SlideShare a Scribd company logo
Copyright @ 2011. All rights reserved
From Cost Plan To Bid Evaluation
To Contract Administration
The Earned Value Project Control Cycle
Project Controls Expo – 13th Nov 2013
Twickenham Stadium, London
Copyright @ 2011. All rights reserved
About the Speaker
Roland Horat, Managing Director of Supertech Project Management (Australia)
Pty Ltd. an international project management consulting company.
Roland is a specialist in Earned Value (EVPM) Based Project Management and
Control systems.
Roland’s company are the developers of the EVENGINE range of Earned Value
based project control and reporting software.
The EVENGINE Project Control software is showcased at this Expo.
Copyright @ 2011. All rights reserved
The Earned Value
Project Control Cycle
Overview
The Cycle Overview - Data and Software
CASH FLOW
PRODUCTIVITY
Contractor’s
PRICE
Contractor’s
Schedule
COST
PLAN
SCHEDULE
CASH FLOW
PRODUCTIVITY
ANALYSIS
EARNED VALUE
PERFORMANCE
REPORTS
The Cost Plan
The Bid Evaluation And Award
The Contract Administration
Contractor’s
PRICE
Contractor’s
Schedule
Contractor’s
PRICE
Contractor’s
Schedule
Contract
PRICE
Contractor’s
Schedule
Copyright @ 2011. All rights reserved
The Cost Plan
The Cost Plan - Work Breakdown Structure
What is a Cost Plan ? Cost Plan is the Estimate for the project based on the
Scope of Work Measured Trade Elements
The Cost Plan has a Cost Work Breakdown Structure (CWBS) To Mirror The
Project Scope of Work.
COST
PLAN
Typical CWBS for an Industrial/Infrastructure Project:
 Level 1 - The Project
 Level 2 - Phase/Stage - Separable Portions
 Level 3 - Area /Facility – Construction Zones
 Level 4 - Resource - Trade Based Activities
 Level 5 - Resource Trade Based Elements - Units of Measure and Pricing
 The Estimate Outline Structure is then generally mirrored within the
corresponding schedule.
The Cost Plan - Structure Example
 L1 - THE PROJECT
 L2 – KEY CONTROL MILESTONES
 L2 - SEPARABLE PORTIONS (SP1 – 5)
 L3 - CONSTRUCTION ZONE C7 (SP5)
o L4 - PRELIMINARIES
o L4 - DEMOLITION
o L4 - CIVIL ROAD WORKS
o L4 – SERVICES & FINISHES
o L4 – CONCRETE WORKS
 L5 - 50mm thick blinding concrete - mx2
 L5 - Concrete to protection barriers - mx2
 L5 - Formwork to edge of protection barriers - mx2
 L5 - Reinforcement to protection barries - 100 kg/m3 - t
 L5 - 100mm compressible foam to pylons - mx2
 L5 - Impact attenuator at protection barriers - No
COST
PLAN
Representative CWBS Outline for an Infrastructure Project
The Cost Plan - Structure
Example Infrastructure Level 5 Trade Element Based Estimate
COST
PLAN
L5 - Trade Category
Estimate Element
L3 - Construction ZoneL2 - Separable Portions
L4 - Resource/Trade
Category Estimate Line item
Estimate Extract for Separable
Portion 5, Construction Zone C7,
Resource Trade Category Civil Road
Works, Element Pavement
Estimate Quantity
Estimate Unit
Estimate Price
The Cost Plan - Schedule
LEVEL 1 -
Project
LEVEL 2 - Separable
Portions
LEVEL 3 –
Construction
Zones
LEVEL 4 -
Resource/Trade Category
LEVEL 5 - Trade Category
Estimate Element
Example Cost Plan Corresponding Level 1 to 5 Implementation Schedule
 The Schedule is Structured To
facilitate Mapping to the Cost Plan
SCHEDULE
The Cost Plan - Schedule to Cost Plan Mapping
Schedule and Cost Data Mapped, Imported & Maintained Within EVENGINE
System
COST
PLANSCHEDULE EVENGIE
L1 – The project
Primary Mapping Key UID
Early Start and
Finish Dates
Late Start and
Finish Dates
Baseline Start and
Finish Dates
L4 Resource/Trade Category
L3 Construction Zone
L2 Separable Portions
L5 - Estimate Element
Line item
BAC2 = Budget At Completion 2 = Control Budget
BAC = Budget At Completion = Contract Value
EAC = Estimate At Completion = Contract Value with Cost Trends
Covered By “Not Approved Variations” and “Contractor Other Costs”
BAC Contract Value
BAC2 Control Budget
EAC Contract With Trends
Estimate Extract for Separable
Portion 5, Construction Zone C7,
Resource Trade Category Civil Road
Works, Element Pavement
The Cost Plan – Earned Value Based Reports Benefits
 Used to Estimate Expected Preliminary Costs (Overhead & Profit)
 Cash Flow - Expected Funding Requirements - Bank Facility - Interest
 Cash Flow - Expected Phased & Staged Funds Commitments
 Allocation for Funds for Risk and Inclement Weather Allowances
 Allocation of Contingency Time and Funds
 Identification Of Provisional Sums
 Allocation of Management Reserve
 Trade Based Labour Analysis - Used for Contractor Tender Selection
 Productivity Analysis to Assess Contractor’s Requirement for Plant &
Equipment - Used for Contractor Tender Selection
 Supply Chain Management - Assess Requirement for Early Placement of
Bulk Orders Time Line and Value for Novation
 Data is Used to Shape the Contracting Plan
The Benefits Early Integration of Cost Plan with Corresponding Implementation
Schedule brings:
EVENGINE
The Cost Plan – Earned Value Based Reports and Graphs
 Trade Based Resource Analysis - Productivity Analysis to Assess Contractor’s
Requirement for Plant & Equipment - Used for Contractor Tender Selection
EVENGINE
Require a Contractor with Plant
and Equipment to deliver
20,000 mx2 of pavement per
month
The Cost Plan – Earned Value Based Reports and Graphs
 Cash Flow - Expected Funding Requirements - Bank Facility - Interest
EVENGINE
Require Monthly and
Cumulative Funding to Sustain
The Project – Used to establish
the Bank Finance Facility
The Cost Plan – Earned Value Based Reports and Graphs
 Supply Chain Management - Assess Requirement for Early Placement of
Bulk Orders Time Line and Value for Novation
EVENGINE
Monthly and Cumulative
Requirement of Pipe Delivery
over the expected contract
period.
Contractor supplied or free
issue of material ?
Copyright @ 2011. All rights reserved
The Bid Evaluation and
Award
The Bid Evaluation and Award
 The Cost Plan and Schedule forms the Basis of the Contractor’s Bid
COST
PLANSCHEDULE
 Prequalify and Select the Bidders based on Labour,
Plant and Equipment requirements and Contractor
Financial Capability to service the contract.
 Issue as part of the Tender Documentation The
Schedule Template and Contract Bill for Pricing
Corresponding the Cost Plan
Contractor
Provides
Level 4 Early
Start & Early
Finish Dates Level 5
Material and
Items Pricing
Data Provided
By QS
Contractor
Provides Level 5
Price & Direct
Labour Hours
The Bid Evaluation and Award
 Contractor Submits Implementation Schedule To Level 4 (Minimum)
 Contractor Submits Priced Bill of
Quantities to QS Requirements
 Cost Data is Integrated Into the EVENGINE Project Data Sheet
 Cost Data is Re-Mapped to the Contractor Tender Schedule To Facilitate
Comparative Tender Pricing Against Contract Plan Estimate
COST
PLANSCHEDULE EVENGINE
The Bid Evaluation and Award
Contractor Tender Evaluation Checklist
COST
PLANSCHEDULE EVENGINE
FOR EACH BIDDER EVENGINE CHECK ON:
 Available Construction Plant to Sustain Planned Production
 Available Labour by Trade Category to Sustain Planned Production
 Assessment of Variance between QS Budget and Contractor Price
(Thresholds should not be more than a range of 5% -10%))
 Contractor Cash Flow Versus Control Estimate (Check on Loadings)
 Conformance to Schedule Requirements, CPM Rules
 Productivity Check for key Commodities
 Model Potential Variation Claims to Assess Impact on Schedule and
Cost
CONTRACT FINALIZATION:
 Select Contractor on Price and Schedule Delivery.
 Formalize the Contract Reporting and Progress Evaluation Process
 Revised Finance Facility Based on Contract Schedule and Program
The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
Burn/Production
Rate Lower Than
Planned
Price Higher than
the Cost Plan
Estimate
A completion Date
Later Than The
Cost Plan
 Assessment of Variance between QS Budget and Contractor Price Cash Flow
Design &
Mobilization Period
Longer than
Planned
