SlideShare a Scribd company logo
1 of 32
Download to read offline
SETTING OUT
CONSTRUCTION ENGINEERING CE-375
SE SHAHID HUSSAIN
Aims - Setting out
• Understand roles of various personnel involved in setting out
• Understand the aims of setting out
• Acquaint with good working practices
• Horizontal/Vertical control requirements of setting out
• Methods of setting out design points on site
• Stages of setting out
• Quality control measures/checks
Setting out
• It is simply the physical transfer of the building drawing plans
onto the ground.
• It is one application of surveying , rather the reverse of
surveying.
• Most of the techniques and equipment used in surveying are
also used in setting out.
• Mistakes in setting out can be costly.
• Setting out is the responsibility of the contractor.
Principles of Setting Out
The various elements of the scheme must be correct in all three dimensions,
that is each must be its correct size, in its correct plan position and correct
reduced level.
• Horizontal control techniques
• The Easting and Northing coordinates are located by fixing at least two
or three of them so that the work can be independently checked.
• The design points must be set out to the accuracy stated in the
specifications.
• Vertical control techniques
• In order that design points on the works can be positioned at their
correct levels, vertical control points of known elevation relative to
some specified vertical datum are established.
Control Points
• Principle of working from the whole to
the part using two different levels of
control is used.
• On some schemes the same control
points that were used in the production
of the site plan prior to design work are
used. These must be re-measured
before setting out as positions may
have changed.
• Horizontal control points should be
located as near as possible to the site in
open positions for ease of working, but
well away from the construction area
and traffic routes to avoid them being
disturbed.
Control Points
• Construction and protection of control points is very
important.
• Wooden pegs are often used for non-permanent stations.
• For permanent control points it is recommended that they
be constructed with concrete.
Reference Grids
A control grid enables points to be set over a large
area. Several different grids can be used in setting out
• Survey grid is drawn on the survey plan from the
original traverse. Grid points have known Eastings
and Northings related either to some arbitrary origin
or to the national grid.
• Site grid: Used by designer & related in some way to
survey.
• Structural grid is established around a particular
building or structure which contains much detail
such as columns, which cannot be set out with
sufficient accuracy from the site grid.
• Secondary grid is established inside the structure
from the structural grid when it is no longer possible
to use the structural grid to establish internal
features of the building – as the vision becomes
obscured.
Tools for Setting out
Setting out Techniques
• Setting out using a theodolite and tape
Setting out by Total Station
• Total station is levelled and centred over a control point. Orient
it horizontally and vertically to the site coordinate system.
• For horizontal orientation, the coordinates of the control point
at which the instrument is set up are entered into the total
station then it automatically computes the bearing from the
total station to other points.
• For vertical orientation, the height of collimation of the total
station has to be determined. If the height of the control point
at which the total station is known, this is entered into the
instrument .
• Once the total station has been orientated it can be used for
setting out horizontal and vertical positions either using the
coordinates of the points to be set out directly or using bearing
and distance values calculated from these coordinates.
Stages in setting out
• First stage setting out.
• In practice, first stage setting out involves the use of
many of the horizontal and vertical control methods
and positioning techniques.
• To locate the boundaries of the works on ground and
define major elements.
• Second stage setting out.
• Second stage setting out continues on from the first
stage, beginning at the ground floor slab, road sub-
base level etc.
• Up to this point, all the control will be outside the
main construction, e.g, the pegs defining building
corners, centre lines and so on will have been
knocked out during the earthmoving work and only
the original control will be undisturbed.
Setting out
Misc Points/Tips
• Get the overall site handed over to you by the client through competent
authorities as per the site plan.
• Check/Study the block plan and site layout plan carefully before starting
setting out. Specially check for the existing features and their consistency
with the site plan and proposed buildings.
• Walk over the site and check that there is no evidence of hidden features
that might affect the setting-out or construction of the works.
• Don’t trust the existing neighbouring boundary as they may not be
legally/correctly installed. Making them reference will result in faults in
your plans.
• Install permanent bench marks and reference points.
• Clear/Strip the site, remove the trees & their roots, all vegetation and
bushes before setting out as per the contract agreement.
Misc Points/Tips
• Check the dimensions of the rooms, walls and building area and compare the
proposed plans with the area available. Do not scale the drawings. Use the
dimensions and check that intermediate dimensions agree with overall
dimensions.
• Calculate the centre lines of the walls if not already shown in drawings.
• Find out the diagonal of the rooms and the building using the centre lines.
Note that Rectangles have same diagonals.
• During excavation, the centre points marked during initial setting may get
removed. Therefore the centre lines are extended and the centre points are
marked about 2m away from the outer edge of excavation.
• Centre lines should be shown clearly by stretched thread or rope.
Misc Points/Tip
• If the plan is much too complicated and follows zigzag pattern, then
the centre pegs are kept at suitable positions according to site
conditions.
• One of the classic mistakes is getting the floor plan out of square.
• Adjust the errors internally if exteriors areas are fixed.
• Offset the line around the obstacle.
• Check levels by ‘eyeing-in’ on known levels.
• It is good practice to only square one corner and set out subsequent
walls by parallel measurements. This will ensure that if a true
rectangle is not set out (and all measurements are still accurate), the
shape will be a parallelogram (rhombus) and will therefore be easy to
correct.
• Use spirit level frequently.
Misc Points/Tip
• Report any discrepancies found in drawings and/or at site in writing and
keep a copy.
• Confirm any oral instructions in writing.
• Set up a system of recording and communicating information.
• Set up the CAD system to ease in making copies of drawings, getting minor
details/blowups and working out details/angles/radius offsets etc
• Apply manual/traditional checks for work executed using modern survey
equipments.
• Never conceal your errors or your doubts.
• Check pegs from offsets, do not assume they are correct or remain
undisturbed.
Any Questions ????

