Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat
The Cost Plan - Work Breakdown Structure
What is a Cost Plan ? Cost Plan is the Estimate for the project based on the Scope of Work Measured Trade Elements
The Cost Plan has a Cost Work Breakdown Structure (CWBS) To Mirror The Project Scope of Work.
Typical CWBS for an Industrial/Infrastructure Project:
Level 1 - The Project
Level 2 - Phase/Stage - Separable Portions
Level 3 - Area /Facility – Construction Zones
Level 4 - Resource - Trade Based Activities
Level 5 - Resource Trade Based Elements - Units of Measure and Pricing
A thorough analysis of FIDIC and it implication on COnstruction industry explained in this presentation for the beginners. It has been broken down to simplified version
A thorough analysis of FIDIC and it implication on COnstruction industry explained in this presentation for the beginners. It has been broken down to simplified version
On 23 May 2012, McLachlan Lister's Anamaria Popescu made a presentation on "Extensions of Time - Avoiding the Traps or Taking Advantage of Them" in conjunction with well-known Australian law firm Holding Redlich
John Doller of Carollo Engineers discusses the procurement process as it relates to design-build projects at the American Water Works Association's ACE13 Annual Conference & Exposition.
McLachlan Lister provides a range of management consulting and project management services. These are offered either discretely or as an integrated service - you control the depth of our relationship:
Free notes on Project Scope Management,PMP Chapter 5, PMBOK, PMP Exam Preparation training
Why Manage Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope
Online PMP Training,Instructor led PMP training,PMP training online,PMP Training in USA,PMP Training in California,PMP Training in Qatar,PMP training in Saudi Arabia,PMP training in India,PMP training in Mumbai,PMP Training in Bangalore
This material is intended to provide project leaders with a foundational understanding of leading practice project management processes, activities, tools, techniques, and deliverables as prescribed the Project Management Institute (PMI).
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
ARES PRISM - Integrating Project & Portfolio Management by "Lateef Daly"- Director of Operations, Europe & Middle East for ARES PRISM, UK at Project Controls Expo 2017, Arsenal Stadium, London
On 23 May 2012, McLachlan Lister's Anamaria Popescu made a presentation on "Extensions of Time - Avoiding the Traps or Taking Advantage of Them" in conjunction with well-known Australian law firm Holding Redlich
John Doller of Carollo Engineers discusses the procurement process as it relates to design-build projects at the American Water Works Association's ACE13 Annual Conference & Exposition.
McLachlan Lister provides a range of management consulting and project management services. These are offered either discretely or as an integrated service - you control the depth of our relationship:
Free notes on Project Scope Management,PMP Chapter 5, PMBOK, PMP Exam Preparation training
Why Manage Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope
Online PMP Training,Instructor led PMP training,PMP training online,PMP Training in USA,PMP Training in California,PMP Training in Qatar,PMP training in Saudi Arabia,PMP training in India,PMP training in Mumbai,PMP Training in Bangalore
This material is intended to provide project leaders with a foundational understanding of leading practice project management processes, activities, tools, techniques, and deliverables as prescribed the Project Management Institute (PMI).
Similar to Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
ARES PRISM - Integrating Project & Portfolio Management by "Lateef Daly"- Director of Operations, Europe & Middle East for ARES PRISM, UK at Project Controls Expo 2017, Arsenal Stadium, London
Resume- Mechanical Engineer 8 Years Experience in Pipeline construction and manufacturing Industries Including support services for Construction, Manufacturing, Quality Assurance and Equipment selection, Project Deliverables as well as with good Techno commercial Acumen.
Renewable Energy Feed-in Tarriff presentationJerry Sakala
The Energy Regulation Board (ERB), with the support of the USAID Trade Hub Southern Africa (SATH) has developed the draft Renewable Energy Feed in Tariffs (REFiT) Regulatory Framework. The REFiT Regulatory Framework was developed in line with REFiT Policy of 2015 developed by the Ministry of Mines Energy and Water Development. The REFiT regulatory framework was presented to stakeholders on Tuesday 22nd September 2015.
