The Estimate Activity Resources process involves estimating the types and quantities of resources needed to complete project activities. Inputs include the project management plan, project documents, enterprise environmental factors, and organizational process assets. Tools and techniques used include expert judgment, bottom-up estimating, analogous estimating, parametric estimating, data analysis, project management information systems, and meetings. Outputs include resource requirements, basis of estimates, a resource breakdown structure, and updates to project documents.
Plan Resource Management involves defining how to estimate, acquire, manage, and use team and physical resources for a project. Key inputs include the project charter, management plan, and documents. Expert judgement, data representation techniques, organizational theory, and meetings are used. The main outputs are a resource management plan defining resource roles and control, a team charter establishing guidelines, and updates to documents like the assumption and risk logs.
This document provides an overview of software project management. It discusses that software development requires management due to budget and schedule constraints. Project management activities include proposal writing, planning, costing, monitoring, personnel selection, and reporting. Techniques from engineering project management can also apply to software projects. Calculating the critical path and using techniques like PERT are important for scheduling projects and accounting for uncertainty in duration estimates. Float refers to slack time in a project schedule where tasks can be delayed without impacting subsequent tasks or the overall completion date.
Here are the key steps to cost a WBS:
1. Estimate the cost of each work package or activity at the lowest level of the WBS using estimating techniques like analogous, parametric, bottom-up etc.
2. Assign resources like labor, materials, equipment to each activity and apply the appropriate cost rates.
3. Use project management software to automatically sum or "roll up" the costs of individual activities to higher levels and the total project cost.
4. The software allows viewing and reporting the costs against the WBS structure to identify areas that may need attention or re-estimating.
5. The costed WBS provides the basis for developing the project budget and cost baseline for monitoring
The concepts and processes on how to perform project resource management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan resource management, estimate activity resources, acquire team, develop team, manage team, and control resources.
The document provides tips for creating a project management plan. It summarizes each of the key sections that should be included in the plan: integration, scope management, schedule management, cost management, quality management, human resource management, communication management, risk management, and procurement management. For each section, it provides high-level descriptions of the types of information that should be included as well as tips for developing each part of the plan.
Project scope management includes processes for defining and controlling what work needs to be done to deliver the project, beginning with developing a scope management plan, collecting requirements, and creating a detailed project scope statement that outlines the deliverables, exclusions, assumptions and acceptance criteria. It also involves breaking the work down into a work breakdown structure and validating that the project scope accurately reflects stakeholder needs through requirements traceability and change control. Effective scope management is crucial for project success by ensuring the project includes all necessary work and only the work required to complete the project.
This document discusses project scope management. It begins by defining project scope as the work involved in creating project deliverables and processes. It then outlines the key processes in scope management: collecting requirements, defining scope, creating a work breakdown structure (WBS), verifying scope, and controlling scope. The document provides details on each step, including how to document requirements, develop a project charter and scope statement, and create a WBS. It emphasizes the importance of scope management in developing accurate estimates and clearly communicating work responsibilities.
Plan Resource Management involves defining how to estimate, acquire, manage, and use team and physical resources for a project. Key inputs include the project charter, management plan, and documents. Expert judgement, data representation techniques, organizational theory, and meetings are used. The main outputs are a resource management plan defining resource roles and control, a team charter establishing guidelines, and updates to documents like the assumption and risk logs.
This document provides an overview of software project management. It discusses that software development requires management due to budget and schedule constraints. Project management activities include proposal writing, planning, costing, monitoring, personnel selection, and reporting. Techniques from engineering project management can also apply to software projects. Calculating the critical path and using techniques like PERT are important for scheduling projects and accounting for uncertainty in duration estimates. Float refers to slack time in a project schedule where tasks can be delayed without impacting subsequent tasks or the overall completion date.
Here are the key steps to cost a WBS:
1. Estimate the cost of each work package or activity at the lowest level of the WBS using estimating techniques like analogous, parametric, bottom-up etc.
2. Assign resources like labor, materials, equipment to each activity and apply the appropriate cost rates.
3. Use project management software to automatically sum or "roll up" the costs of individual activities to higher levels and the total project cost.
4. The software allows viewing and reporting the costs against the WBS structure to identify areas that may need attention or re-estimating.
5. The costed WBS provides the basis for developing the project budget and cost baseline for monitoring
The concepts and processes on how to perform project resource management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan resource management, estimate activity resources, acquire team, develop team, manage team, and control resources.
The document provides tips for creating a project management plan. It summarizes each of the key sections that should be included in the plan: integration, scope management, schedule management, cost management, quality management, human resource management, communication management, risk management, and procurement management. For each section, it provides high-level descriptions of the types of information that should be included as well as tips for developing each part of the plan.
Project scope management includes processes for defining and controlling what work needs to be done to deliver the project, beginning with developing a scope management plan, collecting requirements, and creating a detailed project scope statement that outlines the deliverables, exclusions, assumptions and acceptance criteria. It also involves breaking the work down into a work breakdown structure and validating that the project scope accurately reflects stakeholder needs through requirements traceability and change control. Effective scope management is crucial for project success by ensuring the project includes all necessary work and only the work required to complete the project.
This document discusses project scope management. It begins by defining project scope as the work involved in creating project deliverables and processes. It then outlines the key processes in scope management: collecting requirements, defining scope, creating a work breakdown structure (WBS), verifying scope, and controlling scope. The document provides details on each step, including how to document requirements, develop a project charter and scope statement, and create a WBS. It emphasizes the importance of scope management in developing accurate estimates and clearly communicating work responsibilities.
