Content
No. Topic Page
1 Introduction 1
2 Manufacturing Process 2-4
3 Advantages and disadvantages 5-6
4 Case Study 7-14
5 Reference 15
Introduction
Blockwork is construction with concrete or cement blocks that are larger than
a standard clay or concrete brick. To make them lighter and easier to work with they
have a hollow core that also improves their insulation capacity. They are available in
a variety of densities to suit different applications. Their convenience and cost
effectiveness have made them a popular alternative to clay bricks although they
require an additional finish for reasons of aesthetics and water resistance. They are
often used to build internal partition walls and retaining walls.
Block work in IBS system is interlocking concrete block that are a way to
build a strong wall without mortar. Interlocking block walls don't require a footing,
but some styles require you to set the first course in a trench to hold the bottom of the
wall in place
The Malaysia construction industry faces unique challenges in transforming
construction into a modern and efficient industry by using Industrialised Building
System . It involves prefabrication and installation of components at the construction
site. Currently the most popular type of manufacturing in Malaysia is off-site which is
situated at a significant distance from the site. The current system of IBS consists of
precast component systems, formworks systems, steel framing systems, prefabricated
timber framing systems, block work systems and innovative systems, which have
started to replace the traditional method. This research studies is to highlight the
manufacture process,advantages and disadvantages and case study of block work
systems in the Malaysian construction industry and international industry.
Manufacturing Process
Block work system(IBS) is a pre-cast component or it can be made on site using
compaction.It’s material could found easily in local. The production of these block
work include of four process which is mixing, molding, curing and cubing in the
factory.
Material used
The block is made up of a mixture of powdered portland cement, water, sand, and
gravel.The concrete mixture has a higher percentage of sand and a lower percentage
of gravel and water than the concrete mixtures .This is based on the construction
general information.This produces a dry and hard block that maintain its shape. The
block also could contain various chemicals or admixtures to decrease curing time,
increase strength or improve workability.
Mixing
1. The sand and gravel are stored outside in piles and are transferred into storage bins
in the plant by a conveyor belt as they are needed. The portland cement is stored
outside in large vertical silos to protect it from moisture.
2. As a production run starts, the required amounts of sand, gravel, and cement are
transferred by gravity or by mechanical means to a weigh batcher which measures
the proper amounts of each material.
3. The dry materials then flow into a stationary mixer where they are mixed together
for several minutes.
4. After the dry materials are blended, a small amount of water is added to the mixer.
Admixture may also be added at this time. The concrete is then mixed few
minutes.
Molding
1. The concrete mixture is moving to an inclined bucket and move to an elevated
hopper.The mixing cycle start again.
2. The concrete is conveyed to another hopper on top of block machine.The
concrete is forcing downward to the mold.
3. When the mold is full, the concrete is compacted with supplemented by air or
hydraulic pressure cylinders on the mold head.Some machines use mechanical
vibration for compaction.
4. The compacted blocks are pushed down and out of the molds onto a flat steel
pallet. The pallet and blocks are pushed out of the machine and onto a chain
conveyor. The blocks then pass under a rotating brush to removes loose
material from the top.
Curing
1. The blocks are move to an automated stacker or loader which places them in a
curing rack and move into curing klin.
2. There are 2 types of curing klin which are low-pressure steam klin which rest at
room temperature to allow them to harden slightly and steam temperature will be
raised and high-pressure steam klin which rapidly raise the temperature and
pressure and vented rapidly.
Cubing
1. This is the process where the cured block will be remove from klin and the pallets
of blocks are unstacked and placed on a chain conveyor.
2. Then, place them in order into a cube form for storage or transfer to site.
Installation Process
The block work has the same installation process as the brick work. For the
interlocking blocks, the only different is where the interlocking blocks only need a
minimum amount of mortar to combine the blocks.
1.The blocks a stack on the first layer.
2.A small amount of mortal is place in the middle and additional rebar is place at the
same time.
3.The blocks is stack on the first layer with the interlocking shape.
4.The process is repeating again and again.
ADVANTAGES
1: Blockwork constructions are durable
They can withstand severe weather and temperatures, and as long you have decent
insulation they can have a very low U value.
2: You can construct entirely on site
You can keep all the work in one area. This means that fewer journeys are required to
transport construction materials from one place to another. In this respect, brick and
block constructions are therefore much greener.
3: Finding professionals will be easy
Finding skilled workers to work on them will be very simple. And as the construction
all happens on-site, it will be quick to rectify any problems which arise as everybody
involved will be in the same place.
4: Blockwork constructions have a higher thermal mass
With all constructions it’s important that good insulation is installed. However, brick
