SlideShare a Scribd company logo
OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTEE
Barangay of Aslum
Municipality of Julita
Province of Leyte
SUB-PROJECT PROGRAM OF WORK
Sub-Project Title Diversion Works Structure
Sub-Project Category
Physical Target 1
Total Sub-Project Cost
Project Description Implementation Mode Administration
Construction of Diversion Work Structure
Sub-Project Duration
Equipment Needed 1 Bagger Concrete Mixer, Water Pump
Technical Personnel 2
Item No. Scope of Work Percentage Quantity Unit Unit Price Total
1.00 Coffer Dam 20.00 LM 1,597.33 31,946.50
2.00 Diversion of Water & Care of Creek 123.25 cu.m. 50.45 6,217.80
3.00 Intake Weir Structure
3.10 Excavation 261.51 cu.m. 68.37 17,880.00
3.20 Boulder Fill 42.50 cu.m. 1,035.29 44,000.00
3.30 Gravel Bedding 17.00 cu.m. 832.29 14,149.00
3.40 Concrete Class "A" (3000 psi) 83.88 cu.m. 4,255.66 356,956.50
3.50 Reinforcing Steel Bars 4,131.67 kgs. 43.77 180,861.00
3.60 Structural Backfill 130.38 cu.m. 78.70 10,260.00
4.00 Handlaid Riprap
4.10 Excavation 24.00 cu.m. 62.08 1,490.00
4.20 Gravel Bedding 8.00 cu.m. 953.00 7,624.00
4.30 Riprap (Handlaid) 16.00 cu.m. 1,036.25 16,580.00
5.00 Grouted Riprap -
5.10 Excavation cu.m. -
5.20 Gravel Bedding cu.m. -
5.30 Riprap (Grouted) cu.m. -
6.00 Intake Works -
6.10 Excavation cu.m. -
6.20 Concrete Class "A" (3000 psi) cu.m. -
6.30 Reinforcing Steel Bars kgs -
6.40 Structural Backfill cu.m. -
Total 687,964.80
Breakdown of Estimated Source of Fund Total
Sub-Project Cost KALAHI-CIDSS Grant Community LGUs Other Source Cost
A. Direct Cost
Material Cost
Equipment Rental
Labor Cost
Sub-Total A
B. Indirect Cost
Pre-Engineering
Engineering Supervision
Contractor's Profit
Taxes
Hand Tools
Materials Testing
Capability Building
Administrative & Overhead
Sub-Total B
TOTAL (A+B)
Add: Contingency
Percent
Total Estimated Cost
Add: O & M (other amenities)
GRAND TOTAL
Prepared by: Approved by:
BUENAVENTURA L. PITAO
Engr.II, Prov'l. Agr'l. Office - Leyte Chairperson - Brgy. Sub-Project Mgt. Com.
Reviewed by: Noted by:
Deputy Area Coordinator Regional Infrastructure Engineer
Note:
b.) Costing of O & M will be monitored during the conduct of the SET
*Costing to be supported with detailed Training Schedules
a.) Skilled
b.) Unskilled
a.) Costing to be used on the MIBF will be the Total Cost Estimate
CONCRETE VOLUME:
Thickness, m. Width, m. Height, m. Length,m. Volume, cu.m.
Retaining Wall:
Retain Wall Left 0.20 2.50 10.41 5.21
0.20 2.00 14.00 5.60
Retain Wall Right 0.20 2.50 10.41 5.21
0.20 2.00 14.00 5.60 21.61
Cut-off Wall:
Left Ret. Wall 0.20 1.00 24.41 4.88
0.20 1.00 14.00 2.80
Right Ret. Wall 0.20 1.00 24.41 4.88
0.20 1.00 14.00 2.80
Upstream 0.20 1.00 6.00 1.20
Downstream 0.20 1.00 8.00 1.60 18.17
Wall Footing
Left Abutment 0.20 1.20 22.00 5.28
Right Abutment 0.20 1.20 22.00 5.28 10.56
No. of Units
Pier 0.20 0.85 2.50 2 0.85
0.30 0.30 2.50 2 0.45
0.20 0.05 2.50 2 0.05
0.30 0.10 2.50 2 0.15
0.30 0.30 2.50 2 0.23
Flooring:
Wier 0.20 6.00 14 16.80
0.20 1.00 1 0.20
R/L Abutment 0.10 5.12 14 7.17
0.10 5.12 14 7.17 31.33
Cut Walk: 0.10 0.60 8 0.48
Total Concrete Volume Total 83.88 60.06
Boulder Fill (200-400mmØ)
Gravel Bedding 0.20 6.00 14 16.80
0.20 1.00 1 0.20
Total 17.00
Boulder (200-400mmØ) 0.50 6.00 14 42.00
0.50 1.00 1 0.50
Total 42.50
Grouted Riprap:(200-400mm)
Right Abutment 0.30 4.83 5.00 7.24
Left Abutment 0.30 4.83 5.00 7.24
Total 14.49
Handlaid Riprap:(300-400mm) 0.40 8.00 5.00 16.00
Gravel Bedding 0.20 8.00 5.00 8.00
Total 24.00
Reinf. Steel Bars
Retain Wall Left Width, m. Height, m. Length,m. No. of pcs. Total Length, m
Bar A 12mm 0.75 1.25 24.00 121.00 242.00
Bar B 12mm 1.10 2.45 24.00 121.00 429.55
Temp. Bars 10mm 3.50 24.00 12.67 304.00
Retain Wall Right
Bar A 12mm 0.75 1.25 24.00 121.00 242.00
Bar B 12mm 1.10 2.45 24.00 121.00 429.55
Temp. Bars 10mm 2.50 24.00 9.33 224.00
Wall Footing:
Left Footing 12mm 1.50 22.00 111.00 166.50
1.50 22.00 8.50 187.00
Right Footing 12mm 1.50 22.00 111.00 166.50
1.50 22.00 8.50 187.00
Flooring: 6.00 14.00 31.00 434.00
6.00 14.00 71.00 426.00
Cut-off Wall:
Left Abutment:
Vertical Bars (12mm) 1.50 37.41 188.07 282.11
Temp. Bars (12mm) 1.00 37.41 6.00 224.49
Right Abutment:
Vertical Bars (12mm) 1.50 37.41 188.07 282.11
Temp. Bars (12mm) 1.00 37.41 6.00 224.49
Upstream
Vertical Bars (12mm) 1.30 6.00 31.00 40.30
Temp. Bars (12mm) 1.00 6.00 6.00 36.00
Downstream
Vertical Bars (12mm) 1.30 8.00 41.00 53.30
Temp. Bars (12mm) 1.00 8.00 6.00 48.00
Pier: No. of Units
Bracing (Vert.) 12mm 2.00 0.85 2.70 5.25 28.35
Horizontal 12mm 2.00 0.85 2.60 14.00 23.80
Pier Post 12mm 2.00 2.70 7.00 37.80
Stirrups 10mm 2.00 2.60 2.40 14.00 67.20
Cut Walk:
Longitudinal 12 mm 0.60 8.00 4.00 32.00
Temp. Bars 10mm 0.60 8.00 41.00 24.60
Intake Wall:
12mm Bothways 0.90 0.90 20.00 101.00 363.60
0.90 0.90 20.00 19.00 380.00
Discharge end (Two sides)
Vert. 12mm 2.00 0.50 1.34 3.50 9.38
Hor.12mm 2.00 0.50 0.90 5.50 5.50
Cut-off 12mm
Vert.12mm 0.45 1.80 10.00 4.50
0.45 1.80 3.25 5.85
Total 12mm dia.
10mm dia.
Excavation: Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m.
Retaining Wall:
Retain Wall Left U/S 2.00 1.40 1.90 5.00 16.15
1.80 1.40 1.90 12.00 36.48
D/S 2.00 1.40 1.90 5.00 16.15
0.30 0.30 0.25 14.00 1.05
Retain Wall Right U/S 2.00 1.40 2.10 5.00 17.85
1.80 1.40 1.75 12.00 33.60
D/S 2.00 1.40 1.75 5.00 14.88
0.30 0.30 0.50 14.00 2.10 138.26
Cut-off Wall
Left U/S 0.70 0.40 1.00 5.00 2.75
0.70 0.40 1.00 12.00 6.60
D/S 0.70 0.40 1.00 5.00 2.75
0.70 0.40 1.00 6.00 3.30
Right U/S 0.70 0.40 1.00 5.00 2.75
0.70 0.40 1.00 12.00 6.60
D/S 0.70 0.40 1.00 5.00 2.75
0.70 0.40 1.00 8.00 4.40 31.90
Flooring: 6.00 0.70 14.00 58.80
1.20 0.50 1.00 14.00 11.90
0.50 0.15 2.00 14.00 9.10
0.15 0.40 3.00 14.00 11.55 123.25
Total 261.51
Grouted Excav.
Left Abutment 2.30 0.50 2.50 5.00 17.50
Right Abutment 2.00 0.50 3.00 5.00 15.00
2.00 0.50 5.00 5.00
Total 37.50
Handlaid Riprap:Excav. 8.00 0.60 5.00 24.00
Struc. Backfill:
Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m.
Retaining Wall:
Retain Wall Left 1.80 1.20 1.70 5.00 12.75
1.55 1.20 1.70 12.00 28.05
1.80 1.20 1.70 5.00 12.75