More Related Content

Similar to CE Lec Slides, Setting out.pdf

Introduction to garden planning and design session 2 slides no safety content...
Introduction to garden planning and design session 2 slides no safety content...Introduction to garden planning and design session 2 slides no safety content...
Introduction to garden planning and design session 2 slides no safety content...vikkis
 
Autodesk_Field_Layout_Guide
Autodesk_Field_Layout_GuideAutodesk_Field_Layout_Guide
Autodesk_Field_Layout_GuideJarrod Krug
 
Design Principles
Design PrinciplesDesign Principles
Design PrinciplesNishma2
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
Road construction on mountain
Road construction on mountainRoad construction on mountain
Road construction on mountainMuhammad Adnan
 
surveying Work methodology
surveying Work methodologysurveying Work methodology
surveying Work methodologysimon mhando
 
BUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptxBUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptxRavi Shastri
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Modular coordination
Modular coordinationModular coordination
Modular coordinationShubham Jain
 
Piping Drawings Basics.pdf
Piping Drawings Basics.pdfPiping Drawings Basics.pdf
Piping Drawings Basics.pdfRubenAngelFelix1
 
Piping drawing Knowledge.pdf
Piping drawing Knowledge.pdfPiping drawing Knowledge.pdf
Piping drawing Knowledge.pdfewwervq2323452
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptxGabrielBentil1
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Padmasinh Patil
 
Check list for case
Check list for case Check list for case
Check list for case Rakshith Rai
 
Check list for case study
Check list for case studyCheck list for case study
Check list for case studyRakshith Rai
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01Rajesh Rajguru
 

Similar to CE Lec Slides, Setting out.pdf (20)

Introduction to garden planning and design session 2 slides no safety content...
Introduction to garden planning and design session 2 slides no safety content...Introduction to garden planning and design session 2 slides no safety content...
Introduction to garden planning and design session 2 slides no safety content...
 
Autodesk_Field_Layout_Guide
Autodesk_Field_Layout_GuideAutodesk_Field_Layout_Guide
Autodesk_Field_Layout_Guide
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Design Principles
Design PrinciplesDesign Principles
Design Principles
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
Road construction on mountain
Road construction on mountainRoad construction on mountain
Road construction on mountain
 
surveying Work methodology
surveying Work methodologysurveying Work methodology
surveying Work methodology
 
BUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptxBUILDING LAYOUT ppt Ravi.pptx
BUILDING LAYOUT ppt Ravi.pptx
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Modular coordination
Modular coordinationModular coordination
Modular coordination
 
Piping Drawings Basics.pdf
Piping Drawings Basics.pdfPiping Drawings Basics.pdf
Piping Drawings Basics.pdf
 
Piping drawing Knowledge.pdf
Piping drawing Knowledge.pdfPiping drawing Knowledge.pdf
Piping drawing Knowledge.pdf
 
Comparators
ComparatorsComparators
Comparators
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Check list for case
Check list for case Check list for case
Check list for case
 
Check list for case study
Check list for case studyCheck list for case study
Check list for case study
 
Presentation (4).pptx
Presentation (4).pptxPresentation (4).pptx
Presentation (4).pptx
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

