SlideShare a Scribd company logo
1 of 15
Download to read offline
Royal University of Bhutan
Jigme Namgyel Engineering College
Department of Civil Engineering & Surveying
Tutor : Phurba Tamang
Designation: Associate lecturer
Department of Civil Engineering and Surveying
SETTING OUT WORKS
MODULE: SURVEYING
Spring Semester 2020
MID-TERM REVIEW, 2017
Setting Out Works
Introduction
Setting out is a survey undertaken in order to transfer onto the site, the plans prepared as a result
of some previous survey. Here, instead of using data from the site to prepare plans, the plans and
designs prepared by the designer are transferred accurately onto the actual site. It may be
described as the fixing of well defined points in the filed showing the horizontal and vertical
positions required by the plans.
To build according to the plan, a contractor must have reference lines and points established in
the field. This involves placing of pegs or marks to define the lines and levels of work where after,
the construction proceeds according to these marks. Some factors to be considered during setting
out works are:
1. The reference lines and points should be well defined, not easily perishable, close to the work
yet out of way or actual construction operations.
2. A very high degree of accuracy should be maintained and only extremely low tolerances
should be allowed. In order to achieve this, frequent and independent checking should be
done.
3. The instrument used should be checked frequently and discrepancies if any should be
removed.
MID-TERM REVIEW, 2017
Setting Out of Buildings
Setting out of a building involves the transfer of the architect’s plan form paper onto the actual
site. The objective of setting out a building is to provide the builder with clearly defined outlines for
excavation. Two methods are generally used for setting out a building.
A. By Using a Circumscribing Rectangle
MID-TERM REVIEW, 2017
Setting Out of Buildings
A. By Using a Circumscribing Rectangle
Since stakes cannot be set at the exact corner points of a building ( if set so, these will be lost
during excavation , these are fixed at the corner of a bigger rectangle circumscribing the actual
building. Any suitable distance of the outer rectangle from the building can be chosen, but a
distance of usually 2 to 4 m is considered to be ideal. The actual procedure consist of the following
steps.
a. Preparation of the foundation trench plan showing the width of the foundation for various
walls.
b. Temporary pegs are driven at the actual corner points of the buildings.
c. Then using these pegs as reference a parallel line say AB of required length is set out at an
arbitrarily selected distance ( say 2 m ) from the actual center line.
d. A chord is stretched between the pegs A and B. At A, a line is set out perpendicular to AB
( with a tape using 3, 4. 5 method ). On this line, the position D is marked by setting a peg.
e. Set (d) is repeated at point B so as to obtain point C.
f. Having now set out the reference rectangle ABCD, the actual corners can be marked using the
sides of the reference rectangle ABCD.
g. Once all the points are staked, a chord is passed around the periphery of the rectangle and the
actual excavation lines are marked using lime.
MID-TERM REVIEW, 2017
Setting Out of Buildings
B. By Centerline Method
MID-TERM REVIEW, 2017
Setting Out of Buildings
B. By Centerline Method ( Commonly Preferred )
Procedure
a. From the plan, the centre lines of the walls are calculated. Then the centre lines of the rooms
are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are A, B, C,
D, E, F and G which are marked by pegs with nails on top.
b. The setting of the corner points is checked according to diagonals AC, BD, CF and EG.
c. During excavation, the centre points A, B, C,…. may be removed. Therefore, the centre lines are
extended and the centre points marked about 2 m away from the outer edge of excavation.
Thus, the points A1, A2, B1, B2 . . . . . are marked outside the trench. The centre lines are shown
clearly by stretching thread or rope.
d. From the plan, the width of excavation is found out and set out around the centre. The
excavation width is also marked by thread with pegs at appropriate positions.
e. The excavation width is then marked by lime or by making a furrow with a spade.
f. If the plan is much too complicated and follows a zig zag pattern, the centre pegs are kept at
suitable positions according to site conditions.
MID-TERM REVIEW, 2017
G
List of Equipment for Staking Out
• Ranging Rods
• Wooden Pegs with Nails on top
• Measuring Tape
• Thread or Rope
Ranging Rods
Wooden Pegs
Measuring Tape
Thread or Rope
MID-TERM REVIEW, 2017
G
3-4-5 Method
Note: Any Multiple of 3, 4, 5 can be used. Example: 6, 8, 10 or 12, 16, 20, etc.
MID-TERM REVIEW, 2017
G
3-4-5 Method
Source: http://auromafrenchvillaments.blogspot.com/2014/02/marking-of-excavation-pits.html
MID-TERM REVIEW, 2017
Setting Out of Buildings
Example:
Describe the procedure of setting out of a two storeyed building with 200 m thick load bearing
outer walls all around. The foundation width is 750 mm. The building is absolutely rectangular and
outside dimensions above plinth level are 12000 mm x 18000 mm. Draw the foundation plan of the
outer walls showing all the dimensions ( not to scale ). In the above plan show the positions of
different pegs required for setting out of the above building.
Solution:
The Outside Dimensions are 12000 mm x 18000 mm
Thickness of the wall: 200 mm
Center line dimensions are ( 12000 – 200 ) = 11800 mm and ( 18000 – 200 ) = 17800 mm
= 11800 mm x 17800 mm
With foundation width 750 mm, the outside dimensions of foundation wall are 12550 x 18550
Inside Dimensions are 11050 x 17050.
Here the OFFSET PEGS are used.
MID-TERM REVIEW, 2017
Setting Out of Buildings
Wall thickness 200 mm
MID-TERM REVIEW, 2017
Setting Out of Buildings
Reference line connected by Thread or Rope
Maintained at 2 m from the outer wall
MID-TERM REVIEW, 2017
Setting Out of Buildings
MID-TERM REVIEW, 2017
Setting Out of Buildings
MID-TERM REVIEW, 2017
Setting Out of Buildings
Steps:
• Mark the centerline of the longest wall on the ground by stretching a string between offset
pegs 1 – 1.
• Similarly stake strings along 2 – 2, 3 -3 and 4 – 4.
• Pegs marked as red dots in the figure are the reference pegs for all the other pegs.
• These pegs are marked at 2 m offset from all sides of the building plan. The pegs should project
25 to 50 mm above the ground level.
• The intersections are maintained at right angle using the 3:4:5 method or tri-square.
• Referring to the reference pegs ( marked red ) other temporary pegs are established ( marked
purple ).
• Once all the pegs are fixed, the lines are marked with lime.
• Once the lines are marked with the lime, the pegs are removed except for the reference pegs.