The REFiT Regulatory framework outlines the following:
REFiT Indicative Tariffs for solar projects;
Rules and Guidelines for RE projects to be implemented under the REFiT Policy of 2015; and
Guidelines for REFiT Power Purchase Agreements, and application procedures for project developers.
These rules and guidelines are only applicable to small scale renewable energy systems as defined in the REFiT Policy of 2015.
Similar to Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat (20)
National Grids Project Controls Journey – past, present and futureProject Controls Expo
National Grids Project Controls Journey – past, present and future By, Tim Fenemore - Head of Project Controls for National Grid, UK
Sanjay Lodhia - Head of Governance & Assurance for National Grid, UK
Tony Abiad - Head of Estimating & Cost for National Grid, UK
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs - Founder and CEO for ShapeDo, Israel" at Project Controls Expo 2017, Arsenal Stadium, London
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
Managing the risk of change by "Simon White - Risk Management Consultant for Trigo White Ltd, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior Consultant for QinetiQ, UK" & "Peter Tart - Senior Consultant for QinetiQ, UK at Project Controls Expo 2017, Arsenal Stadium, London
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston - Director of Project Controls for Costain Group PLC, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Founder for Basis PM, Texas, USA" at Project Controls Expo 2017, Arsenal Stadium, London
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Director for WSP, UK" & "Danny Vaughan - Head of Metrolink for TfGM, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
Governance and the art of decision making on Crossrail by "Walter Macharg - Head of Change Control and Cost Assurance for Crossrail, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partner, UK Head of Programme & Project Controls for Arcadis, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
Governance and Assurance for Nationally Significant Infrastructure Projects by "Terri Harrington"- Sponsorship Director - Complex Infrastructure Programme (CIP) for Highways England, UK at Project Controls Expo 2017, Arsenal Stadium, London
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
A review of whether interdependency exists in effective Project Control Methods and project performance by "Michael Halliday" Director for HKA, UK at Project Controls Expo 2017, Arsenal Stadium, London
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
A Source of Project Cost Integration by "David Hurren - Technical Director for RPCuk, UK Marie Trembacki - Associate Director for Faithful+Gould, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh Bhandari - Technical Principal - Project & Programme Controls for Mott MacDonald, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen - DEO Program Management for LA Metro, Los Angeles" at Project Controls Expo 2017, Arsenal Stadium, London
This presentation, created by Syed Faiz ul Hassan, explores the profound influence of media on public perception and behavior. It delves into the evolution of media from oral traditions to modern digital and social media platforms. Key topics include the role of media in information propagation, socialization, crisis awareness, globalization, and education. The presentation also examines media influence through agenda setting, propaganda, and manipulative techniques used by advertisers and marketers. Furthermore, it highlights the impact of surveillance enabled by media technologies on personal behavior and preferences. Through this comprehensive overview, the presentation aims to shed light on how media shapes collective consciousness and public opinion.
0x01 - Newton's Third Law: Static vs. Dynamic AbusersOWASP Beja
f you offer a service on the web, odds are that someone will abuse it. Be it an API, a SaaS, a PaaS, or even a static website, someone somewhere will try to figure out a way to use it to their own needs. In this talk we'll compare measures that are effective against static attackers and how to battle a dynamic attacker who adapts to your counter-measures.
About the Speaker
===============
Diogo Sousa, Engineering Manager @ Canonical
An opinionated individual with an interest in cryptography and its intersection with secure software development.
Acorn Recovery: Restore IT infra within minutesIP ServerOne
Introducing Acorn Recovery as a Service, a simple, fast, and secure managed disaster recovery (DRaaS) by IP ServerOne. A DR solution that helps restore your IT infra within minutes.
Have you ever wondered how search works while visiting an e-commerce site, internal website, or searching through other types of online resources? Look no further than this informative session on the ways that taxonomies help end-users navigate the internet! Hear from taxonomists and other information professionals who have first-hand experience creating and working with taxonomies that aid in navigation, search, and discovery across a range of disciplines.
