FECHA: JULIO 2010
No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL
NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL
1 CAPTACION 4 U
LIMPIA Y CHAPEO 144.00 m² 216.00 216.00 216.00
TRAZO Y ESTAQUEADO 128.00 ml 480.00 480.00 480.00
EXCAVACION 16.00 m³ 336.00 336.00 336.00
MUROS DE CAPTACION DE MAMPOSTERIA 16.00 m³ 1,920.00 1,920.00 1,920.00 3,840.00 5,760.00 7,680.00
CAJA DE MAMPOSTERIA 20.40 m³ 2,244.00 2,244.00 5,455.00 4,860.00 10,315.00 12,559.00
TAPADERAS DE CONCRETO 1.76 m³ 1,560.00 1,560.00 370.00 3,654.02 4,024.02 5,584.02
REPELLO + AFINADO EN CAJA DE MAMPOSTERIA 80.00 m² 960.00 960.00 175.00 720.00 895.00 1,855.00
MATERIAL FILTRANTE 24.00 m² 1,200.00 1,200.00 2,200.00 2,200.00 3,400.00
CONTRA CUNETA DE CONCRETO 24.00 ml 1,552.00 1,552.00 370.00 720.00 1,090.00 2,642.00
TUBERIA, ACCESORIOS Y VALVULAS global 600.00 600.00 2,275.48 2,275.48 2,875.48
TRANSPORTE 200 qq 5,000.00 5,000.00
TOTAL RENGLON 1,032.00 10,036.00 11,068.00 10,490.00 16,069.50 26,559.50 5,000.00 42,627.50
2 CAJA REUNIDORA DE CAUDALES DE 1 M³ 3 U
LIMPIA Y CHAPEO 12.00 m² 18.00 18.00 18.00
TRAZO Y ESTAQUEADO 15.00 ml 56.25 56.25 56.25
EXCAVACION 3.00 m³ 63.00 63.00 63.00
MUROS + FONDO DE MAMPOSTERIA 6.15 m³ 1,200.00 1,200.00 2,820.00 1,530.00 4,350.00 5,550.00
LOSA + TAPADERA DE CONCRETO 0.90 m³ 1,050.00 1,050.00 191.25 1,378.01 1,569.26 2,619.26
REPELLO + AFINADO 41.70 m² 540.00 540.00 112.50 360.00 472.50 1,012.50
TUBERIA, ACCESORIOS Y VALVULAS global 300.00 300.00 1,784.76 1,784.76 2,084.76
TRANSPORTE 63 qq 1,575.00 1,575.00
TOTAL RENGLON 205.88 3,090.00 3,295.88 3,123.75 5,052.77 8,176.52 1,575.00 13,047.39
3 LINEA DE CONDUCCION 14238 ML.
LIMPIA Y CHAPEO 14,238.00 m² 7,119.00 7,119.00 7,119.00
TRAZO Y ESTAQUEADO 14,238.00 ml 3,559.50 3,559.50 3,559.50
EXCAVACION 8,460.00 m³ 177,660.00 177,660.00 177,660.00
RELLENO 8,436.00 m³ 118,104.00 118,104.00 118,104.00
TUBERIA PVC Ø 3/4" C-250 396.00 ml 297.00 297.00 3,714.48 3,714.48 4,011.48
TUBERIA PVC Ø 1" C-160 534.00 ml 400.50 400.50 6,155.24 6,155.24 6,555.74
TUBERÍA PVC Ø 1½" C-160 552.00 ml 414.00 414.00 10,435.56 10,435.56 10,849.56
TUBERÍA PVC Ø 2" C-160 6420.00 ml 6,420.00 6,420.00 189,111.80 189,111.80 195,531.80
TUBERÍA PVC Ø 1½" C-250 1170.00 ml 877.50 877.50 33,214.35 33,214.35 34,091.85
TUBERÍA PVC Ø 2" C-250 4242.00 ml 4,242.00 4,242.00 188,104.42 188,104.42 192,346.42
TUBERÍA HG Ø 1" TL 66.00 ml 148.50 148.50 2,464.00 2,464.00 2,612.50
TUBERÍA HG Ø 1½" TL 54.00 ml 121.50 121.50 3,294.00 3,294.00 3,415.50
TUBERÍA HG Ø 2" TL 804.00 ml 2,412.00 2,412.00 61,640.00 61,640.00 64,052.00
ACCESORIOS global 690.00 690.00 12,634.69 12,634.69 13,324.69
VALVULAS DE AIRE 17.00 u 935.00 935.00 8,364.05 8,364.05 9,299.05
VALVULAS DE LIMPIEZA 22.00 u 1,320.00 1,320.00 3,490.51 3,490.51 4,810.51
CAJAS PARA VALVULAS DE AIRE Y LIMPIEZA 39.00 u 7,800.00 7,800.00 1,455.00 7,546.50 9,001.50 16,801.50
MANO DE OBRA MATERIALES
PROYECTO DE AGUA POTABLE
CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO
PRESUPUESTO
FECHA: JULIO 2010
No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL
NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL
MANO DE OBRA MATERIALES
PROYECTO DE AGUA POTABLE
CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO
PRESUPUESTO
TRANSPORTE 320 qq 8,000.00 8,000.00
TOTAL RENGLON 306,442.50 26,078.00 332,520.50 1,455.00 530,169.60 531,624.60 8,000.00 872,145.10
4 ANCLAJE PARA TUBERIA DE HG 190.00 U
SOPORTES DE CONCRETO ARMADO 190.00 u 2,850.00 8,550.00 11,400.00 3,515.00 18,129.80 21,644.80 33,044.80
TRANSPORTE 171.00 qq 4,275.00 4,275.00
TOTAL RENGLON 2,850.00 8,550.00 11,400.00 3,515.00 18,129.80 21,644.80 4,275.00 37,319.80
5 TANQUE DE DISTRIBUCION 20 M³ MAMPOSTERIA 1 U
LIMPIA Y CHAPEO 27.00 m² 40.50 40.50 40.50
TRAZO Y ESTAQUEADO 21.00 ml 78.75 78.75 78.75
EXCAVACION 22.00 m³ 462.00 462.00 462.00
FONDO DE MAMPOSTERIA 4.20 m³ 525.00 525.00 498.75 960.00 1,458.75 1,983.75
MUROS DE MAMPOSTERIA 35.00 m³ 4,375.00 4,375.00 6,025.00 8,445.00 14,470.00 18,845.00
LOSA + TAPADERA + VIGA 2.90 m³ 2,465.00 2,465.00 585.00 3,867.12 4,452.12 6,917.12
REPELLO + AFINADO 89.00 m² 1,260.00 1,260.00 225.00 240.00 465.00 1,725.00
ESCALERAS + VENTILACION global 300.00 300.00 588.20 588.20 888.20
TUBERIA Y ACCESORIOS global 200.00 200.00 1,069.06 1,069.06 1,269.06
CAJAS PARA VALVULAS 3.00 u 600.00 600.00 101.25 724.00 825.25 1,425.25
TRANSPORTE 194 qq 4,850.00 4,850.00
TOTAL RENGLON 581.25 9,725.00 10,306.25 7,435.00 15,893.38 23,328.38 4,850.00 38,484.63
6 PASO DE ZANJON TIPO E 3 U
LIMPIA Y CHAPEO 54.00 m² 81.00 81.00 81.00
EXCAVACION 4.95 m³ 103.95 103.95 103.95
BASES DE CONCRETO 5.40 m3 225.00 900.00 1,125.00 1,923.75 5,929.38 7,853.13 8,978.13
ACCESORIOS DEL PASO DE ZANJON global 450.00 450.00 2,085.00 2,085.00 2,535.00
TRANSPORTE 60 qq 1,500.00 1,500.00
TOTAL RENGLON 409.95 1,350.00 1,759.95 1,923.75 8,014.38 9,938.13 1,500.00 13,198.08
7 PASO AEREO DE 12 mts. 2 U
LIMPIA Y CHAPEO 24.00 m² 36.00 36.00 36.00
EXCAVACION 3.30 m³ 42.00 42.00 42.00
MUERTOS DE CONCRETO 12.00 m³ 1,320.00 1,320.00 2,075.00 4,800.00 6,875.00 8,195.00
ZAPATAS 1.20 m³ 600.00 600.00 240.00 1,506.70 1,746.70 2,346.70
COLUMNAS 1.56 m³ 1,200.00 1,200.00 2,072.50 3,331.40 5,403.90 6,603.90
CABLEADO Y ACCESORIOS global 800.00 800.00 6,817.64 6,817.64 7,617.64
TRANSPORTE 132 qq 3,300.00 3,300.00
TOTAL RENGLON 78.00 3,920.00 3,998.00 4,387.50 16,455.74 20,843.24 3,300.00 28,141.24
FECHA: JULIO 2010
No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL
NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL
MANO DE OBRA MATERIALES
PROYECTO DE AGUA POTABLE
CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO
PRESUPUESTO
8 PASO AEREO DE 18 mts. 5 U
LIMPIA Y CHAPEO 90.00 m² 135.00 135.00 135.00
EXCAVACION 8.25 m³ 173.25 173.25 173.25
MUERTOS DE CONCRETO 43.25 m³ 5,625.00 5,625.00 8,018.75 19,500.00 27,518.75 33,143.75
ZAPATAS 3.00 m³ 1,650.00 1,650.00 600.00 3,766.75 4,366.75 6,016.75