Introduction to project management( framework and processes )Qussay Karam
Project management involves balancing scope, schedule, budget, resources, quality and risk to achieve project objectives. It is accomplished through applying knowledge, skills, tools and techniques from the five process groups of initiating, planning, executing, monitoring and controlling, and closing. The project manager leads the project team and is responsible for meeting stakeholder needs and project requirements.
This document discusses software project management techniques for work breakdown structures (WBS), estimation, and scheduling. It defines the key differences between planning, estimating, and scheduling. It provides guidance on creating a WBS using top-down, bottom-up, or other techniques. Estimation methodologies like algorithmic measures, reuse factors, and the COCOMO model are explained. The importance of understanding deadline types for scheduling is also covered.
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Pedram Danesh-Mand
As a quantitative risk analysis tool, Schedule Risk Analysis enables stakeholders to identify and quantify the project risks and opportunities and, through comparative analysis of possible scenarios, to develop project programmes and budgets with a more level of confidence.
This document outlines the scope of a project to <Meaningful Title for Project>. It describes the background and need for the project, objectives, deliverables, resources, budget, and approval process. The key stakeholders are identified as the project manager, technical lead, client, and sponsor. The project will <Describe the product or service that this project will produce> to address a specific business need. Upon completion, the deliverables will be tested and signed off by the client before closing the project.
This document provides an overview of basic project management concepts. It discusses that a project has defined scope, time, cost, quality and resource constraints. The key aspects of project management include planning the work, working the plan, and endorsing the plan. The project manager's role is to manage expectations, direct the team, track progress, communicate status, and resolve issues. Effective project management balances the triple constraints of scope, time and cost. The project life cycle begins with initiation, which involves defining objectives, assembling a team, and getting approval. Planning then further develops the scope, schedule, budget, risks and other elements of the project.
This project charter outlines a project to achieve specific objectives that align with organizational strategy and priorities. It will resolve problems and realize benefits. The charter defines the project scope and key milestones or deliverables. It also identifies assumptions that must be validated, impacts on systems, and roles for the sponsor, project manager, team members, customer, and subject matter experts. Resources committed to the project are specified. Risks and strategies to mitigate them are also identified. The charter is approved by signatures of the customer, sponsors, and project manager.
Risk analysis is a systematic process to estimate the probability and impact of identified project risks. There are qualitative and quantitative approaches to risk analysis. Qualitative approaches use scales to assess probability and impact and assign risk levels like low, medium, high. Quantitative approaches use techniques like expected value analysis to generate probabilistic estimates of project outcomes. Monte Carlo simulation is commonly used to model project risks and determine the likelihood of meeting objectives within given cost and schedule constraints. Effective risk management involves identifying, analyzing, prioritizing and developing response plans for risks throughout the project lifecycle.
The document outlines the key phases and processes of traditional project management including defining, planning, executing, monitoring and controlling, and closing. It describes the traditional project management life cycle as involving scoping, developing a project plan, launching the project, monitoring progress, and closing out the project. Additionally, it discusses quality management, risk management, procurement management, and how project management relates to other methodologies.
This is the part of the presentation done by a PMP Workgroup which includes the project managers from NashTech, Trobz and Besco to study the Project Management and get the PMP certification. This part describes the process of Estimate Activity Durations in the Project Schedule Management knowledge area.
The document discusses project monitoring and control. It describes the various activities that must be regularly monitored during a project, including scope, schedule, budget, risk, and contract management. It also explains the key elements of project control: baseline development, change control, and progress monitoring. Baselines establish plans for scope, schedule, budget, and stakeholder satisfaction. Change control manages changes to the project baselines and progress. Regular monitoring compares progress to the plans to identify variances requiring corrective action.
1) The document discusses various methods for estimating project times and costs, including top-down macro approaches like consensus methods and ratio methods, and bottom-up micro approaches like template methods and parametric procedures applied to specific tasks.
2) It explains that estimates are important for project planning, scheduling, budgeting, and progress monitoring. Factors like people, structure, and culture can influence estimate quality.
3) Guidelines are provided for developing estimates, such as having familiar people make estimates, treating tasks independently, and including risk assessments to avoid surprises. Contingency funds and time buffers can be used to refine estimates.
The presentation discusses project control and outlines steps to improve project control systems. It introduces basic concepts of projects, project control systems, and the current lack of effective controls. The presentation proposes formalizing processes, training, clarifying roles, and improving communication, documentation, and accountability to enhance project performance monitoring and management.
- What is project scope?
- why scope management is important?
- what are the processes of scope management?
- what is Scope Baseline?
- how to create WBS?
The document outlines an agenda for a project management seminar. It will cover topics such as project governance, the project management knowledge areas, methodology, fundamentals, and introductions. The seminar leader has a background in information technology and project management. Breakout sessions are planned to discuss identifying potential projects, writing a project charter, and prioritizing projects. The seminar aims to provide an overview of key project management concepts.
The project management monitoring and controlling starts as soon as a project begins. Project monitoring and controlling processes are where the performance of the project is measured and action is taken based on an analysis of this data.
The document provides an overview of project management using MS Project 2010. It discusses starting a project and identifying the main parts of the Project window. It also covers exploring different MS Project views and reports. The document outlines setting up a project plan, including defining working and non-working time and other properties. It then summarizes chapters on creating a task list, setting up resources, and assigning resources to tasks. Key points include estimating task durations, creating milestones and task relationships, documenting tasks, and controlling how resources are scheduled.
The document discusses project cost management. It defines key terms like life cycle costing, value analysis, types of costs (variable, fixed, direct, indirect), and cost versus price. It also covers the processes of planning cost management, estimating costs, and controlling costs. Planning cost management establishes policies and procedures for managing project costs. Estimating costs develops an approximation of resources needed to complete project activities. Controlling costs involves monitoring and influencing changes to the project budget.