The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
 Productivity Check for key Commodities
 Available Labour by Trade Category to Sustain Planned Production
Multiple Peaks
indicating
additional crews
for set periods
Multiple Peaks
indicating
additional crews
for set periods
One Crew
Average
Production
Production Gap
The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
 Productivity Rate Check for key Commodities
Variable Cost Rate
for Pavement Per
mx2
Variable Work
Hour Rate Per
Pavement mx2
Evaluate Cost per Units of Quantity
over the Execution Period and
Compare Against Expected
Expected Hour
Rate Per Pavement
Type mx2
Expected Cost
Rate for Pavement
Per mx2
Evaluate Productivity Work (Hrs) per
Units of Quantity over the Execution
Period and Compare Against Industry
Published Constants
Copyright @ 2011. All rights reserved
The Contract
Administration Cycle
The Contract Administration
COST
PLANSCHEDULE EVENGINE
The Fortnightly Report Cycle (Recommended)
Project Controls
Schedule
Verification
Possible Advice
on Replanning
Mid-Month Report With
Earned Value and
Schedule Analysis
Project Controls
Schedule &
Claim
Verification
Monthly Report with
Earned Value and
Schedule Analysis
Variations, Certificate of
Payment
Possible Advice
on Replanning
and Claim
Resubmission
Mid Month
Contractor
Schedule Update
EVENGINE Data
Integration and Data
Processing
End of Month
Contractor
Schedule Update
End of Month
Contractor
Claim
EVENGINE Data
Integration and Data
Processing
The Contract Administration Checklist
Contract Update Checklist
CONTRACTSCHEDULE EVENGINE
 Project Scheduler Verifies Contractor Schedule Status and Forecast
To Completion (Use Audit Filters for Compliance to CPM Rules)
 Project Quantity Surveyor Verifies Materials Placed and To
Complete and Corresponding % C
 Schedule, Units of Work and Material Placement EVENGINE data
import and update
 Add Variations Approved and Not Approved As Cost Trend
 Run Earned Value and Earned Schedule Based Reports and Graphs
 Undertake Data Performance Analysis and Report To Project
Management Team
 Combined Review With Contractor and If Necessary Replan and
Resubmit Claim
 Issue Certificate of Payment
 Prepare Data for Monthly Dash Board Report
Contract Administration – Representative Cost Reports
Project Summary Report – Earned Value & Schedule Metrics, Indicators and Predictors
COST
PLANSCHEDULE EVENGINE
Generate The Project Summary
Report the basis of all Earned
Value and Schedule Reporting
Contract Administration – Representative Reports
COST
PLANSCHEDULE EVENGINE
Combined Histogram S-Curve Metrics
BAC Includes
Approved
Variations
EAC Includes
Pending
Variations
Undertake Performance Analysis
Graphically EV versus PV
Contract Administration – Representative Cost Reports
Cost & Schedule Variance Indicators
COST
PLANSCHEDULE EVENGINE
CV = EV- AC
Pending
Variations
SV(t) = ES –AT
Schedule
Variance in Days
SV = EV – PV
Schedule
Variance By Cost
Note:
SV at Completion always = 0 as PV and EV = BAC
SV (t) is in Days and Represents the ES-AT
<=> than 1 in Days Where ES = Earned Schedule
and AT = Actual Time
Contract Administration – Representative Cost Reports
Cost & Schedule Performance Indices
COST
PLANSCHEDULE EVENGINE
Cost (SPI) and Earned
Schedule
(SPI(t))Performance
Indices can be used as a
Contractor Key
Performance Indicator
Note:
SPI at Completion always = 1
SPI (t) can be <=> than 1
Note: It is difficult for a
contractor to Recover
Schedule when the SPI(t)
drops below 0.95
SPI (t)
Optimistic Schedule and
Production Improvement To
be challenged in the Review
Period
SPI Consistently < 1
with a end recovery
>1 to be challenged
SPI (t)
Trend Line
Contract Administration – Representative Cost Reports
Project Status Report – Using Cost Management Reports (Mining Industry)
COST
PLANSCHEDULE EVENGINE
Project Status Report – Using Contract Performance Report - Format 2 (Government )
Cost Engineering Progress
Reports Representing Metrics
and Indicators
Government Agency Reports Representing Metrics and Indicators
Contract Administration – Representative Cost Reports
Variations & Management Reserve Drawdown
COST
PLANSCHEDULE EVENGINE
Monitor Progressive Drawdown on Management
Reserve/Contingency based on Approved and
Not Approved (Trended) Variations.
Contract Administration – Representative Schedule Reports
Schedule Tracking By Separable Portions
COST
PLANSCHEDULE EVENGINE
Monthly Performance Schedule
and Metrics Data is Captured at
CA Level = Separable Portions,
facilitates:
Schedule Variance and
Completion Variance Tracking by
Report Period
(Supplemental to the Schedule
Tracking system)
Schedule Variance
Tracking by Separable
Portions
Schedule Variance
Tracking by Finish Date
Analysis
Contract Administration – Representative Cost Reports
Certificate of Payment
COST
PLANSCHEDULE EVENGINE
Streamline the whole of the Payment
Process with Payment Certification, in
sync with Performance Measurement
and Reporting.
Agree with the Contractor on the Price
distribution against the Level 4
activities and then automate the
claims and claims approval process.
Schedule Update and Physical %C
Complete Update within EVENGINE.
Complete Payments Record
Contract Administration – Representative Productivity Reports
Productivity Analysis – Material Metrics
COST
PLANSCHEDULE EVENGINE
Use to Examine Actual Productivity Against
Planned, Look to Recovery or Improving
Productivity for Key Tracking Commodities ,
Used to Challenge Contractor Response
Capabilities
Significant Production
Upgrade To Meet
Contractors Forecast
Completion
Average
Production
Less Than
Planned
Contract Administration – Representative Productivity Reports
Trade Based Time Displacement – Metrics
COST
PLANSCHEDULE EVENGINE
Used to analyse Trade Separation and
Congestion, Possible congestion
effects on follow on Trades
Possible Areas
of Conjestion
Contract Administration – Representative Cost Reports
Consolidate Reports to a Single Usable Management Dash Board
COST
PLANSCHEDULE EVENGINE
The contract works on analysis of the
Separable Portions is marginally behind
schedule (-10 calendar days) with delays
mainly due to ground conditions in
construction Zone 8 and (-7 calendar days)
and delay in Separable Portion 4.
Acceleration measures are underway to lift
Production and bring the schedule back on
track within the Next report period. Overall
Forecast Completion remains1-Dec-2015.
Acceleration measures include additional
dewatering pumps, carry haul scrapers,
additional dozers, vibrating rollers and
dump trucks lifting productivity form 4,000
mx2 per day to 20,000 mx2 per day.
Variations
Rigorous control is being exercised to
monitor contractor scope creep and
variations attributable to out of contract
works. Current Outstanding variations
amount to $995,000 related to must
design changes to accommodate
operational requirements. A study is
initiated to look at expected cost trends
based on firming up provisional sums
amounting to $10,000,000 of work.
Copyright @ 2011. All rights reserved
Case Histories
Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
Update of Scheduling
Information also from
Photographic Evidence
and QS report
Assessment of % Complete of the Photographic
Evidence and Quantity Surveyor Report
Contractors Priced Bill Held
within EVENGINE
Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
Actual Versus Planned Metrics used to assess
Pavement Subgrade Placement Production and
assess Contractor’s Forecast for Completion.
Case Histories – Civil Construction Works
Civil Construction Works – Dash Board Example (P1)
COST
PLANSCHEDULE EVENGINE
Case Histories – Civil Construction Works
Civil Construction Works – Dash Board Example (P2)
COST
PLANSCHEDULE EVENGINE
Case Histories – Industrial Project
Heavy Industrial Project = 1.5 MTA
India
Case Histories – Industrial Project