5.00 0.60 14.00 42.00
Retain Wall Right 1.80 1.20 1.70 5.00 12.75
1.55 1.20 1.70 12.00 28.05
1.80 1.20 1.70 5.00 12.75
5.00 0.20 14.00 14.00
Cut-off Wall 0.50 0.20 1.00 5.00 1.75
0.50 0.20 1.00 12.00 4.20
0.50 0.20 1.00 5.00 1.75
0.50 0.20 1.00 6.00 2.10
0.50 0.20 1.00 5.00 1.75
0.50 0.20 1.00 12.00 4.20
0.50 0.20 1.00 5.00 1.75
0.50 0.20 1.00 8.00 2.80
Total 183.40
Intake Works:
Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m.
Excavation 1.10 1.10 0.40 20.00 8.80
Backfill 0.30 0.20 0.28 20.00 1.40
1.00 1.00 0.20 5.00 1.00 2.40
Concrete Volume 0.24 0.24 20.00 1.15
1.80 1.34 0.12 0.29
0.80 0.92 0.12 (0.09)
Total Concrete Volume 1.35
Concrete
Division Box: Length,m. Top, m Height, m. Width, m. Volume, cu.m.
Flooring -
CHB Footing 0.30 -
Total -
No. of CHB's (3.00) pcs.
Mortar/Plaster (0.02)
Concrete Mortar Total
Cement -
Sand -
Gravel -
Reinforcing Bars Length,m. Width, m. Height, m. No. of Pcs.Total Bar Length
Vertical Bar -
Horizontal Bar -
CHB Found. -
-
Total -
Bar nos. -
Weight, kgs.
214.90
381.44
187.26
214.90
381.44
137.98
147.85
166.06
147.85
166.06
385.39
378.29
250.51
199.34
250.51
199.34
35.79
31.97
47.33
42.62
25.17
21.13
33.57
41.40
28.42
15.15
322.88
337.44 660.32
8.33
4.88
4.00
5.19 22.40
3,749.88
381.80
Conc. Vol. Backfill
21.61 116.64
18.17 13.73
130.38
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
1.00 Coffer Dam Linear Meter (Lm)20 1,597.33
A Material Quantity Unit Unit Cost Cost
1 1/2" X 4' X 8' Marine Plyboard 7.50 pcs. 835.00 6,262.50
2 2" X 2" Coco Lumber (False work) 180.00 bd.ft. 9.50 1,710.00
3 Assorted Common Wire Nails 12.00 kgs. 50.00 600.00
Sub-Total 8,572.50
B Name & Capacity of Equipment Number No. of Days Rate/Day Cost
None
C
Hour/board foot 0.064
Board foot per Linear meter 180.00
Hour/Linear meter 20.00 11.52 3.00 28.80
Labor Requirement Number No. of Day Rate/Day Cost
Skilled Laborer 1.00 29.00 350.00 10,150.00
Unskilled Laborer 2.00 29.00 228.00 13,224.00
Sub-Total 23,374.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of
Manpower Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Diversion of Water and Care of Creek cu.m.2.00 123.25 50.45
A Material Quantity Unit Unit Cost Cost
1 Diesel Fuel 8.00 liters 39.85 318.80
Total 318.80
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
4"Ø Water Pumps and accessories 1.00 17.00 119.00 2,023.00
Total 2,023.00
C
Dewatering/pumping ( cu.m./day) 123.25 7.25 1.00 17.00
Labor Requirement Number No. of Days Rate/Day Cost
Water Pump Operator 1.00 17.00 228.00 3,876.00
Total 3,876.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of
Manpower Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Excavation cubic meter (cu.m.)3.10 261.51 68.37
A Material Quantity Unit Unit Cost Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Cu.m./Man-day @ 0-4m throwing dist 261.51 3.50 6.00 12.45
Labor Requirement Number No. of Days Rate/Day Cost
Skilled Laborer 1.00 12.00 350.00 4,200.00
Unskilled Laborer 5.00 12.00 228.00 13,680.00
Sub-Total 17,880.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
3.40 cubic meter (cu.m.)83.88 4,255.66
A Material Quantity Unit Unit Cost Cost
1 Portland Cement 800.00 bags 195.00 156,000.00
2 Fresh Sand 53.00 cu.m. 350.00 18,550.00
3 Gravel (G1) 70.00 cu.m. 725.00 50,750.00
4 1/4" X 4' X 8' Ordinary Plywood 57.00 pcs. 385.00 21,945.00
5 Coco Lumber (False Work) 5,033.00 bd.ft. 10.50 52,846.50
6 Nails and Hardware 210.00 kgs. 52.50 11,025.00
Total 311,116.50
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
Concrete Mixer (1 bagger) 1.00 24.00 298.00 7,152.00
Total 7,152.00
C
Concrete Works (cu.m./day) 83.88 3.50 6.00 23.97
Labor Requirement Number No.of Days Rate/Day Cost
Skilled Laborer 2.00 24.00 350.00 16,800.00
Unskilled Laborer 4.00 24.00 228.00 21,888.00
Total 38,688.00
Concrete Class "A"
(3000 psi)
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Reinforcing Steel Bars Kgs.3.50 4,131.67 43.77
A Material Quantity Unit Unit Cost Cost
1 12mm Ø X 20' Reinforcing Bars 704.00 pcs. 180.00 126,720.00
2 10mm Ø X 20' Reinforcing Bars 103.00 pcs. 165.00 16,995.00
3 # 16 Tie Wire 124.00 kgs. 55.00 6,820.00
4 Hacksaw Blade 6.00 pcs. 45.00 270.00
Total 150,805.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Cutting, Bending & Placing of RSB 4,131.67 80.00 2.00 51.65
(kgs/day)
Labor Requirement Number No. of Days Rate/Day Cost
Skilled Laborer 1.00 52.00 350.00 18,200.00
Unskilled Laborer 1.00 52.00 228.00 11,856.00
Total 30,056.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No. Work Description Quantity Unit
A Material Quantity Unit Unit Cost
B Name & Capacity of Equipment Number No. of Day Rate/Day
C
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Labor Requirement Number No. of Day Rate/Day
Unit Cost
Cost
Cost
Number of Days to
Complete the Work
Cost
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Structural Backfill cubic meter (cu.m.)3.60 130.38 78.70
A Material Quantity Unit Unit Cost Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Backfilling & Tamping (cu.m./man-day) 130.38 3.00 5.00 8.69
Labor Requirement Number No. of Day Rate/Day Cost
Unskilled Laborer 5.00 9.00 228.00 10,260.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
4.10 Excavation (Handlaid Riprap) cubic meter (cu.m.)24.00 62.08
A Material Quantity Unit Unit Cost Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Cu.m./Man-day @ 0-4m throwing dist. 24.00 3.50 6.00 1.14
Labor Requirement Number No. of Days Rate/Day Cost
Skilled Laborer 1.00 1.00 350.00 350.00
Unskilled Laborer 5.00 1.00 228.00 1,140.00
Sub-Total 1,490.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
4.30 Handlaid Riprap cubic meters (cu.m.)16.00 1,036.25
A Material Quantity Unit Unit Cost Cost
1 Boulder (300mm-400mmØ) 16.00 cu.m. 850.00 13,600.00
Total 13,600.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Handlaid Riprap (cu.m./day) 16.00 8.50 6.00 1.88
Labor Requirement Number No. of Day Rate/Day Cost
Skilled Laborer 1.00 2.00 350.00 700.00
Unskilled Laborer 5.00 2.00 228.00 2,280.00
Total 2,980.00
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