COLUMNAS 3.90 m³ 3,320.00 3,320.00 5,181.25 8,328.50 13,509.75 16,829.75
CABLEADO Y ACCESORIOS global 3,000.00 3,000.00 19,194.10 19,194.10 22,194.10
TRANSPORTE 330 qq 8,250.00 8,250.00
TOTAL RENGLON 308.25 13,595.00 13,903.25 13,800.00 50,789.35 64,589.35 8,250.00 86,742.60
9 PASO AEREO DE 20 mts. 2.00 U
LIMPIA Y CHAPEO 36.00 m² 54.00 54.00 54.00
EXCAVACION 3.30 m³ 69.30 69.30 69.30
MUERTOS DE CONCRETO 17.30 m³ 2,250.00 2,250.00 3,207.50 7,800.00 11,007.50 13,257.50
ZAPATAS 1.20 m³ 660.00 660.00 240.00 1,506.70 1,746.70 2,406.70
COLUMNAS 1.56 m³ 1,328.00 1,328.00 2,072.50 3,331.40 5,403.90 6,731.90
CABLEADO Y ACCESORIOS global 1,200.00 1,200.00 7,677.64 7,677.64 8,877.64
TRANSPORTE 90 qq 2,250.00 2,250.00
TOTAL RENGLON 123.30 5,438.00 5,561.30 5,520.00 20,315.74 25,835.74 2,250.00 33,647.04
10 PASO AEREO DE 30 mts. 4 U
LIMPIA Y CHAPEO 72.00 m² 108.00 108.00 108.00
EXCAVACION 6.60 m³ 138.60 138.60 138.60
MUERTOS DE CONCRETO 34.60 m³ 4,500.00 4,500.00 6,415.00 15,600.00 22,015.00 26,515.00
ZAPATAS 2.40 m³ 1,320.00 1,320.00 480.00 3,013.40 3,493.40 4,813.40
COLUMNAS 3.12 m³ 2,656.00 2,656.00 4,145.00 6,662.80 10,807.80 13,463.80
CABLEADO Y ACCESORIOS global 3,200.00 3,200.00 17,183.28 17,183.28 20,383.28
TRANSPORTE 400 qq 10,000.00 10,000.00
TOTAL RENGLON 246.60 11,676.00 11,922.60 11,040.00 42,459.48 53,499.48 10,000.00 75,422.08
11 PASO AEREO DE 40 mts. 3 U
LIMPIA Y CHAPEO 54.00 m² 81.00 81.00 81.00
EXCAVACION 4.95 m³ 103.95 103.95 103.95
MUERTOS DE CONCRETO 25.95 m³ 3,375.00 3,375.00 4,811.25 11,700.00 16,511.25 19,886.25
ZAPATAS 1.98 m³ 990.00 990.00 412.50 2,927.58 3,340.08 4,330.08
COLUMNAS 2.55 m³ 1,992.00 1,992.00 2,103.75 5,312.61 7,416.36 9,408.36
CABLEADO Y ACCESORIOS global 2,400.00 2,400.00 14,147.46 14,147.46 16,547.46
TRANSPORTE 300 qq 7,500.00 7,500.00
TOTAL RENGLON 184.95 8,757.00 8,941.95 7,327.50 34,087.65 41,415.15 7,500.00 57,857.10
12 PASO AEREO DE 75 mts. 1 U
FECHA: JULIO 2010
No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL
NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL
MANO DE OBRA MATERIALES
PROYECTO DE AGUA POTABLE
CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO
PRESUPUESTO
LIMPIA Y CHAPEO 25.00 m² 37.50 37.50 37.50
EXCAVACION 6.30 m³ 132.30 132.30 132.30
RELLENO 3.60 m³ 50.40 50.40 50.40
MUERTOS DE CONCRETO 8.65 m³ 1,125.00 1,125.00 1,603.75 3,900.00 5,503.75 6,628.75
ZAPATAS 1.22 m³ 450.00 450.00 245.00 1,275.86 1,520.86 1,970.86
COLUMNAS 1.56 m³ 900.00 900.00 1,016.25 4,370.55 5,386.80 6,286.80
CABLEADO Y ACCESORIOS global 1,500.00 1,500.00 8,469.10 8,469.10 9,969.10
TRANSPORTE 110 qq 2,750.00 2,750.00
TOTAL RENGLON 220.20 3,975.00 4,195.20 2,865.00 18,015.51 20,880.51 2,750.00 27,825.71
13 RED DE DISTRIBUCION 10188 ML.
TRAZO Y ESTAQUEADO 10,188.00 ml 2,547.00 2,547.00 2,547.00
EXCAVACION 6,255.00 m³ 87,570.00 87,570.00 87,570.00
RELLENO 6,248.00 m³ 43,736.00 43,736.00 43,736.00
TUBERIA PVC Ø 3/4" C-250 5490.00 ml 5,490.00 5,490.00 51,496.20 51,496.20 56,986.20
TUBERIA PVC Ø 1" C-160 2484.00 ml 2,484.00 2,484.00 28,632.24 28,632.24 31,116.24
TUBERÍA PVC Ø 1¼" C-160 384.00 ml 576.00 576.00 5,557.76 5,557.76 6,133.76
TUBERÍA PVC Ø 1½" C-160 102.00 ml 76.50 76.50 1,928.31 1,928.31 2,004.81
TUBERÍA PVC Ø 2" C-160 1386.00 ml 1,386.00 1,386.00 40,826.94 40,826.94 42,212.94
TUBERÍA PVC Ø 2" C-250 240.00 ml 240.00 240.00 10,642.40 10,642.40 10,882.40
TUBERÍA HG Ø 1" TL 60.00 ml 135.00 135.00 2,240.00 2,240.00 2,375.00
TUBERÍA HG Ø 2" TL 42.00 ml 126.00 126.00 3,220.00 3,220.00 3,346.00
ACCESORIOS global 635.00 635.00 3,821.14 3,821.14 4,456.14
TRANSPORTE 80 qq 2,000.00 2,000.00
TOTAL RENGLON 133,853.00 11,148.50 145,001.50 0.00 148,364.99 148,364.99 2,000.00 295,366.49
14 CAJA ROMPE PRESION DE 1 M³ CON VALVULA FLOTE 19 U
LIMPIA Y CHAPEO 76.00 m² 114.00 114.00 114.00
TRAZO Y ESTAQUEADO 95.00 ml 356.25 356.25 356.25
EXCAVACION 19.00 m³ 399.00 399.00 399.00
MUROS + FONDO DE MAMPOSTERIA 38.95 m³ 6,650.00 6,650.00 17,860.00 9,690.00 27,550.00 34,200.00
LOSA + TAPADERA DE CONCRETO 5.70 m³ 4,750.00 4,750.00 1,211.25 8,727.37 9,938.62 14,688.62
REPELLO + AFINADO 264.10 m² 2,850.00 2,850.00 712.50 2,280.00 2,992.50 5,842.50
TUBERIA, ACCESORIOS Y VALVULAS global 1,425.00 1,425.00 13,084.82 13,084.82 14,509.82
TRANSPORTE 399 qq 9,975.00 9,975.00
TOTAL RENGLON 1,303.88 15,675.00 16,978.88 19,783.75 33,782.19 53,565.94 9,975.00 80,519.81
15 CONEXIONES DOMICILIARES 130 U
TRAZO Y ESTAQUEADO 2,340.00 ml 585.00 585.00 585.00
EXCAVACION 2,600.00 m³ 36,400.00 36,400.00 36,400.00
RELLENO 2,599.00 m³ 18,193.00 18,193.00 18,193.00
TUBERIA, ACCESORIOS Y VALVULAS global 5,850.00 5,850.00 103,793.89 103,793.89 109,643.89
FECHA: JULIO 2010
No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL
NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL
MANO DE OBRA MATERIALES
PROYECTO DE AGUA POTABLE
CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO
PRESUPUESTO
BASES DE CONCRETO 130.00 u 4,550.00 4,550.00 1,300.00 1,657.50 2,957.50 7,507.50
TRANSPORTE 32.50 qq 812.50 812.50
TOTAL RENGLON 55,178.00 10,400.00 65,578.00 1,300.00 105,451.39 106,751.39 812.50 173,141.89
16 HIPOCLORADOR 1 U
TRAZO Y ESTAQUEADO 4.00 ml 25.00 25.00 25.00
DEPOSITO DE CONCRETO ARMADO 1.00 m³ 765.00 765.00 550.00 1,166.17 1,716.17 2,481.17
TUBERIA Y ACCESORIOS global 150.00 150.00 327.25 327.25 477.25
TRANSPORTE 15 qq 375.00 375.00
TOTAL RENGLON 25.00 915.00 940.00 550.00 1,493.42 2,043.42 375.00 3,358.42
17 SUMIDEROS PARA CONEXIONES 130 U
TRAZO Y ESTAQUEADO 468.00 ml 117.00 117.00 117.00
EXCAVACION 150.80 m³ 2,111.20 2,111.20 2,111.20
TRAMPA DE GRASA Y SUMIDERO 130.00 u 32,500.00 32,500.00 39,325.00 64,010.83 103,335.83 135,835.83
TRANSPORTE 780 qq 19,500.00 19,500.00
TOTAL RENGLON 2,228.20 32,500.00 34,728.20 39,325.00 64,010.83 103,335.83 19,500.00 157,564.03
COSTO DIRECTO DEL TOTAL DE RENGLONES 505,270.95 176,828.50 682,099.45 133,841.25 1,128,555.70 1,262,396.95 91,912.50 2,036,408.90