This document provides an overview of Module 11 on Project Risk Management. It covers 8 lessons: (1) key concepts and terms, (2) plan risk management, (3) identify risks, (4) perform qualitative risk analysis, (5) perform quantitative risk analysis, (6) plan risk responses, (7) implement risk responses, and (8) monitor risks. The module defines risk management and its processes. It discusses risk types, tools and techniques for risk planning, identification, analysis, response planning, implementation, and monitoring. The goal is to increase probability of opportunities and decrease probability of threats to optimize project success.
Estimate Costs is the process of developing an approximation of the cost of resources needed to complete project work. It involves considering inputs like the project management plan, project documents, and enterprise environmental factors. Tools like expert judgment, analogous estimating, parametric estimating, and three-point estimating are used. The outputs are cost estimates, basis of estimates, and potential updates to project documents like the assumption log, lessons learned register, and risk register.
Determine Budget is the process of aggregating estimated costs from work packages and activities to establish an authorized cost baseline for the project. It uses inputs like the cost management plan, cost estimates, and risk register to perform cost aggregation and establish the cost baseline and project funding requirements outputs through techniques like expert judgement, data analysis, and historical reviews. The process coincides with PMBOK 7.3 Determine Budget knowledge area.
Introduction to project management( framework and processes )Qussay Karam
Project management involves balancing scope, schedule, budget, resources, quality and risk to achieve project objectives. It is accomplished through applying knowledge, skills, tools and techniques from the five process groups of initiating, planning, executing, monitoring and controlling, and closing. The project manager leads the project team and is responsible for meeting stakeholder needs and project requirements.
This document discusses software project management techniques for work breakdown structures (WBS), estimation, and scheduling. It defines the key differences between planning, estimating, and scheduling. It provides guidance on creating a WBS using top-down, bottom-up, or other techniques. Estimation methodologies like algorithmic measures, reuse factors, and the COCOMO model are explained. The importance of understanding deadline types for scheduling is also covered.
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Pedram Danesh-Mand
As a quantitative risk analysis tool, Schedule Risk Analysis enables stakeholders to identify and quantify the project risks and opportunities and, through comparative analysis of possible scenarios, to develop project programmes and budgets with a more level of confidence.
This document outlines the scope of a project to <Meaningful Title for Project>. It describes the background and need for the project, objectives, deliverables, resources, budget, and approval process. The key stakeholders are identified as the project manager, technical lead, client, and sponsor. The project will <Describe the product or service that this project will produce> to address a specific business need. Upon completion, the deliverables will be tested and signed off by the client before closing the project.
This document provides an overview of basic project management concepts. It discusses that a project has defined scope, time, cost, quality and resource constraints. The key aspects of project management include planning the work, working the plan, and endorsing the plan. The project manager's role is to manage expectations, direct the team, track progress, communicate status, and resolve issues. Effective project management balances the triple constraints of scope, time and cost. The project life cycle begins with initiation, which involves defining objectives, assembling a team, and getting approval. Planning then further develops the scope, schedule, budget, risks and other elements of the project.
This project charter outlines a project to achieve specific objectives that align with organizational strategy and priorities. It will resolve problems and realize benefits. The charter defines the project scope and key milestones or deliverables. It also identifies assumptions that must be validated, impacts on systems, and roles for the sponsor, project manager, team members, customer, and subject matter experts. Resources committed to the project are specified. Risks and strategies to mitigate them are also identified. The charter is approved by signatures of the customer, sponsors, and project manager.
Risk analysis is a systematic process to estimate the probability and impact of identified project risks. There are qualitative and quantitative approaches to risk analysis. Qualitative approaches use scales to assess probability and impact and assign risk levels like low, medium, high. Quantitative approaches use techniques like expected value analysis to generate probabilistic estimates of project outcomes. Monte Carlo simulation is commonly used to model project risks and determine the likelihood of meeting objectives within given cost and schedule constraints. Effective risk management involves identifying, analyzing, prioritizing and developing response plans for risks throughout the project lifecycle.
The document outlines the key phases and processes of traditional project management including defining, planning, executing, monitoring and controlling, and closing. It describes the traditional project management life cycle as involving scoping, developing a project plan, launching the project, monitoring progress, and closing out the project. Additionally, it discusses quality management, risk management, procurement management, and how project management relates to other methodologies.
This is the part of the presentation done by a PMP Workgroup which includes the project managers from NashTech, Trobz and Besco to study the Project Management and get the PMP certification. This part describes the process of Estimate Activity Durations in the Project Schedule Management knowledge area.
The document discusses project monitoring and control. It describes the various activities that must be regularly monitored during a project, including scope, schedule, budget, risk, and contract management. It also explains the key elements of project control: baseline development, change control, and progress monitoring. Baselines establish plans for scope, schedule, budget, and stakeholder satisfaction. Change control manages changes to the project baselines and progress. Regular monitoring compares progress to the plans to identify variances requiring corrective action.
1) The document discusses various methods for estimating project times and costs, including top-down macro approaches like consensus methods and ratio methods, and bottom-up micro approaches like template methods and parametric procedures applied to specific tasks.
2) It explains that estimates are important for project planning, scheduling, budgeting, and progress monitoring. Factors like people, structure, and culture can influence estimate quality.
3) Guidelines are provided for developing estimates, such as having familiar people make estimates, treating tasks independently, and including risk assessments to avoid surprises. Contingency funds and time buffers can be used to refine estimates.