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Orkestra
UIIN Conference, Madrid, 27-29 May 2024
James Wilson, Orkestra and Deusto Business School
Emily Wise, Lund University
Madeline Smith, The Glasgow School of Art
This presentation by Morris Kleiner (University of Minnesota), was made during the discussion “Competition and Regulation in Professions and Occupations” held at the Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found out at oe.cd/crps.
This presentation was uploaded with the author’s consent.
Getting started with Amazon Bedrock Studio and Control Tower
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Contract Administration The Earned Value Project Control Cycle" By Roland Horat
1. Copyright @ 2011. All rights reserved
From Cost Plan To Bid Evaluation
To Contract Administration
The Earned Value Project Control Cycle
Project Controls Expo – 13th Nov 2013
Twickenham Stadium, London
2. Copyright @ 2011. All rights reserved
About the Speaker
Roland Horat, Managing Director of Supertech Project Management (Australia)
Pty Ltd. an international project management consulting company.
Roland is a specialist in Earned Value (EVPM) Based Project Management and
Control systems.
Roland’s company are the developers of the EVENGINE range of Earned Value
based project control and reporting software.
The EVENGINE Project Control software is showcased at this Expo.
3. Copyright @ 2011. All rights reserved
The Earned Value
Project Control Cycle
Overview
4. The Cycle Overview - Data and Software
CASH FLOW
PRODUCTIVITY
Contractor’s
PRICE
Contractor’s
Schedule
COST
PLAN
SCHEDULE
CASH FLOW
PRODUCTIVITY
ANALYSIS
EARNED VALUE
PERFORMANCE
REPORTS
The Cost Plan
The Bid Evaluation And Award
The Contract Administration
Contractor’s
PRICE
Contractor’s
Schedule
Contractor’s
PRICE
Contractor’s
Schedule
Contract
PRICE
Contractor’s
Schedule
6. The Cost Plan - Work Breakdown Structure
What is a Cost Plan ? Cost Plan is the Estimate for the project based on the
Scope of Work Measured Trade Elements
The Cost Plan has a Cost Work Breakdown Structure (CWBS) To Mirror The
Project Scope of Work.
COST
PLAN
Typical CWBS for an Industrial/Infrastructure Project:
Level 1 - The Project
Level 2 - Phase/Stage - Separable Portions
Level 3 - Area /Facility – Construction Zones
Level 4 - Resource - Trade Based Activities
Level 5 - Resource Trade Based Elements - Units of Measure and Pricing
The Estimate Outline Structure is then generally mirrored within the
corresponding schedule.
7. The Cost Plan - Structure Example
L1 - THE PROJECT
L2 – KEY CONTROL MILESTONES
L2 - SEPARABLE PORTIONS (SP1 – 5)
L3 - CONSTRUCTION ZONE C7 (SP5)
o L4 - PRELIMINARIES
o L4 - DEMOLITION
o L4 - CIVIL ROAD WORKS
o L4 – SERVICES & FINISHES
o L4 – CONCRETE WORKS
L5 - 50mm thick blinding concrete - mx2
L5 - Concrete to protection barriers - mx2
L5 - Formwork to edge of protection barriers - mx2
L5 - Reinforcement to protection barries - 100 kg/m3 - t
L5 - 100mm compressible foam to pylons - mx2
L5 - Impact attenuator at protection barriers - No
COST
PLAN
Representative CWBS Outline for an Infrastructure Project
8. The Cost Plan - Structure
Example Infrastructure Level 5 Trade Element Based Estimate
COST
PLAN
L5 - Trade Category
Estimate Element
L3 - Construction ZoneL2 - Separable Portions
L4 - Resource/Trade
Category Estimate Line item
Estimate Extract for Separable
Portion 5, Construction Zone C7,
Resource Trade Category Civil Road
Works, Element Pavement
Estimate Quantity
Estimate Unit
Estimate Price
9. The Cost Plan - Schedule
LEVEL 1 -
Project
LEVEL 2 - Separable
Portions
LEVEL 3 –
Construction
Zones
LEVEL 4 -
Resource/Trade Category
LEVEL 5 - Trade Category
Estimate Element
Example Cost Plan Corresponding Level 1 to 5 Implementation Schedule
The Schedule is Structured To
facilitate Mapping to the Cost Plan
SCHEDULE
10. The Cost Plan - Schedule to Cost Plan Mapping
Schedule and Cost Data Mapped, Imported & Maintained Within EVENGINE
System
COST