More Related Content

What's hot

Cerco perimetrico
Cerco perimetricoCerco perimetrico
Cerco perimetrico
Luis Carrasco Domínguez
 
Catalogo de rendimientos de partidas
Catalogo de rendimientos de partidasCatalogo de rendimientos de partidas
Catalogo de rendimientos de partidas
FidelAnt Quispe Jayo
 
Analisis de costos unitarios
Analisis de costos unitariosAnalisis de costos unitarios
Analisis de costos unitarios
Julio Leon
 
Analisisdepreciosunitarios 120807235739-phpapp01
Analisisdepreciosunitarios 120807235739-phpapp01Analisisdepreciosunitarios 120807235739-phpapp01
Analisisdepreciosunitarios 120807235739-phpapp01Alfredo Ramos
 
SUPLEMENTO TECNICO MARZO 2022.pdf
SUPLEMENTO TECNICO MARZO 2022.pdfSUPLEMENTO TECNICO MARZO 2022.pdf
SUPLEMENTO TECNICO MARZO 2022.pdf
DamianMateoVega
 
precios unitarios.pdf
precios unitarios.pdfprecios unitarios.pdf
precios unitarios.pdf
AleCajija
 
CatáLogo De Conceptos
CatáLogo De ConceptosCatáLogo De Conceptos
CatáLogo De ConceptosLuis Morales
 
Suplemento tecnico 314.2 nov
Suplemento tecnico 314.2 novSuplemento tecnico 314.2 nov
Suplemento tecnico 314.2 nov
Eyair Tovar
 
Rendimiento por-cuadrilla-de-las-principales-actividades
Rendimiento por-cuadrilla-de-las-principales-actividadesRendimiento por-cuadrilla-de-las-principales-actividades
Rendimiento por-cuadrilla-de-las-principales-actividades
Emmanuel Velasco
 
Ae2 catalogo de conceptos
Ae2   catalogo de conceptosAe2   catalogo de conceptos
Ae2 catalogo de conceptos
Eduardo Lopez Clemente
 