The presentation discusses project control and outlines steps to improve project control systems. It introduces basic concepts of projects, project control systems, and the current lack of effective controls. The presentation proposes formalizing processes, training, clarifying roles, and improving communication, documentation, and accountability to enhance project performance monitoring and management.
- What is project scope?
- why scope management is important?
- what are the processes of scope management?
- what is Scope Baseline?
- how to create WBS?
The document outlines an agenda for a project management seminar. It will cover topics such as project governance, the project management knowledge areas, methodology, fundamentals, and introductions. The seminar leader has a background in information technology and project management. Breakout sessions are planned to discuss identifying potential projects, writing a project charter, and prioritizing projects. The seminar aims to provide an overview of key project management concepts.
The project management monitoring and controlling starts as soon as a project begins. Project monitoring and controlling processes are where the performance of the project is measured and action is taken based on an analysis of this data.
The document provides an overview of project management using MS Project 2010. It discusses starting a project and identifying the main parts of the Project window. It also covers exploring different MS Project views and reports. The document outlines setting up a project plan, including defining working and non-working time and other properties. It then summarizes chapters on creating a task list, setting up resources, and assigning resources to tasks. Key points include estimating task durations, creating milestones and task relationships, documenting tasks, and controlling how resources are scheduled.
The document discusses project cost management. It defines key terms like life cycle costing, value analysis, types of costs (variable, fixed, direct, indirect), and cost versus price. It also covers the processes of planning cost management, estimating costs, and controlling costs. Planning cost management establishes policies and procedures for managing project costs. Estimating costs develops an approximation of resources needed to complete project activities. Controlling costs involves monitoring and influencing changes to the project budget.
This document provides an overview of Module 11 on Project Risk Management. It covers 8 lessons: (1) key concepts and terms, (2) plan risk management, (3) identify risks, (4) perform qualitative risk analysis, (5) perform quantitative risk analysis, (6) plan risk responses, (7) implement risk responses, and (8) monitor risks. The module defines risk management and its processes. It discusses risk types, tools and techniques for risk planning, identification, analysis, response planning, implementation, and monitoring. The goal is to increase probability of opportunities and decrease probability of threats to optimize project success.
Estimate Costs is the process of developing an approximation of the cost of resources needed to complete project work. It involves considering inputs like the project management plan, project documents, and enterprise environmental factors. Tools like expert judgment, analogous estimating, parametric estimating, and three-point estimating are used. The outputs are cost estimates, basis of estimates, and potential updates to project documents like the assumption log, lessons learned register, and risk register.
Determine Budget is the process of aggregating estimated costs from work packages and activities to establish an authorized cost baseline for the project. It uses inputs like the cost management plan, cost estimates, and risk register to perform cost aggregation and establish the cost baseline and project funding requirements outputs through techniques like expert judgement, data analysis, and historical reviews. The process coincides with PMBOK 7.3 Determine Budget knowledge area.
Control Resources is the process of monitoring resource expenditures, identifying resource shortages or surpluses, and ensuring resources are used and released as planned. It uses data analysis, problem solving, and interpersonal skills to analyze resource utilization and make adjustments. The key outputs are updates to the work performance reports, project management plan, and project documents like the issue log.
The Acquire Resources process involves obtaining the team members, facilities, equipment, materials, supplies and other resources needed to complete project work. Key inputs include the project management plan, project documents, enterprise environmental factors and organizational process assets. Tools and techniques used include decision making, negotiation, pre-assignment and virtual teams. Outputs include physical and team resource assignments, resource calendars, change requests and updates to the project management plan and documents.
This document discusses the Identify Risks process, which involves identifying individual project risks and sources of overall project risk, and documenting their characteristics. It is an iterative process that occurs throughout the project life cycle. Key inputs include the project management plan, project documents, agreements, procurement documentation, enterprise environmental factors, and organizational process assets. Tools and techniques used include expert judgment, data gathering, data analysis, interpersonal skills, prompt lists, and meetings. The main output is the project risk register.
The Develop Schedule process involves analyzing activity sequences, durations, resources, and constraints to create a project schedule model. Key steps include identifying milestones, sequencing activities, estimating durations, and resolving conflicts. Tools like critical path method, resource optimization, and data analysis help generate the schedule. The output is a schedule baseline approved by stakeholders, which is later used to measure project performance.
Sequence Activities is the process of identifying and documenting the logical relationships between project activities. This helps define the most efficient sequence of work given project constraints. Key tools used include precedence diagramming to visually map dependencies between activities using logical relationships like finish-to-start. The output is a project schedule network diagram that graphically shows the sequence of activities.
The document discusses project planning processes based on the Capability Maturity Model Integration (CMMI). It describes the key process areas, specific goals, and specific practices for effective project planning. Specifically, it covers the Project Planning process area which has three specific goals: (1) establish estimates for the project, (2) develop a detailed project plan, and (3) obtain commitment to the project plan from stakeholders. For each specific goal, it provides details on the typical work products and subpractices required to meet the goal. The document aims to guide project teams on how to systematically plan their projects using the CMMI framework.
Graded application of project management reqGlen Alleman
This document outlines a graded approach for applying project management processes based on project complexity and risk level. It provides descriptions of project requirements and documentation for four different risk levels - minimal, minor, major, and full implementation. For each project management knowledge area (initiation, planning, execution, monitoring and control, and closeout), it specifies the expected level of documentation, activities, and process implementation for projects at each risk level.
This document discusses the six key processes involved in project time management: define activities, sequence activities, estimate activity resources, estimate activity duration, develop schedule, and control schedule. For each process, it identifies the typical inputs, tools and techniques, and outputs. The main goal of project time management is to ensure timely completion of the project through planning, monitoring, and controlling the schedule.
