im proper social upliftment.
SEE VIDEO CLIP
• downstream ecological and hydrological
hazards.
• social upliftment programme extension in
other VDC,s than 14 scheduled .
6.OUR OPENION:
• This is the transition phase of nepal to enter in well
developed country from this situation. Here ,in
Nepal we have unbelievable potentiality, e.g. Water
resources, green forests, huge technical manpower,
and others too.
• Kathamandu valley will celebrate at the moment
when water drop falls in tap of Kathmandu from
MWSP.
• There are various technical, social and
environmental causes hampering all civil
construction in Nepal
• It is also intresting that in nepal ,there is a
major administrative and political amaturity
towards construction projects.
• Various plans (long/short) in nepal do not
complete until deadline, because of lack of
well equipped machines, well convinced
manpower,.
• There are conflict between locals and national
agencies during planning/construction phase.
• The concept of public private partnership
(PPP) is one of the advance tool to manage
such disputes.
• In this case, there we conclude major problem that
hinder and delay the project is unaccurate
contracting with chinese company. (Such as nothing
mentained about variation in tunnelling process.)
• We have been suffering in delay every where
because of our culture is not efficient.
• There should be legal ,ethical and moral evaluation
of each parts in any project to promote contractors ,
that may enhance the progress of projects.
7.CONCLUSION:
• Nepal government (GON) and melamchi
water supply development board(MWSDB)
has scheduled its completion date sept-2016.
• Current contractor Italian company CRC has
expected completion date before six month of
sept-2016.
• Melanchi is not a day dream of Kathmandu,
because monthly work progress report also
proofs its reality that it is possible to complete
this project in scheduled time.
• The date is not so far that people of Kathmandu
collect water in the home.
• It is too late to be pessimistic by complaining only
to politicians and others except ownself.
• There is equal role of everyone who exist in this
nation to be alert and careful about this weak
condition of Nepal in civil engineering evolution.
• Almost half of the Nepalese civil engineers and
youth manpower are completely dependent upon
foreign, although we and our country have higher
potentiality than our current demand in any civil
engineering field.
sf7df8f} af;Lsf] d]nDrLsf] kfgL lkpg] ;kgf
THANK YOU
ANY QUARRIES…???

More Related Content

What's hot

Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)
IRFAN UR REHMAN
 
water supply scheme
water supply schemewater supply scheme
water supply scheme
sunil9666
 
Chennai floods
Chennai floodsChennai floods
Chennai floods
Deepu Kishore
 
Dams and barrages
Dams and barragesDams and barrages
Dams and barrages
Mohsin Amir
 
Mumbai Floods (2005)- A brief report from Disaster Management Perspective
Mumbai Floods (2005)- A brief report from Disaster Management PerspectiveMumbai Floods (2005)- A brief report from Disaster Management Perspective
Mumbai Floods (2005)- A brief report from Disaster Management Perspective
Prasad Thanthratey
 
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Denish Jangid
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
Arpita Gupta
 
Water for Hydroelectric Generation
Water for Hydroelectric GenerationWater for Hydroelectric Generation
Water for Hydroelectric Generation
haroldtaylor1113
 
Reasons behind flood in chennai
Reasons behind flood in chennaiReasons behind flood in chennai
Reasons behind flood in chennai
deesha joshi
 
CEE559_Gummaraj_Bharath_FinalPresentation
CEE559_Gummaraj_Bharath_FinalPresentationCEE559_Gummaraj_Bharath_FinalPresentation
CEE559_Gummaraj_Bharath_FinalPresentation
Bharath Gummaraj
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
Akepati S. Reddy
 
types of flood & flood mitigation/management techniques - damages
types of  flood & flood mitigation/management techniques - damagestypes of  flood & flood mitigation/management techniques - damages
types of flood & flood mitigation/management techniques - damages
Eddy Ankit Gangani
 
Earth and rockfill dams
Earth and rockfill damsEarth and rockfill dams
Earth and rockfill dams
Civil Zone
 
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, PakistanMalakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
Awais Marwat
 
construction of barrage cum bridge and canal works
construction of barrage cum bridge and canal worksconstruction of barrage cum bridge and canal works
construction of barrage cum bridge and canal works
PANEM SRINIVASULU
 