Metrados estruturas y arquitectura
Metrados   estruturas y arquitecturaMetrados   estruturas y arquitectura
Metrados estruturas y arquitectura
Saul Velasquez Salazar
 
Acu s10 2018
Acu s10 2018Acu s10 2018
Acu s10 2018
Nombre Sobrenome
 
tabla de rendimientos de mano de obra
tabla de rendimientos de mano de obratabla de rendimientos de mano de obra
tabla de rendimientos de mano de obra
nicorob79
 
Desagregado de costos indirectos
Desagregado de costos indirectosDesagregado de costos indirectos
Desagregado de costos indirectos
Antonio Aparicio
 
presupuesto mod. 70 m2 b
presupuesto   mod. 70 m2 bpresupuesto   mod. 70 m2 b
presupuesto mod. 70 m2 b
nicorob79
 
REVISTA COSTOS ABRIL, MAYO 2020
REVISTA COSTOS ABRIL, MAYO 2020REVISTA COSTOS ABRIL, MAYO 2020
REVISTA COSTOS ABRIL, MAYO 2020
SIMON MELGAREJO
 

What's hot (20)

Cerco perimetrico
Cerco perimetricoCerco perimetrico
Cerco perimetrico
 
Catalogo de rendimientos de partidas
Catalogo de rendimientos de partidasCatalogo de rendimientos de partidas
Catalogo de rendimientos de partidas
 
Ppto sedapal
Ppto sedapalPpto sedapal
Ppto sedapal
 
Analisis de costos unitarios
Analisis de costos unitariosAnalisis de costos unitarios
Analisis de costos unitarios
 
Analisisdepreciosunitarios 120807235739-phpapp01
Analisisdepreciosunitarios 120807235739-phpapp01Analisisdepreciosunitarios 120807235739-phpapp01
Analisisdepreciosunitarios 120807235739-phpapp01
 
SUPLEMENTO TECNICO MARZO 2022.pdf
SUPLEMENTO TECNICO MARZO 2022.pdfSUPLEMENTO TECNICO MARZO 2022.pdf
SUPLEMENTO TECNICO MARZO 2022.pdf
 
precios unitarios.pdf
precios unitarios.pdfprecios unitarios.pdf
precios unitarios.pdf
 
A.p.u 2009
A.p.u 2009A.p.u 2009
A.p.u 2009
 
CatáLogo De Conceptos
CatáLogo De ConceptosCatáLogo De Conceptos
CatáLogo De Conceptos
 
Presupuesto
PresupuestoPresupuesto
Presupuesto
 
Suplemento tecnico 314.2 nov
Suplemento tecnico 314.2 novSuplemento tecnico 314.2 nov
Suplemento tecnico 314.2 nov
 
ESQUEMA PRESUPUESTO DE OBRA
ESQUEMA PRESUPUESTO DE OBRA ESQUEMA PRESUPUESTO DE OBRA
ESQUEMA PRESUPUESTO DE OBRA
 
Rendimiento por-cuadrilla-de-las-principales-actividades
Rendimiento por-cuadrilla-de-las-principales-actividadesRendimiento por-cuadrilla-de-las-principales-actividades
Rendimiento por-cuadrilla-de-las-principales-actividades
 
Ae2 catalogo de conceptos
Ae2   catalogo de conceptosAe2   catalogo de conceptos
Ae2 catalogo de conceptos
 
Metrados estruturas y arquitectura
Metrados   estruturas y arquitecturaMetrados   estruturas y arquitectura
Metrados estruturas y arquitectura
 
Acu s10 2018
Acu s10 2018Acu s10 2018
Acu s10 2018
 
tabla de rendimientos de mano de obra
tabla de rendimientos de mano de obratabla de rendimientos de mano de obra
tabla de rendimientos de mano de obra
 
Desagregado de costos indirectos
Desagregado de costos indirectosDesagregado de costos indirectos
Desagregado de costos indirectos
 
presupuesto mod. 70 m2 b
presupuesto   mod. 70 m2 bpresupuesto   mod. 70 m2 b
presupuesto mod. 70 m2 b
 
REVISTA COSTOS ABRIL, MAYO 2020
REVISTA COSTOS ABRIL, MAYO 2020REVISTA COSTOS ABRIL, MAYO 2020
REVISTA COSTOS ABRIL, MAYO 2020
 

Viewers also liked

Estudio económico parte 01 costos de producción
Estudio económico parte 01   costos de producciónEstudio económico parte 01   costos de producción
Estudio económico parte 01 costos de producción
bus3
 
formato presupuesto
formato presupuestoformato presupuesto
formato presupuesto
Juan Reyes
 
Cómo crear un presupuesto del evento
Cómo crear un presupuesto del eventoCómo crear un presupuesto del evento
Cómo crear un presupuesto del evento
Paola Batlle
 
Calculo de cantidades de acuerdo a planos
Calculo de cantidades de acuerdo a planosCalculo de cantidades de acuerdo a planos
Calculo de cantidades de acuerdo a planoshyesidtapias
 
Planificacion y organizacion de eventos y banquete
Planificacion y organizacion de eventos y banquetePlanificacion y organizacion de eventos y banquete
Planificacion y organizacion de eventos y banquete
Ysrael Quereigua
 

Viewers also liked (7)

Presupuestos 2
Presupuestos 2Presupuestos 2
Presupuestos 2
 
Estudio económico parte 01 costos de producción
Estudio económico parte 01   costos de producciónEstudio económico parte 01   costos de producción
Estudio económico parte 01 costos de producción
 
formato presupuesto
formato presupuestoformato presupuesto
formato presupuesto
 
Presupuesto de eventos
Presupuesto de eventosPresupuesto de eventos
Presupuesto de eventos
 
Cómo crear un presupuesto del evento
Cómo crear un presupuesto del eventoCómo crear un presupuesto del evento
Cómo crear un presupuesto del evento
 
Calculo de cantidades de acuerdo a planos
Calculo de cantidades de acuerdo a planosCalculo de cantidades de acuerdo a planos
Calculo de cantidades de acuerdo a planos
 
Planificacion y organizacion de eventos y banquete
Planificacion y organizacion de eventos y banquetePlanificacion y organizacion de eventos y banquete
Planificacion y organizacion de eventos y banquete
 

Similar to 020 ejemplo de presupuesto (mano de obra, materiales y transporte)

Queen burger pres 2 p+f
Queen burger pres 2 p+fQueen burger pres 2 p+f
Queen burger pres 2 p+f
RofoMG
 
Data penawaran subur jaya
Data penawaran subur jayaData penawaran subur jaya
Data penawaran subur jaya
verytudjuka
 
2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes
Deny Sulistio
 
Planing pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahPlaning pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahSekertariat_Akmaliah
 
Planing pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahPlaning pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahReguti
 
Lista de precios iccu 2016
Lista de precios iccu 2016 Lista de precios iccu 2016
Lista de precios iccu 2016
Freddy Zamudio Alvarez
 
