SlideShare a Scribd company logo
1 of 23
BACHELOR OF QUANTITY
SURVEYING (HONS) BLD
60304
CONSTRUCTION TECHNOLOGY 3
BLOCK WORK SYSTEM
CK
MUHAMMAD FAREEZ
WEN JUN
INTRODUCTIO
N
Blockwork is construction with concrete or cement blocks that are larger than a
standard clay or concrete brick. To make them lighter and easier to work with
they have a hollow core that also improves their insulation capacity. They are
available in a variety of densities to suit different applications. Their
convenience and cost effectiveness have made them a popular alternative to
clay bricks although they require an additional finish for reasons of aesthetics
and water resistance. They are often used to build internal partition walls and
MANUFACTURING
PROCESS
CubingCuringMoldingMixing
Raw
Material
RAW
MATERIAL
GRAVEL SAND WATER PORTLAND CEMENT
Common concrete blocks
• This produces a light gray block with a fine surface texture and a high compressive strength
PORTLAND
CEMENT
VOLCANIC
CINDERS
WATER
Cinder block
• This produces a dark gray block with a medium-to-coarse surface texture, good
strength, good sound-deadening properties, and a higher thermal insulating value
than a concrete block
WATER
PORTLAND
CEMENT
CLAY SLATE
Lightweight concrete block
• A typical light-weight block weighs 22-28 lb (10.0-12.7 kg) and is used to build non-load-
bearing walls and partitions. Expanded blast furnace slag, as well as natural volcanic
materials such as pumice and scoria, are also used to make lightweight blocks.
MIXING &
MOLDING
CEMENT SILO SAND & GRAVEL
MIXING PROCESS:
1. The sand and gravel are stored outside in piles and are transferred into storage bins in the plant by a conveyor belt as they are needed. The Portland or
common cement is stored outside in large vertical silos to protect it from moisture.
2. As a production run starts, the required amounts of sand, gravel, and cement are transferred by gravity or by mechanical means to a weigh batcher which
measures the proper amounts of each material
MOLDING PROCESS:
1. The concrete mixture is moving to an inclined bucket and move to an elevated hopper.
2. The concrete is conveyed to another hopper on top of block machine. The concrete is forcing downward to the mold.
3. When the mold is full, the concrete is compacted with supplemented by air or hydraulic pressure cylinders on the mold head.
4. The compacted blocks are pushed down and out of the molds onto a flat steel pallet. The pallet and blocks are pushed out of the machine and onto a chain
conveyor. The blocks then pass under a rotating brush to removes loose material from the top.
+
BATCHING
MACHINE
(MIXING
PROCESS)
MOLDING MACHINE
(MOLDING PROCESS)
CURING &
CUBING
CURING PROCESS :
1.The pallets of blocks are conveyed to an automated stacker or loader which places them in a curing rack. Each rack holds several hundred blocks.
When a rack is full, it is rolled onto a set of rails and moved into a curing kiln
2. The kiln is an enclosed room with the capacity to hold several racks of blocks at a time. There are two basic types of curing kilns. The most
common type is a low-pressure steam kiln. In this type, the blocks are held in the kiln for one to three hours at room temperature to allow them to
harden slightly.
3. Steam is then gradually introduced to raise the temperature at a controlled rate
4. The whole curing cycle takes about 24 hours
CUBING PROCESS :
1. This is the process where the cured block will be remove from klin and the pallets of blocks are unstacked and placed on a chain conveyor.
2. Then, place them in order into a cube form for storage or transfer to site
RESULT OF CUBING PROCESS
CUBING PROCESS
CURING PROCESS
ADVANTAGES &
DISADVANTAGES
ADVANTAGES
1: Blockwork constructions are durable
• They can withstand severe weather and temperatures
2: You can construct entirely on site
• Timber constructions require lots of work to take place off site, but brick and block constructions can
keep all the work in one area. In this respect, brick and block constructions are therefore much greener.
ADVANTAGES
3: Finding professionals will be easy
• Because these constructions are popular, finding skilled workers to work on them will be simple.
4: Blockwork constructions have a higher thermal mass
