SlideShare a Scribd company logo
1 of 1
Download to read offline
RISK LEVEL FOR GRADED APPROACH
SIMPLE PROJECTS COMPLEX PROJECTS
PROCESS
GROUPS
PROJECT
MANAGEMENT
KNOWLEDGE
AREAS
SUB–PROCESSES
DEFINITION OF
SUB–PROCESSES
Level 4 – Minimal
Implementation
Level 3 – Minor
Implementation
Level 2 – Major Implementation
Level 1 – Full Implementation
w/Earned Value Management
System ANSI–748
PROJECT
INITIATION
Scope
Management
Initiation
Generate the Project Initiation
Documentation and Initiate the
Project Planning
Section 3
Integration
Management
Project Plan Development
Project Plan Development –
taking the results from the
planning process to develop a
document to guide project
execution. Section
4.1
Planning Document will include:
Project Objective, Scope,
Schedule, Cost documented in
memo form.
Document Technical, Cost,
Schedule, Risk, Procurement
plans in Project Plan.
Document Project Plan per outline in
exhibit include WBS Dictionary,
Performance Baseline, and
Contingency Analysis documented in
a detailed report.
Document Project Plan per outline in
exhibit include: WBS Dictionary,
Performance Baseline and
Contingency Analysis, and other
project–specific planning per
stakeholder requirements
documented in a detailed report.
Scope
Management
Scope Planning Scope
Definition
Developing a written scope
statement/baseline based on
customer requirements,
subdivide project deliverables
into smaller components with
Work Breakdown Structure
(WBS)
Section 4.2
Scope – straight forward,
well–defined, at a minimum, a
paragraph defining
purpose/objective and work
scope of project.
Requires a Technical Scope
statement consisting of detailed
work statement and
assumptions, WBS at one level
below project level.
Prepare a detailed Technical Baseline
consisting of work scope
requirements, project assumptions.
WBS developed 2 to 3 levels below
Project Level with WBS Dictionary.
Critical decisions identified Technical
Baseline for Earned Value
measurement.
Prepare a detailed Technical Baseline
consisting of work scope
requirements, project assumptions,
and alternative/options. WBS
developed to at least 4 levels below
Project Level with WBS Dictionary.
Critical decisions identified Technical
Baseline for Earned Value
measurement.
Time Management
SCHEDULE PLANNING
Activity Definition Activity
Sequencing Activity
Duration Estimating
Schedule Development
Identify specific activities that
must be performed to produce
deliverables, durations,
analyze sequencing, and
calculate dates to determine
project schedule.
Section 4.3
Schedule is prepared with
minimal number of activities to
complete project scope,
determine start/stop dates.
Schedule is developed to Identify
phases of work and their
duration, identify one–two
deliverables and Project
milestones.
Network Schedule identifying detail
activities and durations, several
deliverables, calculate dates, analyze
critical path. Identify Earned Value
methodology. Critical Decision
Milestones and Project milestones
identified.
Develop Network schedules w/critical
path Analysis, multiple deliverables,
Critical Decision Milestones
identified, and hierarchical roll–up of
schedule. Identify Earned Value
Methodology. Estimate schedule
contingency, document Schedule
Baseline for measurement per
ANSI–748.
Cost Management
COST PLANNING
Resource Planning
Cost Estimating Cost
Budgeting
Determine resources,
quantity, and Cost to perform
activities. Develop budget
request, Cost Baseline.
Section 4.4
Estimate of Labor hours,
Material, Equipment, and
Contracts dollars. Develop
budget request from Cost
estimate.
Definitive Estimate of
Engineering Labor/Construction
Labor/Purchased Material/
Contracts at WBS level. Allocate
Cost estimate to activities,
develop budget request.
Detail estimate for life cycle of project
by Resource type and detail backup,
Contingency estimating based on risk.
Allocate Cost estimate to activities,
develop budget request and Cost
Baseline for performance
measurement.
Life Cycle Cost Estimate – Most
detailed with estimates from
performing organizations and detail
backup, Apply Value Engineering,
Contingency estimating based on
risk. Cost Baseline for performance
measurement per ANSI–748.
Risk
Management
Planning, Risk
Identification
Quantitative/Qualitative
Risk Analysis Risk
Response Planning
Determine process for
defining and managing risk
(scope, schedule, cost,
environmental, safety, health,
etc.). Characterize/evaluate all
risks to assess outcomes.
Define strategies to respond
to risks.
Section 4.5
Identify project risks and steps
to manage the risks. Use the
Risk Management Plan Form for
Simple Projects.
Identify and quantify risks.
Develop Risk Response
strategies in a section of the
Project Plan. Use the Risk
Management Plan Form for
Simple Projects.
Identify, assess impact, and quantify
risks. Assign responsibility in a risk
rating matrix. Document basis for
cost/schedule contingency. Develop
Risk Response as part of the Risk
Management Plan. See the Sample
Risk Management Plan for Complex
Projects exhibit.
Identify/quantify risks, assess impact
on project, define Risk Response
strategy, assign responsibilities.
Document basis for Cost/Schedule
Contingency. Develop a Risk
Management Plan and include a risk
rating, risk response strategies,
tracking system, and closure
process. See the Sample Risk
Management Plan for Complex
Projects exhibit.
Quality
Management
Quality Planning
Identify relevant Project
Quality Standards.
Section 4.6
Human Resource
Management
Organizational Planning
Staff Acquisition
Develop R2A2. Obtain project
staff.
Section 4.7
Small number of participants,
usually no outside organizations.
Assign responsible individuals.
Small number of participants,
some outside organizations.
Develop Responsibility
Assignment Matrix (RAM).