PLANSCHEDULE EVENGIE
L1 – The project
Primary Mapping Key UID
Early Start and
Finish Dates
Late Start and
Finish Dates
Baseline Start and
Finish Dates
L4 Resource/Trade Category
L3 Construction Zone
L2 Separable Portions
L5 - Estimate Element
Line item
BAC2 = Budget At Completion 2 = Control Budget
BAC = Budget At Completion = Contract Value
EAC = Estimate At Completion = Contract Value with Cost Trends
Covered By “Not Approved Variations” and “Contractor Other Costs”
BAC Contract Value
BAC2 Control Budget
EAC Contract With Trends
Estimate Extract for Separable
Portion 5, Construction Zone C7,
Resource Trade Category Civil Road
Works, Element Pavement
11. The Cost Plan – Earned Value Based Reports Benefits
Used to Estimate Expected Preliminary Costs (Overhead & Profit)
Cash Flow - Expected Funding Requirements - Bank Facility - Interest
Cash Flow - Expected Phased & Staged Funds Commitments
Allocation for Funds for Risk and Inclement Weather Allowances
Allocation of Contingency Time and Funds
Identification Of Provisional Sums
Allocation of Management Reserve
Trade Based Labour Analysis - Used for Contractor Tender Selection
Productivity Analysis to Assess Contractor’s Requirement for Plant &
Equipment - Used for Contractor Tender Selection
Supply Chain Management - Assess Requirement for Early Placement of
Bulk Orders Time Line and Value for Novation
Data is Used to Shape the Contracting Plan
The Benefits Early Integration of Cost Plan with Corresponding Implementation
Schedule brings:
EVENGINE
12. The Cost Plan – Earned Value Based Reports and Graphs
Trade Based Resource Analysis - Productivity Analysis to Assess Contractor’s
Requirement for Plant & Equipment - Used for Contractor Tender Selection
EVENGINE
Require a Contractor with Plant
and Equipment to deliver
20,000 mx2 of pavement per
month
13. The Cost Plan – Earned Value Based Reports and Graphs
Cash Flow - Expected Funding Requirements - Bank Facility - Interest
EVENGINE
Require Monthly and
Cumulative Funding to Sustain
The Project – Used to establish
the Bank Finance Facility
14. The Cost Plan – Earned Value Based Reports and Graphs
Supply Chain Management - Assess Requirement for Early Placement of
Bulk Orders Time Line and Value for Novation
EVENGINE
Monthly and Cumulative
Requirement of Pipe Delivery
over the expected contract
period.
Contractor supplied or free
issue of material ?
16. The Bid Evaluation and Award
The Cost Plan and Schedule forms the Basis of the Contractor’s Bid
COST
PLANSCHEDULE
Prequalify and Select the Bidders based on Labour,
Plant and Equipment requirements and Contractor
Financial Capability to service the contract.
Issue as part of the Tender Documentation The
Schedule Template and Contract Bill for Pricing
Corresponding the Cost Plan
Contractor
Provides
Level 4 Early
Start & Early
Finish Dates Level 5
Material and
Items Pricing
Data Provided
By QS
Contractor
Provides Level 5
Price & Direct
Labour Hours
17. The Bid Evaluation and Award
Contractor Submits Implementation Schedule To Level 4 (Minimum)
Contractor Submits Priced Bill of
Quantities to QS Requirements
Cost Data is Integrated Into the EVENGINE Project Data Sheet
Cost Data is Re-Mapped to the Contractor Tender Schedule To Facilitate
Comparative Tender Pricing Against Contract Plan Estimate
COST
PLANSCHEDULE EVENGINE
18. The Bid Evaluation and Award
Contractor Tender Evaluation Checklist
COST
PLANSCHEDULE EVENGINE
FOR EACH BIDDER EVENGINE CHECK ON:
Available Construction Plant to Sustain Planned Production
Available Labour by Trade Category to Sustain Planned Production
Assessment of Variance between QS Budget and Contractor Price
(Thresholds should not be more than a range of 5% -10%))
Contractor Cash Flow Versus Control Estimate (Check on Loadings)
Conformance to Schedule Requirements, CPM Rules
Productivity Check for key Commodities
Model Potential Variation Claims to Assess Impact on Schedule and
Cost
CONTRACT FINALIZATION:
Select Contractor on Price and Schedule Delivery.