The document discusses project time management and the processes involved. It describes 7 processes: 1) plan schedule management, 2) define activities, 3) sequence activities, 4) estimate activity resources, 5) estimate activity durations, 6) develop schedule, and 7) control schedule. For each process, it provides the key inputs, tools and techniques, and outputs. The develop schedule process in particular takes the activity list, attributes, durations, resources, and relationships to generate a project schedule model and baseline using techniques like critical path method.
Perform Qualitative Risk Analysis assesses the priority of identified individual project risks using probability and impact assessments. It establishes relative risk priorities for further analysis or response planning. Key tools include expert judgment, interviews, data analysis methods, and probability/impact matrices to categorize and represent risks. Updated risk documents include the risk register and risk report.
This document discusses project management techniques for managing the triple constraints of scope, time, and cost on projects. It defines key terms for scope, time, and cost management and describes tools and techniques for planning, controlling, and completing each area successfully. These include work breakdown structures, Gantt charts, estimating techniques like analogous and parametric estimating, variance analysis, and change control systems. The goal is to incorporate these techniques to deliver projects on budget, on schedule, and according to defined objectives and requirements.
The Plan Cost Management process defines how project costs will be estimated, budgeted, managed, monitored and controlled. It provides guidance on cost management throughout the project. Key inputs include the project charter, schedule and risk plans. Expert judgement, data analysis and meetings are used. The main output is the Cost Management Plan which documents the cost processes, tools, units of measure and control thresholds.
The document discusses project cost management. It provides details on planning cost management, estimating costs, and determining the project budget. Key points include:
1) Planning cost management establishes policies and procedures for managing project costs and results in a cost management plan.
2) Estimating costs develops approximations of resource needs and uses techniques like expert judgment, analogous and parametric estimating.
3) Determining the budget aggregates activity cost estimates to establish a cost baseline.
The document discusses project time management and sequencing activities. It defines sequencing activities as identifying and documenting relationships among project activities to determine the logical sequence of work. The key inputs are the activity list, attributes, and milestone list. Techniques include precedence diagramming and determining dependencies. The main outputs are project schedule network diagrams that visually depict the logical relationships between activities using techniques like finish-to-start, start-to-start, and leads/lags.
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
This document provides information about project time management processes from the PMP certification training website GlobalSkillUp.com. It discusses the seven time management processes including plan schedule management, define activities, sequence activities, estimate activity resources, estimate activity durations, develop schedule, and control schedule. For each process, it describes the inputs, tools and techniques, and outputs. It also provides examples and additional details about scheduling methods, schedule management plans, activity listing and sequencing, resource estimating, and other related topics. The overall purpose is to help readers understand the various aspects of time management required to deliver projects on schedule.
Manage Quality is the process of implementing quality activities outlined in the quality management plan. This includes activities like failure analysis, design of experiments, and quality improvement. Manage Quality uses tools like checklists, data analysis techniques, decision making methods, and quality audits to gather and analyze quality data. Outputs include quality reports, test evaluation documents, and updates to project documents and the project management plan. The goal is to ensure the project meets its quality objectives.
The document discusses the Plan Resource Management processes from PMBOK 9.0. It identifies the six processes as Plan Resource Management, Estimate Activity Resources, Acquire Resources, Develop Team, Manage Team, and Control Resources. It provides overviews of these processes in the planning, executing, and monitoring and controlling process groups. It also discusses key concepts, trends and emerging practices, tailoring considerations, and considerations for agile or adaptive environments related to Plan Resource Management.
An effective communications management plan is developed early to recognize stakeholders' diverse information needs. The plan considers methods for storing, retrieving, and disposing of project information. Regular reviews ensure the plan remains applicable. Key outputs include the communications management plan, updates to the project management plan such as the stakeholder engagement plan, and updates to documents like the project schedule and stakeholder register.
Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance. It involves skills like communication, conflict management, negotiation, and leadership. The key inputs are the project management plan, project documents like issues logs and lessons learned, work performance reports, and team performance assessments. Tools include conflict management techniques, decision making, influencing skills, and project management software. The main outputs are change requests, updates to the project management plan and documents, and updates to enterprise environmental factors.
This document discusses different types of contracts used in project management. It describes contracts as legal agreements between two or more parties. There are two main types of contracts: fixed-price contracts, used when requirements are well-defined, and cost-reimbursable contracts, best used when the scope is expected to change. Specific contract types are defined, including firm fixed price (FFP), fixed price incentive fee (FPIF), cost plus fixed fee (CPFF), and time and material (T&M) contracts.
This document describes the Conduct Procurements process, which coincides with PMBOK 12.2. The key inputs, tools/techniques, and outputs of the process are outlined. The process involves obtaining seller responses, selecting a seller, and awarding a contract. Expert judgement, data analysis, and negotiation are tools that can be used. The main output is selecting qualified sellers and establishing legal agreements/contracts.
Control Procurements is the process of managing procurement relationships and monitoring contract performance to ensure requirements are met. It involves reviewing agreements and documentation, analyzing work performance data, and addressing any issues through inspection, audits, and change requests. The goal is to close out contracts after requirements have been fulfilled based on the terms of the agreement. Updates from this process include updated procurement documentation, project management plans, and organizational process assets.
The document discusses Plan Scope Management, which coincides with PMBOK Knowledge Area 5.1. It involves creating a scope management plan to define, validate, and control the project and product scope. The key benefit is providing guidance on how scope will be managed. Inputs include the project charter, project management plan, enterprise environmental factors and organizational process assets. Tools include expert judgment, data analysis and meetings. The main outputs are the scope management plan and requirements management plan.