Disaster Management in Chennai Floods (2015)
Disaster Management in Chennai Floods (2015)Disaster Management in Chennai Floods (2015)
Disaster Management in Chennai Floods (2015)
ADITYA SRIKAR KOTA
 
Macchu dam
Macchu dam Macchu dam
Macchu dam
vishvjeet tholia
 
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Er. Abhushan Neupane
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
Joseph Jincy
 
Chennai flood 2015- causes and effects
Chennai flood 2015- causes and effectsChennai flood 2015- causes and effects
Chennai flood 2015- causes and effects
AbinayaMeenapriya
 

What's hot (20)

Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)Neelum Jhelum Hydropower Project (NJHP)
Neelum Jhelum Hydropower Project (NJHP)
 
water supply scheme
water supply schemewater supply scheme
water supply scheme
 
Chennai floods
Chennai floodsChennai floods
Chennai floods
 
Dams and barrages
Dams and barragesDams and barrages
Dams and barrages
 
Mumbai Floods (2005)- A brief report from Disaster Management Perspective
Mumbai Floods (2005)- A brief report from Disaster Management PerspectiveMumbai Floods (2005)- A brief report from Disaster Management Perspective
Mumbai Floods (2005)- A brief report from Disaster Management Perspective
 
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
 
Water for Hydroelectric Generation
Water for Hydroelectric GenerationWater for Hydroelectric Generation
Water for Hydroelectric Generation
 
Reasons behind flood in chennai
Reasons behind flood in chennaiReasons behind flood in chennai
Reasons behind flood in chennai
 
CEE559_Gummaraj_Bharath_FinalPresentation
CEE559_Gummaraj_Bharath_FinalPresentationCEE559_Gummaraj_Bharath_FinalPresentation
CEE559_Gummaraj_Bharath_FinalPresentation
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
types of flood & flood mitigation/management techniques - damages
types of  flood & flood mitigation/management techniques - damagestypes of  flood & flood mitigation/management techniques - damages
types of flood & flood mitigation/management techniques - damages
 
Earth and rockfill dams
Earth and rockfill damsEarth and rockfill dams
Earth and rockfill dams
 
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, PakistanMalakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
Malakand III Hydro Power Project (81MW), Dargai, Khyber Pakhtunkhwa, Pakistan
 
construction of barrage cum bridge and canal works
construction of barrage cum bridge and canal worksconstruction of barrage cum bridge and canal works
construction of barrage cum bridge and canal works
 
Disaster Management in Chennai Floods (2015)
Disaster Management in Chennai Floods (2015)Disaster Management in Chennai Floods (2015)
Disaster Management in Chennai Floods (2015)
 
Macchu dam
Macchu dam Macchu dam
Macchu dam
 
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Chennai flood 2015- causes and effects
Chennai flood 2015- causes and effectsChennai flood 2015- causes and effects
Chennai flood 2015- causes and effects
 

Viewers also liked

Melamchi Drinking Water Project
Melamchi Drinking Water ProjectMelamchi Drinking Water Project
Melamchi Drinking Water Project
Ujjwal Joshi
 
Tirupur Water Supply and Sanitation
Tirupur Water Supply and SanitationTirupur Water Supply and Sanitation
Tirupur Water Supply and Sanitation
Ipsit Dash
 
Water Sources & Pathogens
Water Sources & PathogensWater Sources & Pathogens
Water Sources & Pathogens
Tom Mahin
 
Restoring running water to a school in The Gambia
Restoring running water to a school in The GambiaRestoring running water to a school in The Gambia
Restoring running water to a school in The Gambia
Justin Spees, MBA
 
Conflict and Transboundary Water Issues
Conflict and Transboundary Water IssuesConflict and Transboundary Water Issues
Conflict and Transboundary Water Issues
environmentalconflicts
 
Nepal; Eco Home For Sustainable Water Management: A Case Study In Kathmandu
Nepal;  Eco Home For Sustainable Water Management:  A Case Study In KathmanduNepal;  Eco Home For Sustainable Water Management:  A Case Study In Kathmandu
Nepal; Eco Home For Sustainable Water Management: A Case Study In Kathmandu
V9X
 