and block is the best material in terms of its natural ability to reflect internal heat back
into the home. Lighter constructions require large amounts of insulation to be
additionally fitted to make them satisfy modern building regulations. Building with
brick and block means you’ll save energy and money without having to reduce your
indoor temperature.
5: They’re also fire resistant and block out more sound
In parts of the world which are prone to wildfires, brick and block should be the
number one form of construction because it increases the chance of a home not
burning to the ground. This is why chimneys are ordinarily constructed out of brick,
regardless what the rest of the house consists of.
The density of brick and block masonry also means you’ll have less noise pollution
invading your house from outside. It easily absorbs sound and blocks it out, especially
when you also fit cavity wall or solid wall insulation.
DISADVANTAGES
1: There’s a limit to how much insulation can be installed in a brick cavity wall
While brick and block constructions can be insulated to have one of the lowest U
values possible, there is a limit to how much can be installed between cavity walls.
Ideally the cavity shouldn’t be more than 10 cm if you don’t want to risk structural
issues.
2: Despite construction taking place in one location, it can be very slow
Masonry is a form of wet construction, meaning it needs time to fully dry out at
several intervals. Therefore building with brick and block can take longer than
building with timber and other materials.
3: In cavity construction, there is a risk of settlement cracks
Because the individual walls used for cavity walls are usually tall and thin, they can
often be prone to settlement cracks. You should therefore be very careful and have a
good attention to detail if you’re mainly using brick and block for your cavity walls.
4: Block constructions can’t take place in severe weather
If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be
laid or it will form a building that’s structurally unsound. This is because, as
mentioned above, it’s a wet form of construction and needs to dry adequately. If it
freezes, certain parts of the construction could expand and need replacing. This is why
in some parts of the world where the climate is very cold or moist, you’ll notice more
timber constructions than brick and block.
5: Block walling cavities could allow a route indoors for dampness
If too much mortar drops on the cavity ties above the dpc (damp proof course) level or
by the insulation bats, unintended bridges could form and allow damp to seep through
to the inner skin of the wall. It wouldn’t take long for this to become a big problem, so
it’s very important to be vigilant with the cleanliness of the inside of cavity walls.
Otherwise, the energy efficiency of your home would be limited from the very
beginning.
CASE STUDY (LOCAL)
SMK Bandar Enstek Secondary School
Project name: SMK Bandar Enstek
Description of project: Classroom secondary school with 11 buildings for
classrooms, labs, workshops, OKU, Admin, Canteen, Guardhouse etc.
Function of building: Education school with facilities for secondary science and art
streams and handicapped students
Location: Bandar Enstek, Negeri Sembilan
Construction date: 27 March 2013 (start) to 27 March 2015 (end)
Construction period: 24 months
Owner: Ministry of Education
Project Teams:
Project Management Consultant: NIL Management Consultancy
Architect: Syed Ahmad Ibrahim Associate Architects Sdn. Bhd.
Consulting Engineer: ATE Consult Sdn. Bhd. / Perunding Inovasi
Contractor: Dasacon Sdn. Bhd.
Type of IBS:
Manufacturer: Integrated Brickworks Sdn. Bhd.
IBS System: Loadbearing Blockwork System
IBS Products/Components: Concrete Masonry System
Classroom:
Blockwork system used to construct columns and wall panels for the classrooms.
Concrete blocks used are hollow at the centre to reduce the overall weight of the
block. The holes at the centre of the block will be filled with reinforced concrete and
rebar to
improve
its
durability and strength.
Classroom after constructed the second floor with blocks. The blocks are also mesh
with reinforcement bars to increase the tensile strength.
Laboratory:
The beginning of construction of the laboratory. The ground is filled with wet
concrete for stability and is trowelled to smoothen the surface. Concrete blocks are
then stacked at the bottom on the wet concrete.
Laboratory is constructing in midway and concrete block is stacked for the wall
panels.
Workshop:
Blockwork is also used to construct the workshop for the secondary school. Block are
stacked at the edge to build wall panels.
Workshop constructed is partially done. Block wall is left with an appealing face-
brick finish and left exposed.
CASE STUDY (INTERNATIONAL)
Oyster Grande Apartment
Project name: Oyster Grande
Description of project: Residential unit, gym, multi-purpose hall, clubhouse, garden
deck, shopping mall
Function of building: Living apartment with features and facilities for convenience
of residents
Location: Gurgaon, New Delhi, India
Construction date: 2012 (start) to 2016 (end)
Construction period: 48 months
Owner: Adani Group and M2K Group
Type of IBS: Blockwork system
Tower A:
4th floor of concrete is partially completed
Block work in progress for wall panel. The block wall will be plaster and paint to be
finished.
Tower B:
4th floor reinforcement and shuttering in progress
Blockwork in progress for wall panel and to be plaster and paint to be finished.
REFERENCE
1. http://www.yourhome.gov.au/materials/brickwork-and-blockwork
2. https://www.homebuilding.co.uk/the-best-ways-to-build-in-blockwork/
3.http://www.soundivide.com/uploads/content_file/concrete_block_ctu-n13_eng-
46.pdf
4. https://wn.com/jom_ibs__blockwork_system_
5. http://www.adanim2k.com/