CE Lec Slides, Setting out.pdf

  • 1. SETTING OUT CONSTRUCTION ENGINEERING CE-375 SE SHAHID HUSSAIN
  • 2. Aims - Setting out • Understand roles of various personnel involved in setting out • Understand the aims of setting out • Acquaint with good working practices • Horizontal/Vertical control requirements of setting out • Methods of setting out design points on site • Stages of setting out • Quality control measures/checks
  • 3. Setting out • It is simply the physical transfer of the building drawing plans onto the ground. • It is one application of surveying , rather the reverse of surveying. • Most of the techniques and equipment used in surveying are also used in setting out. • Mistakes in setting out can be costly. • Setting out is the responsibility of the contractor.
  • 4. Principles of Setting Out The various elements of the scheme must be correct in all three dimensions, that is each must be its correct size, in its correct plan position and correct reduced level. • Horizontal control techniques • The Easting and Northing coordinates are located by fixing at least two or three of them so that the work can be independently checked. • The design points must be set out to the accuracy stated in the specifications. • Vertical control techniques • In order that design points on the works can be positioned at their correct levels, vertical control points of known elevation relative to some specified vertical datum are established.
  • 5. Control Points • Principle of working from the whole to the part using two different levels of control is used. • On some schemes the same control points that were used in the production of the site plan prior to design work are used. These must be re-measured before setting out as positions may have changed. • Horizontal control points should be located as near as possible to the site in open positions for ease of working, but well away from the construction area and traffic routes to avoid them being disturbed.
  • 6. Control Points • Construction and protection of control points is very important. • Wooden pegs are often used for non-permanent stations. • For permanent control points it is recommended that they be constructed with concrete.
  • 7. Reference Grids A control grid enables points to be set over a large area. Several different grids can be used in setting out • Survey grid is drawn on the survey plan from the original traverse. Grid points have known Eastings and Northings related either to some arbitrary origin or to the national grid. • Site grid: Used by designer & related in some way to survey. • Structural grid is established around a particular building or structure which contains much detail such as columns, which cannot be set out with sufficient accuracy from the site grid. • Secondary grid is established inside the structure from the structural grid when it is no longer possible to use the structural grid to establish internal features of the building – as the vision becomes obscured.
  • 9. Setting out Techniques • Setting out using a theodolite and tape
  • 10. Setting out by Total Station • Total station is levelled and centred over a control point. Orient it horizontally and vertically to the site coordinate system. • For horizontal orientation, the coordinates of the control point at which the instrument is set up are entered into the total station then it automatically computes the bearing from the total station to other points. • For vertical orientation, the height of collimation of the total station has to be determined. If the height of the control point at which the total station is known, this is entered into the instrument . • Once the total station has been orientated it can be used for setting out horizontal and vertical positions either using the coordinates of the points to be set out directly or using bearing and distance values calculated from these coordinates.
  • 11. Stages in setting out • First stage setting out. • In practice, first stage setting out involves the use of many of the horizontal and vertical control methods and positioning techniques. • To locate the boundaries of the works on ground and define major elements. • Second stage setting out. • Second stage setting out continues on from the first stage, beginning at the ground floor slab, road sub- base level etc. • Up to this point, all the control will be outside the main construction, e.g, the pegs defining building corners, centre lines and so on will have been knocked out during the earthmoving work and only the original control will be undisturbed.
  • 12.
  • 13.
  • 14.
  • 15.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. Misc Points/Tips • Get the overall site handed over to you by the client through competent authorities as per the site plan. • Check/Study the block plan and site layout plan carefully before starting setting out. Specially check for the existing features and their consistency with the site plan and proposed buildings. • Walk over the site and check that there is no evidence of hidden features that might affect the setting-out or construction of the works. • Don’t trust the existing neighbouring boundary as they may not be legally/correctly installed. Making them reference will result in faults in your plans. • Install permanent bench marks and reference points. • Clear/Strip the site, remove the trees & their roots, all vegetation and bushes before setting out as per the contract agreement.
  • 27. Misc Points/Tips • Check the dimensions of the rooms, walls and building area and compare the proposed plans with the area available. Do not scale the drawings. Use the dimensions and check that intermediate dimensions agree with overall dimensions. • Calculate the centre lines of the walls if not already shown in drawings. • Find out the diagonal of the rooms and the building using the centre lines. Note that Rectangles have same diagonals. • During excavation, the centre points marked during initial setting may get removed. Therefore the centre lines are extended and the centre points are marked about 2m away from the outer edge of excavation. • Centre lines should be shown clearly by stretched thread or rope.
  • 28. Misc Points/Tip • If the plan is much too complicated and follows zigzag pattern, then the centre pegs are kept at suitable positions according to site conditions. • One of the classic mistakes is getting the floor plan out of square. • Adjust the errors internally if exteriors areas are fixed. • Offset the line around the obstacle. • Check levels by ‘eyeing-in’ on known levels. • It is good practice to only square one corner and set out subsequent walls by parallel measurements. This will ensure that if a true rectangle is not set out (and all measurements are still accurate), the shape will be a parallelogram (rhombus) and will therefore be easy to correct. • Use spirit level frequently.
  • 29. Misc Points/Tip • Report any discrepancies found in drawings and/or at site in writing and keep a copy. • Confirm any oral instructions in writing. • Set up a system of recording and communicating information. • Set up the CAD system to ease in making copies of drawings, getting minor details/blowups and working out details/angles/radius offsets etc • Apply manual/traditional checks for work executed using modern survey equipments. • Never conceal your errors or your doubts. • Check pegs from offsets, do not assume they are correct or remain undisturbed.
  • 30.
  • 31.