SlideShare a Scribd company logo
Estimate Activity Resources
Coincides with PMBOK 9.2
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Estimate Activity Resources
What is it?
Estimate Activity Resources is the process of estimating team
resources and the type and quantities of materials, equipment, and
supplies necessary to perform project work
Why?
The key benefit of this process is that it identifies the type, quantity,
and characteristics of resources required to complete the project.
Estimate Activity Resources
Coincides with PMBOK 9.2
Estimate Activity Resources
Coincides with PMBOK 9.2
Inputs Tools & Techniques Outputs
1. Project management plan
• Resource management plan
• Scope baseline
2. Project documents
• Activity attributes
• Activity list
• Assumption log
• Cost estimates
• Resource calendars
• Risk register
3. Enterprise environmental factors
4. Organizational process assets
1. Expert judgment
2. Bottom-up estimating
3. Analogous estimating
4. Parametric estimating
5. Data analysis
• Alternatives analysis
6. Project Management
Information System
7. Meetings
1. Resource requirements
2. Basis of estimates
3. Resource breakdown structure
4. Project documents updates
• Activity attributes
• Assumption log
• Risk register
Inputs, Tools & Techniques, Outputs
Coincides with PMBOK 9.2
9.2 Estimate
Activity
Resources
Project
Management
Plan
Enterprise/Orga
nization
• Resource requirements
• Basis of estimates
• Resource breakdown
structure
• Resource
management plan
• Scope baseline
• Enterprise
environmental factors
• Organizational
process assets
Project Documents
• Assumption Log
• Lessons Learned Register
• Activity attributes
Project Documents
• Activity attributes
• Activity list
• Assumption log
• Cost estimates
• Resource calendars
• Risk register
Estimate Activity Resources
Overview
The Estimate Activity Resources process is closely coordinated with other processes,
such as the Estimate Costs process. Example:
• An automotive design team will need to be familiar with the latest automated
assembly techniques. The requisite knowledge could be obtained by hiring a
consultant, by sending a designer to a seminar on robotics, or by including someone
from manufacturing as a member of the project team.
Coincides with PMBOK 9.2
Estimate Activity Resources
Estimate Activity Resources - Inputs
Coincides with PMBOK 9.2
Project Management Plan
Project management plan components include:
• Resource management plan
• Scope baseline
Coincides with PMBOK 9.2
Project Documents
Project documents that can be considered as inputs for this process include:
• Activity attributes
• Activity list
• Assumption log
• Cost estimates
• Resource calendars
• Risk register
Estimate Activity Resources - Inputs
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Estimate Activity
Resources process include:
• Resource location,
• Resource availability
• Team resource skills
• Organizational culture
• Published estimating data
• Marketplace conditions
Coincides with PMBOK 9.2
Estimate Activity Resources - Inputs
Organisational Process Assets
The organizational process assets that can influence the Estimate Activity Resources
process include :
• Policies and procedures regarding staffing
• Policies and procedures relating to supplies and equipment
• Historical information regarding types of resources used for similar work on
previous projects.
Coincides with PMBOK 9.2
Estimate Activity Resources - Inputs
Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Expert Judgement
Expertise should be considered from individuals or groups with
specialized knowledge or training in team and physical resource planning
and estimating.
Coincides with PMBOK 9.2
Bottom-Up Estimating
Team and physical resources are estimated at the activity level and then
aggregated to develop the estimates for work packages, control accounts,
and summary project levels.
Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Analogous Estimating
Analogous estimating uses information regarding resources from a
previous similar project as the basis for estimating a future project. It is
used as quick estimating method and can be used when the project
manager can only identify a few top levels of the WBS.
Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Parametric Estimating
Parametric estimating uses an algorithm or a statistical relationship between
historical data and other variables to calculate resource quantities needed for an
activity, based on historical data and project parameters. This technique can produce
higher levels of accuracy depending on the sophistication and underlying data built
into the model.
Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Data Analysis
A data analysis technique used in this process includes, alternatives analysis.
• Alternatives analysis is used to evaluate identified options in order to select the
options or approaches to use to execute and perform the work of the project.
Alternatives analysis assists in providing the best solution to perform the project
activities, within the defined constraints.
Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Project Management Information System
Estimate Activity Resources – Tools & Techniques
Project management information systems can include resource management software
that can help plan, organize, and manage resource pools and develop resource
estimates. Depending on the sophistication of the software, resource breakdown
structures, resource availability, resource rates, and various resource calendars can be
defined to assist in optimizing resource utilization.
Coincides with PMBOK 9.2
Meetings
Estimate Activity Resources – Tools & Techniques
The project manager may hold planning meetings with functional managers to estimate
the resources needed per activity, level of effort (LoE), skill level of the team resources,
and the quantity of the materials needed. Participants at these meetings may include
the project manager, the project sponsor, selected project team members, selected
stakeholders, and others as needed.
Coincides with PMBOK 9.2
Resource Requirements
Resource requirements identify the types and quantities of resources required for
each work package or activity in a work package and can be aggregated to determine
the estimated resources for each work package, each WBS branch, and the project as
a whole. The resource requirements’ documentation can include assumptions that
were made in determining which types of resources are applied, their availability, and
what quantities are needed.
Estimate Activity Resources – Outputs
Coincides with PMBOK 9.2
Basis of Estimates
The amount and type of additional details supporting the resource estimate vary by
application area. Supporting detail for resource estimates may include:
• Method used to develop the estimate
• Resources used to develop the estimate
• Assumptions associated with the estimate
• Known constraints
• Range of estimates
• Confidence level of the estimate
• Documentation of identified risks influencing the estimate.
Estimate Activity Resources – Outputs
Coincides with PMBOK 9.2
Resource Breakdown Structure
The resource breakdown
structure is a hierarchical
representation of resources
by category and type.
Examples of resource
categories include but are
not limited to labor,
material, equipment, and
supplies.
Estimate Activity Resources – Outputs
Resource Breakdown Structure Sample
Coincides with PMBOK 9.2
Project Document Updates
Project documents that may be updated as a result of carrying out this
process include:
• Activity attributes
• Assumption Log
• Risk Register
Estimate Activity Resources – Outputs