More Related Content

What's hot (20)

Contouring
ContouringContouring
Contouring
 
Levelling
LevellingLevelling
Levelling
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Lecture 1 introdcution to engineering surveying
Lecture 1 introdcution to engineering surveyingLecture 1 introdcution to engineering surveying
Lecture 1 introdcution to engineering surveying
 
Surveying i
Surveying iSurveying i
Surveying i
 
Surveying
SurveyingSurveying
Surveying
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT
 
Setting out of works
Setting out of worksSetting out of works
Setting out of works
 
Theodolite ppt in 7
Theodolite ppt in 7Theodolite ppt in 7
Theodolite ppt in 7
 
BUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptxBUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptx
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
Levelling
LevellingLevelling
Levelling
 
Setting Out Works in Surveying
Setting Out Works in SurveyingSetting Out Works in Surveying
Setting Out Works in Surveying
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
Introduction to surveying, ranging and chaining
Introduction to surveying, ranging and chainingIntroduction to surveying, ranging and chaining
Introduction to surveying, ranging and chaining
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Setting out of bridges
Setting out of bridgesSetting out of bridges
Setting out of bridges
 

Similar to Setting out of Building

SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2Nhatz Marticio
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting outLuke D'Arcy
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptxGabrielBentil1
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportSarchia Khursheed
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringAabid Ansar
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfJunaidMughal34
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)AMIT PAYAL
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communicationmichael mcewan
 
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...IRJET Journal
 

Similar to Setting out of Building (20)

SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Layout of a House Plan Foundation - Report
Layout of a House Plan Foundation - ReportLayout of a House Plan Foundation - Report
Layout of a House Plan Foundation - Report
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Unit 5
Unit 5Unit 5
Unit 5
 
Seminar
SeminarSeminar
Seminar
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Principles of building construction, information and communication
Principles of building construction, information and communicationPrinciples of building construction, information and communication
Principles of building construction, information and communication
 
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
IRJET -, How to Encourage the Students Interest to Engineering Graphics, Meth...
 