More Related Content

What's hot

IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Btech report final
Btech report finalBtech report final
Btech report finalSarah Esa
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building SolutionLee Wan Xuan
 
Building services report
Building services report Building services report
Building services report Soh Shing
 
Building Service 2 Report on Tesco Extra
Building Service 2 Report on Tesco ExtraBuilding Service 2 Report on Tesco Extra
Building Service 2 Report on Tesco ExtraKellyann Hiew
 
UiTM Stadium (Building Maintenance)
UiTM Stadium (Building Maintenance)UiTM Stadium (Building Maintenance)
UiTM Stadium (Building Maintenance)Mohd. Ikhwan
 
Building Services II Assginment Report
Building Services II Assginment ReportBuilding Services II Assginment Report
Building Services II Assginment Reportashleyyeap
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
Klasifikasi dan kriteria ibs
Klasifikasi dan kriteria ibsKlasifikasi dan kriteria ibs
Klasifikasi dan kriteria ibsyelo_roses
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achahAisyah Asyikin
 
Report Istana Negara, Balairung Seri
Report Istana Negara, Balairung Seri Report Istana Negara, Balairung Seri
Report Istana Negara, Balairung Seri Wooley Shirley
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1zerospaces_
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roofMELVIN tan
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report마 이환
 

What's hot (20)

IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Btech report final
Btech report finalBtech report final
Btech report final
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
Ibs part1
Ibs part1Ibs part1
Ibs part1
 
Building services report
Building services report Building services report
Building services report
 
Building Service 2 Report on Tesco Extra
Building Service 2 Report on Tesco ExtraBuilding Service 2 Report on Tesco Extra
Building Service 2 Report on Tesco Extra
 
UiTM Stadium (Building Maintenance)
UiTM Stadium (Building Maintenance)UiTM Stadium (Building Maintenance)
UiTM Stadium (Building Maintenance)
 
Building Services II Assginment Report
Building Services II Assginment ReportBuilding Services II Assginment Report
Building Services II Assginment Report
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Klasifikasi dan kriteria ibs
Klasifikasi dan kriteria ibsKlasifikasi dan kriteria ibs
Klasifikasi dan kriteria ibs
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Report Istana Negara, Balairung Seri
Report Istana Negara, Balairung Seri Report Istana Negara, Balairung Seri
Report Istana Negara, Balairung Seri
 
ibs 304
ibs 304ibs 304
ibs 304
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roof
 
Construction technology ii report
Construction technology ii   reportConstruction technology ii   report
Construction technology ii report
 