• Building with brick and block can save energy and money without having to reduce your indoor
temperature.
5: They’re also fire resistant and block out more sound
• Brick and block should be the number one form of construction because it increases the chances of
resistant against fire.
• The density of brick and block masonry also will have less noise pollution invading your house from
DISADVANTAGES
1: There’s a limit to how much insulation can be installed in a brick cavity wall
• While brick and block constructions can be insulated, there is a limit to how much it can be installed between cavity walls.
Ideally the cavity shouldn’t be more than 10 cm if you don’t want to risk structural issues.
2: Despite construction taking place in one location, it can be very slow
• Masonry is a form of wet construction, it needs time to fully dry out at several intervals. Therefore building with brick and
block can take longer than building with timber and other materials.
3: In cavity construction, there is a risk of settlement cracks
• Because individual walls used for cavity walls are usually tall and thin, they can often be prone to settlement cracks.
Therefore precaution and good attention is required to detail if you’re mainly using brick and block for your cavity walls.
4: Block constructions can’t take place in severe weather
• If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be laid or it will form a building that’s
structurally unsound. This is because it is a wet form of construction and needs to dry adequately.
DISADVANTAGES
4: Block constructions can’t take place in severe weather
• If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be laid or it will form a
building that’s structurally unsound. This is because it is a wet form of construction and needs to dry adequately.
5: Block walling cavities could allow a route indoors for dampness
• If too much mortar drops on the cavity ties above the dpc (damp proof course) level, unintended bridges could
form and allow damp to seep through to the inner skin of the wall. So it’s very important to be precise with the
cleanliness of the inside of cavity walls.
CASE STUDY
LOCAL
SMK BANDAR ENSTEK
SECONDARY SCHOOL
INFORMATION
• Project name: SMK Bandar Enstek
• Description of project: Classroom secondary school with 11 buildings
for classrooms, labs, workshops, canteen, guardhouse etc.
• Function of building: Education school with facilities for secondary
science and art streams and handicapped students
• Location: Bandar Enstek, Negeri Sembilan
• Construction period: 24 months
• Owner: Ministry of Education
TYPE OF IBS
• Manufacturer: Integrated Brickworks Sdn. Bhd.
• IBS System: Loadbearing Blockwork System
• IBS Products/Components: Concrete Masonry System
CLASSROOM
• Blockwork system used to construct columns and wall panels for the
classrooms. Concrete blocks used are hollow at the centre to reduce the
overall weight of the block. The holes at the centre of the block will be filled
with reinforced concrete and rebar to improve its durability and strength.
LABORATORY
• The beginning construction of the laboratory. The ground is filled with wet
concrete for stability and is trowelled to smoothen the surface. Concrete
blocks are then stacked for the wall panel.
Workshop
• Blockwork is also used to construct the workshop for the secondary school.
Block are stacked at the edge to build wall panels. Block wall is left with an
appealing face-brick finish and left exposed.
CASE STUDY
INTERNATIONAL
OYSTER GRANDE
APARTMENT
INFORMATION
• Project name: Oyster Grande Apartment
• Description of project: Residential unit, gym, multi-purpose hall,
clubhouse, garden deck, shopping mall
• Function of building: Living apartment with features and facilities for
convenient of residents
• Location: Gurgaon, New Delhi, India
• Construction period: 48 months
• Owner: Adani Group and M2K Group
• Type of IBS: Blockwork system
TOWER A
• 4th floor of concrete is partially completed
• Block work in progress for wall panel. The block wall will be plaster and paint
to be finished
TOWER B
• 4th floor reinforcement and shuttering in progress
• Blockwork in progress for wall panel and to be plaster and paint to be
finished.