4.20 Gravel Bedding (Handlaid) cubic meters (cu.m.)8.00 953.00
A Material Quantity Unit Unit Cost Cost
1 Gravel (G1) 8.00 cu.m. 725.00 5,800.00
Total 5,800.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Bedding (cu.m./hour) 8.00 2.00 8.00 0.50
Labor Requirement Number No. of Day Rate/Day Cost
Unskilled Laborer 8.00 1.00 228.00 1,824.00
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
Total 1,824.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
1 Excavation (Grouted Riprap) 37.50 cubic meter (cu.m.) 79.47
A Material Quantity Unit Unit Cost Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Cu.m./Man-day @ 0-4m throwing dist. 37.50 3.50 6.00 1.79
Labor Requirement Number No. of Days Rate/Day Cost
Skilled Laborer 1.00 2.00 350.00 700.00
Unskilled Laborer 5.00 2.00 228.00 2,280.00
Sub-Total 2,980.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of
Manpower Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Grouted Riprap 14.49 cubic meters (cu.m.) 2,280.25
A Material Quantity Unit Unit Cost Cost
1 Portland Cement 61.00 bags 195.00 11,895.00
2 Fresh Sand 5.00 cu.m. 350.00 1,750.00
3 Gravel (G1) 1.00 cu.m. 725.00 725.00
4 Boulder (200mm-350mmØ) 14.00 cu.m. 850.00 11,900.00
Total 26,270.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Grouted Riprap (cu.m./day) 14.49 7.50 13.00 1.93
Labor Requirement Number No. of Day Rate/Day Cost
Foreman 1.00 2.00 400.00 800.00
Skilled Laborer 2.00 2.00 350.00 1,400.00
Unskilled Laborer 10.00 2.00 228.00 4,560.00
Total 6,760.00
Labor Derivation
(Subsidiary Work Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
3.20 Boulder Fill cubic meters (cu.m.)42.50 1,035.29
A Material Quantity Unit Unit Cost Cost
1 Boulder (200mm-400mmØ) 43.00 cu.m. 850.00 36,550.00
Total 36,550.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Handlaid Riprap (cu.m./day) 43.00 8.50 6.00 5.06
Labor Requirement Number No. of Day Rate/Day Cost
Skilled Laborer 1.00 5.00 350.00 1,750.00
Unskilled Laborer 5.00 5.00 228.00 5,700.00
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
Total 7,450.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit
3.30 Gravel Bedding (Boulder Fill) cubic meters (cu.m.)17.00
A Material Quantity Unit Unit Cost
1 Gravel (G1) 17.00 cu.m. 725.00
Total
B Name & Capacity of Equipment Number No. of Day Rate/Day
None
C
Bedding (cu.m./hour) 17.00 2.00 8.00
Labor Requirement Number No. of Day Rate/Day
Unskilled Laborer 8.00 1.00 228.00
Total
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Unit Cost
832.29
Cost
12,325.00
12,325.00
Cost
1.06
Cost
1,824.00
1,824.00
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
1.35 cubic meter (cu.m.) 4,262.00
A Material Quantity Unit Unit Cost Cost
1 Portland Cement 13.00 bags 195.00 2,535.00
2 Fresh Sand 1.00 cu.m. 350.00 350.00
3 Gravel (G1) 1.00 cu.m. 725.00 725.00
4 1/4" X 4' X 8' Ordinary Plywood 1.00 pcs. 385.00 385.00
5 Coco Lumber (False Work) 81.00 bd.ft. 10.50 850.50
6 Nails and Hardware 3.00 kgs. 52.50 157.50
Total 5,003.00
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
Concrete Mixer (1 bagger) 1.00 0.40 298.00 119.20
Total 119.20
C
Concrete Works (cu.m./day) 1.35 3.50 6.00 0.39
Labor Requirement Number No.of Days Rate/Day Cost
Skilled Laborer 2.00 0.40 350.00 280.00
Unskilled Laborer 4.00 0.40 228.00 364.80
Concrete Class "A"
(3000 psi)
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
Total 644.80
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit
1 Excavation (Intake) 8.80 cubic meter (cu.m.)
A Material Quantity Unit Unit Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day
None
C
Cu.m./Man-day @ 0-4m throwing dist. 8.80 3.50 6.00
Labor Requirement Number No. of Days Rate/Day
Skilled Laborer 1.00 0.40 350.00
Unskilled Laborer 5.00 0.40 228.00
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Sub-Total
Unit Cost
67.73
Cost
Cost
0.42
Cost
140.00
456.00
Number of Days to
Complete the Work
596.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Structural Backfill 2.40 cubic meter (cu.m.) 95.00
A Material Quantity Unit Unit Cost Cost
None
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Backfilling & Tamping (cu.m./man-day) 2.40 3.00 5.00 0.16
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
Labor Requirement Number No. of Day Rate/Day Cost
Unskilled Laborer 5.00 0.20 228.00 228.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit
682.72 Kgs.
A Material Quantity Unit Unit Cost
1 12mm Ø X 20' Reinforcing Bars 128.00 pcs. 180.00
2 # 16 Tie Wire 20.00 kgs. 55.00
3 Hacksaw Blade 6.00 pcs. 45.00
Total
B Name & Capacity of Equipment Number No. of Day Rate/Day
None
C
Cutting, Bending & Placing of RSB 682.72 80.00 2.00
(kgs/day)
Labor Requirement Number No. of Days Rate/Day
Skilled Laborer 1.00 9.00 350.00
Unskilled Laborer 1.00 9.00 228.00
Reinforcing Steel Bars
(12mmØ)
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Total
Unit Cost
43.37
Cost
23,040.00
1,100.00
270.00
24,410.00
Cost
8.53
Cost
3,150.00
2,052.00
Number of Days to
Complete the Work
5,202.00
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project: Diversion Works Structure
Location: Barangay Aslum, Julita, Leyte
Item No. Work Description Quantity Unit Unit Cost
Trash Trap 1 LS 1,867.50
A Material Quantity Unit Unit Cost Cost
1.00 pcs. 650.00 650.00
10mmØ X 20' RSB 5.00 pcs. 165.00 825.00
Welding Rod 0.50 kgs. 85.00 42.50
Total 1,517.50
B Name & Capacity of Equipment Number No. of Day Rate/Day Cost
None
C
Trash Fabrication (days per trap) 1.00 1.00 1.00 1.00
Labor Requirement Number No. of Day Rate/Day Cost
Welder 1.00 1.00 350.00 350.00
Total 350.00
¼" X 1½" X 20' Angle Bar
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Number of Days to
Complete the Work
DETAILED ESTIMATES
Supplement to Program of Work
Name of Proposed Sub-Project:
Location:
Item No. Work Description Quantity Unit
A Material Quantity Unit Unit Cost
B Name & Capacity of Equipment Number No. of Day Rate/Day
C
Labor Derivation
(Subsidiary Work
Description)
Quantity
Required
Manpower
Capability
Number of Manpower
Assigned
Labor Requirement Number No. of Day Rate/Day
Unit Cost
Cost
Cost
Number of Days to
Complete the Work
Cost