Similar to Ctblockworksystem. report

Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides lohwenjun
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxBHARISH16
 
Behaviour of Interlocking Hollow Concrete Blocks
Behaviour of Interlocking Hollow Concrete BlocksBehaviour of Interlocking Hollow Concrete Blocks
Behaviour of Interlocking Hollow Concrete Blocksijtsrd
 
Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017   Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017 ABIR A HAPZU
 
Construction-Amit Payal
Construction-Amit PayalConstruction-Amit Payal
Construction-Amit PayalAMIT PAYAL
 
Interlocking Bricks
Interlocking BricksInterlocking Bricks
Interlocking BricksMaliha Mehr
 
Autoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksAutoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksThaju Zaman
 
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...IRJET Journal
 
5 Types of Concrete for Needs of Modern World Construction Civilverse.org
5 Types of Concrete for Needs of Modern World Construction Civilverse.org5 Types of Concrete for Needs of Modern World Construction Civilverse.org
5 Types of Concrete for Needs of Modern World Construction Civilverse.orgSHAZEBALIKHAN1
 
Auto-Claved concrete bricks(AAC) seminar ppt.
Auto-Claved concrete bricks(AAC) seminar ppt.Auto-Claved concrete bricks(AAC) seminar ppt.
Auto-Claved concrete bricks(AAC) seminar ppt.Mr. Lucky
 

Similar to Ctblockworksystem. report (20)

Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides
 
Latest ct3
Latest ct3Latest ct3
Latest ct3
 
Curing of concrete
Curing of concreteCuring of concrete
Curing of concrete
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptx
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Concrete block
Concrete blockConcrete block
Concrete block
 
Behaviour of Interlocking Hollow Concrete Blocks
Behaviour of Interlocking Hollow Concrete BlocksBehaviour of Interlocking Hollow Concrete Blocks
Behaviour of Interlocking Hollow Concrete Blocks
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 
Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017   Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017
 
Property plus articles
Property plus articlesProperty plus articles
Property plus articles
 
Construction-Amit Payal
Construction-Amit PayalConstruction-Amit Payal
Construction-Amit Payal
 
Interlocking Bricks
Interlocking BricksInterlocking Bricks
Interlocking Bricks
 
G1302044952
G1302044952G1302044952
G1302044952
 
my presentation
my presentationmy presentation
my presentation
 
Curing of concrete
Curing of concreteCuring of concrete
Curing of concrete
 
Autoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksAutoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete Blocks
 
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...
An Experimental Investigation on Light Weight Foam Cement Blocks with Quarry ...
 
5 Types of Concrete for Needs of Modern World Construction Civilverse.org
5 Types of Concrete for Needs of Modern World Construction Civilverse.org5 Types of Concrete for Needs of Modern World Construction Civilverse.org
5 Types of Concrete for Needs of Modern World Construction Civilverse.org
 
Cavity wall
Cavity wall Cavity wall
Cavity wall
 
Auto-Claved concrete bricks(AAC) seminar ppt.
Auto-Claved concrete bricks(AAC) seminar ppt.Auto-Claved concrete bricks(AAC) seminar ppt.
Auto-Claved concrete bricks(AAC) seminar ppt.
 

More from lohwenjun

current project (1).pdf
current project (1).pdfcurrent project (1).pdf
current project (1).pdflohwenjun
 
project completed.pdf
project completed.pdfproject completed.pdf
project completed.pdflohwenjun
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slideslohwenjun
 
Individual journal pdf
Individual journal pdfIndividual journal pdf
Individual journal pdflohwenjun
 
Fm assignment final report
Fm assignment final reportFm assignment final report
Fm assignment final reportlohwenjun
 
Compiled report
Compiled reportCompiled report
Compiled reportlohwenjun
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
F inal presentation slides
F inal presentation slidesF inal presentation slides
F inal presentation slideslohwenjun
 
Estimating presentation slides
Estimating presentation slidesEstimating presentation slides
Estimating presentation slideslohwenjun
 
Management science-group report
Management science-group reportManagement science-group report
Management science-group reportlohwenjun
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group reportlohwenjun
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slideslohwenjun
 