This document discusses the process of managing project knowledge according to the Project Management Body of Knowledge (PMBOK). It involves leveraging existing organizational knowledge and creating new knowledge to help achieve project objectives and contribute to organizational learning. Key inputs include the project management plan, project documents like a lessons learned register, and organizational process assets. Tools and techniques used include expert judgment, knowledge management, information management, and interpersonal skills. The main outputs are updates to the lessons learned register, project management plan, and organizational process assets.
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
Cost forecasting techniques are used to estimate the total expected cost of a project based on its current performance and remaining work. This includes estimating the expected total cost (EAC), remaining cost to complete the project (ETC), difference from planned budget (VAC), and level of efficiency needed (TCPI) based on formulas that factor in actual costs, budget, work completed, and current performance trends. An example is provided where a $10,000 project is 30% complete with $5,000 spent so far, and the EAC, ETC, VAC and TCPI are calculated using the relevant formulas.
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
The document outlines the key project management processes involved in planning and executing a project to move 200 employees to a new building. These include planning resource management, procurement, stakeholder engagement, communication, and risk management. The project manager then facilitates acquiring resources, managing risks, and engaging stakeholders. Upon completion, representatives validate the new space and systems before full deployment, with iterative improvements.
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
This document outlines the key processes involved in Project Management Process One. It begins by describing how a project charter and project management plan would be developed for a hypothetical project to move 200 employees to a new building. It then walks through how the scope, schedule, cost, and quality plans would be created by gathering requirements, defining deliverables, creating a work breakdown structure, estimating activities and costs, and developing a quality management plan. The document concludes by noting these initial plans will be used to monitor and control the project as it progresses.
Scenario - The Project Management EnvironmentDavidMcLachlan1
The document discusses a project management scenario where the project manager is tasked with moving 200 employees to a new building including setting up computers, phone systems, and meeting rooms. It describes understanding the organizational environment including existing processes, stakeholders, and systems. The project manager determines they will need knowledge of both project management and the functional area. They choose a waterfall approach given the stable requirements and set budget.
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
The consultant works with company leaders to implement Agile practices starting with one team. They identify 10 practices to implement, with Kanban selected first. A burndown chart and Kanban board are created and used to track progress. After two weeks, the first practice of Kanban is completed. More teams then adopt the approach over iterations and with a Scrum of Scrums process to coordinate progress across teams. After 10 iterations, most teams have implemented the targeted Agile practices.
The document describes an example scenario of a project team using agile practices to develop a new website with a shopping cart for a client. It outlines the key agile practices used: assembling a cross-functional team, working in short iterations to develop features, prioritizing a backlog of user stories, daily stand-ups to track progress, demonstrating work at the end of each iteration, and reflecting on lessons learned to improve. The team uses these practices to iteratively develop and deliver the website's sales page and shopping cart features to the client.
Rolling wave planning is an iterative planning technique where work that will occur sooner is planned in more detail, while future work is planned at a higher level. It involves decomposing work packages into more detailed activities as more information becomes known about upcoming near-term events. Rolling wave planning uses techniques like decomposition and iterative scheduling with a backlog and allows for progressive elaboration of work packages, planning packages, and releases whether using agile or waterfall approaches.
This document summarizes several agile and lean frameworks including Scrum, XP, Kanban, Behavior Driven Development, Agile Unified Process, Dynamic Systems Delivery Method, Crystal, Scrum of Scrums, Large Scale Scrum, Scaled Agile Framework, Enterprise Scrum, and Disciplined Agile. It provides brief descriptions of the core methods, principles, and techniques of each framework.
This document discusses several agile and lean frameworks including Scrum, Kanban, eXtreme Programming (XP), Feature Driven Development (FDD), and others. It provides overviews of each framework, describing their core practices, events, artifacts, principles, and how they relate to agile development.
The document discusses team chartering and measurement in agile environments. It states that in agile projects, teams initiate with a team charter that defines the project vision, stakeholders, definition of done, and working agreements. It also notes that agile favors measuring work completed through iterations using methods like burnup/burndown charts and estimating effort in story points. When adopting agile practices, the document recommends evolving the organization incrementally by treating changes as experiments and tracking progress using kanban boards.
The core Agile practices described in the document include whole team approach, early and frequent feedback, daily stand-ups, retrospectives, release and iteration planning, collaborative user story creation, demonstrations/reviews, and continuous integration. Some key benefits are enhancing communication, leveraging various skill sets, making quality everyone's responsibility, avoiding requirements misunderstandings, and promoting consistent project momentum.
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
The Agile Manifesto outlines four values of agile development: individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, and responding to change over following a plan. It also describes twelve clarifying principles of agile development including delivering working software frequently, having business and developers work closely together daily, and valuing face-to-face conversation.
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
This document discusses different project life cycle models and how to choose the appropriate one based on a project's characteristics. It provides information on predictive, iterative, incremental, agile, and hybrid life cycles. Predictive life cycles are sequential with a single delivery, iterative life cycles use prototypes and feedback, incremental life cycles deliver in frequent smaller releases, and agile life cycles expect requirements to change with customer satisfaction increasing through early delivery. Hybrid models combine elements. The document also lists factors like demand patterns, team experience, and quality that influence tailoring the approach.
The chapter Lifelines of National Economy in Class 10 Geography focuses on the various modes of transportation and communication that play a vital role in the economic development of a country. These lifelines are crucial for the movement of goods, services, and people, thereby connecting different regions and promoting economic activities.