Kathmandu's water supply operators_Mr. Dibesh Shrestha
Kathmandu's water supply operators_Mr. Dibesh ShresthaKathmandu's water supply operators_Mr. Dibesh Shrestha
Kathmandu's water supply operators_Mr. Dibesh Shrestha
SaciWATERs
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
Koppolu Abishek
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
mitesh patel
 
Shantigram Presentation
Shantigram PresentationShantigram Presentation
Shantigram Presentation
Hetal Gudhka Khimasiya
 
Simulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanetSimulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanet
Riki Rahmadhan KS
 
Geography Revision Pack AQA/Edexcel
Geography Revision Pack AQA/EdexcelGeography Revision Pack AQA/Edexcel
Geography Revision Pack AQA/Edexcel
anicholls1234
 
Water supply system
Water supply systemWater supply system
Water supply system
aishah
 
Aranya Low Cost Housing
Aranya Low Cost HousingAranya Low Cost Housing
Aranya Low Cost Housing
Ankita Kolamkar
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
Manish Pandey
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment board
Bhim Upadhyaya
 
Water Supply - Design Approach And Methodologies
Water  Supply - Design Approach And MethodologiesWater  Supply - Design Approach And Methodologies
Water Supply - Design Approach And Methodologies
Ir. Abdul Aziz Abas
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
Bibhabasu Mohanty
 

Viewers also liked (18)

Melamchi Drinking Water Project
Melamchi Drinking Water ProjectMelamchi Drinking Water Project
Melamchi Drinking Water Project
 
Tirupur Water Supply and Sanitation
Tirupur Water Supply and SanitationTirupur Water Supply and Sanitation
Tirupur Water Supply and Sanitation
 
Water Sources & Pathogens
Water Sources & PathogensWater Sources & Pathogens
Water Sources & Pathogens
 
Restoring running water to a school in The Gambia
Restoring running water to a school in The GambiaRestoring running water to a school in The Gambia
Restoring running water to a school in The Gambia
 
Conflict and Transboundary Water Issues
Conflict and Transboundary Water IssuesConflict and Transboundary Water Issues
Conflict and Transboundary Water Issues
 
Nepal; Eco Home For Sustainable Water Management: A Case Study In Kathmandu
Nepal;  Eco Home For Sustainable Water Management:  A Case Study In KathmanduNepal;  Eco Home For Sustainable Water Management:  A Case Study In Kathmandu
Nepal; Eco Home For Sustainable Water Management: A Case Study In Kathmandu
 
Kathmandu's water supply operators_Mr. Dibesh Shrestha
Kathmandu's water supply operators_Mr. Dibesh ShresthaKathmandu's water supply operators_Mr. Dibesh Shrestha
Kathmandu's water supply operators_Mr. Dibesh Shrestha
 
Intze tank design
Intze tank designIntze tank design
Intze tank design
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
Shantigram Presentation
Shantigram PresentationShantigram Presentation
Shantigram Presentation
 
Simulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanetSimulation of water distribution networks the use of epanet
Simulation of water distribution networks the use of epanet
 
Geography Revision Pack AQA/Edexcel
Geography Revision Pack AQA/EdexcelGeography Revision Pack AQA/Edexcel
Geography Revision Pack AQA/Edexcel
 
Water supply system
Water supply systemWater supply system
Water supply system
 
Aranya Low Cost Housing
Aranya Low Cost HousingAranya Low Cost Housing
Aranya Low Cost Housing
 
P.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish PandeyP.P.T on water distribution system by Manish Pandey
P.P.T on water distribution system by Manish Pandey
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment board
 
Water Supply - Design Approach And Methodologies
Water  Supply - Design Approach And MethodologiesWater  Supply - Design Approach And Methodologies
Water Supply - Design Approach And Methodologies
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
 

Similar to A case study of melamchi water supply project(mwsp)

Proposal
ProposalProposal
Proposal
prabinzoc
 
Project LlifeCycle
Project LlifeCycleProject LlifeCycle
Project LlifeCycle
Saravanan rulez
 
Sustainibility assessment in hydropower project a case study of nyadi hp
Sustainibility assessment in hydropower project a case study of nyadi hpSustainibility assessment in hydropower project a case study of nyadi hp
Sustainibility assessment in hydropower project a case study of nyadi hp
Suwash Acharya
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Oswar Mungkasa
 
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
'Denish Makvana'
 