More Related Content

What's hot

Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )
Qussay Karam
 
Wbs
WbsWbs
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Pedram Danesh-Mand
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
Aditya Pandey
 
Project Mangement
Project MangementProject Mangement
Project Mangement
Gaurav Shrivastava
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
Naseer Muhammud
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Markos Mulat G
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2
Mazhar Poohlah
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
341741357
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
Kishan Solankimbaccepmp
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
Ahmed Alageed
 
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
ChandraShekhar Patel
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
Mazen Elsayed
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
Mazen Zbib
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
Agus Suhanto
 

What's hot (20)

Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )
 
Wbs
WbsWbs
Wbs
 
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Project scope statement template v2.3
Project scope statement template v2.3Project scope statement template v2.3
Project scope statement template v2.3
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
2. traditional project management -ch2
2. traditional project management -ch22. traditional project management -ch2
2. traditional project management -ch2
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Project Management
Project ManagementProject Management
Project Management
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 

Similar to 9.2 Estimate Activity Resources

7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
DavidMcLachlan1
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
DavidMcLachlan1
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
DavidMcLachlan1
 
9.3 Acquire Resources
9.3 Acquire Resources9.3 Acquire Resources
9.3 Acquire Resources
DavidMcLachlan1
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
DavidMcLachlan1
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
DavidMcLachlan1
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
DavidMcLachlan1
 
Ch 8(spi)cm mi-pp
Ch 8(spi)cm mi-ppCh 8(spi)cm mi-pp
Ch 8(spi)cm mi-pp
Kittitouch Suteeca
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
Glen Alleman
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
MohamadAGhareb
 
Time management
Time managementTime management
Time management
Mostafa Elgamala
 
Project time management
Project time managementProject time management
Project time management
Imran Jamil
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
DavidMcLachlan1
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
university(kust)
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
DavidMcLachlan1
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
Omer Alsayed PhD,MBA, PMP®
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
Omer Alsayed PhD,MBA, PMP®
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
GlobalSkillup
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
DavidMcLachlan1
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
DavidMcLachlan1
 

Similar to 9.2 Estimate Activity Resources (20)

7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
9.3 Acquire Resources
9.3 Acquire Resources9.3 Acquire Resources
9.3 Acquire Resources
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
Ch 8(spi)cm mi-pp
Ch 8(spi)cm mi-ppCh 8(spi)cm mi-pp
Ch 8(spi)cm mi-pp
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
4- Project Cost Management.ppt
4- Project Cost Management.ppt4- Project Cost Management.ppt
4- Project Cost Management.ppt
 
Time management
Time managementTime management
Time management
 
Project time management
Project time managementProject time management
Project time management
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 

More from DavidMcLachlan1

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
DavidMcLachlan1
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
DavidMcLachlan1
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
DavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
DavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
DavidMcLachlan1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
DavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
DavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
DavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
DavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
DavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
DavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
DavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
DavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
DavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
DavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
DavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
DavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
DavidMcLachlan1
 

More from DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 

Recently uploaded

SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
MysoreMuleSoftMeetup
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Vivekanand Anglo Vedic Academy
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
danielkiash986
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
nitinpv4ai
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
RidwanHassanYusuf
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
melliereed
 
B. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdfB. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdf
BoudhayanBhattachari
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
zuzanka
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Henry Hollis
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
RamseyBerglund
 

Recently uploaded (20)

SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
 
Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47Mule event processing models | MuleSoft Mysore Meetup #47
Mule event processing models | MuleSoft Mysore Meetup #47
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
Bonku-Babus-Friend by Sathyajith Ray (9)
Bonku-Babus-Friend by Sathyajith Ray  (9)Bonku-Babus-Friend by Sathyajith Ray  (9)
Bonku-Babus-Friend by Sathyajith Ray (9)
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
 
B. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdfB. Ed Syllabus for babasaheb ambedkar education university.pdf
B. Ed Syllabus for babasaheb ambedkar education university.pdf
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
 

9.2 Estimate Activity Resources

  • 2. Coincides with PMBOK 9.2 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement Estimate Activity Resources
  • 3. What is it? Estimate Activity Resources is the process of estimating team resources and the type and quantities of materials, equipment, and supplies necessary to perform project work Why? The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the project. Estimate Activity Resources Coincides with PMBOK 9.2
  • 4. Estimate Activity Resources Coincides with PMBOK 9.2 Inputs Tools & Techniques Outputs 1. Project management plan • Resource management plan • Scope baseline 2. Project documents • Activity attributes • Activity list • Assumption log • Cost estimates • Resource calendars • Risk register 3. Enterprise environmental factors 4. Organizational process assets 1. Expert judgment 2. Bottom-up estimating 3. Analogous estimating 4. Parametric estimating 5. Data analysis • Alternatives analysis 6. Project Management Information System 7. Meetings 1. Resource requirements 2. Basis of estimates 3. Resource breakdown structure 4. Project documents updates • Activity attributes • Assumption log • Risk register Inputs, Tools & Techniques, Outputs
  • 5. Coincides with PMBOK 9.2 9.2 Estimate Activity Resources Project Management Plan Enterprise/Orga nization • Resource requirements • Basis of estimates • Resource breakdown structure • Resource management plan • Scope baseline • Enterprise environmental factors • Organizational process assets Project Documents • Assumption Log • Lessons Learned Register • Activity attributes Project Documents • Activity attributes • Activity list • Assumption log • Cost estimates • Resource calendars • Risk register Estimate Activity Resources
  • 6. Overview The Estimate Activity Resources process is closely coordinated with other processes, such as the Estimate Costs process. Example: • An automotive design team will need to be familiar with the latest automated assembly techniques. The requisite knowledge could be obtained by hiring a consultant, by sending a designer to a seminar on robotics, or by including someone from manufacturing as a member of the project team. Coincides with PMBOK 9.2 Estimate Activity Resources
  • 7. Estimate Activity Resources - Inputs Coincides with PMBOK 9.2 Project Management Plan Project management plan components include: • Resource management plan • Scope baseline
  • 8. Coincides with PMBOK 9.2 Project Documents Project documents that can be considered as inputs for this process include: • Activity attributes • Activity list • Assumption log • Cost estimates • Resource calendars • Risk register Estimate Activity Resources - Inputs
  • 9. Enterprise Environmental Factors The enterprise environmental factors that can influence the Estimate Activity Resources process include: • Resource location, • Resource availability • Team resource skills • Organizational culture • Published estimating data • Marketplace conditions Coincides with PMBOK 9.2 Estimate Activity Resources - Inputs
  • 10. Organisational Process Assets The organizational process assets that can influence the Estimate Activity Resources process include : • Policies and procedures regarding staffing • Policies and procedures relating to supplies and equipment • Historical information regarding types of resources used for similar work on previous projects. Coincides with PMBOK 9.2 Estimate Activity Resources - Inputs
  • 11. Estimate Activity Resources – Tools & Techniques Coincides with PMBOK 9.2 Expert Judgement Expertise should be considered from individuals or groups with specialized knowledge or training in team and physical resource planning and estimating.
  • 12. Coincides with PMBOK 9.2 Bottom-Up Estimating Team and physical resources are estimated at the activity level and then aggregated to develop the estimates for work packages, control accounts, and summary project levels. Estimate Activity Resources – Tools & Techniques
  • 13. Coincides with PMBOK 9.2 Analogous Estimating Analogous estimating uses information regarding resources from a previous similar project as the basis for estimating a future project. It is used as quick estimating method and can be used when the project manager can only identify a few top levels of the WBS. Estimate Activity Resources – Tools & Techniques
  • 14. Coincides with PMBOK 9.2 Parametric Estimating Parametric estimating uses an algorithm or a statistical relationship between historical data and other variables to calculate resource quantities needed for an activity, based on historical data and project parameters. This technique can produce higher levels of accuracy depending on the sophistication and underlying data built into the model. Estimate Activity Resources – Tools & Techniques
  • 15. Coincides with PMBOK 9.2 Data Analysis A data analysis technique used in this process includes, alternatives analysis. • Alternatives analysis is used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project. Alternatives analysis assists in providing the best solution to perform the project activities, within the defined constraints. Estimate Activity Resources – Tools & Techniques
  • 16. Coincides with PMBOK 9.2 Project Management Information System Estimate Activity Resources – Tools & Techniques Project management information systems can include resource management software that can help plan, organize, and manage resource pools and develop resource estimates. Depending on the sophistication of the software, resource breakdown structures, resource availability, resource rates, and various resource calendars can be defined to assist in optimizing resource utilization.
  • 17. Coincides with PMBOK 9.2 Meetings Estimate Activity Resources – Tools & Techniques The project manager may hold planning meetings with functional managers to estimate the resources needed per activity, level of effort (LoE), skill level of the team resources, and the quantity of the materials needed. Participants at these meetings may include the project manager, the project sponsor, selected project team members, selected stakeholders, and others as needed.
  • 18. Coincides with PMBOK 9.2 Resource Requirements Resource requirements identify the types and quantities of resources required for each work package or activity in a work package and can be aggregated to determine the estimated resources for each work package, each WBS branch, and the project as a whole. The resource requirements’ documentation can include assumptions that were made in determining which types of resources are applied, their availability, and what quantities are needed. Estimate Activity Resources – Outputs
  • 19. Coincides with PMBOK 9.2 Basis of Estimates The amount and type of additional details supporting the resource estimate vary by application area. Supporting detail for resource estimates may include: • Method used to develop the estimate • Resources used to develop the estimate • Assumptions associated with the estimate • Known constraints • Range of estimates • Confidence level of the estimate • Documentation of identified risks influencing the estimate. Estimate Activity Resources – Outputs
  • 20. Coincides with PMBOK 9.2 Resource Breakdown Structure The resource breakdown structure is a hierarchical representation of resources by category and type. Examples of resource categories include but are not limited to labor, material, equipment, and supplies. Estimate Activity Resources – Outputs Resource Breakdown Structure Sample
  • 21. Coincides with PMBOK 9.2 Project Document Updates Project documents that may be updated as a result of carrying out this process include: • Activity attributes • Assumption Log • Risk Register Estimate Activity Resources – Outputs