Large number of participants,
dependance on outside organizations.
Develop R2A2s and MOUs as needed.
Develop RAM.
Large matrix organization, significant
dependance on outside
organizations. Develop R2A2s, MOUs,
and RAM.
Communications
Management
Communications
Planning
Determine communications
plan and reporting criteria.
Section 4.8
Reporting based on stakeholder
needs.
Monthly reporting based on
internal project needs and
customer requirements;
document change control
process.
Develop Communications plan
identifying stakeholders information
and reporting needs, report criteria,
frequency, and change control
thresholds. Establish change control
procedures.
Develop Communications plan
identifying stakeholders information
and reporting needs, report criteria,
frequency, and change control
thresholds. Establish Change Control
Board and procedures per ANSI–748
and DOE O 413.3.
Procurement
Management
Procurement Planning
Solicitation Planning
Determine what to
procure/contract and when.
Section 4.9
Identify outside procurements
work with Procurement &
Property Management Division.
Identify outside procurements
work with Procurement &
Property Management Division
develop procurement strategy.
Develop procurement/contracting
strategy, identify items, define timing,
develop Contract & Procurement
Management Plan.
Develop procurement/contracting
strategy, identify items, define timing,
develop Contract & Procurement
Management Plan.
Integration
Management
Project Plan Execution
Carry out the Project Plan by
performing the activities.
Section 5.1
Communications
Management
Information Distribution
Timely information
distribution to stakeholders.
Section 5.2
Distribute reports. Hold
project reviews based on
stakeholder needs.
Distribute reports. Hold
project reviews based on
Project Plan.
Distribute reports. Hold project
reviews based on Project Plan and
stakeholder requirements.
Distribute reports. Hold project
reviews based on Project Plan
and requirements per DOE O
413.3.
Procurement
Management
Solicitation
Source Selection
Contract Administration
Solicitation/Source
Selection/Contract
Administration
Section 5.3
Execute procurement
strategy.
Document procurement
strategy, identify contract
types.
Human Resource
Management
Team Development
Develop skills to enhance
project performance.
Section 5.4
Quality
Management
Quality Assurance
Evaluate overall project
performance.
Section 5.5
Integration
Management
Integrated Change
Control (Scope,
Schedule, Cost)
Identify, control, manage and
document project changes.
Section 6.1
Document changes to project
scope.
Document all changes to
Project Plan using Change
Control Procedure.
Document changes to Baseline
per Project Plan and change
control procedures for scope,
schedule, cost, quality, and risk.
Implement Change Control Log.
Document changes to Baseline
per Project Plan and change
control procedures for scope,
schedule, cost, quality, and risk.
Implement Change Control Board
and Log. Follow DOE thresholds
per DOE O 413.3.
Communications
Management
Performance Reporting
Progress
Measurement/Reporting
Forecasting/Performance
Reviews
Section 6.2
Reporting based on
stakeholder needs.
Quarterly Project Status
Reports, Cost/Schedule data,
Quarterly Performance
Reviews
Monthly Schedule/Milestone
Status of Baseline Schedule,
Earned Value calculation Monthly
Progress Report, Financial Status,
Monthly Performance
Reviews/Independent Reviews
Monthly Progress Reporting
–Earned Value calculation as per
ANSI/EIA–748 Earned Value
Management Systems including
Variance Analysis and Corrective
Action plans, Calculate EACs,
Financial Status, Monthly
Performance
Reviews/Independent Reviews
Risk Management Risk Monitoring & Control
Monitor and evaluate project
risks. Implement Risk
Management Plans.
Section 6.3
Quality
Management
Quality Control
Monitor QA results to Quality
standards.
Section 6.4
Communications
Management
Administrative Closure
Formalizing Project/Contract
Completion.
Section 7.1
Document Project
Completion/Lessons Learned per
stakeholder requirements, include
ES&H Review.
Comprehensive documentation
of Project Completion/Lessons
Learned per stakeholder
requirements include ES&H
Review.
Procurement
Management
Contract Closeout
Formalizing Contract
Completion.
Section 7.2
Document Contract Completion per stakeholder requirements.
Document Project Completion per stakeholder
requirements, include ES&H Review
Document procurement strategy, identify contract types. Assign
project procurement specialist.
PROCESS GROUPS
See the section Determination of Applicable Quality–related Activities in the Graded Approach for Quality Requirements Subject Area
Note: Failure to properly categorize Risk Level may result in incorrect or inappropriate identification of Project Quality Standards as well as
potential noncompliance, enforceable under the Price Anderson Amendments Act.
P
R
O
J
E
C
T
P
L
A
N
N
I
N
G
PROJECT
CLOSEOUT
Meetings as required.
Execute work per the Project Plan.
Conduct regular project meetings and team building sessions as
required.
Graded Application of Project Management Processes
P
R
O
J
E
C
T
P
L
A
N
N
I
N
G
P
R
O
J
E
C
T
E
X
E
C
U
T
I
O
N
P
R
O
J
E
C
T
C
O
N
T
R
O
L
Generate Project Initiation documentation to include stakeholder requirements, technical approach,
summary cost/schedule, and risk assessment
Implement Risk Management Plan. Monitor and evaluate
effectiveness of risk management strategies.
See the section Determination of Applicable Quality–related Activities in the Graded
Approach for Quality Requirements Subject Area.
Monitor and Evaluate Risks. Implement risk management
strategies.
See the Quality Activity Guide exhibit in the Graded Approach for Quality Requirements Subject Area.
*Section numbers refer to the text in Subject Area
1j03e011.xls 1 (01/2002)