Overview of the construction management unit (1).pptx
Overview of the construction management unit (1).pptxOverview of the construction management unit (1).pptx
Overview of the construction management unit (1).pptx
SaharFekry3
 
Government project
Government projectGovernment project
Government project
lutuf Ullah
 
Impact of road extension project on the residents of ktm
Impact of road extension project on the residents of ktmImpact of road extension project on the residents of ktm
Impact of road extension project on the residents of ktm
Nabin Bhattarai
 
Integrated Water Resources Management in Bangladesh: LGED Context
Integrated Water Resources Management in Bangladesh: LGED ContextIntegrated Water Resources Management in Bangladesh: LGED Context
Integrated Water Resources Management in Bangladesh: LGED Context
MdNurulHuda16
 
Planning of Water Resource Planning Projects
Planning of Water Resource Planning ProjectsPlanning of Water Resource Planning Projects
Planning of Water Resource Planning Projects
DARSHAN MEHTA
 
RIVER INTERLINKING (BY CANAL AND TUNNELS)
RIVER INTERLINKING (BY CANAL AND TUNNELS)RIVER INTERLINKING (BY CANAL AND TUNNELS)
RIVER INTERLINKING (BY CANAL AND TUNNELS)
IRJET Journal
 
The wet valley crisis in Koula lampur Malaysia
The wet valley crisis in Koula lampur Malaysia The wet valley crisis in Koula lampur Malaysia
The wet valley crisis in Koula lampur Malaysia
Dahman Ben
 
Nick Tandi
Nick TandiNick Tandi
Nick Tandi
7391456
 
PROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORTPROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORT
Adibah Awang
 
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
IRJET Journal
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
Kartikeya Pandey
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
Festo Wasukira
 
TNT'CV-2016
TNT'CV-2016TNT'CV-2016
TNT'CV-2016
Nam Trung Tran
 
Final book project
Final book projectFinal book project
Final book project
yaasiin123
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
JunaidAshraf31
 

Similar to A case study of melamchi water supply project(mwsp) (20)

Proposal
ProposalProposal
Proposal
 
Project LlifeCycle
Project LlifeCycleProject LlifeCycle
Project LlifeCycle
 
Sustainibility assessment in hydropower project a case study of nyadi hp
Sustainibility assessment in hydropower project a case study of nyadi hpSustainibility assessment in hydropower project a case study of nyadi hp
Sustainibility assessment in hydropower project a case study of nyadi hp
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
 
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
Rural Infrastructure Development Projects Under MGNREGA, Clean Village : A St...
 
Overview of the construction management unit (1).pptx
Overview of the construction management unit (1).pptxOverview of the construction management unit (1).pptx
Overview of the construction management unit (1).pptx
 
Government project
Government projectGovernment project
Government project
 
Impact of road extension project on the residents of ktm
Impact of road extension project on the residents of ktmImpact of road extension project on the residents of ktm
Impact of road extension project on the residents of ktm
 
Integrated Water Resources Management in Bangladesh: LGED Context
Integrated Water Resources Management in Bangladesh: LGED ContextIntegrated Water Resources Management in Bangladesh: LGED Context
Integrated Water Resources Management in Bangladesh: LGED Context
 
Planning of Water Resource Planning Projects
Planning of Water Resource Planning ProjectsPlanning of Water Resource Planning Projects
Planning of Water Resource Planning Projects
 
RIVER INTERLINKING (BY CANAL AND TUNNELS)
RIVER INTERLINKING (BY CANAL AND TUNNELS)RIVER INTERLINKING (BY CANAL AND TUNNELS)
RIVER INTERLINKING (BY CANAL AND TUNNELS)
 
The wet valley crisis in Koula lampur Malaysia
The wet valley crisis in Koula lampur Malaysia The wet valley crisis in Koula lampur Malaysia
The wet valley crisis in Koula lampur Malaysia
 
Nick Tandi
Nick TandiNick Tandi
Nick Tandi
 
PROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORTPROJECT MANAGEMENT PROJECT 2 REPORT
PROJECT MANAGEMENT PROJECT 2 REPORT
 
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
Canal Oriented Development Concept as a tool for Canal: A case of Ugat canal,...
 