Formalize the Contract Reporting and Progress Evaluation Process
Revised Finance Facility Based on Contract Schedule and Program
19. The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
Burn/Production
Rate Lower Than
Planned
Price Higher than
the Cost Plan
Estimate
A completion Date
Later Than The
Cost Plan
Assessment of Variance between QS Budget and Contractor Price Cash Flow
Design &
Mobilization Period
Longer than
Planned
20. The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
Productivity Check for key Commodities
Available Labour by Trade Category to Sustain Planned Production
Multiple Peaks
indicating
additional crews
for set periods
Multiple Peaks
indicating
additional crews
for set periods
One Crew
Average
Production
Production Gap
21. The Bid Evaluation and Award
COST
PLANSCHEDULE EVENGINE
Productivity Rate Check for key Commodities
Variable Cost Rate
for Pavement Per
mx2
Variable Work
Hour Rate Per
Pavement mx2
Evaluate Cost per Units of Quantity
over the Execution Period and
Compare Against Expected
Expected Hour
Rate Per Pavement
Type mx2
Expected Cost
Rate for Pavement
Per mx2
Evaluate Productivity Work (Hrs) per
Units of Quantity over the Execution
Period and Compare Against Industry
Published Constants
22. Copyright @ 2011. All rights reserved
The Contract
Administration Cycle
23. The Contract Administration
COST
PLANSCHEDULE EVENGINE
The Fortnightly Report Cycle (Recommended)
Project Controls
Schedule
Verification
Possible Advice
on Replanning
Mid-Month Report With
Earned Value and
Schedule Analysis
Project Controls
Schedule &
Claim
Verification
Monthly Report with
Earned Value and
Schedule Analysis
Variations, Certificate of
Payment
Possible Advice
on Replanning
and Claim
Resubmission
Mid Month
Contractor
Schedule Update
EVENGINE Data
Integration and Data
Processing
End of Month
Contractor
Schedule Update
End of Month
Contractor
Claim
EVENGINE Data
Integration and Data
Processing
24. The Contract Administration Checklist
Contract Update Checklist
CONTRACTSCHEDULE EVENGINE
Project Scheduler Verifies Contractor Schedule Status and Forecast
To Completion (Use Audit Filters for Compliance to CPM Rules)
Project Quantity Surveyor Verifies Materials Placed and To
Complete and Corresponding % C
Schedule, Units of Work and Material Placement EVENGINE data
import and update
Add Variations Approved and Not Approved As Cost Trend
Run Earned Value and Earned Schedule Based Reports and Graphs
Undertake Data Performance Analysis and Report To Project
Management Team
Combined Review With Contractor and If Necessary Replan and
Resubmit Claim
Issue Certificate of Payment
Prepare Data for Monthly Dash Board Report
25. Contract Administration – Representative Cost Reports
Project Summary Report – Earned Value & Schedule Metrics, Indicators and Predictors
COST
PLANSCHEDULE EVENGINE
Generate The Project Summary
Report the basis of all Earned
Value and Schedule Reporting
26. Contract Administration – Representative Reports
COST
PLANSCHEDULE EVENGINE
Combined Histogram S-Curve Metrics
BAC Includes
Approved
Variations
EAC Includes
Pending
Variations
Undertake Performance Analysis
Graphically EV versus PV
27. Contract Administration – Representative Cost Reports
Cost & Schedule Variance Indicators
COST
PLANSCHEDULE EVENGINE
CV = EV- AC
Pending
Variations
SV(t) = ES –AT
Schedule
Variance in Days
SV = EV – PV
Schedule
Variance By Cost
Note:
SV at Completion always = 0 as PV and EV = BAC
SV (t) is in Days and Represents the ES-AT
<=> than 1 in Days Where ES = Earned Schedule
and AT = Actual Time
28. Contract Administration – Representative Cost Reports
Cost & Schedule Performance Indices
COST
PLANSCHEDULE EVENGINE
Cost (SPI) and Earned
Schedule
(SPI(t))Performance