More Related Content

What's hot

Project time management
Project time managementProject time management
Project time managementImran Jamil
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management areaZaur Ahmadov, PMP
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Project control wps office
Project control wps officeProject control wps office
Project control wps officekaransingh1064
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aForbes Chanakira
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARYSoumya De
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changesPeg Duggan
 
Project implimentation
Project implimentationProject implimentation
Project implimentationMazhar Poohlah
 
project time management
 project time management project time management
project time managementHira Atiq
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr. Pramod Deshpande
 

What's hot (20)

Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Project time management
Project time managementProject time management
Project time management
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project control wps office
Project control wps officeProject control wps office
Project control wps office
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARY
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changes
 
Project control
Project controlProject control
Project control
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
 
project time management
 project time management project time management
project time management
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 

Viewers also liked

Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Glen Alleman
 
Architecture Centered Design
Architecture Centered DesignArchitecture Centered Design
Architecture Centered DesignGlen Alleman
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Glen Alleman
 
Architecture centered publishing systems
Architecture centered publishing systemsArchitecture centered publishing systems
Architecture centered publishing systemsGlen Alleman
 
Agile Project Management for ERP Projects
Agile Project Management for ERP ProjectsAgile Project Management for ERP Projects
Agile Project Management for ERP ProjectsGlen Alleman
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio managementGlen Alleman
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk managementGlen Alleman
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project ManagementGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Glen Alleman
 
Making Change Happen
Making Change HappenMaking Change Happen
Making Change Happenkevin murphy
 
Deterministic versus probabilistic
Deterministic versus probabilisticDeterministic versus probabilistic
Deterministic versus probabilisticGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
The simple problem of schedule performance indices (neutral)
The simple problem of schedule performance indices (neutral)The simple problem of schedule performance indices (neutral)
The simple problem of schedule performance indices (neutral)Glen Alleman
 