Alandur sewerage proj arun
Alandur sewerage proj   arunAlandur sewerage proj   arun
Alandur sewerage proj arun
 
Pader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement ReportPader SCAP100 Stakeholder Engagement Report
Pader SCAP100 Stakeholder Engagement Report
 
TNT'CV-2016
TNT'CV-2016TNT'CV-2016
TNT'CV-2016
 
Final book project
Final book projectFinal book project
Final book project
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 

Recently uploaded

ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
MiscAnnoy1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 

Recently uploaded (20)

ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 

A case study of melamchi water supply project(mwsp)

  • 1. DELAY IN MAJOR CIVIL CONSTRUCTION PROJECTS: A CASE STUDY OF MELAMCHI WATER SUPPLY PROJECT(MWSP) Presented By: PROJECT GROUP School Of Engineering Pokhara University 067/BCE
  • 2. GROUP MEMBERS: MAHESH RAJ BHATT SUNDAR ADHIKARI RAJU KHATRI RAM KRISHNAACHARYA SANJU SHARMA SADANA TIWARI MUKESH KR. SWARNKAR
  • 3.
  • 4. ABSTRACT  Nepal is a landlocked country in between two giant civil developed countries named China & India.  As being in developing era , Nepal has been suffering from delay problem in major civil construction projects such as hydroelectric project , water supply project, irrigation project ,projects related to transportation and other too.
  • 5.  Various news articles from online newspaper and documents of MWSDP were studied and analyzed to collect published data related to MWSDP in central region of Nepal.  .Major study is oriented with contracting process, tendering process, various construction problems, technical and socio- economical aspects these causes delay in completion.  Melamchi Khanepani development committee (MKDC) was established under developing act 2034 has scheduled its completion date as 2 September 2013.
  • 6. • Key words: Delay in major civil engineering projects, water supply project, technical causes of delay.
  • 7. 1. INTRODUCTION • In the moment the country is entering into the new era of democratic republic and feudal autocratic kingdom was abolished by the peoples movement, many horizons of new opportunities are emerging . • Investment in civil construction projects mainly water supply project is very important for the development of any country . • As water is not only essential for human being it is also necessary to all livestock and plants..
  • 8. • The Melamchi water supply project (MWSP) is considered to be the most viable long-term alternative to ease the chronic water shortage situation within the Kathmandu valley . • The project is designed to divert about 170 MLD of fresh water to Kathmandu valley from the Melamchi river in Sindhupalchowk district . Augmenting this supply by adding about the further 170 MLD each from the Yangri and Larke rivers. • Project is located in Kathmandu and Sindhupalchowk central development region.
  • 9. • The intake site is located in the upper part of the Melamchi river basin about 1 km North West of Dorin village and about 0.5 km south east of Ghawakang village at the elevation of about 1425 m. • The project area stretches from the intake at Melamchi River to the outlet at Sundarijal, about 14 km north east of Kathmandu city. • The MWSP was projected to cost US $464 million in 2000 A.D .Out of which financial separation as GON US $118 million and US $ 346 million for donor agencies.
  • 10. • Current financing plan and sources to respective project is.. 1.GON US $118 million 2.ADB US $120 million 3.WB US $80 million 4.JBIC US $52 million 5.NORAD US $28 million 6.SIDA US $25 million 7.JICA US $18 million, and others..
  • 11. • China Railway 15 Bureau Group Co- orporation and CMIICJV has selected as contractor for project in 2008. • Currently Italian Co-operation Muritorie cementisti ( CMC ) is constructing tunneling part with completition schedule targeted as April 14,2016. SEE VIDEO CLIP1
  • 12. 2.STUDY AREA OF MWSP • Located in Kathamandu and Sindhupalchowk district in Central Development Region of Nepal. • The intake site is located in the upper part of the Melamchi river basin about 1 km North West of Dorin village and about 0.5 km south east of Ghawakang village at the elevation of about 1425 m. • The project area stretches from the intake at Melamchi River to the outlet at Sundarijal, about 14 km north east of Kathmandu city.
  • 13.
  • 14.
  • 15.