More from Phurba Tamang

Water sources and water quality parameters
Water sources and water quality parametersWater sources and water quality parameters
Water sources and water quality parametersPhurba Tamang
 
Introduction to Environmental Engineering
Introduction to Environmental EngineeringIntroduction to Environmental Engineering
Introduction to Environmental EngineeringPhurba Tamang
 
Introduction to StaadPro
Introduction to StaadProIntroduction to StaadPro
Introduction to StaadProPhurba Tamang
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveyingPhurba Tamang
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in SurveyingPhurba Tamang
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersPhurba Tamang
 
Design of Sewage Treatment Plant
Design of Sewage Treatment PlantDesign of Sewage Treatment Plant
Design of Sewage Treatment PlantPhurba Tamang
 
Introduction to Surveying
Introduction to SurveyingIntroduction to Surveying
Introduction to SurveyingPhurba Tamang
 
Engineering Mechanics Manual
Engineering Mechanics ManualEngineering Mechanics Manual
Engineering Mechanics ManualPhurba Tamang
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of FoundationPhurba Tamang
 

More from Phurba Tamang (12)

Water sources and water quality parameters
Water sources and water quality parametersWater sources and water quality parameters
Water sources and water quality parameters
 
Introduction to Environmental Engineering
Introduction to Environmental EngineeringIntroduction to Environmental Engineering
Introduction to Environmental Engineering
 
Introduction to StaadPro
Introduction to StaadProIntroduction to StaadPro
Introduction to StaadPro
 
Contouring
ContouringContouring
Contouring
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
 
Design of Sewage Treatment Plant
Design of Sewage Treatment PlantDesign of Sewage Treatment Plant
Design of Sewage Treatment Plant
 
Introduction to Surveying
Introduction to SurveyingIntroduction to Surveying
Introduction to Surveying
 
Engineering Mechanics Manual
Engineering Mechanics ManualEngineering Mechanics Manual
Engineering Mechanics Manual
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of Foundation
 
Autocad training
Autocad trainingAutocad training
Autocad training
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 