1.concretos mortero 179
1.concretos mortero 1791.concretos mortero 179
1.concretos mortero 179
jjjj
 
7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oeKashmir Brown
 
Maiz grano para blog
Maiz grano para blogMaiz grano para blog
Maiz grano para blogMiguel Lopez
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimateimaduddin91
 
Space 134 - Statement of Probable Cost
Space 134 - Statement of Probable CostSpace 134 - Statement of Probable Cost
Space 134 - Statement of Probable Cost
Community Development Department-Glendale, CA
 
Magazina M1
Magazina M1Magazina M1
Magazina M1
Self-employed
 
Aluminium Architectural Section Profiles Manufacturer & Supplier
Aluminium Architectural Section Profiles Manufacturer & SupplierAluminium Architectural Section Profiles Manufacturer & Supplier
Aluminium Architectural Section Profiles Manufacturer & Supplier
Banco Aluminium
 
Gjendje magazine
Gjendje magazineGjendje magazine
Gjendje magazine
Self-employed
 
Dyqani D1
Dyqani D1Dyqani D1
Dyqani D1
Self-employed
 
Inventario 16 09-10
Inventario 16 09-10Inventario 16 09-10
Inventario 16 09-10
Celso Rangel
 
Tema 12 diapositivas
Tema 12 diapositivasTema 12 diapositivas
Tema 12 diapositivas
NiltonCondorRojas
 

Similar to 020 ejemplo de presupuesto (mano de obra, materiales y transporte) (20)

Queen burger pres 2 p+f
Queen burger pres 2 p+fQueen burger pres 2 p+f
Queen burger pres 2 p+f
 
Data penawaran subur jaya
Data penawaran subur jayaData penawaran subur jaya
Data penawaran subur jaya
 
2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes2.pengajuanrabcandramas terasdepanatapasbes
2.pengajuanrabcandramas terasdepanatapasbes
 
Planing pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahPlaning pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliah
 
Planing pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliahPlaning pembangunan masjid_akmaliah
Planing pembangunan masjid_akmaliah
 
Lista de precios iccu 2016
Lista de precios iccu 2016 Lista de precios iccu 2016
Lista de precios iccu 2016
 
1.concretos mortero 179
1.concretos mortero 1791.concretos mortero 179
1.concretos mortero 179
 
Sorgo para blog
Sorgo para blogSorgo para blog
Sorgo para blog
 
7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe
 
Maiz grano para blog
Maiz grano para blogMaiz grano para blog
Maiz grano para blog
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimate
 
Space 134 - Statement of Probable Cost
Space 134 - Statement of Probable CostSpace 134 - Statement of Probable Cost
Space 134 - Statement of Probable Cost
 
Magazina M1
Magazina M1Magazina M1
Magazina M1
 
Aluminium Architectural Section Profiles Manufacturer & Supplier
Aluminium Architectural Section Profiles Manufacturer & SupplierAluminium Architectural Section Profiles Manufacturer & Supplier
Aluminium Architectural Section Profiles Manufacturer & Supplier
 
Gjendje magazine
Gjendje magazineGjendje magazine
Gjendje magazine
 
Dyqani D1
Dyqani D1Dyqani D1
Dyqani D1
 
Facade man hour
Facade man hourFacade man hour
Facade man hour
 
Inventario 16 09-10
Inventario 16 09-10Inventario 16 09-10
Inventario 16 09-10
 
Tema 12 diapositivas
Tema 12 diapositivasTema 12 diapositivas
Tema 12 diapositivas
 
Revit Samples
Revit SamplesRevit Samples
Revit Samples
 

Recently uploaded

DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdfDOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
Pushpendra Kumar
 
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Chapters 3  Contracts.pptx Chapters 3  Contracts.pptxChapters 3  Contracts.pptx Chapters 3  Contracts.pptx
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Sheldon Byron
 
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
Dirk Spencer Corporate Recruiter LION
 
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
larisashrestha558
 
Operating system. short answes and Interview questions .pdf
Operating system. short answes and Interview questions .pdfOperating system. short answes and Interview questions .pdf
Operating system. short answes and Interview questions .pdf
harikrishnahari6276
 
DIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptxDIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptx
FarzanaRbcomcs
 
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
foismail170
 
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
gobogo3542
 
133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research
Manu Mitra
 
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaaInteractive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
23211a7274
 
Luke Royak's Personal Brand Exploration!
Luke Royak's Personal Brand Exploration!Luke Royak's Personal Brand Exploration!
Luke Royak's Personal Brand Exploration!
LukeRoyak
 
Full Sail_Morales_Michael_SMM_2024-05.pptx
Full Sail_Morales_Michael_SMM_2024-05.pptxFull Sail_Morales_Michael_SMM_2024-05.pptx
Full Sail_Morales_Michael_SMM_2024-05.pptx
mmorales2173
 
135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering
Manu Mitra
 
134. Reviewer Certificate in Computer Science
134. Reviewer Certificate in Computer Science134. Reviewer Certificate in Computer Science
134. Reviewer Certificate in Computer Science
Manu Mitra
 
Heidi Livengood Resume Senior Technical Recruiter / HR Generalist
Heidi Livengood Resume Senior Technical Recruiter / HR GeneralistHeidi Livengood Resume Senior Technical Recruiter / HR Generalist
Heidi Livengood Resume Senior Technical Recruiter / HR Generalist
HeidiLivengood
 
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdfDr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam
 
Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.
alexthomas971
 
132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences
Manu Mitra
 
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
foismail170
 
How to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and BusinessHow to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and Business
ideatoipo
 

Recently uploaded (20)

DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdfDOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
DOC-20240602-WA0001..pdf DOC-20240602-WA0001..pdf
 
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
Chapters 3  Contracts.pptx Chapters 3  Contracts.pptxChapters 3  Contracts.pptx Chapters 3  Contracts.pptx
Chapters 3 Contracts.pptx Chapters 3 Contracts.pptx
 
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
Transferable Skills - Your Roadmap - Part 1 and 2 - Dirk Spencer Senior Recru...
 
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
皇冠体育- 皇冠体育官方网站- CROWN SPORTS| 立即访问【ac123.net】
 
Operating system. short answes and Interview questions .pdf
Operating system. short answes and Interview questions .pdfOperating system. short answes and Interview questions .pdf
Operating system. short answes and Interview questions .pdf
 
DIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptxDIGITAL MARKETING COURSE IN CHENNAI.pptx
DIGITAL MARKETING COURSE IN CHENNAI.pptx
 
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
太阳城娱乐-太阳城娱乐推荐-太阳城娱乐官方网站| 立即访问【ac123.net】
 
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
15385-LESSON PLAN- 7TH - SS-Insian Constitution an Introduction.pdf
 
133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research133. Reviewer Certificate in Advances in Research
133. Reviewer Certificate in Advances in Research
 
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaaInteractive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
Interactive Dictionary AIDS-B.pptx aaaaaaaaaaaaaaaaaaaaaaaaaa
 
Luke Royak's Personal Brand Exploration!
Luke Royak's Personal Brand Exploration!Luke Royak's Personal Brand Exploration!
Luke Royak's Personal Brand Exploration!
 