More Related Content

What's hot

reinforced concrete arki.ppt
reinforced concrete arki.pptreinforced concrete arki.ppt
reinforced concrete arki.ppt
ChristopherArce4
 
Flexural design of beam...PRC-I
Flexural design of beam...PRC-IFlexural design of beam...PRC-I
Flexural design of beam...PRC-I
Irfan Malik
 
300 solved-problems
300 solved-problems300 solved-problems
300 solved-problems
MD.Yeasin Mostafiz
 
Geotech2.pptx
Geotech2.pptxGeotech2.pptx
Geotech2.pptx
ChristopherArce4
 
Setting time test
Setting time testSetting time test
Setting time test
Muhammad Saleem
 
Liquid limit & plastic limit test
Liquid limit & plastic limit testLiquid limit & plastic limit test
Liquid limit & plastic limit test
Raz Azad
 
Determination of Field Density Using Sand Cone Method | Jameel Academy
Determination of Field Density Using Sand Cone Method | Jameel AcademyDetermination of Field Density Using Sand Cone Method | Jameel Academy
Determination of Field Density Using Sand Cone Method | Jameel Academy
Jameel Academy
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
Priodeep Chowdhury
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
SantistebanCampos
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement paste
Hafizullah Sadat
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
AberaMamoJaleta
 
Examples on stress distribution
Examples on stress distributionExamples on stress distribution
Examples on stress distribution
Malika khalil
 
Sieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - ReportSieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - Report
Sarchia Khursheed
 
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel AcademySetting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Jameel Academy
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidation
Malika khalil
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
maylene san luis
 
Making and curing concrete test specimens in the
Making and curing concrete test specimens in theMaking and curing concrete test specimens in the
Making and curing concrete test specimens in the
Farrukh Khan
 
Square footing design
Square footing designSquare footing design
Square footing design
Southern University Bangladesh
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
Pratap Shinde
 
_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)
sharda university
 

What's hot (20)

reinforced concrete arki.ppt
reinforced concrete arki.pptreinforced concrete arki.ppt
reinforced concrete arki.ppt
 
Flexural design of beam...PRC-I
Flexural design of beam...PRC-IFlexural design of beam...PRC-I
Flexural design of beam...PRC-I
 
300 solved-problems
300 solved-problems300 solved-problems
300 solved-problems
 
Geotech2.pptx
Geotech2.pptxGeotech2.pptx
Geotech2.pptx
 
Setting time test
Setting time testSetting time test
Setting time test
 
Liquid limit & plastic limit test
Liquid limit & plastic limit testLiquid limit & plastic limit test
Liquid limit & plastic limit test
 
Determination of Field Density Using Sand Cone Method | Jameel Academy
Determination of Field Density Using Sand Cone Method | Jameel AcademyDetermination of Field Density Using Sand Cone Method | Jameel Academy
Determination of Field Density Using Sand Cone Method | Jameel Academy
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement paste
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
Examples on stress distribution
Examples on stress distributionExamples on stress distribution
Examples on stress distribution
 
Sieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - ReportSieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - Report
 
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel AcademySetting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidation
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
Making and curing concrete test specimens in the
Making and curing concrete test specimens in theMaking and curing concrete test specimens in the
Making and curing concrete test specimens in the
 
Square footing design
Square footing designSquare footing design
Square footing design
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 
_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)_lateral_earth_pressure_(foundation engineering)
_lateral_earth_pressure_(foundation engineering)
 