The Master Schedule > Project Control Software Link
COST
PLANSCHEDULE EVENGINE
EVENGINE holds and maintains all current and
baseline Earned Value Units for Cost, Work and
Material (Commodity) Usage
Primary key used is the Project and Activity Unique ID
Microsoft Project maintains all of the scheduling
information: Current and Baseline
EVENGINE refreshes by report period current and
baseline schedule data
Update of Scheduling
Information also from
Photographic Evidence
and QS report
Assessment of % Complete by Photographic Evidence
and Measurement By Project Control’s Team Quantity
Surveyor
Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Project Wide Commodity Specific Time Displacement Specific % S-Curves
Commodity Time displacement Curves allows
analysis of trade separation
Identification of congestion with possible delay
effects
Report on Trade Category Progress and Schedule
To Completion
Identification of acceleration measures for early
completion for Mechanical, Piping & Electrical
Disciplines
Regression Analysis
requires a production
rate double that
presently achieved
Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Using EVENGINE Filters for Facility Specific – Time Displacement Specific % S-Curves
Details the production history and planned work
to completion by % and discipline for specific
facility
Identifies trade separation, congestion or
acceleration
Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Project Wide Commodity Specific – Concrete & Steel Productivity S-Curves & Histograms
Commodity Concrete Placement - Actual
Versus Planned
Commodity Steel Erection with S-curve in
% Completion - Actual Versus Planned
Used to assess period performance and feasibility of production
rates to completion
Other commodity curves would be related
to: Plate-work, Platforms, Hand Rail,
Mechanical Installation, Piping
Installation, Electrical Cable Tray, Cable,
Terminations, Instrument Installation
Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Contractor allocation of budgeted work for key
commodity groupings
Time phased Actual and Forecast to Completion
Quantities against baseline or target period quantities
for commodity based contracts
Data is used to set and track period actuals against
targets.
Facility Specific – Production Reports
Case Histories – High Rise Construction
13 Floor High Rise Apartment Construction– Metrics
Case Histories – High Rise Construction
High Rise Construction– Metrics
COST
PLANSCHEDULE EVENGINE
Assessment of % Complete of
the Photographic EvidenceUpdate of Scheduling
Information also from
Photographic Evidence
Contractors Priced Bill Held
within EVENGINE
Case Histories – High Rise Construction
High Rise Construction– Metrics, Indicators and Predictors
COST
PLANSCHEDULE EVENGINE
Performance Graphs AC versus
PV used to FORECAST Expected
Completion and Progress
EVENGINE Project Summary
Report used to verify QS
Certification for Payment.
Case Histories – Other Specialist Application
Litigation Case
COST
PLANSCHEDULE EVENGINE
Financial Modelling Using Discounted Cash Flow
Investment Return
Period
Business Intelligence System
COST
PLANSCHEDULE EVENGINE
Case Histories – Other Specialist Application
Cost of
Bidding
Bid Price Versus
Contractors Cost
Expected Gross
Profit if 100%
Successful
Bid Effort By
Industry Sector
Copyright @ 2011. All rights reserved
The Earned Value
Project Control Cycle
Summary
Earned Value & Schedule Project Report Cycle Summary
Schedule Cost &
%Complete
Reports
EVENGINE
Interpretation Decision &
Action
System Using EVENGINE can be simple and cost effective
Shift from 80% of
Time in Data and
Report Preparation
to 20% Data
Preparation and 80%
Interpretation and
Decision Making
Copyright @ 2011. All rights reserved
Implementation
Challenges
Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
Demonstration
Earned Value & Schedule Project Report Cycle Summary
Using EVENGINE can be simple and cost effective
Rare Earths Industrial Pant – Estimate Import
Step
1
Step
2
485 Estimate / PRICED
ITEM TASKS
Earned Value & Schedule Project Report Cycle Summary
System Using EVENGINE can be simple and cost effective
Rare Earths Industrial Pant – Basic Reports
Step
3
Earned Value & Schedule Project Report Cycle Summary
System Using EVENGINE can be simple and cost effective
Port Infrastructure – Basic Reports
1365 Estimate /
PRICED ITEM TASKS
Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
Options & Pricing
EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ STANDARD
Entry level project performance reporting system designed for those
organizations wishing to trial and evaluate the benefits gained from
the introduction of an Earned Value based project control and
reporting system. Annual Subscription £320 plus VAT
Features include:
• Standard project Metrics, Indicators and Predictors expanded to include
Revenue to undertake profit analysis to industry guidelines and best
practice.
• Extend Earned Value reporting to units of work and material usage with all
graphs/charts and report tables saved to a Microsoft Excel workbook as
sheets.
• As your analysis and reporting requirements grow to a full project, program
and portfolio management reporting, seamlessly migrate your data to the
more capable EVENGINE™ PREMIUM and EVENGINE™ PROJECT
CONTROL.
EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ PREMIUM
This is a world-class project control system developed for financial and
technical project management professionals that builds on Earned
Value basics to track, influence and deliver their projects on time and
budget. Annual Subscription £980 plus VAT
Features additional to STANDARD include:
• External estimate import and planning data integration.
• Job Cost Accounting System Accrued Actual data import.
• Progressive capture of historical data for budget tracking.
• Expanded report types, code fields, advanced filtering and roll-up options.
• Track performance by Stage/Phase, Area/Facility, User Defined Code
Fields 1 & 2.
• Productivity analysis by combined cost, work and material usage units.
• Advanced schedule tracking and forecasting features.
• Government Agency reports including CPR/Formants 1, 2,3, 4 & 5 is
supported.
EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ PROJECT CONTROL
Developed for Project Controllers, Cost Engineers, Project Managers
engaged in Engineering, Procurement, Construction Contract Management
(EPCM) Environment. Annual Subscription £1,950 plus VAT
Features additional to PREMIUM include:
• Advanced Task Tracking and Forecasting of cost, work and material usage
to completion.
• Contract Administration using Certificates of Claim and Payment.
• Visualize project cash flow and profit based on the negotiated payment
conditions.
• Track contracts and purchase orders by awarded and not awarded status.
• Track Approved and Not-approved Variations, and drawdown on
Management Reserve.
• Track commitments against planned to maintain the contract schedule.
• Supports a range of Cost Management Reports based on selected metrics
and code groupings.
• Undertake Investment Analysis, using discounted cash flow, to rank a
portfolio of projects for their best return on investment.
Copyright @ 2011. All rights reserved
EVENGINE EXPO
SPECIAL OFFER
EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ STANDARD
Become fully familiar with EVENGINE Standard project control software and deliver reports
and graphs to Project Management Institute (PMI) and APM Earned Value Management
Guidelines.
One Year’s Subscription of EVENGINE Standard including a Half Day
Training Worksop Price: £384 including VAT
Venue: The Oakwood Centre, Headley Road, Woodley Berks RG5 4JZ
Date: Friday 22 November 2013 (1:00 PM)
Contact: James Sykes 07815875606
Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
http://www.evengine.net/
For Trial & Purchase