Bs final report
Bs final reportBs final report
Bs final reportlohwenjun
 
Supply chain individual assignment final
Supply chain individual assignment finalSupply chain individual assignment final
Supply chain individual assignment finallohwenjun
 
Building service-1-prsentation-slide
Building service-1-prsentation-slideBuilding service-1-prsentation-slide
Building service-1-prsentation-slidelohwenjun
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembslohwenjun
 
Maths survey (print this) (final) 1
Maths survey (print this) (final)  1Maths survey (print this) (final)  1
Maths survey (print this) (final) 1lohwenjun
 
Mathematics assignment finalll
Mathematics assignment finalllMathematics assignment finalll
Mathematics assignment finallllohwenjun
 

More from lohwenjun (20)

current project (1).pdf
current project (1).pdfcurrent project (1).pdf
current project (1).pdf
 
project completed.pdf
project completed.pdfproject completed.pdf
project completed.pdf
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
 
Individual journal pdf
Individual journal pdfIndividual journal pdf
Individual journal pdf
 
Fm assignment final report
Fm assignment final reportFm assignment final report
Fm assignment final report
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
F inal presentation slides
F inal presentation slidesF inal presentation slides
F inal presentation slides
 
Estimating presentation slides
Estimating presentation slidesEstimating presentation slides
Estimating presentation slides
 
Management science-group report
Management science-group reportManagement science-group report
Management science-group report
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group report
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slides
 
Bs final report
Bs final reportBs final report
Bs final report
 
Supply chain individual assignment final
Supply chain individual assignment finalSupply chain individual assignment final
Supply chain individual assignment final
 
Item
ItemItem
Item
 
Building service-1-prsentation-slide
Building service-1-prsentation-slideBuilding service-1-prsentation-slide
Building service-1-prsentation-slide
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembs
 
Maths survey (print this) (final) 1
Maths survey (print this) (final)  1Maths survey (print this) (final)  1
Maths survey (print this) (final) 1
 
Mathematics assignment finalll
Mathematics assignment finalllMathematics assignment finalll
Mathematics assignment finalll
 

Recently uploaded

Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 

Recently uploaded (20)

Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 

Ctblockworksystem. report

  • 1. BACHELOR OF QUANTITY SURVEYING (HONOURS) CONSTRUCTION TECHNOLOGY III (QSB2514 / BLD60304) GROUP ASSIGNMENT BLOCK WORK SYSTEM (IBS) Group Member : LOH WEN JUN 0323551 : NG CHUAN KAI 0323738 : MUHAMMAD FAREZ 0322961 TUTOR :MR CHAI VOON CHIET INTAKE :MARCH 2017 SEMESTER 3 Content
  • 2. No. Topic Page 1 Introduction 1 2 Manufacturing Process 2-4 3 Advantages and disadvantages 5-6 4 Case Study 7-14 5 Reference 15 Introduction Blockwork is construction with concrete or cement blocks that are larger than a standard clay or concrete brick. To make them lighter and easier to work with they
  • 3. have a hollow core that also improves their insulation capacity. They are available in a variety of densities to suit different applications. Their convenience and cost effectiveness have made them a popular alternative to clay bricks although they require an additional finish for reasons of aesthetics and water resistance. They are often used to build internal partition walls and retaining walls. Block work in IBS system is interlocking concrete block that are a way to build a strong wall without mortar. Interlocking block walls don't require a footing, but some styles require you to set the first course in a trench to hold the bottom of the wall in place The Malaysia construction industry faces unique challenges in transforming construction into a modern and efficient industry by using Industrialised Building System . It involves prefabrication and installation of components at the construction site. Currently the most popular type of manufacturing in Malaysia is off-site which is situated at a significant distance from the site. The current system of IBS consists of precast component systems, formworks systems, steel framing systems, prefabricated timber framing systems, block work systems and innovative systems, which have started to replace the traditional method. This research studies is to highlight the manufacture process,advantages and disadvantages and case study of block work systems in the Malaysian construction industry and international industry. Manufacturing Process Block work system(IBS) is a pre-cast component or it can be made on site using compaction.It’s material could found easily in local. The production of these block work include of four process which is mixing, molding, curing and cubing in the
  • 4. factory. Material used The block is made up of a mixture of powdered portland cement, water, sand, and gravel.The concrete mixture has a higher percentage of sand and a lower percentage of gravel and water than the concrete mixtures .This is based on the construction general information.This produces a dry and hard block that maintain its shape. The block also could contain various chemicals or admixtures to decrease curing time, increase strength or improve workability. Mixing 1. The sand and gravel are stored outside in piles and are transferred into storage bins in the plant by a conveyor belt as they are needed. The portland cement is stored outside in large vertical silos to protect it from moisture. 2. As a production run starts, the required amounts of sand, gravel, and cement are transferred by gravity or by mechanical means to a weigh batcher which measures the proper amounts of each material. 3. The dry materials then flow into a stationary mixer where they are mixed together for several minutes. 4. After the dry materials are blended, a small amount of water is added to the mixer. Admixture may also be added at this time. The concrete is then mixed few minutes.
  • 5. Molding 1. The concrete mixture is moving to an inclined bucket and move to an elevated hopper.The mixing cycle start again. 2. The concrete is conveyed to another hopper on top of block machine.The concrete is forcing downward to the mold. 3. When the mold is full, the concrete is compacted with supplemented by air or hydraulic pressure cylinders on the mold head.Some machines use mechanical vibration for compaction. 4. The compacted blocks are pushed down and out of the molds onto a flat steel pallet. The pallet and blocks are pushed out of the machine and onto a chain conveyor. The blocks then pass under a rotating brush to removes loose material from the top. Curing 1. The blocks are move to an automated stacker or loader which places them in a curing rack and move into curing klin. 2. There are 2 types of curing klin which are low-pressure steam klin which rest at room temperature to allow them to harden slightly and steam temperature will be raised and high-pressure steam klin which rapidly raise the temperature and pressure and vented rapidly. Cubing 1. This is the process where the cured block will be remove from klin and the pallets of blocks are unstacked and placed on a chain conveyor. 2. Then, place them in order into a cube form for storage or transfer to site.
  • 6. Installation Process The block work has the same installation process as the brick work. For the interlocking blocks, the only different is where the interlocking blocks only need a minimum amount of mortar to combine the blocks. 1.The blocks a stack on the first layer. 2.A small amount of mortal is place in the middle and additional rebar is place at the same time. 3.The blocks is stack on the first layer with the interlocking shape. 4.The process is repeating again and again. ADVANTAGES 1: Blockwork constructions are durable They can withstand severe weather and temperatures, and as long you have decent