More Related Content

What's hot

Various types of Concrete Blocks used in Commercial Construction
Various types of Concrete Blocks used in Commercial ConstructionVarious types of Concrete Blocks used in Commercial Construction
Various types of Concrete Blocks used in Commercial ConstructionAsanduff Construction
 
Blocks_Specially about Cement Concrete Blocks
Blocks_Specially about Cement Concrete BlocksBlocks_Specially about Cement Concrete Blocks
Blocks_Specially about Cement Concrete Blocksnipuna_bopage
 
Building consTRUCTION
Building consTRUCTIONBuilding consTRUCTION
Building consTRUCTIONsahil saini
 
Concrete blocks and their types
Concrete blocks and their typesConcrete blocks and their types
Concrete blocks and their typesMaliha Mehr
 
Special concrete and advanced construction materials
Special concrete and advanced construction materialsSpecial concrete and advanced construction materials
Special concrete and advanced construction materialsDereje Jima
 
Tile Roofing- Materials and Techniques
Tile Roofing- Materials and TechniquesTile Roofing- Materials and Techniques
Tile Roofing- Materials and TechniquesPrasad Thanthratey
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207sharad_kadbhane
 
Autoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksAutoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksThaju Zaman
 
Special concrete in concrete technology
Special concrete in concrete technologySpecial concrete in concrete technology
Special concrete in concrete technologySunny Saha
 
Eco button- One small click one big change
Eco button- One small click one big changeEco button- One small click one big change
Eco button- One small click one big changealind tiwari
 
Auto bricks making equpments and process
Auto bricks making equpments and processAuto bricks making equpments and process
Auto bricks making equpments and processLucky Meme
 
Building Material (Concrete)
Building Material (Concrete) Building Material (Concrete)
Building Material (Concrete) Melvin Lim
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkCivil 4M
 
Interlocking Bricks
Interlocking BricksInterlocking Bricks
Interlocking BricksMaliha Mehr
 

What's hot (19)

Various types of Concrete Blocks used in Commercial Construction
Various types of Concrete Blocks used in Commercial ConstructionVarious types of Concrete Blocks used in Commercial Construction
Various types of Concrete Blocks used in Commercial Construction
 
Blocks_Specially about Cement Concrete Blocks
Blocks_Specially about Cement Concrete BlocksBlocks_Specially about Cement Concrete Blocks
Blocks_Specially about Cement Concrete Blocks
 
Building consTRUCTION
Building consTRUCTIONBuilding consTRUCTION
Building consTRUCTION
 
Bricks
BricksBricks
Bricks
 
Concrete blocks and their types
Concrete blocks and their typesConcrete blocks and their types
Concrete blocks and their types
 
Special concrete and advanced construction materials
Special concrete and advanced construction materialsSpecial concrete and advanced construction materials
Special concrete and advanced construction materials
 
Tile Roofing- Materials and Techniques
Tile Roofing- Materials and TechniquesTile Roofing- Materials and Techniques
Tile Roofing- Materials and Techniques
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207
 
Autoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete BlocksAutoclaved Aerated Concrete Blocks
Autoclaved Aerated Concrete Blocks
 
Bricks
BricksBricks
Bricks
 
Special concrete in concrete technology
Special concrete in concrete technologySpecial concrete in concrete technology
Special concrete in concrete technology
 
Eco button- One small click one big change
Eco button- One small click one big changeEco button- One small click one big change
Eco button- One small click one big change
 
Auto bricks making equpments and process
Auto bricks making equpments and processAuto bricks making equpments and process
Auto bricks making equpments and process
 
Thermoton hollow blocks
Thermoton hollow blocksThermoton hollow blocks
Thermoton hollow blocks
 
Building Material (Concrete)
Building Material (Concrete) Building Material (Concrete)
Building Material (Concrete)
 
Bricks
Bricks Bricks
Bricks
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC Blockwork
 
Bricks
BricksBricks
Bricks
 
Interlocking Bricks
Interlocking BricksInterlocking Bricks
Interlocking Bricks
 

Similar to Ct3 presentation slides

Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxBHARISH16
 
Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017   Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017 ABIR A HAPZU
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdfNithyashree594058
 
CHAPTER 01 lecture 1.pptx
CHAPTER 01 lecture 1.pptxCHAPTER 01 lecture 1.pptx
CHAPTER 01 lecture 1.pptxYohannes345717
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
 
Floors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxFloors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxAraniProbha1
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesSayedaAmrin
 
BRICKS - Construction materials and testing
BRICKS - Construction materials and testing BRICKS - Construction materials and testing
BRICKS - Construction materials and testing Sheena Marie Salvador
 