Indices can be used as a
Contractor Key
Performance Indicator
Note:
SPI at Completion always = 1
SPI (t) can be <=> than 1
Note: It is difficult for a
contractor to Recover
Schedule when the SPI(t)
drops below 0.95
SPI (t)
Optimistic Schedule and
Production Improvement To
be challenged in the Review
Period
SPI Consistently < 1
with a end recovery
>1 to be challenged
SPI (t)
Trend Line
29. Contract Administration – Representative Cost Reports
Project Status Report – Using Cost Management Reports (Mining Industry)
COST
PLANSCHEDULE EVENGINE
Project Status Report – Using Contract Performance Report - Format 2 (Government )
Cost Engineering Progress
Reports Representing Metrics
and Indicators
Government Agency Reports Representing Metrics and Indicators
30. Contract Administration – Representative Cost Reports
Variations & Management Reserve Drawdown
COST
PLANSCHEDULE EVENGINE
Monitor Progressive Drawdown on Management
Reserve/Contingency based on Approved and
Not Approved (Trended) Variations.
31. Contract Administration – Representative Schedule Reports
Schedule Tracking By Separable Portions
COST
PLANSCHEDULE EVENGINE
Monthly Performance Schedule
and Metrics Data is Captured at
CA Level = Separable Portions,
facilitates:
Schedule Variance and
Completion Variance Tracking by
Report Period
(Supplemental to the Schedule
Tracking system)
Schedule Variance
Tracking by Separable
Portions
Schedule Variance
Tracking by Finish Date
Analysis
32. Contract Administration – Representative Cost Reports
Certificate of Payment
COST
PLANSCHEDULE EVENGINE
Streamline the whole of the Payment
Process with Payment Certification, in
sync with Performance Measurement
and Reporting.
Agree with the Contractor on the Price
distribution against the Level 4
activities and then automate the
claims and claims approval process.
Schedule Update and Physical %C
Complete Update within EVENGINE.
Complete Payments Record
33. Contract Administration – Representative Productivity Reports
Productivity Analysis – Material Metrics
COST
PLANSCHEDULE EVENGINE
Use to Examine Actual Productivity Against
Planned, Look to Recovery or Improving
Productivity for Key Tracking Commodities ,
Used to Challenge Contractor Response
Capabilities
Significant Production
Upgrade To Meet
Contractors Forecast
Completion
Average
Production
Less Than
Planned
34. Contract Administration – Representative Productivity Reports
Trade Based Time Displacement – Metrics
COST
PLANSCHEDULE EVENGINE
Used to analyse Trade Separation and
Congestion, Possible congestion
effects on follow on Trades
Possible Areas
of Conjestion
35. Contract Administration – Representative Cost Reports
Consolidate Reports to a Single Usable Management Dash Board
COST
PLANSCHEDULE EVENGINE
The contract works on analysis of the
Separable Portions is marginally behind
schedule (-10 calendar days) with delays
mainly due to ground conditions in
construction Zone 8 and (-7 calendar days)
and delay in Separable Portion 4.
Acceleration measures are underway to lift
Production and bring the schedule back on
track within the Next report period. Overall
Forecast Completion remains1-Dec-2015.
Acceleration measures include additional
dewatering pumps, carry haul scrapers,
additional dozers, vibrating rollers and
dump trucks lifting productivity form 4,000
mx2 per day to 20,000 mx2 per day.
Variations
Rigorous control is being exercised to
monitor contractor scope creep and
variations attributable to out of contract
works. Current Outstanding variations
amount to $995,000 related to must
design changes to accommodate
operational requirements. A study is
initiated to look at expected cost trends
based on firming up provisional sums
amounting to $10,000,000 of work.
37. Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
38. Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
Update of Scheduling
Information also from
Photographic Evidence
and QS report
Assessment of % Complete of the Photographic
Evidence and Quantity Surveyor Report
Contractors Priced Bill Held
within EVENGINE
39. Case Histories – Civil Construction Works
Civil Construction Works – Production Analysis of Key Trade Elements (Commodities)
COST
PLANSCHEDULE EVENGINE
Actual Versus Planned Metrics used to assess
Pavement Subgrade Placement Production and
assess Contractor’s Forecast for Completion.
40. Case Histories – Civil Construction Works
Civil Construction Works – Dash Board Example (P1)
COST
PLANSCHEDULE EVENGINE
41. Case Histories – Civil Construction Works
Civil Construction Works – Dash Board Example (P2)
COST
PLANSCHEDULE EVENGINE
42. Case Histories – Industrial Project
Heavy Industrial Project = 1.5 MTA
India
43. Case Histories – Industrial Project
The Master Schedule > Project Control Software Link
COST
PLANSCHEDULE EVENGINE
EVENGINE holds and maintains all current and
baseline Earned Value Units for Cost, Work and
Material (Commodity) Usage
Primary key used is the Project and Activity Unique ID
Microsoft Project maintains all of the scheduling
information: Current and Baseline
EVENGINE refreshes by report period current and
baseline schedule data
Update of Scheduling
Information also from
Photographic Evidence
and QS report
Assessment of % Complete by Photographic Evidence
and Measurement By Project Control’s Team Quantity
Surveyor
44. Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Project Wide Commodity Specific Time Displacement Specific % S-Curves
Commodity Time displacement Curves allows
analysis of trade separation
Identification of congestion with possible delay
effects
Report on Trade Category Progress and Schedule
To Completion
Identification of acceleration measures for early
completion for Mechanical, Piping & Electrical
Disciplines
Regression Analysis
requires a production
rate double that
presently achieved
45. Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Using EVENGINE Filters for Facility Specific – Time Displacement Specific % S-Curves
Details the production history and planned work
to completion by % and discipline for specific
facility
Identifies trade separation, congestion or
acceleration
46. Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Project Wide Commodity Specific – Concrete & Steel Productivity S-Curves & Histograms
Commodity Concrete Placement - Actual
Versus Planned
Commodity Steel Erection with S-curve in
% Completion - Actual Versus Planned
Used to assess period performance and feasibility of production
rates to completion
Other commodity curves would be related
to: Plate-work, Platforms, Hand Rail,
Mechanical Installation, Piping
Installation, Electrical Cable Tray, Cable,
Terminations, Instrument Installation
47. Case Histories – Industrial Project
COST
PLANSCHEDULE EVENGINE
Contractor allocation of budgeted work for key
commodity groupings
Time phased Actual and Forecast to Completion
Quantities against baseline or target period quantities
for commodity based contracts
Data is used to set and track period actuals against
targets.
Facility Specific – Production Reports
48. Case Histories – High Rise Construction
13 Floor High Rise Apartment Construction– Metrics
49. Case Histories – High Rise Construction
High Rise Construction– Metrics
COST
PLANSCHEDULE EVENGINE
Assessment of % Complete of
the Photographic EvidenceUpdate of Scheduling
Information also from
Photographic Evidence
Contractors Priced Bill Held
within EVENGINE
50. Case Histories – High Rise Construction
High Rise Construction– Metrics, Indicators and Predictors
COST
PLANSCHEDULE EVENGINE
Performance Graphs AC versus
PV used to FORECAST Expected
Completion and Progress
EVENGINE Project Summary
Report used to verify QS
Certification for Payment.