More Related Content

What's hot

Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
Kishan Solankimbaccepmp
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
Anand Bobade
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
Saad Merie
 
Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management Serdar Temiz
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
Hisham Ali,PMP
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
Mohamed Abdalla
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
johnkirth1898
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
Anand Bobade
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
NAVNEET KUMAR JHA
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
Water Design-Build Council
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
McLachlan Lister Pty Limited
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
JustAcademy
 
Project management
Project managementProject management
Project management
Al Amin Neaz Ahmed
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
tltiede
 

What's hot (20)

Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Project Control
Project ControlProject Control
Project Control
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Project management
Project managementProject management
Project management
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 

Similar to Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat

ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
Project Controls Expo
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016
khaja jeelani
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef samNermeen gerges
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
Vengadesh Vengadesh
 
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERRESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
Shafeek Nazar
 
N.V.VAIDYA-05-06-2016
N.V.VAIDYA-05-06-2016N.V.VAIDYA-05-06-2016
N.V.VAIDYA-05-06-2016NITIN VAIDYA
 
Spec
SpecSpec
A Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction IndustryA Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction Industry
IRJET Journal
 
Mechanical engineer 8 years projects
Mechanical engineer  8 years projectsMechanical engineer  8 years projects
Mechanical engineer 8 years projects
Rakin Karunan
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentation
Giselle Duran
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 
M&R of Project
M&R of ProjectM&R of Project
M&R of Project
VISHALRAJ572726
 
PETER CRAMER CV April 2016
PETER CRAMER CV April 2016PETER CRAMER CV April 2016
PETER CRAMER CV April 2016Peter Cramer
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
Jerry Sakala
 
Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016Saad Alkhathami
 

Similar to Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat (20)

hisham ibrahim CV
hisham ibrahim CVhisham ibrahim CV
hisham ibrahim CV
 
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
CV_Cost Engineer
CV_Cost EngineerCV_Cost Engineer
CV_Cost Engineer
 
Resume-Aero
Resume-AeroResume-Aero
Resume-Aero
 
Shahzad Sikandaruk
Shahzad SikandarukShahzad Sikandaruk
Shahzad Sikandaruk
 
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERRESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
 
N.V.VAIDYA-05-06-2016
N.V.VAIDYA-05-06-2016N.V.VAIDYA-05-06-2016
N.V.VAIDYA-05-06-2016
 
Spec
SpecSpec
Spec
 
A Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction IndustryA Contract Bidding Process in Construction Industry
A Contract Bidding Process in Construction Industry
 
Mechanical engineer 8 years projects
Mechanical engineer  8 years projectsMechanical engineer  8 years projects
Mechanical engineer 8 years projects
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentation
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
M&R of Project
M&R of ProjectM&R of Project
M&R of Project
 
sp - Copy
sp - Copysp - Copy
sp - Copy
 
PETER CRAMER CV April 2016
PETER CRAMER CV April 2016PETER CRAMER CV April 2016
PETER CRAMER CV April 2016
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
 
Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
Project Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
Sebastiano Panichella
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Access Innovations, Inc.
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Sebastiano Panichella
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
faizulhassanfaiz1670
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
OWASP Beja
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
IP ServerOne
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
Access Innovations, Inc.
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Orkestra
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
Faculty of Medicine And Health Sciences
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
eCommerce Institute
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Sebastiano Panichella
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
khadija278284
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
OECD Directorate for Financial and Enterprise Affairs
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Matjaž Lipuš
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
Howard Spence
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
Vladimir Samoylov
 

Recently uploaded (16)

International Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software TestingInternational Workshop on Artificial Intelligence in Software Testing
International Workshop on Artificial Intelligence in Software Testing
 
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdfSupercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
Supercharge your AI - SSP Industry Breakout Session 2024-v2_1.pdf
 
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...Doctoral Symposium at the 17th IEEE International Conference on Software Test...
Doctoral Symposium at the 17th IEEE International Conference on Software Test...
 