Setting out of Building

  • 1. Royal University of Bhutan Jigme Namgyel Engineering College Department of Civil Engineering & Surveying Tutor : Phurba Tamang Designation: Associate lecturer Department of Civil Engineering and Surveying SETTING OUT WORKS MODULE: SURVEYING Spring Semester 2020
  • 2. MID-TERM REVIEW, 2017 Setting Out Works Introduction Setting out is a survey undertaken in order to transfer onto the site, the plans prepared as a result of some previous survey. Here, instead of using data from the site to prepare plans, the plans and designs prepared by the designer are transferred accurately onto the actual site. It may be described as the fixing of well defined points in the filed showing the horizontal and vertical positions required by the plans. To build according to the plan, a contractor must have reference lines and points established in the field. This involves placing of pegs or marks to define the lines and levels of work where after, the construction proceeds according to these marks. Some factors to be considered during setting out works are: 1. The reference lines and points should be well defined, not easily perishable, close to the work yet out of way or actual construction operations. 2. A very high degree of accuracy should be maintained and only extremely low tolerances should be allowed. In order to achieve this, frequent and independent checking should be done. 3. The instrument used should be checked frequently and discrepancies if any should be removed.
  • 3. MID-TERM REVIEW, 2017 Setting Out of Buildings Setting out of a building involves the transfer of the architect’s plan form paper onto the actual site. The objective of setting out a building is to provide the builder with clearly defined outlines for excavation. Two methods are generally used for setting out a building. A. By Using a Circumscribing Rectangle
  • 4. MID-TERM REVIEW, 2017 Setting Out of Buildings A. By Using a Circumscribing Rectangle Since stakes cannot be set at the exact corner points of a building ( if set so, these will be lost during excavation , these are fixed at the corner of a bigger rectangle circumscribing the actual building. Any suitable distance of the outer rectangle from the building can be chosen, but a distance of usually 2 to 4 m is considered to be ideal. The actual procedure consist of the following steps. a. Preparation of the foundation trench plan showing the width of the foundation for various walls. b. Temporary pegs are driven at the actual corner points of the buildings. c. Then using these pegs as reference a parallel line say AB of required length is set out at an arbitrarily selected distance ( say 2 m ) from the actual center line. d. A chord is stretched between the pegs A and B. At A, a line is set out perpendicular to AB ( with a tape using 3, 4. 5 method ). On this line, the position D is marked by setting a peg. e. Set (d) is repeated at point B so as to obtain point C. f. Having now set out the reference rectangle ABCD, the actual corners can be marked using the sides of the reference rectangle ABCD. g. Once all the points are staked, a chord is passed around the periphery of the rectangle and the actual excavation lines are marked using lime.
  • 5. MID-TERM REVIEW, 2017 Setting Out of Buildings B. By Centerline Method
  • 6. MID-TERM REVIEW, 2017 Setting Out of Buildings B. By Centerline Method ( Commonly Preferred ) Procedure a. From the plan, the centre lines of the walls are calculated. Then the centre lines of the rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are A, B, C, D, E, F and G which are marked by pegs with nails on top. b. The setting of the corner points is checked according to diagonals AC, BD, CF and EG. c. During excavation, the centre points A, B, C,…. may be removed. Therefore, the centre lines are extended and the centre points marked about 2 m away from the outer edge of excavation. Thus, the points A1, A2, B1, B2 . . . . . are marked outside the trench. The centre lines are shown clearly by stretching thread or rope. d. From the plan, the width of excavation is found out and set out around the centre. The excavation width is also marked by thread with pegs at appropriate positions. e. The excavation width is then marked by lime or by making a furrow with a spade. f. If the plan is much too complicated and follows a zig zag pattern, the centre pegs are kept at suitable positions according to site conditions.
  • 7. MID-TERM REVIEW, 2017 G List of Equipment for Staking Out • Ranging Rods • Wooden Pegs with Nails on top • Measuring Tape • Thread or Rope Ranging Rods Wooden Pegs Measuring Tape Thread or Rope
  • 8. MID-TERM REVIEW, 2017 G 3-4-5 Method Note: Any Multiple of 3, 4, 5 can be used. Example: 6, 8, 10 or 12, 16, 20, etc.
  • 9. MID-TERM REVIEW, 2017 G 3-4-5 Method Source: http://auromafrenchvillaments.blogspot.com/2014/02/marking-of-excavation-pits.html
  • 10. MID-TERM REVIEW, 2017 Setting Out of Buildings Example: Describe the procedure of setting out of a two storeyed building with 200 m thick load bearing outer walls all around. The foundation width is 750 mm. The building is absolutely rectangular and outside dimensions above plinth level are 12000 mm x 18000 mm. Draw the foundation plan of the outer walls showing all the dimensions ( not to scale ). In the above plan show the positions of different pegs required for setting out of the above building. Solution: The Outside Dimensions are 12000 mm x 18000 mm Thickness of the wall: 200 mm Center line dimensions are ( 12000 – 200 ) = 11800 mm and ( 18000 – 200 ) = 17800 mm = 11800 mm x 17800 mm With foundation width 750 mm, the outside dimensions of foundation wall are 12550 x 18550 Inside Dimensions are 11050 x 17050. Here the OFFSET PEGS are used.
  • 11. MID-TERM REVIEW, 2017 Setting Out of Buildings Wall thickness 200 mm
  • 12. MID-TERM REVIEW, 2017 Setting Out of Buildings Reference line connected by Thread or Rope Maintained at 2 m from the outer wall
  • 13. MID-TERM REVIEW, 2017 Setting Out of Buildings
  • 14. MID-TERM REVIEW, 2017 Setting Out of Buildings
  • 15. MID-TERM REVIEW, 2017 Setting Out of Buildings Steps: • Mark the centerline of the longest wall on the ground by stretching a string between offset pegs 1 – 1. • Similarly stake strings along 2 – 2, 3 -3 and 4 – 4. • Pegs marked as red dots in the figure are the reference pegs for all the other pegs. • These pegs are marked at 2 m offset from all sides of the building plan. The pegs should project 25 to 50 mm above the ground level. • The intersections are maintained at right angle using the 3:4:5 method or tri-square. • Referring to the reference pegs ( marked red ) other temporary pegs are established ( marked purple ). • Once all the pegs are fixed, the lines are marked with lime. • Once the lines are marked with the lime, the pegs are removed except for the reference pegs.