General Building Construction-Foundation walls topic 3.
General Building Construction-Foundation walls topic 3.General Building Construction-Foundation walls topic 3.
General Building Construction-Foundation walls topic 3.VICTOR A. KIPLAGAT
 

Similar to Ct3 presentation slides (20)

Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
Concrete block
Concrete blockConcrete block
Concrete block
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
KISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptxKISHORE SEMINAR (2).pptx
KISHORE SEMINAR (2).pptx
 
Special Concrete - Concrete Technology
Special Concrete - Concrete TechnologySpecial Concrete - Concrete Technology
Special Concrete - Concrete Technology
 
Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017   Civil Engineering Materiel's 2017
Civil Engineering Materiel's 2017
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
CHAPTER 01 lecture 1.pptx
CHAPTER 01 lecture 1.pptxCHAPTER 01 lecture 1.pptx
CHAPTER 01 lecture 1.pptx
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
Brick as a material
Brick as a materialBrick as a material
Brick as a material
 
Site report
Site reportSite report
Site report
 
Floors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxFloors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptx
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
BRICKS - Construction materials and testing
BRICKS - Construction materials and testing BRICKS - Construction materials and testing
BRICKS - Construction materials and testing
 
Monolithic dome ppt
Monolithic dome pptMonolithic dome ppt
Monolithic dome ppt
 
Ct3
Ct3Ct3
Ct3
 
General Building Construction-Foundation walls topic 3.
General Building Construction-Foundation walls topic 3.General Building Construction-Foundation walls topic 3.
General Building Construction-Foundation walls topic 3.
 
Basic requirements of building as a whole
Basic requirements of building as a whole Basic requirements of building as a whole
Basic requirements of building as a whole
 

More from lohwenjun

current project (1).pdf
current project (1).pdfcurrent project (1).pdf
current project (1).pdflohwenjun
 
project completed.pdf
project completed.pdfproject completed.pdf
project completed.pdflohwenjun
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slideslohwenjun
 
Individual journal pdf
Individual journal pdfIndividual journal pdf
Individual journal pdflohwenjun
 
Fm assignment final report
Fm assignment final reportFm assignment final report
Fm assignment final reportlohwenjun
 
Compiled report
Compiled reportCompiled report
Compiled reportlohwenjun
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
F inal presentation slides
F inal presentation slidesF inal presentation slides
F inal presentation slideslohwenjun
 
Estimating presentation slides
Estimating presentation slidesEstimating presentation slides
Estimating presentation slideslohwenjun
 
Management science-group report
Management science-group reportManagement science-group report
Management science-group reportlohwenjun
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group reportlohwenjun
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slideslohwenjun
 
Bs final report
Bs final reportBs final report
Bs final reportlohwenjun
 
Supply chain individual assignment final
Supply chain individual assignment finalSupply chain individual assignment final
Supply chain individual assignment finallohwenjun
 
Building service-1-prsentation-slide
Building service-1-prsentation-slideBuilding service-1-prsentation-slide
Building service-1-prsentation-slidelohwenjun
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembslohwenjun
 
Maths survey (print this) (final) 1
Maths survey (print this) (final)  1Maths survey (print this) (final)  1
Maths survey (print this) (final) 1lohwenjun
 
Mathematics assignment finalll
Mathematics assignment finalllMathematics assignment finalll
Mathematics assignment finallllohwenjun
 

More from lohwenjun (20)

current project (1).pdf
current project (1).pdfcurrent project (1).pdf
current project (1).pdf
 
project completed.pdf
project completed.pdfproject completed.pdf
project completed.pdf
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
 
Individual journal pdf
Individual journal pdfIndividual journal pdf
Individual journal pdf
 
Fm assignment final report
Fm assignment final reportFm assignment final report
Fm assignment final report
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
F inal presentation slides
F inal presentation slidesF inal presentation slides
F inal presentation slides
 
Estimating presentation slides
Estimating presentation slidesEstimating presentation slides
Estimating presentation slides
 
Management science-group report
Management science-group reportManagement science-group report
Management science-group report
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group report
 
Bs powerpoint slides
Bs powerpoint slidesBs powerpoint slides
Bs powerpoint slides
 