Media as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern EraMedia as a Mind Controlling Strategy In Old and Modern Era
Media as a Mind Controlling Strategy In Old and Modern Era
 
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
0x01 - Newton's Third Law:  Static vs. Dynamic Abusers0x01 - Newton's Third Law:  Static vs. Dynamic Abusers
0x01 - Newton's Third Law: Static vs. Dynamic Abusers
 
Acorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutesAcorn Recovery: Restore IT infra within minutes
Acorn Recovery: Restore IT infra within minutes
 
Eureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 PresentationEureka, I found it! - Special Libraries Association 2021 Presentation
Eureka, I found it! - Special Libraries Association 2021 Presentation
 
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...
 
Obesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditionsObesity causes and management and associated medical conditions
Obesity causes and management and associated medical conditions
 
María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024María Carolina Martínez - eCommerce Day Colombia 2024
María Carolina Martínez - eCommerce Day Colombia 2024
 
Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...Announcement of 18th IEEE International Conference on Software Testing, Verif...
Announcement of 18th IEEE International Conference on Software Testing, Verif...
 
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdfBonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
Bonzo subscription_hjjjjjjjj5hhhhhhh_2024.pdf
 
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
Competition and Regulation in Professional Services – KLEINER – June 2024 OEC...
 
Bitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXOBitcoin Lightning wallet and tic-tac-toe game XOXO
Bitcoin Lightning wallet and tic-tac-toe game XOXO
 
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptxsomanykidsbutsofewfathers-140705000023-phpapp02.pptx
somanykidsbutsofewfathers-140705000023-phpapp02.pptx
 
Getting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control TowerGetting started with Amazon Bedrock Studio and Control Tower
Getting started with Amazon Bedrock Studio and Control Tower
 

Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat

  • 1. Copyright @ 2011. All rights reserved From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle Project Controls Expo – 13th Nov 2013 Twickenham Stadium, London
  • 2. Copyright @ 2011. All rights reserved About the Speaker Roland Horat, Managing Director of Supertech Project Management (Australia) Pty Ltd. an international project management consulting company. Roland is a specialist in Earned Value (EVPM) Based Project Management and Control systems. Roland’s company are the developers of the EVENGINE range of Earned Value based project control and reporting software. The EVENGINE Project Control software is showcased at this Expo.
  • 3. Copyright @ 2011. All rights reserved The Earned Value Project Control Cycle Overview
  • 4. The Cycle Overview - Data and Software CASH FLOW PRODUCTIVITY Contractor’s PRICE Contractor’s Schedule COST PLAN SCHEDULE CASH FLOW PRODUCTIVITY ANALYSIS EARNED VALUE PERFORMANCE REPORTS The Cost Plan The Bid Evaluation And Award The Contract Administration Contractor’s PRICE Contractor’s Schedule Contractor’s PRICE Contractor’s Schedule Contract PRICE Contractor’s Schedule
  • 5. Copyright @ 2011. All rights reserved The Cost Plan
  • 6. The Cost Plan - Work Breakdown Structure What is a Cost Plan ? Cost Plan is the Estimate for the project based on the Scope of Work Measured Trade Elements The Cost Plan has a Cost Work Breakdown Structure (CWBS) To Mirror The Project Scope of Work. COST PLAN Typical CWBS for an Industrial/Infrastructure Project:  Level 1 - The Project  Level 2 - Phase/Stage - Separable Portions  Level 3 - Area /Facility – Construction Zones  Level 4 - Resource - Trade Based Activities  Level 5 - Resource Trade Based Elements - Units of Measure and Pricing  The Estimate Outline Structure is then generally mirrored within the corresponding schedule.
  • 7. The Cost Plan - Structure Example  L1 - THE PROJECT  L2 – KEY CONTROL MILESTONES  L2 - SEPARABLE PORTIONS (SP1 – 5)  L3 - CONSTRUCTION ZONE C7 (SP5) o L4 - PRELIMINARIES o L4 - DEMOLITION o L4 - CIVIL ROAD WORKS o L4 – SERVICES & FINISHES o L4 – CONCRETE WORKS  L5 - 50mm thick blinding concrete - mx2  L5 - Concrete to protection barriers - mx2  L5 - Formwork to edge of protection barriers - mx2  L5 - Reinforcement to protection barries - 100 kg/m3 - t  L5 - 100mm compressible foam to pylons - mx2  L5 - Impact attenuator at protection barriers - No COST PLAN Representative CWBS Outline for an Infrastructure Project
  • 8. The Cost Plan - Structure Example Infrastructure Level 5 Trade Element Based Estimate COST PLAN L5 - Trade Category Estimate Element L3 - Construction ZoneL2 - Separable Portions L4 - Resource/Trade Category Estimate Line item Estimate Extract for Separable Portion 5, Construction Zone C7, Resource Trade Category Civil Road Works, Element Pavement Estimate Quantity Estimate Unit Estimate Price
  • 9. The Cost Plan - Schedule LEVEL 1 - Project LEVEL 2 - Separable Portions LEVEL 3 – Construction Zones LEVEL 4 - Resource/Trade Category LEVEL 5 - Trade Category Estimate Element Example Cost Plan Corresponding Level 1 to 5 Implementation Schedule  The Schedule is Structured To facilitate Mapping to the Cost Plan SCHEDULE
  • 10. The Cost Plan - Schedule to Cost Plan Mapping Schedule and Cost Data Mapped, Imported & Maintained Within EVENGINE System COST PLANSCHEDULE EVENGIE L1 – The project Primary Mapping Key UID Early Start and Finish Dates Late Start and Finish Dates Baseline Start and Finish Dates L4 Resource/Trade Category L3 Construction Zone L2 Separable Portions L5 - Estimate Element Line item BAC2 = Budget At Completion 2 = Control Budget BAC = Budget At Completion = Contract Value EAC = Estimate At Completion = Contract Value with Cost Trends Covered By “Not Approved Variations” and “Contractor Other Costs” BAC Contract Value BAC2 Control Budget EAC Contract With Trends Estimate Extract for Separable Portion 5, Construction Zone C7, Resource Trade Category Civil Road Works, Element Pavement
  • 11. The Cost Plan – Earned Value Based Reports Benefits  Used to Estimate Expected Preliminary Costs (Overhead & Profit)  Cash Flow - Expected Funding Requirements - Bank Facility - Interest  Cash Flow - Expected Phased & Staged Funds Commitments  Allocation for Funds for Risk and Inclement Weather Allowances  Allocation of Contingency Time and Funds  Identification Of Provisional Sums  Allocation of Management Reserve  Trade Based Labour Analysis - Used for Contractor Tender Selection  Productivity Analysis to Assess Contractor’s Requirement for Plant & Equipment - Used for Contractor Tender Selection  Supply Chain Management - Assess Requirement for Early Placement of Bulk Orders Time Line and Value for Novation  Data is Used to Shape the Contracting Plan The Benefits Early Integration of Cost Plan with Corresponding Implementation Schedule brings: EVENGINE
  • 12. The Cost Plan – Earned Value Based Reports and Graphs  Trade Based Resource Analysis - Productivity Analysis to Assess Contractor’s Requirement for Plant & Equipment - Used for Contractor Tender Selection EVENGINE Require a Contractor with Plant and Equipment to deliver 20,000 mx2 of pavement per month
  • 13. The Cost Plan – Earned Value Based Reports and Graphs  Cash Flow - Expected Funding Requirements - Bank Facility - Interest EVENGINE Require Monthly and Cumulative Funding to Sustain The Project – Used to establish the Bank Finance Facility
  • 14. The Cost Plan – Earned Value Based Reports and Graphs  Supply Chain Management - Assess Requirement for Early Placement of Bulk Orders Time Line and Value for Novation EVENGINE Monthly and Cumulative Requirement of Pipe Delivery over the expected contract period. Contractor supplied or free issue of material ?
  • 15. Copyright @ 2011. All rights reserved The Bid Evaluation and Award
  • 16. The Bid Evaluation and Award  The Cost Plan and Schedule forms the Basis of the Contractor’s Bid COST PLANSCHEDULE  Prequalify and Select the Bidders based on Labour, Plant and Equipment requirements and Contractor Financial Capability to service the contract.  Issue as part of the Tender Documentation The Schedule Template and Contract Bill for Pricing Corresponding the Cost Plan Contractor Provides Level 4 Early Start & Early Finish Dates Level 5 Material and Items Pricing Data Provided By QS Contractor Provides Level 5 Price & Direct Labour Hours
  • 17. The Bid Evaluation and Award  Contractor Submits Implementation Schedule To Level 4 (Minimum)  Contractor Submits Priced Bill of Quantities to QS Requirements  Cost Data is Integrated Into the EVENGINE Project Data Sheet  Cost Data is Re-Mapped to the Contractor Tender Schedule To Facilitate Comparative Tender Pricing Against Contract Plan Estimate COST PLANSCHEDULE EVENGINE
  • 18. The Bid Evaluation and Award Contractor Tender Evaluation Checklist COST PLANSCHEDULE EVENGINE FOR EACH BIDDER EVENGINE CHECK ON:  Available Construction Plant to Sustain Planned Production  Available Labour by Trade Category to Sustain Planned Production  Assessment of Variance between QS Budget and Contractor Price (Thresholds should not be more than a range of 5% -10%))  Contractor Cash Flow Versus Control Estimate (Check on Loadings)  Conformance to Schedule Requirements, CPM Rules  Productivity Check for key Commodities  Model Potential Variation Claims to Assess Impact on Schedule and Cost CONTRACT FINALIZATION:  Select Contractor on Price and Schedule Delivery.  Formalize the Contract Reporting and Progress Evaluation Process  Revised Finance Facility Based on Contract Schedule and Program
  • 19. The Bid Evaluation and Award COST PLANSCHEDULE EVENGINE Burn/Production Rate Lower Than Planned Price Higher than the Cost Plan Estimate A completion Date Later Than The Cost Plan  Assessment of Variance between QS Budget and Contractor Price Cash Flow Design & Mobilization Period Longer than Planned
  • 20. The Bid Evaluation and Award COST PLANSCHEDULE EVENGINE  Productivity Check for key Commodities  Available Labour by Trade Category to Sustain Planned Production Multiple Peaks indicating additional crews for set periods Multiple Peaks indicating additional crews for set periods One Crew Average Production Production Gap