Managing Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainManaging Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainGlen Alleman
 
Integrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program successIntegrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program successGlen Alleman
 
Connecting it and business value
Connecting it and business valueConnecting it and business value
Connecting it and business valueGlen Alleman
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 

Viewers also liked (20)

Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
 
Architecture Centered Design
Architecture Centered DesignArchitecture Centered Design
Architecture Centered Design
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)
 
Architecture centered publishing systems
Architecture centered publishing systemsArchitecture centered publishing systems
Architecture centered publishing systems
 
Agile Project Management for ERP Projects
Agile Project Management for ERP ProjectsAgile Project Management for ERP Projects
Agile Project Management for ERP Projects
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk management
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project Management
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
 
Making Change Happen
Making Change HappenMaking Change Happen
Making Change Happen
 
Deterministic versus probabilistic
Deterministic versus probabilisticDeterministic versus probabilistic
Deterministic versus probabilistic
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
The simple problem of schedule performance indices (neutral)
The simple problem of schedule performance indices (neutral)The simple problem of schedule performance indices (neutral)
The simple problem of schedule performance indices (neutral)
 
Managing Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainManaging Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing Domain
 
Integrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program successIntegrated master plan (imp) - the foundation of the program success
Integrated master plan (imp) - the foundation of the program success
 
Connecting it and business value
Connecting it and business valueConnecting it and business value
Connecting it and business value
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 

Similar to Graded application of project management req

NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2Future Managers
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReEXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReBetseyCalderon89
 
Projects Management
Projects ManagementProjects Management
Projects ManagementNirmal Shah
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 
RICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 MayRICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 MaySaeed Shalbafan
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areaslinajarruti
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkitsIT-Toolkits.org
 
cost Management V4
cost Management V4cost Management V4
cost Management V4Qussay Karam
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Project and project management
Project and project managementProject and project management
Project and project managementwodato
 

Similar to Graded application of project management req (20)

NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReEXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
EXECUTION PLAN REVISION HISTORYVersion #Implemented byRe
 
Project Management : Project Planning by iFour Technolab Pvt. Ltd.
Project Management : Project Planning by iFour Technolab Pvt. Ltd.Project Management : Project Planning by iFour Technolab Pvt. Ltd.
Project Management : Project Planning by iFour Technolab Pvt. Ltd.
 
Projects Management
Projects ManagementProjects Management
Projects Management
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
RICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 MayRICS Project Controls 240415-final 12 May
RICS Project Controls 240415-final 12 May
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areas
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
 
cost Management V4
cost Management V4cost Management V4
cost Management V4
 
6396901
63969016396901
6396901
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
Project planning
Project planningProject planning
Project planning
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Project and project management
Project and project managementProject and project management
Project and project management
 
Identify risks
Identify risksIdentify risks
Identify risks
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Graded application of project management req