Bs final report
Bs final reportBs final report
Bs final report
 
Supply chain individual assignment final
Supply chain individual assignment finalSupply chain individual assignment final
Supply chain individual assignment final
 
Item
ItemItem
Item
 
Building service-1-prsentation-slide
Building service-1-prsentation-slideBuilding service-1-prsentation-slide
Building service-1-prsentation-slide
 
Energy efficientventilationsystembs
Energy efficientventilationsystembsEnergy efficientventilationsystembs
Energy efficientventilationsystembs
 
Maths survey (print this) (final) 1
Maths survey (print this) (final)  1Maths survey (print this) (final)  1
Maths survey (print this) (final) 1
 
Mathematics assignment finalll
Mathematics assignment finalllMathematics assignment finalll
Mathematics assignment finalll
 

Recently uploaded

Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 

Recently uploaded (20)

Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 

Ct3 presentation slides

  • 1. BACHELOR OF QUANTITY SURVEYING (HONS) BLD 60304 CONSTRUCTION TECHNOLOGY 3 BLOCK WORK SYSTEM CK MUHAMMAD FAREEZ WEN JUN
  • 2. INTRODUCTIO N Blockwork is construction with concrete or cement blocks that are larger than a standard clay or concrete brick. To make them lighter and easier to work with they have a hollow core that also improves their insulation capacity. They are available in a variety of densities to suit different applications. Their convenience and cost effectiveness have made them a popular alternative to clay bricks although they require an additional finish for reasons of aesthetics and water resistance. They are often used to build internal partition walls and
  • 4. RAW MATERIAL GRAVEL SAND WATER PORTLAND CEMENT Common concrete blocks • This produces a light gray block with a fine surface texture and a high compressive strength PORTLAND CEMENT VOLCANIC CINDERS WATER Cinder block • This produces a dark gray block with a medium-to-coarse surface texture, good strength, good sound-deadening properties, and a higher thermal insulating value than a concrete block WATER PORTLAND CEMENT CLAY SLATE Lightweight concrete block • A typical light-weight block weighs 22-28 lb (10.0-12.7 kg) and is used to build non-load- bearing walls and partitions. Expanded blast furnace slag, as well as natural volcanic materials such as pumice and scoria, are also used to make lightweight blocks.
  • 5. MIXING & MOLDING CEMENT SILO SAND & GRAVEL MIXING PROCESS: 1. The sand and gravel are stored outside in piles and are transferred into storage bins in the plant by a conveyor belt as they are needed. The Portland or common cement is stored outside in large vertical silos to protect it from moisture. 2. As a production run starts, the required amounts of sand, gravel, and cement are transferred by gravity or by mechanical means to a weigh batcher which measures the proper amounts of each material MOLDING PROCESS: 1. The concrete mixture is moving to an inclined bucket and move to an elevated hopper. 2. The concrete is conveyed to another hopper on top of block machine. The concrete is forcing downward to the mold. 3. When the mold is full, the concrete is compacted with supplemented by air or hydraulic pressure cylinders on the mold head. 4. The compacted blocks are pushed down and out of the molds onto a flat steel pallet. The pallet and blocks are pushed out of the machine and onto a chain conveyor. The blocks then pass under a rotating brush to removes loose material from the top. + BATCHING MACHINE (MIXING PROCESS) MOLDING MACHINE (MOLDING PROCESS)
  • 6. CURING & CUBING CURING PROCESS : 1.The pallets of blocks are conveyed to an automated stacker or loader which places them in a curing rack. Each rack holds several hundred blocks. When a rack is full, it is rolled onto a set of rails and moved into a curing kiln 2. The kiln is an enclosed room with the capacity to hold several racks of blocks at a time. There are two basic types of curing kilns. The most common type is a low-pressure steam kiln. In this type, the blocks are held in the kiln for one to three hours at room temperature to allow them to harden slightly. 3. Steam is then gradually introduced to raise the temperature at a controlled rate 4. The whole curing cycle takes about 24 hours CUBING PROCESS : 1. This is the process where the cured block will be remove from klin and the pallets of blocks are unstacked and placed on a chain conveyor. 2. Then, place them in order into a cube form for storage or transfer to site RESULT OF CUBING PROCESS CUBING PROCESS CURING PROCESS