Similar to 23262483 unit-cost-derivation

EQS - EARTHWORK FOR ROADS AND CANALS.pdf
EQS -  EARTHWORK FOR ROADS AND CANALS.pdfEQS -  EARTHWORK FOR ROADS AND CANALS.pdf
EQS - EARTHWORK FOR ROADS AND CANALS.pdf
GovindarajuluBadana
 
7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oeKashmir Brown
 
Cost of breeder farm
Cost of breeder farmCost of breeder farm
Cost of breeder farm
Omar Faruque
 
Data penawaran subur jaya
Data penawaran subur jayaData penawaran subur jaya
Data penawaran subur jaya
verytudjuka
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-houseimaduddin91
 
Master Schedule vs Actual Progress Bp Andi Week 13.pdf
Master Schedule vs Actual Progress Bp Andi Week 13.pdfMaster Schedule vs Actual Progress Bp Andi Week 13.pdf
Master Schedule vs Actual Progress Bp Andi Week 13.pdf
AJI DARMAWAN
 
Intro. to management lecture 09
Intro. to management lecture 09Intro. to management lecture 09
Intro. to management lecture 09
Haitham Sharnouby
 
2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes
Deny Sulistio
 
rating curve
rating curverating curve
rating curve
Bialas Kaczmarek
 
Rab
RabRab
Rab
AL Vet
 
sm ch2 open akan.pdf
sm ch2 open akan.pdfsm ch2 open akan.pdf
sm ch2 open akan.pdf
MoizAhmedKhan6
 
second review.pptx
second review.pptxsecond review.pptx
second review.pptx
KSelvakumarCIVIL
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimateimaduddin91
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Avin Kharel
 
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
independiente
 
Intro. to management lecture 08
Intro. to management lecture 08Intro. to management lecture 08
Intro. to management lecture 08
Haitham Sharnouby
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
Shze Hwa Lee
 

Similar to 23262483 unit-cost-derivation (20)

EQS - EARTHWORK FOR ROADS AND CANALS.pdf
EQS -  EARTHWORK FOR ROADS AND CANALS.pdfEQS -  EARTHWORK FOR ROADS AND CANALS.pdf
EQS - EARTHWORK FOR ROADS AND CANALS.pdf
 
7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe
 
Cost of breeder farm
Cost of breeder farmCost of breeder farm
Cost of breeder farm
 
Data penawaran subur jaya
Data penawaran subur jayaData penawaran subur jaya
Data penawaran subur jaya
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-house
 
Master Schedule vs Actual Progress Bp Andi Week 13.pdf
Master Schedule vs Actual Progress Bp Andi Week 13.pdfMaster Schedule vs Actual Progress Bp Andi Week 13.pdf
Master Schedule vs Actual Progress Bp Andi Week 13.pdf
 
Intro. to management lecture 09
Intro. to management lecture 09Intro. to management lecture 09
Intro. to management lecture 09
 
2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes
 
BQ
BQBQ
BQ
 
rating curve
rating curverating curve
rating curve
 
Rab
RabRab
Rab
 
sm ch2 open akan.pdf
sm ch2 open akan.pdfsm ch2 open akan.pdf
sm ch2 open akan.pdf
 
second review.pptx
second review.pptxsecond review.pptx
second review.pptx
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimate
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
 
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)020 ejemplo de presupuesto (mano de obra, materiales y transporte)
020 ejemplo de presupuesto (mano de obra, materiales y transporte)
 
Intro. to management lecture 08
Intro. to management lecture 08Intro. to management lecture 08
Intro. to management lecture 08
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
 
Revit Samples
Revit SamplesRevit Samples
Revit Samples
 
Revit Samples
Revit SamplesRevit Samples
Revit Samples
 

More from imaduddin91

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplicationsimaduddin91
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringimaduddin91
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural designimaduddin91
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplicationsimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsimaduddin91
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural designimaduddin91
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesignimaduddin91
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagementimaduddin91
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplicationsimaduddin91
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagementimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
Statistical metods
Statistical metodsStatistical metods
Statistical metodsimaduddin91
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference conceptsimaduddin91
 

More from imaduddin91 (20)

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplications
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineering
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplications
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural design
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagement
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
Statistical metods
Statistical metodsStatistical metods
Statistical metods
 
Sas cheat
Sas cheatSas cheat
Sas cheat
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference concepts
 