  • 16. 3.METHODS AND MATERIALS • The desk study is followed by the literature review. • Scientific literature such as journal , articles , books /documents including research/project reports. • Study of Progress reports of MWSDB. • study of online news. • study of old national newspapers of various dates.
  • 17. • 4.SPECIAL FEATURES OF THE PROJECTS S.N. NAME DIMENSION LOCATION REM. 1 TUNNEL 27.582 k.m. 2 AMBATHAN ADIT 298.3m 3 GYALTHUM AUDIT 330.5 M. 4 SINDHU AUDIT 752 m. 5 TREATMENT PLANT 4 NOS. WITH 85 MLD SUNDARIJAL 6 ACCESS ROAD 6.5 K.M. KATHMANDU 7 ACCESS ROAD 59.5 KM. MELANCHI 8 OUTLET 1.5 K.M. SUNDARIJAL
  • 18. 5.PROBLEMS: Major problems/ challenges causing delay of project can be categorized as A. Technical • Political situation aggrement with ADB was done in 2002 for 6 years, but it completed without any starting of work up to 2008. • Detail estimate conflict/controversial estimation. ;g @))* df af]nkq cfJxfg ubf{ k]z ePsf af]nkqx? dWo] ;a}eGbf sd c+s saf]n ug]{af]nkqbftf afx]s cGo af]nkqbftfx?sf] af]nkq tTsflng cj:Yffdf ;d]t nfut cg'dfg eGbfsl/a #* b]lv &# k|ltzt a9L /x]sf] lyof] . o;/L tTsflng cj:yfdf g} af]nkqbftfx?sf] cf};tsaf]n c+s Go'gtd saf]n c+seGbf nueu ?= Ps ca{ krf; s/f]8 al9 /x]sf] b]lvG5 . o;af6tTsflng cj:yfdf klg o; sfo{sf] k|rlnt ahf/ d"No nfut cg'dfg eGbf a9L /x]sf] cj:yfb]lvG5 . •
  • 19. • Administrative problems • tendering process/ contracting process. With first contractor aggrement about Niches and pregrouting was not done accurately. That causes serious problem between both parties during construction. Termination of first contractor without completion of work (only 23%) in 25 sep2012. And rebidding with CMC in 21 June 3013. this causes hamper of nearly one and half year.
  • 20. B.Geographic problems -landslides -weak interior geography in tunneling line. C.Social and environmental • obstruction of local people. Because of im proper social upliftment. SEE VIDEO CLIP • downstream ecological and hydrological hazards. • social upliftment programme extension in other VDC,s than 14 scheduled .
  • 21.
  • 22. 6.OUR OPENION: • This is the transition phase of nepal to enter in well developed country from this situation. Here ,in Nepal we have unbelievable potentiality, e.g. Water resources, green forests, huge technical manpower, and others too. • Kathamandu valley will celebrate at the moment when water drop falls in tap of Kathmandu from MWSP. • There are various technical, social and environmental causes hampering all civil construction in Nepal
  • 23. • It is also intresting that in nepal ,there is a major administrative and political amaturity towards construction projects. • Various plans (long/short) in nepal do not complete until deadline, because of lack of well equipped machines, well convinced manpower,. • There are conflict between locals and national agencies during planning/construction phase. • The concept of public private partnership (PPP) is one of the advance tool to manage such disputes.
  • 24. • In this case, there we conclude major problem that hinder and delay the project is unaccurate contracting with chinese company. (Such as nothing mentained about variation in tunnelling process.) • We have been suffering in delay every where because of our culture is not efficient. • There should be legal ,ethical and moral evaluation of each parts in any project to promote contractors , that may enhance the progress of projects.
  • 25. 7.CONCLUSION: • Nepal government (GON) and melamchi water supply development board(MWSDB) has scheduled its completion date sept-2016. • Current contractor Italian company CRC has expected completion date before six month of sept-2016. • Melanchi is not a day dream of Kathmandu, because monthly work progress report also proofs its reality that it is possible to complete this project in scheduled time.
  • 26. • The date is not so far that people of Kathmandu collect water in the home. • It is too late to be pessimistic by complaining only to politicians and others except ownself. • There is equal role of everyone who exist in this nation to be alert and careful about this weak condition of Nepal in civil engineering evolution. • Almost half of the Nepalese civil engineers and youth manpower are completely dependent upon foreign, although we and our country have higher potentiality than our current demand in any civil engineering field.
  • 27. sf7df8f} af;Lsf] d]nDrLsf] kfgL lkpg] ;kgf