  • 7. insulation they can have a very low U value. 2: You can construct entirely on site You can keep all the work in one area. This means that fewer journeys are required to transport construction materials from one place to another. In this respect, brick and block constructions are therefore much greener. 3: Finding professionals will be easy Finding skilled workers to work on them will be very simple. And as the construction all happens on-site, it will be quick to rectify any problems which arise as everybody involved will be in the same place. 4: Blockwork constructions have a higher thermal mass With all constructions it’s important that good insulation is installed. However, brick and block is the best material in terms of its natural ability to reflect internal heat back into the home. Lighter constructions require large amounts of insulation to be additionally fitted to make them satisfy modern building regulations. Building with brick and block means you’ll save energy and money without having to reduce your indoor temperature. 5: They’re also fire resistant and block out more sound In parts of the world which are prone to wildfires, brick and block should be the number one form of construction because it increases the chance of a home not burning to the ground. This is why chimneys are ordinarily constructed out of brick, regardless what the rest of the house consists of. The density of brick and block masonry also means you’ll have less noise pollution invading your house from outside. It easily absorbs sound and blocks it out, especially when you also fit cavity wall or solid wall insulation. DISADVANTAGES 1: There’s a limit to how much insulation can be installed in a brick cavity wall While brick and block constructions can be insulated to have one of the lowest U values possible, there is a limit to how much can be installed between cavity walls. Ideally the cavity shouldn’t be more than 10 cm if you don’t want to risk structural
  • 8. issues. 2: Despite construction taking place in one location, it can be very slow Masonry is a form of wet construction, meaning it needs time to fully dry out at several intervals. Therefore building with brick and block can take longer than building with timber and other materials. 3: In cavity construction, there is a risk of settlement cracks Because the individual walls used for cavity walls are usually tall and thin, they can often be prone to settlement cracks. You should therefore be very careful and have a good attention to detail if you’re mainly using brick and block for your cavity walls. 4: Block constructions can’t take place in severe weather If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be laid or it will form a building that’s structurally unsound. This is because, as mentioned above, it’s a wet form of construction and needs to dry adequately. If it freezes, certain parts of the construction could expand and need replacing. This is why in some parts of the world where the climate is very cold or moist, you’ll notice more timber constructions than brick and block. 5: Block walling cavities could allow a route indoors for dampness If too much mortar drops on the cavity ties above the dpc (damp proof course) level or by the insulation bats, unintended bridges could form and allow damp to seep through to the inner skin of the wall. It wouldn’t take long for this to become a big problem, so it’s very important to be vigilant with the cleanliness of the inside of cavity walls. Otherwise, the energy efficiency of your home would be limited from the very beginning. CASE STUDY (LOCAL)
  • 9. SMK Bandar Enstek Secondary School Project name: SMK Bandar Enstek Description of project: Classroom secondary school with 11 buildings for classrooms, labs, workshops, OKU, Admin, Canteen, Guardhouse etc. Function of building: Education school with facilities for secondary science and art streams and handicapped students Location: Bandar Enstek, Negeri Sembilan Construction date: 27 March 2013 (start) to 27 March 2015 (end) Construction period: 24 months Owner: Ministry of Education Project Teams: Project Management Consultant: NIL Management Consultancy
  • 10. Architect: Syed Ahmad Ibrahim Associate Architects Sdn. Bhd. Consulting Engineer: ATE Consult Sdn. Bhd. / Perunding Inovasi Contractor: Dasacon Sdn. Bhd. Type of IBS: Manufacturer: Integrated Brickworks Sdn. Bhd. IBS System: Loadbearing Blockwork System IBS Products/Components: Concrete Masonry System Classroom:
  • 11. Blockwork system used to construct columns and wall panels for the classrooms. Concrete blocks used are hollow at the centre to reduce the overall weight of the block. The holes at the centre of the block will be filled with reinforced concrete and rebar to improve its durability and strength.
  • 12. Classroom after constructed the second floor with blocks. The blocks are also mesh with reinforcement bars to increase the tensile strength. Laboratory:
  • 13. The beginning of construction of the laboratory. The ground is filled with wet concrete for stability and is trowelled to smoothen the surface. Concrete blocks are then stacked at the bottom on the wet concrete. Laboratory is constructing in midway and concrete block is stacked for the wall panels. Workshop: Blockwork is also used to construct the workshop for the secondary school. Block are
  • 14. stacked at the edge to build wall panels. Workshop constructed is partially done. Block wall is left with an appealing face- brick finish and left exposed. CASE STUDY (INTERNATIONAL) Oyster Grande Apartment
  • 15. Project name: Oyster Grande Description of project: Residential unit, gym, multi-purpose hall, clubhouse, garden deck, shopping mall Function of building: Living apartment with features and facilities for convenience of residents Location: Gurgaon, New Delhi, India Construction date: 2012 (start) to 2016 (end) Construction period: 48 months Owner: Adani Group and M2K Group Type of IBS: Blockwork system Tower A: 4th floor of concrete is partially completed
  • 16. Block work in progress for wall panel. The block wall will be plaster and paint to be finished. Tower B: 4th floor reinforcement and shuttering in progress
  • 17. Blockwork in progress for wall panel and to be plaster and paint to be finished. REFERENCE 1. http://www.yourhome.gov.au/materials/brickwork-and-blockwork 2. https://www.homebuilding.co.uk/the-best-ways-to-build-in-blockwork/ 3.http://www.soundivide.com/uploads/content_file/concrete_block_ctu-n13_eng- 46.pdf 4. https://wn.com/jom_ibs__blockwork_system_ 5. http://www.adanim2k.com/