23262483 unit-cost-derivation

  • 1. OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTEE Barangay of Aslum Municipality of Julita Province of Leyte SUB-PROJECT PROGRAM OF WORK Sub-Project Title Diversion Works Structure Sub-Project Category Physical Target 1 Total Sub-Project Cost Project Description Implementation Mode Administration Construction of Diversion Work Structure Sub-Project Duration Equipment Needed 1 Bagger Concrete Mixer, Water Pump Technical Personnel 2 Item No. Scope of Work Percentage Quantity Unit Unit Price Total 1.00 Coffer Dam 20.00 LM 1,597.33 31,946.50 2.00 Diversion of Water & Care of Creek 123.25 cu.m. 50.45 6,217.80 3.00 Intake Weir Structure 3.10 Excavation 261.51 cu.m. 68.37 17,880.00 3.20 Boulder Fill 42.50 cu.m. 1,035.29 44,000.00 3.30 Gravel Bedding 17.00 cu.m. 832.29 14,149.00 3.40 Concrete Class "A" (3000 psi) 83.88 cu.m. 4,255.66 356,956.50 3.50 Reinforcing Steel Bars 4,131.67 kgs. 43.77 180,861.00 3.60 Structural Backfill 130.38 cu.m. 78.70 10,260.00 4.00 Handlaid Riprap 4.10 Excavation 24.00 cu.m. 62.08 1,490.00 4.20 Gravel Bedding 8.00 cu.m. 953.00 7,624.00 4.30 Riprap (Handlaid) 16.00 cu.m. 1,036.25 16,580.00 5.00 Grouted Riprap - 5.10 Excavation cu.m. - 5.20 Gravel Bedding cu.m. - 5.30 Riprap (Grouted) cu.m. - 6.00 Intake Works - 6.10 Excavation cu.m. - 6.20 Concrete Class "A" (3000 psi) cu.m. - 6.30 Reinforcing Steel Bars kgs - 6.40 Structural Backfill cu.m. - Total 687,964.80 Breakdown of Estimated Source of Fund Total Sub-Project Cost KALAHI-CIDSS Grant Community LGUs Other Source Cost A. Direct Cost Material Cost Equipment Rental Labor Cost Sub-Total A B. Indirect Cost Pre-Engineering Engineering Supervision Contractor's Profit Taxes Hand Tools Materials Testing Capability Building Administrative & Overhead Sub-Total B TOTAL (A+B) Add: Contingency Percent Total Estimated Cost Add: O & M (other amenities) GRAND TOTAL Prepared by: Approved by: BUENAVENTURA L. PITAO Engr.II, Prov'l. Agr'l. Office - Leyte Chairperson - Brgy. Sub-Project Mgt. Com. Reviewed by: Noted by: Deputy Area Coordinator Regional Infrastructure Engineer Note: b.) Costing of O & M will be monitored during the conduct of the SET *Costing to be supported with detailed Training Schedules a.) Skilled b.) Unskilled a.) Costing to be used on the MIBF will be the Total Cost Estimate
  • 2. CONCRETE VOLUME: Thickness, m. Width, m. Height, m. Length,m. Volume, cu.m. Retaining Wall: Retain Wall Left 0.20 2.50 10.41 5.21 0.20 2.00 14.00 5.60 Retain Wall Right 0.20 2.50 10.41 5.21 0.20 2.00 14.00 5.60 21.61 Cut-off Wall: Left Ret. Wall 0.20 1.00 24.41 4.88 0.20 1.00 14.00 2.80 Right Ret. Wall 0.20 1.00 24.41 4.88 0.20 1.00 14.00 2.80 Upstream 0.20 1.00 6.00 1.20 Downstream 0.20 1.00 8.00 1.60 18.17 Wall Footing Left Abutment 0.20 1.20 22.00 5.28 Right Abutment 0.20 1.20 22.00 5.28 10.56 No. of Units Pier 0.20 0.85 2.50 2 0.85 0.30 0.30 2.50 2 0.45 0.20 0.05 2.50 2 0.05 0.30 0.10 2.50 2 0.15 0.30 0.30 2.50 2 0.23 Flooring: Wier 0.20 6.00 14 16.80 0.20 1.00 1 0.20 R/L Abutment 0.10 5.12 14 7.17 0.10 5.12 14 7.17 31.33 Cut Walk: 0.10 0.60 8 0.48 Total Concrete Volume Total 83.88 60.06 Boulder Fill (200-400mmØ) Gravel Bedding 0.20 6.00 14 16.80 0.20 1.00 1 0.20 Total 17.00 Boulder (200-400mmØ) 0.50 6.00 14 42.00 0.50 1.00 1 0.50 Total 42.50 Grouted Riprap:(200-400mm) Right Abutment 0.30 4.83 5.00 7.24 Left Abutment 0.30 4.83 5.00 7.24 Total 14.49 Handlaid Riprap:(300-400mm) 0.40 8.00 5.00 16.00 Gravel Bedding 0.20 8.00 5.00 8.00 Total 24.00
  • 3. Reinf. Steel Bars Retain Wall Left Width, m. Height, m. Length,m. No. of pcs. Total Length, m Bar A 12mm 0.75 1.25 24.00 121.00 242.00 Bar B 12mm 1.10 2.45 24.00 121.00 429.55 Temp. Bars 10mm 3.50 24.00 12.67 304.00 Retain Wall Right Bar A 12mm 0.75 1.25 24.00 121.00 242.00 Bar B 12mm 1.10 2.45 24.00 121.00 429.55 Temp. Bars 10mm 2.50 24.00 9.33 224.00 Wall Footing: Left Footing 12mm 1.50 22.00 111.00 166.50 1.50 22.00 8.50 187.00 Right Footing 12mm 1.50 22.00 111.00 166.50 1.50 22.00 8.50 187.00 Flooring: 6.00 14.00 31.00 434.00 6.00 14.00 71.00 426.00 Cut-off Wall: Left Abutment: Vertical Bars (12mm) 1.50 37.41 188.07 282.11 Temp. Bars (12mm) 1.00 37.41 6.00 224.49 Right Abutment: Vertical Bars (12mm) 1.50 37.41 188.07 282.11 Temp. Bars (12mm) 1.00 37.41 6.00 224.49 Upstream Vertical Bars (12mm) 1.30 6.00 31.00 40.30 Temp. Bars (12mm) 1.00 6.00 6.00 36.00 Downstream Vertical Bars (12mm) 1.30 8.00 41.00 53.30 Temp. Bars (12mm) 1.00 8.00 6.00 48.00 Pier: No. of Units Bracing (Vert.) 12mm 2.00 0.85 2.70 5.25 28.35 Horizontal 12mm 2.00 0.85 2.60 14.00 23.80 Pier Post 12mm 2.00 2.70 7.00 37.80 Stirrups 10mm 2.00 2.60 2.40 14.00 67.20 Cut Walk: Longitudinal 12 mm 0.60 8.00 4.00 32.00 Temp. Bars 10mm 0.60 8.00 41.00 24.60 Intake Wall: 12mm Bothways 0.90 0.90 20.00 101.00 363.60 0.90 0.90 20.00 19.00 380.00 Discharge end (Two sides) Vert. 12mm 2.00 0.50 1.34 3.50 9.38 Hor.12mm 2.00 0.50 0.90 5.50 5.50 Cut-off 12mm Vert.12mm 0.45 1.80 10.00 4.50 0.45 1.80 3.25 5.85 Total 12mm dia. 10mm dia. Excavation: Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m. Retaining Wall: Retain Wall Left U/S 2.00 1.40 1.90 5.00 16.15
  • 4. 1.80 1.40 1.90 12.00 36.48 D/S 2.00 1.40 1.90 5.00 16.15 0.30 0.30 0.25 14.00 1.05 Retain Wall Right U/S 2.00 1.40 2.10 5.00 17.85 1.80 1.40 1.75 12.00 33.60 D/S 2.00 1.40 1.75 5.00 14.88 0.30 0.30 0.50 14.00 2.10 138.26 Cut-off Wall Left U/S 0.70 0.40 1.00 5.00 2.75 0.70 0.40 1.00 12.00 6.60 D/S 0.70 0.40 1.00 5.00 2.75 0.70 0.40 1.00 6.00 3.30 Right U/S 0.70 0.40 1.00 5.00 2.75 0.70 0.40 1.00 12.00 6.60 D/S 0.70 0.40 1.00 5.00 2.75 0.70 0.40 1.00 8.00 4.40 31.90 Flooring: 6.00 0.70 14.00 58.80 1.20 0.50 1.00 14.00 11.90 0.50 0.15 2.00 14.00 9.10 0.15 0.40 3.00 14.00 11.55 123.25 Total 261.51 Grouted Excav. Left Abutment 2.30 0.50 2.50 5.00 17.50 Right Abutment 2.00 0.50 3.00 5.00 15.00 2.00 0.50 5.00 5.00 Total 37.50 Handlaid Riprap:Excav. 8.00 0.60 5.00 24.00 Struc. Backfill: Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m. Retaining Wall: Retain Wall Left 1.80 1.20 1.70 5.00 12.75 1.55 1.20 1.70 12.00 28.05 1.80 1.20 1.70 5.00 12.75 5.00 0.60 14.00 42.00 Retain Wall Right 1.80 1.20 1.70 5.00 12.75 1.55 1.20 1.70 12.00 28.05 1.80 1.20 1.70 5.00 12.75 5.00 0.20 14.00 14.00 Cut-off Wall 0.50 0.20 1.00 5.00 1.75 0.50 0.20 1.00 12.00 4.20 0.50 0.20 1.00 5.00 1.75 0.50 0.20 1.00 6.00 2.10 0.50 0.20 1.00 5.00 1.75 0.50 0.20 1.00 12.00 4.20 0.50 0.20 1.00 5.00 1.75 0.50 0.20 1.00 8.00 2.80 Total 183.40 Intake Works: Top,m. Bottom,m. Height, m. Length,m. Volume, cu.m. Excavation 1.10 1.10 0.40 20.00 8.80