  • 21. The Bid Evaluation and Award COST PLANSCHEDULE EVENGINE  Productivity Rate Check for key Commodities Variable Cost Rate for Pavement Per mx2 Variable Work Hour Rate Per Pavement mx2 Evaluate Cost per Units of Quantity over the Execution Period and Compare Against Expected Expected Hour Rate Per Pavement Type mx2 Expected Cost Rate for Pavement Per mx2 Evaluate Productivity Work (Hrs) per Units of Quantity over the Execution Period and Compare Against Industry Published Constants
  • 22. Copyright @ 2011. All rights reserved The Contract Administration Cycle
  • 23. The Contract Administration COST PLANSCHEDULE EVENGINE The Fortnightly Report Cycle (Recommended) Project Controls Schedule Verification Possible Advice on Replanning Mid-Month Report With Earned Value and Schedule Analysis Project Controls Schedule & Claim Verification Monthly Report with Earned Value and Schedule Analysis Variations, Certificate of Payment Possible Advice on Replanning and Claim Resubmission Mid Month Contractor Schedule Update EVENGINE Data Integration and Data Processing End of Month Contractor Schedule Update End of Month Contractor Claim EVENGINE Data Integration and Data Processing
  • 24. The Contract Administration Checklist Contract Update Checklist CONTRACTSCHEDULE EVENGINE  Project Scheduler Verifies Contractor Schedule Status and Forecast To Completion (Use Audit Filters for Compliance to CPM Rules)  Project Quantity Surveyor Verifies Materials Placed and To Complete and Corresponding % C  Schedule, Units of Work and Material Placement EVENGINE data import and update  Add Variations Approved and Not Approved As Cost Trend  Run Earned Value and Earned Schedule Based Reports and Graphs  Undertake Data Performance Analysis and Report To Project Management Team  Combined Review With Contractor and If Necessary Replan and Resubmit Claim  Issue Certificate of Payment  Prepare Data for Monthly Dash Board Report
  • 25. Contract Administration – Representative Cost Reports Project Summary Report – Earned Value & Schedule Metrics, Indicators and Predictors COST PLANSCHEDULE EVENGINE Generate The Project Summary Report the basis of all Earned Value and Schedule Reporting
  • 26. Contract Administration – Representative Reports COST PLANSCHEDULE EVENGINE Combined Histogram S-Curve Metrics BAC Includes Approved Variations EAC Includes Pending Variations Undertake Performance Analysis Graphically EV versus PV
  • 27. Contract Administration – Representative Cost Reports Cost & Schedule Variance Indicators COST PLANSCHEDULE EVENGINE CV = EV- AC Pending Variations SV(t) = ES –AT Schedule Variance in Days SV = EV – PV Schedule Variance By Cost Note: SV at Completion always = 0 as PV and EV = BAC SV (t) is in Days and Represents the ES-AT <=> than 1 in Days Where ES = Earned Schedule and AT = Actual Time
  • 28. Contract Administration – Representative Cost Reports Cost & Schedule Performance Indices COST PLANSCHEDULE EVENGINE Cost (SPI) and Earned Schedule (SPI(t))Performance Indices can be used as a Contractor Key Performance Indicator Note: SPI at Completion always = 1 SPI (t) can be <=> than 1 Note: It is difficult for a contractor to Recover Schedule when the SPI(t) drops below 0.95 SPI (t) Optimistic Schedule and Production Improvement To be challenged in the Review Period SPI Consistently < 1 with a end recovery >1 to be challenged SPI (t) Trend Line
  • 29. Contract Administration – Representative Cost Reports Project Status Report – Using Cost Management Reports (Mining Industry) COST PLANSCHEDULE EVENGINE Project Status Report – Using Contract Performance Report - Format 2 (Government ) Cost Engineering Progress Reports Representing Metrics and Indicators Government Agency Reports Representing Metrics and Indicators
  • 30. Contract Administration – Representative Cost Reports Variations & Management Reserve Drawdown COST PLANSCHEDULE EVENGINE Monitor Progressive Drawdown on Management Reserve/Contingency based on Approved and Not Approved (Trended) Variations.
  • 31. Contract Administration – Representative Schedule Reports Schedule Tracking By Separable Portions COST PLANSCHEDULE EVENGINE Monthly Performance Schedule and Metrics Data is Captured at CA Level = Separable Portions, facilitates: Schedule Variance and Completion Variance Tracking by Report Period (Supplemental to the Schedule Tracking system) Schedule Variance Tracking by Separable Portions Schedule Variance Tracking by Finish Date Analysis
  • 32. Contract Administration – Representative Cost Reports Certificate of Payment COST PLANSCHEDULE EVENGINE Streamline the whole of the Payment Process with Payment Certification, in sync with Performance Measurement and Reporting. Agree with the Contractor on the Price distribution against the Level 4 activities and then automate the claims and claims approval process. Schedule Update and Physical %C Complete Update within EVENGINE. Complete Payments Record
  • 33. Contract Administration – Representative Productivity Reports Productivity Analysis – Material Metrics COST PLANSCHEDULE EVENGINE Use to Examine Actual Productivity Against Planned, Look to Recovery or Improving Productivity for Key Tracking Commodities , Used to Challenge Contractor Response Capabilities Significant Production Upgrade To Meet Contractors Forecast Completion Average Production Less Than Planned
  • 34. Contract Administration – Representative Productivity Reports Trade Based Time Displacement – Metrics COST PLANSCHEDULE EVENGINE Used to analyse Trade Separation and Congestion, Possible congestion effects on follow on Trades Possible Areas of Conjestion
  • 35. Contract Administration – Representative Cost Reports Consolidate Reports to a Single Usable Management Dash Board COST PLANSCHEDULE EVENGINE The contract works on analysis of the Separable Portions is marginally behind schedule (-10 calendar days) with delays mainly due to ground conditions in construction Zone 8 and (-7 calendar days) and delay in Separable Portion 4. Acceleration measures are underway to lift Production and bring the schedule back on track within the Next report period. Overall Forecast Completion remains1-Dec-2015. Acceleration measures include additional dewatering pumps, carry haul scrapers, additional dozers, vibrating rollers and dump trucks lifting productivity form 4,000 mx2 per day to 20,000 mx2 per day. Variations Rigorous control is being exercised to monitor contractor scope creep and variations attributable to out of contract works. Current Outstanding variations amount to $995,000 related to must design changes to accommodate operational requirements. A study is initiated to look at expected cost trends based on firming up provisional sums amounting to $10,000,000 of work.
  • 36. Copyright @ 2011. All rights reserved Case Histories
  • 37. Case Histories – Civil Construction Works Civil Construction Works – Production Analysis of Key Trade Elements (Commodities) COST PLANSCHEDULE EVENGINE
  • 38. Case Histories – Civil Construction Works Civil Construction Works – Production Analysis of Key Trade Elements (Commodities) COST PLANSCHEDULE EVENGINE Update of Scheduling Information also from Photographic Evidence and QS report Assessment of % Complete of the Photographic Evidence and Quantity Surveyor Report Contractors Priced Bill Held within EVENGINE
  • 39. Case Histories – Civil Construction Works Civil Construction Works – Production Analysis of Key Trade Elements (Commodities) COST PLANSCHEDULE EVENGINE Actual Versus Planned Metrics used to assess Pavement Subgrade Placement Production and assess Contractor’s Forecast for Completion.
  • 40. Case Histories – Civil Construction Works Civil Construction Works – Dash Board Example (P1) COST PLANSCHEDULE EVENGINE
  • 41. Case Histories – Civil Construction Works Civil Construction Works – Dash Board Example (P2) COST PLANSCHEDULE EVENGINE
  • 42. Case Histories – Industrial Project Heavy Industrial Project = 1.5 MTA India