Editor's Notes

  1. This process is performed periodically throughout the project as needed.
  2. A construction project team will need to be familiar with local building codes. Such knowledge is often readily available from local sellers. If the internal labor pool lacks experience with unusual or specialized construction techniques, the additional cost for a consultant may be the most effective way to secure knowledge of the local building codes.
  3. Resource management plan - The resource management plan defines the approach to identify the different resources needed for the project. It also defines the methods to quantify the resources needed for each activity and aggregates this information. Scope baseline - The scope baseline identifies the project and product scope necessary to meet the project objectives. The scope drives the needs for both team and physical resources.
  4. Activity attributes - Activity attributes provide the primary data source for use in estimating team and physical resources required for each activity on the activity list. Activity list - The activity list identifies the activities that will need resources. Assumption log - The assumption log may have information on productivity factors, availability, cost estimates, and approaches to work that will influence the nature and number of team and physical resources. Cost estimates - The cost of resources may impact resource selection from the quantity and skill level perspectives. Resource calendars - A resource calendar identifies the working days, shifts, start and end of normal business hours, weekends, and public holidays when each specific resource is available. Risk register - The risk register describes the individual risks that can impact resource selection and availability.
  5. For example, if an activity needs 4,000 hours of coding and it needs to finish it in 1 year, it will require two people to code (each doing 2,000 hours a year).
  6. The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area.
  7. Regardless of the level of detail, the supporting documentation should provide a clear and complete understanding of how the resource estimate was derived.
  8. Resource types may include the skill level, grade level, required certifications, or other information as appropriate to the project. In Plan Resource Management, the resource breakdown structure was used to guide the categorization for the project. In this process it is a completed document that will be used to acquire and monitor resources.
  9. Activity attributes - The activity attributes are updated with the resource requirements. Assumption log - The assumption log is updated with assumptions regarding the types and quantities of resources required. Additionally, any resource constraints are entered including collective bargaining agreements, continuous hours of operation, planned leave, etc. Lessons learned register - The lessons learned register can be updated with techniques that were efficient and effective in developing resource estimates, and information on those techniques that were not efficient or effective.