  • 5. Backfill 0.30 0.20 0.28 20.00 1.40 1.00 1.00 0.20 5.00 1.00 2.40 Concrete Volume 0.24 0.24 20.00 1.15 1.80 1.34 0.12 0.29 0.80 0.92 0.12 (0.09) Total Concrete Volume 1.35 Concrete Division Box: Length,m. Top, m Height, m. Width, m. Volume, cu.m. Flooring - CHB Footing 0.30 - Total - No. of CHB's (3.00) pcs. Mortar/Plaster (0.02) Concrete Mortar Total Cement - Sand - Gravel - Reinforcing Bars Length,m. Width, m. Height, m. No. of Pcs.Total Bar Length Vertical Bar - Horizontal Bar - CHB Found. - - Total - Bar nos. -
  • 6.
  • 9.
  • 10. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 1.00 Coffer Dam Linear Meter (Lm)20 1,597.33 A Material Quantity Unit Unit Cost Cost 1 1/2" X 4' X 8' Marine Plyboard 7.50 pcs. 835.00 6,262.50 2 2" X 2" Coco Lumber (False work) 180.00 bd.ft. 9.50 1,710.00 3 Assorted Common Wire Nails 12.00 kgs. 50.00 600.00 Sub-Total 8,572.50 B Name & Capacity of Equipment Number No. of Days Rate/Day Cost None C Hour/board foot 0.064 Board foot per Linear meter 180.00 Hour/Linear meter 20.00 11.52 3.00 28.80 Labor Requirement Number No. of Day Rate/Day Cost Skilled Laborer 1.00 29.00 350.00 10,150.00 Unskilled Laborer 2.00 29.00 228.00 13,224.00 Sub-Total 23,374.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 11. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Diversion of Water and Care of Creek cu.m.2.00 123.25 50.45 A Material Quantity Unit Unit Cost Cost 1 Diesel Fuel 8.00 liters 39.85 318.80 Total 318.80 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost 4"Ø Water Pumps and accessories 1.00 17.00 119.00 2,023.00 Total 2,023.00 C Dewatering/pumping ( cu.m./day) 123.25 7.25 1.00 17.00 Labor Requirement Number No. of Days Rate/Day Cost Water Pump Operator 1.00 17.00 228.00 3,876.00 Total 3,876.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 12. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Excavation cubic meter (cu.m.)3.10 261.51 68.37 A Material Quantity Unit Unit Cost Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Cu.m./Man-day @ 0-4m throwing dist 261.51 3.50 6.00 12.45 Labor Requirement Number No. of Days Rate/Day Cost Skilled Laborer 1.00 12.00 350.00 4,200.00 Unskilled Laborer 5.00 12.00 228.00 13,680.00 Sub-Total 17,880.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 13. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 3.40 cubic meter (cu.m.)83.88 4,255.66 A Material Quantity Unit Unit Cost Cost 1 Portland Cement 800.00 bags 195.00 156,000.00 2 Fresh Sand 53.00 cu.m. 350.00 18,550.00 3 Gravel (G1) 70.00 cu.m. 725.00 50,750.00 4 1/4" X 4' X 8' Ordinary Plywood 57.00 pcs. 385.00 21,945.00 5 Coco Lumber (False Work) 5,033.00 bd.ft. 10.50 52,846.50 6 Nails and Hardware 210.00 kgs. 52.50 11,025.00 Total 311,116.50 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost Concrete Mixer (1 bagger) 1.00 24.00 298.00 7,152.00 Total 7,152.00 C Concrete Works (cu.m./day) 83.88 3.50 6.00 23.97 Labor Requirement Number No.of Days Rate/Day Cost Skilled Laborer 2.00 24.00 350.00 16,800.00 Unskilled Laborer 4.00 24.00 228.00 21,888.00 Total 38,688.00 Concrete Class "A" (3000 psi) Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 14. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Reinforcing Steel Bars Kgs.3.50 4,131.67 43.77 A Material Quantity Unit Unit Cost Cost 1 12mm Ø X 20' Reinforcing Bars 704.00 pcs. 180.00 126,720.00 2 10mm Ø X 20' Reinforcing Bars 103.00 pcs. 165.00 16,995.00 3 # 16 Tie Wire 124.00 kgs. 55.00 6,820.00 4 Hacksaw Blade 6.00 pcs. 45.00 270.00 Total 150,805.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Cutting, Bending & Placing of RSB 4,131.67 80.00 2.00 51.65 (kgs/day) Labor Requirement Number No. of Days Rate/Day Cost Skilled Laborer 1.00 52.00 350.00 18,200.00 Unskilled Laborer 1.00 52.00 228.00 11,856.00 Total 30,056.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 15. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Location: Item No. Work Description Quantity Unit A Material Quantity Unit Unit Cost B Name & Capacity of Equipment Number No. of Day Rate/Day C Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned
  • 16. Labor Requirement Number No. of Day Rate/Day
  • 17. Unit Cost Cost Cost Number of Days to Complete the Work
  • 18. Cost
  • 19. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Structural Backfill cubic meter (cu.m.)3.60 130.38 78.70 A Material Quantity Unit Unit Cost Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Backfilling & Tamping (cu.m./man-day) 130.38 3.00 5.00 8.69 Labor Requirement Number No. of Day Rate/Day Cost Unskilled Laborer 5.00 9.00 228.00 10,260.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 20. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 4.10 Excavation (Handlaid Riprap) cubic meter (cu.m.)24.00 62.08 A Material Quantity Unit Unit Cost Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Cu.m./Man-day @ 0-4m throwing dist. 24.00 3.50 6.00 1.14 Labor Requirement Number No. of Days Rate/Day Cost Skilled Laborer 1.00 1.00 350.00 350.00 Unskilled Laborer 5.00 1.00 228.00 1,140.00 Sub-Total 1,490.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 21. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 4.30 Handlaid Riprap cubic meters (cu.m.)16.00 1,036.25 A Material Quantity Unit Unit Cost Cost 1 Boulder (300mm-400mmØ) 16.00 cu.m. 850.00 13,600.00 Total 13,600.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Handlaid Riprap (cu.m./day) 16.00 8.50 6.00 1.88 Labor Requirement Number No. of Day Rate/Day Cost Skilled Laborer 1.00 2.00 350.00 700.00 Unskilled Laborer 5.00 2.00 228.00 2,280.00 Total 2,980.