Full Sail_Morales_Michael_SMM_2024-05.pptx
Full Sail_Morales_Michael_SMM_2024-05.pptxFull Sail_Morales_Michael_SMM_2024-05.pptx
Full Sail_Morales_Michael_SMM_2024-05.pptx
 
135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering135. Reviewer Certificate in Journal of Engineering
135. Reviewer Certificate in Journal of Engineering
 
134. Reviewer Certificate in Computer Science
134. Reviewer Certificate in Computer Science134. Reviewer Certificate in Computer Science
134. Reviewer Certificate in Computer Science
 
Heidi Livengood Resume Senior Technical Recruiter / HR Generalist
Heidi Livengood Resume Senior Technical Recruiter / HR GeneralistHeidi Livengood Resume Senior Technical Recruiter / HR Generalist
Heidi Livengood Resume Senior Technical Recruiter / HR Generalist
 
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdfDr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
Dr. Nazrul Islam, Northern University Bangladesh - CV (29.5.2024).pdf
 
Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.Personal Brand Exploration Comedy Jxnelle.
Personal Brand Exploration Comedy Jxnelle.
 
132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences132. Acta Scientific Pharmaceutical Sciences
132. Acta Scientific Pharmaceutical Sciences
 
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
欧洲杯买球平台-欧洲杯买球平台推荐-欧洲杯买球平台| 立即访问【ac123.net】
 
How to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and BusinessHow to Master LinkedIn for Career and Business
How to Master LinkedIn for Career and Business
 

020 ejemplo de presupuesto (mano de obra, materiales y transporte)