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxEduSkills OECD
Iván Bornacelly, Policy Analyst at the OECD Centre for Skills, OECD, presents at the webinar 'Tackling job market gaps with a skills-first approach' on 12 June 2024
Chapter wise All Notes of First year Basic Civil Engineering.pptxDenish Jangid
Chapter wise All Notes of First year Basic Civil Engineering
Syllabus
Chapter-1
Introduction to objective, scope and outcome the subject
Chapter 2
Introduction: Scope and Specialization of Civil Engineering, Role of civil Engineer in Society, Impact of infrastructural development on economy of country.
Chapter 3
Surveying: Object Principles & Types of Surveying; Site Plans, Plans & Maps; Scales & Unit of different Measurements.
Linear Measurements: Instruments used. Linear Measurement by Tape, Ranging out Survey Lines and overcoming Obstructions; Measurements on sloping ground; Tape corrections, conventional symbols. Angular Measurements: Instruments used; Introduction to Compass Surveying, Bearings and Longitude & Latitude of a Line, Introduction to total station.
Levelling: Instrument used Object of levelling, Methods of levelling in brief, and Contour maps.
Chapter 4
Buildings: Selection of site for Buildings, Layout of Building Plan, Types of buildings, Plinth area, carpet area, floor space index, Introduction to building byelaws, concept of sun light & ventilation. Components of Buildings & their functions, Basic concept of R.C.C., Introduction to types of foundation
Chapter 5
Transportation: Introduction to Transportation Engineering; Traffic and Road Safety: Types and Characteristics of Various Modes of Transportation; Various Road Traffic Signs, Causes of Accidents and Road Safety Measures.
Chapter 6
Environmental Engineering: Environmental Pollution, Environmental Acts and Regulations, Functional Concepts of Ecology, Basics of Species, Biodiversity, Ecosystem, Hydrological Cycle; Chemical Cycles: Carbon, Nitrogen & Phosphorus; Energy Flow in Ecosystems.
Water Pollution: Water Quality standards, Introduction to Treatment & Disposal of Waste Water. Reuse and Saving of Water, Rain Water Harvesting. Solid Waste Management: Classification of Solid Waste, Collection, Transportation and Disposal of Solid. Recycling of Solid Waste: Energy Recovery, Sanitary Landfill, On-Site Sanitation. Air & Noise Pollution: Primary and Secondary air pollutants, Harmful effects of Air Pollution, Control of Air Pollution. . Noise Pollution Harmful Effects of noise pollution, control of noise pollution, Global warming & Climate Change, Ozone depletion, Greenhouse effect
Text Books:
1. Palancharmy, Basic Civil Engineering, McGraw Hill publishers.
2. Satheesh Gopi, Basic Civil Engineering, Pearson Publishers.
3. Ketki Rangwala Dalal, Essentials of Civil Engineering, Charotar Publishing House.
4. BCP, Surveying volume 1
Leveraging Generative AI to Drive Nonprofit InnovationTechSoup
In this webinar, participants learned how to utilize Generative AI to streamline operations and elevate member engagement. Amazon Web Service experts provided a customer specific use cases and dived into low/no-code tools that are quick and easy to deploy through Amazon Web Service (AWS.)
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.pptHenry Hollis
The History of NZ 1870-1900.
Making of a Nation.
From the NZ Wars to Liberals,
Richard Seddon, George Grey,
Social Laboratory, New Zealand,
Confiscations, Kotahitanga, Kingitanga, Parliament, Suffrage, Repudiation, Economic Change, Agriculture, Gold Mining, Timber, Flax, Sheep, Dairying,
Temple of Asclepius in Thrace. Excavation resultsKrassimira Luka
The temple and the sanctuary around were dedicated to Asklepios Zmidrenus. This name has been known since 1875 when an inscription dedicated to him was discovered in Rome. The inscription is dated in 227 AD and was left by soldiers originating from the city of Philippopolis (modern Plovdiv).
2. Coincides with PMBOK 9.2
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
Estimate Activity Resources
3. What is it?
Estimate Activity Resources is the process of estimating team
resources and the type and quantities of materials, equipment, and
supplies necessary to perform project work
Why?
The key benefit of this process is that it identifies the type, quantity,
and characteristics of resources required to complete the project.
Estimate Activity Resources
Coincides with PMBOK 9.2
6. Overview
The Estimate Activity Resources process is closely coordinated with other processes,
such as the Estimate Costs process. Example:
• An automotive design team will need to be familiar with the latest automated
assembly techniques. The requisite knowledge could be obtained by hiring a
consultant, by sending a designer to a seminar on robotics, or by including someone
from manufacturing as a member of the project team.
Coincides with PMBOK 9.2
Estimate Activity Resources
7. Estimate Activity Resources - Inputs
Coincides with PMBOK 9.2
Project Management Plan
Project management plan components include:
• Resource management plan
• Scope baseline
8. Coincides with PMBOK 9.2
Project Documents
Project documents that can be considered as inputs for this process include:
• Activity attributes
• Activity list
• Assumption log
• Cost estimates
• Resource calendars
• Risk register
Estimate Activity Resources - Inputs
9. Enterprise Environmental Factors
The enterprise environmental factors that can influence the Estimate Activity
Resources process include:
• Resource location,
• Resource availability
• Team resource skills
• Organizational culture
• Published estimating data
• Marketplace conditions
Coincides with PMBOK 9.2
Estimate Activity Resources - Inputs
10. Organisational Process Assets
The organizational process assets that can influence the Estimate Activity Resources
process include :
• Policies and procedures regarding staffing
• Policies and procedures relating to supplies and equipment
• Historical information regarding types of resources used for similar work on
previous projects.