  • 43. Case Histories – Industrial Project The Master Schedule > Project Control Software Link COST PLANSCHEDULE EVENGINE EVENGINE holds and maintains all current and baseline Earned Value Units for Cost, Work and Material (Commodity) Usage Primary key used is the Project and Activity Unique ID Microsoft Project maintains all of the scheduling information: Current and Baseline EVENGINE refreshes by report period current and baseline schedule data Update of Scheduling Information also from Photographic Evidence and QS report Assessment of % Complete by Photographic Evidence and Measurement By Project Control’s Team Quantity Surveyor
  • 44. Case Histories – Industrial Project COST PLANSCHEDULE EVENGINE Project Wide Commodity Specific Time Displacement Specific % S-Curves Commodity Time displacement Curves allows analysis of trade separation Identification of congestion with possible delay effects Report on Trade Category Progress and Schedule To Completion Identification of acceleration measures for early completion for Mechanical, Piping & Electrical Disciplines Regression Analysis requires a production rate double that presently achieved
  • 45. Case Histories – Industrial Project COST PLANSCHEDULE EVENGINE Using EVENGINE Filters for Facility Specific – Time Displacement Specific % S-Curves Details the production history and planned work to completion by % and discipline for specific facility Identifies trade separation, congestion or acceleration
  • 46. Case Histories – Industrial Project COST PLANSCHEDULE EVENGINE Project Wide Commodity Specific – Concrete & Steel Productivity S-Curves & Histograms Commodity Concrete Placement - Actual Versus Planned Commodity Steel Erection with S-curve in % Completion - Actual Versus Planned Used to assess period performance and feasibility of production rates to completion Other commodity curves would be related to: Plate-work, Platforms, Hand Rail, Mechanical Installation, Piping Installation, Electrical Cable Tray, Cable, Terminations, Instrument Installation
  • 47. Case Histories – Industrial Project COST PLANSCHEDULE EVENGINE Contractor allocation of budgeted work for key commodity groupings Time phased Actual and Forecast to Completion Quantities against baseline or target period quantities for commodity based contracts Data is used to set and track period actuals against targets. Facility Specific – Production Reports
  • 48. Case Histories – High Rise Construction 13 Floor High Rise Apartment Construction– Metrics
  • 49. Case Histories – High Rise Construction High Rise Construction– Metrics COST PLANSCHEDULE EVENGINE Assessment of % Complete of the Photographic EvidenceUpdate of Scheduling Information also from Photographic Evidence Contractors Priced Bill Held within EVENGINE
  • 50. Case Histories – High Rise Construction High Rise Construction– Metrics, Indicators and Predictors COST PLANSCHEDULE EVENGINE Performance Graphs AC versus PV used to FORECAST Expected Completion and Progress EVENGINE Project Summary Report used to verify QS Certification for Payment.
  • 51. Case Histories – Other Specialist Application Litigation Case COST PLANSCHEDULE EVENGINE Financial Modelling Using Discounted Cash Flow Investment Return Period
  • 52. Business Intelligence System COST PLANSCHEDULE EVENGINE Case Histories – Other Specialist Application Cost of Bidding Bid Price Versus Contractors Cost Expected Gross Profit if 100% Successful Bid Effort By Industry Sector
  • 53. Copyright @ 2011. All rights reserved The Earned Value Project Control Cycle Summary
  • 54. Earned Value & Schedule Project Report Cycle Summary Schedule Cost & %Complete Reports EVENGINE Interpretation Decision & Action System Using EVENGINE can be simple and cost effective Shift from 80% of Time in Data and Report Preparation to 20% Data Preparation and 80% Interpretation and Decision Making
  • 55. Copyright @ 2011. All rights reserved Implementation Challenges
  • 56. Copyright @ 2011. All rights reserved EVENGINE Project Control Software Demonstration
  • 57. Earned Value & Schedule Project Report Cycle Summary Using EVENGINE can be simple and cost effective Rare Earths Industrial Pant – Estimate Import Step 1 Step 2 485 Estimate / PRICED ITEM TASKS
  • 58. Earned Value & Schedule Project Report Cycle Summary System Using EVENGINE can be simple and cost effective Rare Earths Industrial Pant – Basic Reports Step 3
  • 59. Earned Value & Schedule Project Report Cycle Summary System Using EVENGINE can be simple and cost effective Port Infrastructure – Basic Reports 1365 Estimate / PRICED ITEM TASKS
  • 60. Copyright @ 2011. All rights reserved EVENGINE Project Control Software Options & Pricing
  • 61. EVENGINE SOFTWARE OPTIONS AND PRICING EVENGINE™ STANDARD Entry level project performance reporting system designed for those organizations wishing to trial and evaluate the benefits gained from the introduction of an Earned Value based project control and reporting system. Annual Subscription £320 plus VAT Features include: • Standard project Metrics, Indicators and Predictors expanded to include Revenue to undertake profit analysis to industry guidelines and best practice. • Extend Earned Value reporting to units of work and material usage with all graphs/charts and report tables saved to a Microsoft Excel workbook as sheets. • As your analysis and reporting requirements grow to a full project, program and portfolio management reporting, seamlessly migrate your data to the more capable EVENGINE™ PREMIUM and EVENGINE™ PROJECT CONTROL.
  • 62. EVENGINE SOFTWARE OPTIONS AND PRICING EVENGINE™ PREMIUM This is a world-class project control system developed for financial and technical project management professionals that builds on Earned Value basics to track, influence and deliver their projects on time and budget. Annual Subscription £980 plus VAT Features additional to STANDARD include: • External estimate import and planning data integration. • Job Cost Accounting System Accrued Actual data import. • Progressive capture of historical data for budget tracking. • Expanded report types, code fields, advanced filtering and roll-up options. • Track performance by Stage/Phase, Area/Facility, User Defined Code Fields 1 & 2. • Productivity analysis by combined cost, work and material usage units. • Advanced schedule tracking and forecasting features. • Government Agency reports including CPR/Formants 1, 2,3, 4 & 5 is supported.
  • 63. EVENGINE SOFTWARE OPTIONS AND PRICING EVENGINE™ PROJECT CONTROL Developed for Project Controllers, Cost Engineers, Project Managers engaged in Engineering, Procurement, Construction Contract Management (EPCM) Environment. Annual Subscription £1,950 plus VAT Features additional to PREMIUM include: • Advanced Task Tracking and Forecasting of cost, work and material usage to completion. • Contract Administration using Certificates of Claim and Payment. • Visualize project cash flow and profit based on the negotiated payment conditions. • Track contracts and purchase orders by awarded and not awarded status. • Track Approved and Not-approved Variations, and drawdown on Management Reserve. • Track commitments against planned to maintain the contract schedule. • Supports a range of Cost Management Reports based on selected metrics and code groupings. • Undertake Investment Analysis, using discounted cash flow, to rank a portfolio of projects for their best return on investment.
  • 64. Copyright @ 2011. All rights reserved EVENGINE EXPO SPECIAL OFFER
  • 65. EVENGINE SOFTWARE OPTIONS AND PRICING EVENGINE™ STANDARD Become fully familiar with EVENGINE Standard project control software and deliver reports and graphs to Project Management Institute (PMI) and APM Earned Value Management Guidelines. One Year’s Subscription of EVENGINE Standard including a Half Day Training Worksop Price: £384 including VAT Venue: The Oakwood Centre, Headley Road, Woodley Berks RG5 4JZ Date: Friday 22 November 2013 (1:00 PM) Contact: James Sykes 07815875606
  • 66.
  • 67. Copyright @ 2011. All rights reserved EVENGINE Project Control Software http://www.evengine.net/ For Trial & Purchase