  • 1. FECHA: JULIO 2010 No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL 1 CAPTACION 4 U LIMPIA Y CHAPEO 144.00 m² 216.00 216.00 216.00 TRAZO Y ESTAQUEADO 128.00 ml 480.00 480.00 480.00 EXCAVACION 16.00 m³ 336.00 336.00 336.00 MUROS DE CAPTACION DE MAMPOSTERIA 16.00 m³ 1,920.00 1,920.00 1,920.00 3,840.00 5,760.00 7,680.00 CAJA DE MAMPOSTERIA 20.40 m³ 2,244.00 2,244.00 5,455.00 4,860.00 10,315.00 12,559.00 TAPADERAS DE CONCRETO 1.76 m³ 1,560.00 1,560.00 370.00 3,654.02 4,024.02 5,584.02 REPELLO + AFINADO EN CAJA DE MAMPOSTERIA 80.00 m² 960.00 960.00 175.00 720.00 895.00 1,855.00 MATERIAL FILTRANTE 24.00 m² 1,200.00 1,200.00 2,200.00 2,200.00 3,400.00 CONTRA CUNETA DE CONCRETO 24.00 ml 1,552.00 1,552.00 370.00 720.00 1,090.00 2,642.00 TUBERIA, ACCESORIOS Y VALVULAS global 600.00 600.00 2,275.48 2,275.48 2,875.48 TRANSPORTE 200 qq 5,000.00 5,000.00 TOTAL RENGLON 1,032.00 10,036.00 11,068.00 10,490.00 16,069.50 26,559.50 5,000.00 42,627.50 2 CAJA REUNIDORA DE CAUDALES DE 1 M³ 3 U LIMPIA Y CHAPEO 12.00 m² 18.00 18.00 18.00 TRAZO Y ESTAQUEADO 15.00 ml 56.25 56.25 56.25 EXCAVACION 3.00 m³ 63.00 63.00 63.00 MUROS + FONDO DE MAMPOSTERIA 6.15 m³ 1,200.00 1,200.00 2,820.00 1,530.00 4,350.00 5,550.00 LOSA + TAPADERA DE CONCRETO 0.90 m³ 1,050.00 1,050.00 191.25 1,378.01 1,569.26 2,619.26 REPELLO + AFINADO 41.70 m² 540.00 540.00 112.50 360.00 472.50 1,012.50 TUBERIA, ACCESORIOS Y VALVULAS global 300.00 300.00 1,784.76 1,784.76 2,084.76 TRANSPORTE 63 qq 1,575.00 1,575.00 TOTAL RENGLON 205.88 3,090.00 3,295.88 3,123.75 5,052.77 8,176.52 1,575.00 13,047.39 3 LINEA DE CONDUCCION 14238 ML. LIMPIA Y CHAPEO 14,238.00 m² 7,119.00 7,119.00 7,119.00 TRAZO Y ESTAQUEADO 14,238.00 ml 3,559.50 3,559.50 3,559.50 EXCAVACION 8,460.00 m³ 177,660.00 177,660.00 177,660.00 RELLENO 8,436.00 m³ 118,104.00 118,104.00 118,104.00 TUBERIA PVC Ø 3/4" C-250 396.00 ml 297.00 297.00 3,714.48 3,714.48 4,011.48 TUBERIA PVC Ø 1" C-160 534.00 ml 400.50 400.50 6,155.24 6,155.24 6,555.74 TUBERÍA PVC Ø 1½" C-160 552.00 ml 414.00 414.00 10,435.56 10,435.56 10,849.56 TUBERÍA PVC Ø 2" C-160 6420.00 ml 6,420.00 6,420.00 189,111.80 189,111.80 195,531.80 TUBERÍA PVC Ø 1½" C-250 1170.00 ml 877.50 877.50 33,214.35 33,214.35 34,091.85 TUBERÍA PVC Ø 2" C-250 4242.00 ml 4,242.00 4,242.00 188,104.42 188,104.42 192,346.42 TUBERÍA HG Ø 1" TL 66.00 ml 148.50 148.50 2,464.00 2,464.00 2,612.50 TUBERÍA HG Ø 1½" TL 54.00 ml 121.50 121.50 3,294.00 3,294.00 3,415.50 TUBERÍA HG Ø 2" TL 804.00 ml 2,412.00 2,412.00 61,640.00 61,640.00 64,052.00 ACCESORIOS global 690.00 690.00 12,634.69 12,634.69 13,324.69 VALVULAS DE AIRE 17.00 u 935.00 935.00 8,364.05 8,364.05 9,299.05 VALVULAS DE LIMPIEZA 22.00 u 1,320.00 1,320.00 3,490.51 3,490.51 4,810.51 CAJAS PARA VALVULAS DE AIRE Y LIMPIEZA 39.00 u 7,800.00 7,800.00 1,455.00 7,546.50 9,001.50 16,801.50 MANO DE OBRA MATERIALES PROYECTO DE AGUA POTABLE CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO PRESUPUESTO
  • 2. FECHA: JULIO 2010 No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL MANO DE OBRA MATERIALES PROYECTO DE AGUA POTABLE CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO PRESUPUESTO TRANSPORTE 320 qq 8,000.00 8,000.00 TOTAL RENGLON 306,442.50 26,078.00 332,520.50 1,455.00 530,169.60 531,624.60 8,000.00 872,145.10 4 ANCLAJE PARA TUBERIA DE HG 190.00 U SOPORTES DE CONCRETO ARMADO 190.00 u 2,850.00 8,550.00 11,400.00 3,515.00 18,129.80 21,644.80 33,044.80 TRANSPORTE 171.00 qq 4,275.00 4,275.00 TOTAL RENGLON 2,850.00 8,550.00 11,400.00 3,515.00 18,129.80 21,644.80 4,275.00 37,319.80 5 TANQUE DE DISTRIBUCION 20 M³ MAMPOSTERIA 1 U LIMPIA Y CHAPEO 27.00 m² 40.50 40.50 40.50 TRAZO Y ESTAQUEADO 21.00 ml 78.75 78.75 78.75 EXCAVACION 22.00 m³ 462.00 462.00 462.00 FONDO DE MAMPOSTERIA 4.20 m³ 525.00 525.00 498.75 960.00 1,458.75 1,983.75 MUROS DE MAMPOSTERIA 35.00 m³ 4,375.00 4,375.00 6,025.00 8,445.00 14,470.00 18,845.00 LOSA + TAPADERA + VIGA 2.90 m³ 2,465.00 2,465.00 585.00 3,867.12 4,452.12 6,917.12 REPELLO + AFINADO 89.00 m² 1,260.00 1,260.00 225.00 240.00 465.00 1,725.00 ESCALERAS + VENTILACION global 300.00 300.00 588.20 588.20 888.20 TUBERIA Y ACCESORIOS global 200.00 200.00 1,069.06 1,069.06 1,269.06 CAJAS PARA VALVULAS 3.00 u 600.00 600.00 101.25 724.00 825.25 1,425.25 TRANSPORTE 194 qq 4,850.00 4,850.00 TOTAL RENGLON 581.25 9,725.00 10,306.25 7,435.00 15,893.38 23,328.38 4,850.00 38,484.63 6 PASO DE ZANJON TIPO E 3 U LIMPIA Y CHAPEO 54.00 m² 81.00 81.00 81.00 EXCAVACION 4.95 m³ 103.95 103.95 103.95 BASES DE CONCRETO 5.40 m3 225.00 900.00 1,125.00 1,923.75 5,929.38 7,853.13 8,978.13 ACCESORIOS DEL PASO DE ZANJON global 450.00 450.00 2,085.00 2,085.00 2,535.00 TRANSPORTE 60 qq 1,500.00 1,500.00 TOTAL RENGLON 409.95 1,350.00 1,759.95 1,923.75 8,014.38 9,938.13 1,500.00 13,198.08 7 PASO AEREO DE 12 mts. 2 U LIMPIA Y CHAPEO 24.00 m² 36.00 36.00 36.00 EXCAVACION 3.30 m³ 42.00 42.00 42.00 MUERTOS DE CONCRETO 12.00 m³ 1,320.00 1,320.00 2,075.00 4,800.00 6,875.00 8,195.00 ZAPATAS 1.20 m³ 600.00 600.00 240.00 1,506.70 1,746.70 2,346.70 COLUMNAS 1.56 m³ 1,200.00 1,200.00 2,072.50 3,331.40 5,403.90 6,603.90 CABLEADO Y ACCESORIOS global 800.00 800.00 6,817.64 6,817.64 7,617.64 TRANSPORTE 132 qq 3,300.00 3,300.00 TOTAL RENGLON 78.00 3,920.00 3,998.00 4,387.50 16,455.74 20,843.24 3,300.00 28,141.24