Coincides with PMBOK 9.2
Estimate Activity Resources - Inputs
11. Estimate Activity Resources – Tools & Techniques
Coincides with PMBOK 9.2
Expert Judgement
Expertise should be considered from individuals or groups with
specialized knowledge or training in team and physical resource planning
and estimating.
12. Coincides with PMBOK 9.2
Bottom-Up Estimating
Team and physical resources are estimated at the activity level and then
aggregated to develop the estimates for work packages, control accounts,
and summary project levels.
Estimate Activity Resources – Tools & Techniques
13. Coincides with PMBOK 9.2
Analogous Estimating
Analogous estimating uses information regarding resources from a
previous similar project as the basis for estimating a future project. It is
used as quick estimating method and can be used when the project
manager can only identify a few top levels of the WBS.
Estimate Activity Resources – Tools & Techniques
14. Coincides with PMBOK 9.2
Parametric Estimating
Parametric estimating uses an algorithm or a statistical relationship between
historical data and other variables to calculate resource quantities needed for an
activity, based on historical data and project parameters. This technique can produce
higher levels of accuracy depending on the sophistication and underlying data built
into the model.
Estimate Activity Resources – Tools & Techniques
15. Coincides with PMBOK 9.2
Data Analysis
A data analysis technique used in this process includes, alternatives analysis.
• Alternatives analysis is used to evaluate identified options in order to select the
options or approaches to use to execute and perform the work of the project.
Alternatives analysis assists in providing the best solution to perform the project
activities, within the defined constraints.
Estimate Activity Resources – Tools & Techniques
16. Coincides with PMBOK 9.2
Project Management Information System
Estimate Activity Resources – Tools & Techniques
Project management information systems can include resource management software
that can help plan, organize, and manage resource pools and develop resource
estimates. Depending on the sophistication of the software, resource breakdown
structures, resource availability, resource rates, and various resource calendars can be
defined to assist in optimizing resource utilization.
17. Coincides with PMBOK 9.2
Meetings
Estimate Activity Resources – Tools & Techniques
The project manager may hold planning meetings with functional managers to estimate
the resources needed per activity, level of effort (LoE), skill level of the team resources,
and the quantity of the materials needed. Participants at these meetings may include
the project manager, the project sponsor, selected project team members, selected
stakeholders, and others as needed.
18. Coincides with PMBOK 9.2
Resource Requirements
Resource requirements identify the types and quantities of resources required for
each work package or activity in a work package and can be aggregated to determine
the estimated resources for each work package, each WBS branch, and the project as
a whole. The resource requirements’ documentation can include assumptions that
were made in determining which types of resources are applied, their availability, and
what quantities are needed.
Estimate Activity Resources – Outputs
19. Coincides with PMBOK 9.2
Basis of Estimates
The amount and type of additional details supporting the resource estimate vary by
application area. Supporting detail for resource estimates may include:
• Method used to develop the estimate
• Resources used to develop the estimate
• Assumptions associated with the estimate
• Known constraints
• Range of estimates
• Confidence level of the estimate
• Documentation of identified risks influencing the estimate.
Estimate Activity Resources – Outputs
20. Coincides with PMBOK 9.2
Resource Breakdown Structure
The resource breakdown
structure is a hierarchical
representation of resources
by category and type.
Examples of resource
categories include but are
not limited to labor,
material, equipment, and
supplies.
Estimate Activity Resources – Outputs
Resource Breakdown Structure Sample
21. Coincides with PMBOK 9.2
Project Document Updates
Project documents that may be updated as a result of carrying out this
process include:
• Activity attributes
• Assumption Log
• Risk Register
Estimate Activity Resources – Outputs
Editor's Notes
This process is performed periodically throughout the project as needed.
A construction project team will need to be familiar with local building codes. Such knowledge is often readily available from local sellers. If the internal labor pool lacks experience with unusual or specialized construction techniques, the additional cost for a consultant may be the most effective way to secure knowledge of the local building codes.
Resource management plan - The resource management plan defines the approach to identify the different resources needed for the project. It also defines the methods to quantify the resources needed for each activity and aggregates this information.
Scope baseline - The scope baseline identifies the project and product scope necessary to meet the project objectives. The scope drives the needs for both team and physical resources.
Activity attributes - Activity attributes provide the primary data source for use in estimating team and physical resources required for each activity on the activity list.
Activity list - The activity list identifies the activities that will need resources.
Assumption log - The assumption log may have information on productivity factors, availability, cost estimates, and approaches to work that will influence the nature and number of team and physical resources.
Cost estimates - The cost of resources may impact resource selection from the quantity and skill level perspectives.
Resource calendars - A resource calendar identifies the working days, shifts, start and end of normal business hours, weekends, and public holidays when each specific resource is available.
Risk register - The risk register describes the individual risks that can impact resource selection and availability.
For example, if an activity needs 4,000 hours of coding and it needs to finish it in 1 year, it will require two people to code (each doing 2,000 hours a year).
The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area.
Regardless of the level of detail, the supporting documentation should provide a clear and complete understanding of how the resource estimate was derived.
Resource types may include the skill level, grade level, required certifications, or other information as appropriate to the project.
In Plan Resource Management, the resource breakdown structure was used to guide the categorization for the project.
In this process it is a completed document that will be used to acquire and monitor resources.
Activity attributes - The activity attributes are updated with the resource requirements.
Assumption log - The assumption log is updated with assumptions regarding the types and quantities of resources required. Additionally, any resource constraints are entered including collective bargaining agreements, continuous hours of operation, planned leave, etc.
Lessons learned register - The lessons learned register can be updated with techniques that were efficient and effective in developing resource estimates, and information on those techniques that were not efficient or effective.