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 22. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 4.20 Gravel Bedding (Handlaid) cubic meters (cu.m.)8.00 953.00 A Material Quantity Unit Unit Cost Cost 1 Gravel (G1) 8.00 cu.m. 725.00 5,800.00 Total 5,800.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Bedding (cu.m./hour) 8.00 2.00 8.00 0.50 Labor Requirement Number No. of Day Rate/Day Cost Unskilled Laborer 8.00 1.00 228.00 1,824.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 24. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 1 Excavation (Grouted Riprap) 37.50 cubic meter (cu.m.) 79.47 A Material Quantity Unit Unit Cost Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Cu.m./Man-day @ 0-4m throwing dist. 37.50 3.50 6.00 1.79 Labor Requirement Number No. of Days Rate/Day Cost Skilled Laborer 1.00 2.00 350.00 700.00 Unskilled Laborer 5.00 2.00 228.00 2,280.00 Sub-Total 2,980.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 25. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Grouted Riprap 14.49 cubic meters (cu.m.) 2,280.25 A Material Quantity Unit Unit Cost Cost 1 Portland Cement 61.00 bags 195.00 11,895.00 2 Fresh Sand 5.00 cu.m. 350.00 1,750.00 3 Gravel (G1) 1.00 cu.m. 725.00 725.00 4 Boulder (200mm-350mmØ) 14.00 cu.m. 850.00 11,900.00 Total 26,270.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Grouted Riprap (cu.m./day) 14.49 7.50 13.00 1.93 Labor Requirement Number No. of Day Rate/Day Cost Foreman 1.00 2.00 400.00 800.00 Skilled Laborer 2.00 2.00 350.00 1,400.00 Unskilled Laborer 10.00 2.00 228.00 4,560.00 Total 6,760.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 26. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 3.20 Boulder Fill cubic meters (cu.m.)42.50 1,035.29 A Material Quantity Unit Unit Cost Cost 1 Boulder (200mm-400mmØ) 43.00 cu.m. 850.00 36,550.00 Total 36,550.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Handlaid Riprap (cu.m./day) 43.00 8.50 6.00 5.06 Labor Requirement Number No. of Day Rate/Day Cost Skilled Laborer 1.00 5.00 350.00 1,750.00 Unskilled Laborer 5.00 5.00 228.00 5,700.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 28. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit 3.30 Gravel Bedding (Boulder Fill) cubic meters (cu.m.)17.00 A Material Quantity Unit Unit Cost 1 Gravel (G1) 17.00 cu.m. 725.00 Total B Name & Capacity of Equipment Number No. of Day Rate/Day None C Bedding (cu.m./hour) 17.00 2.00 8.00 Labor Requirement Number No. of Day Rate/Day Unskilled Laborer 8.00 1.00 228.00 Total Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned
  • 29.
  • 31.
  • 32. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost 1.35 cubic meter (cu.m.) 4,262.00 A Material Quantity Unit Unit Cost Cost 1 Portland Cement 13.00 bags 195.00 2,535.00 2 Fresh Sand 1.00 cu.m. 350.00 350.00 3 Gravel (G1) 1.00 cu.m. 725.00 725.00 4 1/4" X 4' X 8' Ordinary Plywood 1.00 pcs. 385.00 385.00 5 Coco Lumber (False Work) 81.00 bd.ft. 10.50 850.50 6 Nails and Hardware 3.00 kgs. 52.50 157.50 Total 5,003.00 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost Concrete Mixer (1 bagger) 1.00 0.40 298.00 119.20 Total 119.20 C Concrete Works (cu.m./day) 1.35 3.50 6.00 0.39 Labor Requirement Number No.of Days Rate/Day Cost Skilled Laborer 2.00 0.40 350.00 280.00 Unskilled Laborer 4.00 0.40 228.00 364.80 Concrete Class "A" (3000 psi) Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 34. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit 1 Excavation (Intake) 8.80 cubic meter (cu.m.) A Material Quantity Unit Unit Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day None C Cu.m./Man-day @ 0-4m throwing dist. 8.80 3.50 6.00 Labor Requirement Number No. of Days Rate/Day Skilled Laborer 1.00 0.40 350.00 Unskilled Laborer 5.00 0.40 228.00 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned
  • 38. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Structural Backfill 2.40 cubic meter (cu.m.) 95.00 A Material Quantity Unit Unit Cost Cost None B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Backfilling & Tamping (cu.m./man-day) 2.40 3.00 5.00 0.16 Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 39. Labor Requirement Number No. of Day Rate/Day Cost Unskilled Laborer 5.00 0.20 228.00 228.00
  • 40. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit 682.72 Kgs. A Material Quantity Unit Unit Cost 1 12mm Ø X 20' Reinforcing Bars 128.00 pcs. 180.00 2 # 16 Tie Wire 20.00 kgs. 55.00 3 Hacksaw Blade 6.00 pcs. 45.00 Total B Name & Capacity of Equipment Number No. of Day Rate/Day None C Cutting, Bending & Placing of RSB 682.72 80.00 2.00 (kgs/day) Labor Requirement Number No. of Days Rate/Day Skilled Laborer 1.00 9.00 350.00 Unskilled Laborer 1.00 9.00 228.00 Reinforcing Steel Bars (12mmØ) Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned
  • 41. Total
  • 44. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Diversion Works Structure Location: Barangay Aslum, Julita, Leyte Item No. Work Description Quantity Unit Unit Cost Trash Trap 1 LS 1,867.50 A Material Quantity Unit Unit Cost Cost 1.00 pcs. 650.00 650.00 10mmØ X 20' RSB 5.00 pcs. 165.00 825.00 Welding Rod 0.50 kgs. 85.00 42.50 Total 1,517.50 B Name & Capacity of Equipment Number No. of Day Rate/Day Cost None C Trash Fabrication (days per trap) 1.00 1.00 1.00 1.00 Labor Requirement Number No. of Day Rate/Day Cost Welder 1.00 1.00 350.00 350.00 Total 350.00 ¼" X 1½" X 20' Angle Bar Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned Number of Days to Complete the Work
  • 45. DETAILED ESTIMATES Supplement to Program of Work Name of Proposed Sub-Project: Location: Item No. Work Description Quantity Unit A Material Quantity Unit Unit Cost B Name & Capacity of Equipment Number No. of Day Rate/Day C Labor Derivation (Subsidiary Work Description) Quantity Required Manpower Capability Number of Manpower Assigned
  • 46. Labor Requirement Number No. of Day Rate/Day
  • 47. Unit Cost Cost Cost Number of Days to Complete the Work
  • 48. Cost