  • 3. FECHA: JULIO 2010 No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL MANO DE OBRA MATERIALES PROYECTO DE AGUA POTABLE CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO PRESUPUESTO 8 PASO AEREO DE 18 mts. 5 U LIMPIA Y CHAPEO 90.00 m² 135.00 135.00 135.00 EXCAVACION 8.25 m³ 173.25 173.25 173.25 MUERTOS DE CONCRETO 43.25 m³ 5,625.00 5,625.00 8,018.75 19,500.00 27,518.75 33,143.75 ZAPATAS 3.00 m³ 1,650.00 1,650.00 600.00 3,766.75 4,366.75 6,016.75 COLUMNAS 3.90 m³ 3,320.00 3,320.00 5,181.25 8,328.50 13,509.75 16,829.75 CABLEADO Y ACCESORIOS global 3,000.00 3,000.00 19,194.10 19,194.10 22,194.10 TRANSPORTE 330 qq 8,250.00 8,250.00 TOTAL RENGLON 308.25 13,595.00 13,903.25 13,800.00 50,789.35 64,589.35 8,250.00 86,742.60 9 PASO AEREO DE 20 mts. 2.00 U LIMPIA Y CHAPEO 36.00 m² 54.00 54.00 54.00 EXCAVACION 3.30 m³ 69.30 69.30 69.30 MUERTOS DE CONCRETO 17.30 m³ 2,250.00 2,250.00 3,207.50 7,800.00 11,007.50 13,257.50 ZAPATAS 1.20 m³ 660.00 660.00 240.00 1,506.70 1,746.70 2,406.70 COLUMNAS 1.56 m³ 1,328.00 1,328.00 2,072.50 3,331.40 5,403.90 6,731.90 CABLEADO Y ACCESORIOS global 1,200.00 1,200.00 7,677.64 7,677.64 8,877.64 TRANSPORTE 90 qq 2,250.00 2,250.00 TOTAL RENGLON 123.30 5,438.00 5,561.30 5,520.00 20,315.74 25,835.74 2,250.00 33,647.04 10 PASO AEREO DE 30 mts. 4 U LIMPIA Y CHAPEO 72.00 m² 108.00 108.00 108.00 EXCAVACION 6.60 m³ 138.60 138.60 138.60 MUERTOS DE CONCRETO 34.60 m³ 4,500.00 4,500.00 6,415.00 15,600.00 22,015.00 26,515.00 ZAPATAS 2.40 m³ 1,320.00 1,320.00 480.00 3,013.40 3,493.40 4,813.40 COLUMNAS 3.12 m³ 2,656.00 2,656.00 4,145.00 6,662.80 10,807.80 13,463.80 CABLEADO Y ACCESORIOS global 3,200.00 3,200.00 17,183.28 17,183.28 20,383.28 TRANSPORTE 400 qq 10,000.00 10,000.00 TOTAL RENGLON 246.60 11,676.00 11,922.60 11,040.00 42,459.48 53,499.48 10,000.00 75,422.08 11 PASO AEREO DE 40 mts. 3 U LIMPIA Y CHAPEO 54.00 m² 81.00 81.00 81.00 EXCAVACION 4.95 m³ 103.95 103.95 103.95 MUERTOS DE CONCRETO 25.95 m³ 3,375.00 3,375.00 4,811.25 11,700.00 16,511.25 19,886.25 ZAPATAS 1.98 m³ 990.00 990.00 412.50 2,927.58 3,340.08 4,330.08 COLUMNAS 2.55 m³ 1,992.00 1,992.00 2,103.75 5,312.61 7,416.36 9,408.36 CABLEADO Y ACCESORIOS global 2,400.00 2,400.00 14,147.46 14,147.46 16,547.46 TRANSPORTE 300 qq 7,500.00 7,500.00 TOTAL RENGLON 184.95 8,757.00 8,941.95 7,327.50 34,087.65 41,415.15 7,500.00 57,857.10 12 PASO AEREO DE 75 mts. 1 U
  • 4. FECHA: JULIO 2010 No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL MANO DE OBRA MATERIALES PROYECTO DE AGUA POTABLE CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO PRESUPUESTO LIMPIA Y CHAPEO 25.00 m² 37.50 37.50 37.50 EXCAVACION 6.30 m³ 132.30 132.30 132.30 RELLENO 3.60 m³ 50.40 50.40 50.40 MUERTOS DE CONCRETO 8.65 m³ 1,125.00 1,125.00 1,603.75 3,900.00 5,503.75 6,628.75 ZAPATAS 1.22 m³ 450.00 450.00 245.00 1,275.86 1,520.86 1,970.86 COLUMNAS 1.56 m³ 900.00 900.00 1,016.25 4,370.55 5,386.80 6,286.80 CABLEADO Y ACCESORIOS global 1,500.00 1,500.00 8,469.10 8,469.10 9,969.10 TRANSPORTE 110 qq 2,750.00 2,750.00 TOTAL RENGLON 220.20 3,975.00 4,195.20 2,865.00 18,015.51 20,880.51 2,750.00 27,825.71 13 RED DE DISTRIBUCION 10188 ML. TRAZO Y ESTAQUEADO 10,188.00 ml 2,547.00 2,547.00 2,547.00 EXCAVACION 6,255.00 m³ 87,570.00 87,570.00 87,570.00 RELLENO 6,248.00 m³ 43,736.00 43,736.00 43,736.00 TUBERIA PVC Ø 3/4" C-250 5490.00 ml 5,490.00 5,490.00 51,496.20 51,496.20 56,986.20 TUBERIA PVC Ø 1" C-160 2484.00 ml 2,484.00 2,484.00 28,632.24 28,632.24 31,116.24 TUBERÍA PVC Ø 1¼" C-160 384.00 ml 576.00 576.00 5,557.76 5,557.76 6,133.76 TUBERÍA PVC Ø 1½" C-160 102.00 ml 76.50 76.50 1,928.31 1,928.31 2,004.81 TUBERÍA PVC Ø 2" C-160 1386.00 ml 1,386.00 1,386.00 40,826.94 40,826.94 42,212.94 TUBERÍA PVC Ø 2" C-250 240.00 ml 240.00 240.00 10,642.40 10,642.40 10,882.40 TUBERÍA HG Ø 1" TL 60.00 ml 135.00 135.00 2,240.00 2,240.00 2,375.00 TUBERÍA HG Ø 2" TL 42.00 ml 126.00 126.00 3,220.00 3,220.00 3,346.00 ACCESORIOS global 635.00 635.00 3,821.14 3,821.14 4,456.14 TRANSPORTE 80 qq 2,000.00 2,000.00 TOTAL RENGLON 133,853.00 11,148.50 145,001.50 0.00 148,364.99 148,364.99 2,000.00 295,366.49 14 CAJA ROMPE PRESION DE 1 M³ CON VALVULA FLOTE 19 U LIMPIA Y CHAPEO 76.00 m² 114.00 114.00 114.00 TRAZO Y ESTAQUEADO 95.00 ml 356.25 356.25 356.25 EXCAVACION 19.00 m³ 399.00 399.00 399.00 MUROS + FONDO DE MAMPOSTERIA 38.95 m³ 6,650.00 6,650.00 17,860.00 9,690.00 27,550.00 34,200.00 LOSA + TAPADERA DE CONCRETO 5.70 m³ 4,750.00 4,750.00 1,211.25 8,727.37 9,938.62 14,688.62 REPELLO + AFINADO 264.10 m² 2,850.00 2,850.00 712.50 2,280.00 2,992.50 5,842.50 TUBERIA, ACCESORIOS Y VALVULAS global 1,425.00 1,425.00 13,084.82 13,084.82 14,509.82 TRANSPORTE 399 qq 9,975.00 9,975.00 TOTAL RENGLON 1,303.88 15,675.00 16,978.88 19,783.75 33,782.19 53,565.94 9,975.00 80,519.81 15 CONEXIONES DOMICILIARES 130 U TRAZO Y ESTAQUEADO 2,340.00 ml 585.00 585.00 585.00 EXCAVACION 2,600.00 m³ 36,400.00 36,400.00 36,400.00 RELLENO 2,599.00 m³ 18,193.00 18,193.00 18,193.00 TUBERIA, ACCESORIOS Y VALVULAS global 5,850.00 5,850.00 103,793.89 103,793.89 109,643.89
  • 5. FECHA: JULIO 2010 No. RENGLON CANTIDAD UNIDAD TRANSPORTE TOTAL NO CALIFICADA CALIFICADA TOTAL LOCALES NO LOCALES TOTAL MANO DE OBRA MATERIALES PROYECTO DE AGUA POTABLE CANTON MORALES, ALDEA GRANADILLO, COLOTENANGO, HUEHUETENANGO PRESUPUESTO BASES DE CONCRETO 130.00 u 4,550.00 4,550.00 1,300.00 1,657.50 2,957.50 7,507.50 TRANSPORTE 32.50 qq 812.50 812.50 TOTAL RENGLON 55,178.00 10,400.00 65,578.00 1,300.00 105,451.39 106,751.39 812.50 173,141.89 16 HIPOCLORADOR 1 U TRAZO Y ESTAQUEADO 4.00 ml 25.00 25.00 25.00 DEPOSITO DE CONCRETO ARMADO 1.00 m³ 765.00 765.00 550.00 1,166.17 1,716.17 2,481.17 TUBERIA Y ACCESORIOS global 150.00 150.00 327.25 327.25 477.25 TRANSPORTE 15 qq 375.00 375.00 TOTAL RENGLON 25.00 915.00 940.00 550.00 1,493.42 2,043.42 375.00 3,358.42 17 SUMIDEROS PARA CONEXIONES 130 U TRAZO Y ESTAQUEADO 468.00 ml 117.00 117.00 117.00 EXCAVACION 150.80 m³ 2,111.20 2,111.20 2,111.20 TRAMPA DE GRASA Y SUMIDERO 130.00 u 32,500.00 32,500.00 39,325.00 64,010.83 103,335.83 135,835.83 TRANSPORTE 780 qq 19,500.00 19,500.00 TOTAL RENGLON 2,228.20 32,500.00 34,728.20 39,325.00 64,010.83 103,335.83 19,500.00 157,564.03 COSTO DIRECTO DEL TOTAL DE RENGLONES 505,270.95 176,828.50 682,099.45 133,841.25 1,128,555.70 1,262,396.95 91,912.50 2,036,408.90