  • 8. ADVANTAGES 1: Blockwork constructions are durable • They can withstand severe weather and temperatures 2: You can construct entirely on site • Timber constructions require lots of work to take place off site, but brick and block constructions can keep all the work in one area. In this respect, brick and block constructions are therefore much greener.
  • 9. ADVANTAGES 3: Finding professionals will be easy • Because these constructions are popular, finding skilled workers to work on them will be simple. 4: Blockwork constructions have a higher thermal mass • Building with brick and block can save energy and money without having to reduce your indoor temperature. 5: They’re also fire resistant and block out more sound • Brick and block should be the number one form of construction because it increases the chances of resistant against fire. • The density of brick and block masonry also will have less noise pollution invading your house from
  • 10. DISADVANTAGES 1: There’s a limit to how much insulation can be installed in a brick cavity wall • While brick and block constructions can be insulated, there is a limit to how much it can be installed between cavity walls. Ideally the cavity shouldn’t be more than 10 cm if you don’t want to risk structural issues. 2: Despite construction taking place in one location, it can be very slow • Masonry is a form of wet construction, it needs time to fully dry out at several intervals. Therefore building with brick and block can take longer than building with timber and other materials. 3: In cavity construction, there is a risk of settlement cracks • Because individual walls used for cavity walls are usually tall and thin, they can often be prone to settlement cracks. Therefore precaution and good attention is required to detail if you’re mainly using brick and block for your cavity walls. 4: Block constructions can’t take place in severe weather • If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be laid or it will form a building that’s structurally unsound. This is because it is a wet form of construction and needs to dry adequately.
  • 11. DISADVANTAGES 4: Block constructions can’t take place in severe weather • If it’s raining heavily or temperatures have dropped below freezing, masonry can’t be laid or it will form a building that’s structurally unsound. This is because it is a wet form of construction and needs to dry adequately. 5: Block walling cavities could allow a route indoors for dampness • If too much mortar drops on the cavity ties above the dpc (damp proof course) level, unintended bridges could form and allow damp to seep through to the inner skin of the wall. So it’s very important to be precise with the cleanliness of the inside of cavity walls.
  • 14. INFORMATION • Project name: SMK Bandar Enstek • Description of project: Classroom secondary school with 11 buildings for classrooms, labs, workshops, canteen, guardhouse etc. • Function of building: Education school with facilities for secondary science and art streams and handicapped students • Location: Bandar Enstek, Negeri Sembilan • Construction period: 24 months • Owner: Ministry of Education
  • 15. TYPE OF IBS • Manufacturer: Integrated Brickworks Sdn. Bhd. • IBS System: Loadbearing Blockwork System • IBS Products/Components: Concrete Masonry System
  • 16. CLASSROOM • Blockwork system used to construct columns and wall panels for the classrooms. Concrete blocks used are hollow at the centre to reduce the overall weight of the block. The holes at the centre of the block will be filled with reinforced concrete and rebar to improve its durability and strength.
  • 17. LABORATORY • The beginning construction of the laboratory. The ground is filled with wet concrete for stability and is trowelled to smoothen the surface. Concrete blocks are then stacked for the wall panel.
  • 18. Workshop • Blockwork is also used to construct the workshop for the secondary school. Block are stacked at the edge to build wall panels. Block wall is left with an appealing face-brick finish and left exposed.
  • 21. INFORMATION • Project name: Oyster Grande Apartment • Description of project: Residential unit, gym, multi-purpose hall, clubhouse, garden deck, shopping mall • Function of building: Living apartment with features and facilities for convenient of residents • Location: Gurgaon, New Delhi, India • Construction period: 48 months • Owner: Adani Group and M2K Group • Type of IBS: Blockwork system
  • 22. TOWER A • 4th floor of concrete is partially completed • Block work in progress for wall panel. The block wall will be plaster and paint to be finished
  • 23. TOWER B • 4th floor reinforcement and shuttering in progress • Blockwork in progress for wall panel and to be plaster and paint to be finished.