51. Case Histories – Other Specialist Application
Litigation Case
COST
PLANSCHEDULE EVENGINE
Financial Modelling Using Discounted Cash Flow
Investment Return
Period
52. Business Intelligence System
COST
PLANSCHEDULE EVENGINE
Case Histories – Other Specialist Application
Cost of
Bidding
Bid Price Versus
Contractors Cost
Expected Gross
Profit if 100%
Successful
Bid Effort By
Industry Sector
53. Copyright @ 2011. All rights reserved
The Earned Value
Project Control Cycle
Summary
54. Earned Value & Schedule Project Report Cycle Summary
Schedule Cost &
%Complete
Reports
EVENGINE
Interpretation Decision &
Action
System Using EVENGINE can be simple and cost effective
Shift from 80% of
Time in Data and
Report Preparation
to 20% Data
Preparation and 80%
Interpretation and
Decision Making
56. Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
Demonstration
57. Earned Value & Schedule Project Report Cycle Summary
Using EVENGINE can be simple and cost effective
Rare Earths Industrial Pant – Estimate Import
Step
1
Step
2
485 Estimate / PRICED
ITEM TASKS
58. Earned Value & Schedule Project Report Cycle Summary
System Using EVENGINE can be simple and cost effective
Rare Earths Industrial Pant – Basic Reports
Step
3
59. Earned Value & Schedule Project Report Cycle Summary
System Using EVENGINE can be simple and cost effective
Port Infrastructure – Basic Reports
1365 Estimate /
PRICED ITEM TASKS
60. Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
Options & Pricing
61. EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ STANDARD
Entry level project performance reporting system designed for those
organizations wishing to trial and evaluate the benefits gained from
the introduction of an Earned Value based project control and
reporting system. Annual Subscription £320 plus VAT
Features include:
• Standard project Metrics, Indicators and Predictors expanded to include
Revenue to undertake profit analysis to industry guidelines and best
practice.
• Extend Earned Value reporting to units of work and material usage with all
graphs/charts and report tables saved to a Microsoft Excel workbook as
sheets.
• As your analysis and reporting requirements grow to a full project, program
and portfolio management reporting, seamlessly migrate your data to the
more capable EVENGINE™ PREMIUM and EVENGINE™ PROJECT
CONTROL.
62. EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ PREMIUM
This is a world-class project control system developed for financial and
technical project management professionals that builds on Earned
Value basics to track, influence and deliver their projects on time and
budget. Annual Subscription £980 plus VAT
Features additional to STANDARD include:
• External estimate import and planning data integration.
• Job Cost Accounting System Accrued Actual data import.
• Progressive capture of historical data for budget tracking.
• Expanded report types, code fields, advanced filtering and roll-up options.
• Track performance by Stage/Phase, Area/Facility, User Defined Code
Fields 1 & 2.
• Productivity analysis by combined cost, work and material usage units.
• Advanced schedule tracking and forecasting features.
• Government Agency reports including CPR/Formants 1, 2,3, 4 & 5 is
supported.
63. EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ PROJECT CONTROL
Developed for Project Controllers, Cost Engineers, Project Managers
engaged in Engineering, Procurement, Construction Contract Management
(EPCM) Environment. Annual Subscription £1,950 plus VAT
Features additional to PREMIUM include:
• Advanced Task Tracking and Forecasting of cost, work and material usage
to completion.
• Contract Administration using Certificates of Claim and Payment.
• Visualize project cash flow and profit based on the negotiated payment
conditions.
• Track contracts and purchase orders by awarded and not awarded status.
• Track Approved and Not-approved Variations, and drawdown on
Management Reserve.
• Track commitments against planned to maintain the contract schedule.
• Supports a range of Cost Management Reports based on selected metrics
and code groupings.
• Undertake Investment Analysis, using discounted cash flow, to rank a
portfolio of projects for their best return on investment.
65. EVENGINE SOFTWARE OPTIONS AND PRICING
EVENGINE™ STANDARD
Become fully familiar with EVENGINE Standard project control software and deliver reports
and graphs to Project Management Institute (PMI) and APM Earned Value Management
Guidelines.
One Year’s Subscription of EVENGINE Standard including a Half Day
Training Worksop Price: £384 including VAT
Venue: The Oakwood Centre, Headley Road, Woodley Berks RG5 4JZ
Date: Friday 22 November 2013 (1:00 PM)
Contact: James Sykes 07815875606
66.
67. Copyright @ 2011. All rights reserved
EVENGINE Project
Control Software
http://www.evengine.net/
For Trial & Purchase