  • 1. RISK LEVEL FOR GRADED APPROACH SIMPLE PROJECTS COMPLEX PROJECTS PROCESS GROUPS PROJECT MANAGEMENT KNOWLEDGE AREAS SUB–PROCESSES DEFINITION OF SUB–PROCESSES Level 4 – Minimal Implementation Level 3 – Minor Implementation Level 2 – Major Implementation Level 1 – Full Implementation w/Earned Value Management System ANSI–748 PROJECT INITIATION Scope Management Initiation Generate the Project Initiation Documentation and Initiate the Project Planning Section 3 Integration Management Project Plan Development Project Plan Development – taking the results from the planning process to develop a document to guide project execution. Section 4.1 Planning Document will include: Project Objective, Scope, Schedule, Cost documented in memo form. Document Technical, Cost, Schedule, Risk, Procurement plans in Project Plan. Document Project Plan per outline in exhibit include WBS Dictionary, Performance Baseline, and Contingency Analysis documented in a detailed report. Document Project Plan per outline in exhibit include: WBS Dictionary, Performance Baseline and Contingency Analysis, and other project–specific planning per stakeholder requirements documented in a detailed report. Scope Management Scope Planning Scope Definition Developing a written scope statement/baseline based on customer requirements, subdivide project deliverables into smaller components with Work Breakdown Structure (WBS) Section 4.2 Scope – straight forward, well–defined, at a minimum, a paragraph defining purpose/objective and work scope of project. Requires a Technical Scope statement consisting of detailed work statement and assumptions, WBS at one level below project level. Prepare a detailed Technical Baseline consisting of work scope requirements, project assumptions. WBS developed 2 to 3 levels below Project Level with WBS Dictionary. Critical decisions identified Technical Baseline for Earned Value measurement. Prepare a detailed Technical Baseline consisting of work scope requirements, project assumptions, and alternative/options. WBS developed to at least 4 levels below Project Level with WBS Dictionary. Critical decisions identified Technical Baseline for Earned Value measurement. Time Management SCHEDULE PLANNING Activity Definition Activity Sequencing Activity Duration Estimating Schedule Development Identify specific activities that must be performed to produce deliverables, durations, analyze sequencing, and calculate dates to determine project schedule. Section 4.3 Schedule is prepared with minimal number of activities to complete project scope, determine start/stop dates. Schedule is developed to Identify phases of work and their duration, identify one–two deliverables and Project milestones. Network Schedule identifying detail activities and durations, several deliverables, calculate dates, analyze critical path. Identify Earned Value methodology. Critical Decision Milestones and Project milestones identified. Develop Network schedules w/critical path Analysis, multiple deliverables, Critical Decision Milestones identified, and hierarchical roll–up of schedule. Identify Earned Value Methodology. Estimate schedule contingency, document Schedule Baseline for measurement per ANSI–748. Cost Management COST PLANNING Resource Planning Cost Estimating Cost Budgeting Determine resources, quantity, and Cost to perform activities. Develop budget request, Cost Baseline. Section 4.4 Estimate of Labor hours, Material, Equipment, and Contracts dollars. Develop budget request from Cost estimate. Definitive Estimate of Engineering Labor/Construction Labor/Purchased Material/ Contracts at WBS level. Allocate Cost estimate to activities, develop budget request. Detail estimate for life cycle of project by Resource type and detail backup, Contingency estimating based on risk. Allocate Cost estimate to activities, develop budget request and Cost Baseline for performance measurement. Life Cycle Cost Estimate – Most detailed with estimates from performing organizations and detail backup, Apply Value Engineering, Contingency estimating based on risk. Cost Baseline for performance measurement per ANSI–748. Risk Management Planning, Risk Identification Quantitative/Qualitative Risk Analysis Risk Response Planning Determine process for defining and managing risk (scope, schedule, cost, environmental, safety, health, etc.). Characterize/evaluate all risks to assess outcomes. Define strategies to respond to risks. Section 4.5 Identify project risks and steps to manage the risks. Use the Risk Management Plan Form for Simple Projects. Identify and quantify risks. Develop Risk Response strategies in a section of the Project Plan. Use the Risk Management Plan Form for Simple Projects. Identify, assess impact, and quantify risks. Assign responsibility in a risk rating matrix. Document basis for cost/schedule contingency. Develop Risk Response as part of the Risk Management Plan. See the Sample Risk Management Plan for Complex Projects exhibit. Identify/quantify risks, assess impact on project, define Risk Response strategy, assign responsibilities. Document basis for Cost/Schedule Contingency. Develop a Risk Management Plan and include a risk rating, risk response strategies, tracking system, and closure process. See the Sample Risk Management Plan for Complex Projects exhibit. Quality Management Quality Planning Identify relevant Project Quality Standards. Section 4.6 Human Resource Management Organizational Planning Staff Acquisition Develop R2A2. Obtain project staff. Section 4.7 Small number of participants, usually no outside organizations. Assign responsible individuals. Small number of participants, some outside organizations. Develop Responsibility Assignment Matrix (RAM). Large number of participants, dependance