2. ACKNOWLEDGEMENT
We would like to express the deepest appreciation to our HOD sir Er.Prashant Thapaliya for his
helpful suggestion and an excitement in regard to guiding to study and preparing this
proposal.Without his guidance this proposal would not have been possible.We would like to
thank Mr.Ashish Kc for his valuable co-operation.Last but not least,we thank MM cyber for it’s
effort in printing the proposal.
Project Team Members:
Abhishek Rauniyar
Anup Regmi
Rupesh Chaudhary
Prashant Joshi
3. ABSTRACT
Shortage of water in Kathmandu valley have increased steadily for several years.The daily water
demand for Kathmanndu valley is more than 360 million litres per day whereas the supply is
around 90 million litres per day in dry season and 140 million per litres per day in wet season
according to the website of Kathmandu Upatyaka Khanepani Limited(KUKL).If we talk about
ground water, its extraction started since 1970’s in the Kathmandu Valley and since then the
extraction has been increasing at an alarming rate.Ground water experts state if the water is
pumped at the similar rate,there will be no ground water at all after around 100 years.Researched
data shows that more than 80% of tap water(primary source of water in the most of households
of Kathmandu valley) were found to be infected with e-coil bacteria making it unsuitable for
drinking directly but even many peoples are drinking it directly.The key problem is identified in
ground water(well and boring) were contaminated with iron and turbidity,making it unsuitable
for drinking.So,Ministry of water supply has been working on Melamchi water supply project
with the objectives to alleviate this shortage ona sustainable and long term basis-improve the
health and well being of the people in the valley.Our main aim is to study on the process of water
treatment plant which is installed in Sundarijal,Water supplying capacity etc.
Project Team Member
4. TABLE OF CONTENTS
CONTENTS PAGE NUMBER
ACKNOWLEDGEMENT
ABSTRACT
INTRODUCTION………………………………………………………………………….1
OBJECTIVES…………………………………………………………………………........2
LOCATION OF VISITING SITE…………………………………………….……..........2
METHODOLOGY……………………………………………………………………........3
MANAGEMENT PLAN…………………………………………………………………..4
LOGICAL FRAMEWORK ANALYSIS…………………………………………….......5
REFERENCES………………………………………………………………………….....6
LIST OF FIGURES
Figure1.1:Source of Water Supply
Figure1.2:Water supplied through Tunnel
Figure1.3:Water Treatment Process
Figure1.4:Google Map of Visiting Site
LIST OF TABLES
Table1.1: Management Plan
Table1.2:Logical Framework Analysis
5. INTRODUCTION
Water Supply is a process of supplying water usually including reservoirs, tunnels and pipelines
.A water supply typically includes:
A raw water collection point where the water accumulates, such as lakes, rivers or ground water
from an underground water acquifer .Raw water may be transferred using uncovered ground
level aqueducts, covered tunnel or underground water pipes to water purification facilities. Water
Treatment plant is any process that improves the quality of water to make it more acceptable for
a specific end-use. The end-use may be drinking ,Industrial water supply etc.
Figure1.1:Source of water supply Figure1.2:Water supplied through tunnel
Figure1.3:Water treatment Process
1
6. Treated water is transferred using water pipes.Water storage facilities such as reservoirs,water
tanks or water towers.Smaller water systems may store the water in cisterns.A pipe network for
distribution of water to the consumers.The proposed review will discuss the amount of water
supplied and process of water treatment plant. The survey will be carried on sundarijal where the
supplied water is treated through water treatment plant.This proposal includes our methods for
gathering information and a schedule for completing the review.
OBJECTIVES
The overall objective is to study about water supply system. Main objectives of this proposed
review are listed as below:
To know the process of water treatment.
To know the amount of water treated and supplied.
To have knowledge about the government steps and action to improve the quality of drinking
water.
LOCATION OF VISITING AREA(STUDY AREA)
The survey will be carried on sundarijal where the supplied water is treated through water
treatment plant which is located at a distance of 22.9km from Sanepa to our study area.
Figure1.4:Google map of visiting site
2
7. METHODOLOGY
This Section highlights our method of collecting informations and data.In order to collect the
necessary data,the following methods are applied:
A)Primary Methods:
(i)Visiting the site carefully and observing various element such as water treatment
plant,reservoirs and supply of the water through the tunnel and underground water pipes.
(ii) Interviewing with some local people and experts opinion for the collection of information.
B)Secondary Methods:
(i)Reading news article,books,articles and searching on internet in order to collect all the
necessary information and data.
3
8. Management Plan/Time Scale
This section presents our schedule,costs for completing the proposed
research.This research culminates in a formal report,which will be completed by the end of this
semester.To reach this goal,we will follow the schedule presented in table:
Table 1.1:Management Plan
4
WBS Activity Name/Task Name DATE
Poush Magh Falgun
25 29 13 14 16 17 18 19 5 6 7 9 2
2
1.1 Planning the Research Project
1.2 Formation of Group
1.3 Choosing Project Topic
2.1 Project Proposal
2.2 Writing Up of Project Proposal
2.3 Submission of Project Proposal
3.1 Reading Books,Novels
4.1 Site Visit & Writing full
Research Project
4.2 Submit the Full Research
Project
4.3 Presentation Of Research
Project
9. LOGICAL FRAMEWORK ANALYSIS
This section highlights an overview of our project's goal,activities and anticipated results.
Table1.2:Logical Framework Analysis
Project Description Objectively verificable
indicators of achievement
Sources and
means of
Verification
Assumptions
Goal To know
water
supply
system.
Project site Visit. Source:Melamchi
Water supply
Project.
Purpose To have
knowledge
about the
government
steps and
action to
improve the
quality of
drinking
water.
Project Data Local
people,experts
engineers.
provide the
information on the
quality of water.
Outputs Detailed
information
on the
sundarijal
water
supply.
Project Report Project Record develops the skill
of our oral
presentation,
promote us for
collecting some
sort of relevant
data.
Activities -Reading
books,new
article.
Resources:
Teacher,Library,Internet.
Costs:
Rs.200-Rs.400
help while underst
-Anding the water
supply system in
working site.
5