on outside organizations. Develop R2A2s and MOUs as needed. Develop RAM. Large matrix organization, significant dependance on outside organizations. Develop R2A2s, MOUs, and RAM. Communications Management Communications Planning Determine communications plan and reporting criteria. Section 4.8 Reporting based on stakeholder needs. Monthly reporting based on internal project needs and customer requirements; document change control process. Develop Communications plan identifying stakeholders information and reporting needs, report criteria, frequency, and change control thresholds. Establish change control procedures. Develop Communications plan identifying stakeholders information and reporting needs, report criteria, frequency, and change control thresholds. Establish Change Control Board and procedures per ANSI–748 and DOE O 413.3. Procurement Management Procurement Planning Solicitation Planning Determine what to procure/contract and when. Section 4.9 Identify outside procurements work with Procurement & Property Management Division. Identify outside procurements work with Procurement & Property Management Division develop procurement strategy. Develop procurement/contracting strategy, identify items, define timing, develop Contract & Procurement Management Plan. Develop procurement/contracting strategy, identify items, define timing, develop Contract & Procurement Management Plan. Integration Management Project Plan Execution Carry out the Project Plan by performing the activities. Section 5.1 Communications Management Information Distribution Timely information distribution to stakeholders. Section 5.2 Distribute reports. Hold project reviews based on stakeholder needs. Distribute reports. Hold project reviews based on Project Plan. Distribute reports. Hold project reviews based on Project Plan and stakeholder requirements. Distribute reports. Hold project reviews based on Project Plan and requirements per DOE O 413.3. Procurement Management Solicitation Source Selection Contract Administration Solicitation/Source Selection/Contract Administration Section 5.3 Execute procurement strategy. Document procurement strategy, identify contract types. Human Resource Management Team Development Develop skills to enhance project performance. Section 5.4 Quality Management Quality Assurance Evaluate overall project performance. Section 5.5 Integration Management Integrated Change Control (Scope, Schedule, Cost) Identify, control, manage and document project changes. Section 6.1 Document changes to project scope. Document all changes to Project Plan using Change Control Procedure. Document changes to Baseline per Project Plan and change control procedures for scope, schedule, cost, quality, and risk. Implement Change Control Log. Document changes to Baseline per Project Plan and change control procedures for scope, schedule, cost, quality, and risk. Implement Change Control Board and Log. Follow DOE thresholds per DOE O 413.3. Communications Management Performance Reporting Progress Measurement/Reporting Forecasting/Performance Reviews Section 6.2 Reporting based on stakeholder needs. Quarterly Project Status Reports, Cost/Schedule data, Quarterly Performance Reviews Monthly Schedule/Milestone Status of Baseline Schedule, Earned Value calculation Monthly Progress Report, Financial Status, Monthly Performance Reviews/Independent Reviews Monthly Progress Reporting –Earned Value calculation as per ANSI/EIA–748 Earned Value Management Systems including Variance Analysis and Corrective Action plans, Calculate EACs, Financial Status, Monthly Performance Reviews/Independent Reviews Risk Management Risk Monitoring & Control Monitor and evaluate project risks. Implement Risk Management Plans. Section 6.3 Quality Management Quality Control Monitor QA results to Quality standards. Section 6.4 Communications Management Administrative Closure Formalizing Project/Contract Completion. Section 7.1 Document Project Completion/Lessons Learned per stakeholder requirements, include ES&H Review. Comprehensive documentation of Project Completion/Lessons Learned per stakeholder requirements include ES&H Review. Procurement Management Contract Closeout Formalizing Contract Completion. Section 7.2 Document Contract Completion per stakeholder requirements. Document Project Completion per stakeholder requirements, include ES&H Review Document procurement strategy, identify contract types. Assign project procurement specialist. PROCESS GROUPS See the section Determination of Applicable Quality–related Activities in the Graded Approach for Quality Requirements Subject Area Note: Failure to properly categorize Risk Level may result in incorrect or inappropriate identification of Project Quality Standards as well as potential noncompliance, enforceable under the Price Anderson Amendments Act. P R O J E C T P L A N N I N G PROJECT CLOSEOUT Meetings as required. Execute work per the Project Plan. Conduct regular project meetings and team building sessions as required. Graded Application of Project Management Processes P R O J E C T P L A N N I N G P R O J E C T E X E C U T I O N P R O J E C T C O N T R O L Generate Project Initiation documentation to include stakeholder requirements, technical approach, summary cost/schedule, and risk assessment Implement Risk Management Plan. Monitor and evaluate effectiveness of risk management strategies. See the section Determination of Applicable Quality–related Activities in the Graded Approach for Quality Requirements Subject Area. Monitor and Evaluate Risks. Implement risk management strategies. See the Quality Activity Guide exhibit in the Graded Approach for Quality Requirements Subject Area. *Section numbers refer to the text in Subject Area 1j03e011.xls 1 (01/2002)