LEVELLING
Edited by
Vedprakash C.
Marlapalle
Levelling
The art of determining relative heights of
different points on or below the surface of the
earth is called LEVELLING, deals with
measurements in the vertical plane.
For execution of Engineering Projects it is very
necessary to determine elevations of different
points along the alignment of proposed project.
Uses or purpose of Levelling
1. To prepare a contour map for fixing sites for reservoirs, dams
etc. & to fix the alignment of roads, railways, irrigation canals
etc.
2. To determine the altitudes of different important points on a
hill or to reduced levels of different points on or below the
surface of the earth.
3. To prepare a longitudinal & cross section of a project (roads,
railways, irrigation canals etc) in order to determine the
volume of earth work.
4. To prepare a layout map for water supply , sanitary or
drainage schemes.
Terms used in Levelling
Level Surface : The surface which is parallel to the mean
spheroidal surface of the earth is known as level surface.
Level line – any line lying on a level surface is called a level line.
Datum Surface or line : This is an imaginary level surface or
level line from which the vertical distances of different points
(above or below this line) are measured.
Mean Sea Level (M.S.L.) : M.S.L. is obtained by making
hourly observations of the tides at any place over a period of
19 years. MSL adopted by Survey of India is now Bombay
which was Karachi earlier.
Reduced Level (RL) : The vertical distances or Height or
depth of a point above or below the assumed datum is called
Reduced level. It may be positive or negative.
Line of Collimation : It is the imaginary line passing
through the intersection of the cross hairs at the diaphragm
and the optical center of the object glass and its extensions, it
is also called line of sight or collimation.
Axis of the Telescope : This axis is an imaginary line passing
through the optical center of the object glass and the optical
centre of the eye piece.
• Bench Mark (BM) :These are fixed reference point or
marks of known elevation or RL determined with reference
to the datum line.
These are very important marks. They serve as reference
points for finding the RL of new points or for conducting
levelling operations in projects involving roads, railways,
etc.
• GTS Bench mark (Great Trigonometrical Survey ):
These Bench marks are established by national agency like
Survey of India Department at a large interval all over the
country ( 100 km. interval). They are established with
highest precision. Their position and elevation above MSL is
given in a special catalogue known as GTS Maps.
Permanent Bench Mark : These are fixed points or marks
established by Government departments like PWD, Railway,
Irrigation, etc. RLs of these points are determined with reference
to GTS Bench mark (10 km. interval) & are kept on permanent
points like the plinth of building, parapet of bridge or culvert etc.
Arbitrary Bench mark : When the RLs of some fixed points
are assumed, they are termed arbitrary bench-marks. These are
adopted in small survey operations.
Temporary Bench mark : When the Bench marks are
established temporarily at the end of a day’s work, they are said
to be temporary Bench mark . They are generally made on the
root of tree, the parapet of a nearby culvert etc.
Back sight (B.S.) : This is the first staff reading taken in any
setup of the instrument after the levelling has been perfectly
done. This reading is always taken on a point of known RL, i.e.
on a bench mark or change point.
Fore Sight (F.S.) : It is the last staff reading in any setup of
the instrument, and indicates the shifting of the instrument.
Intermediate Sight (IS) : It is any other staff reading between
the BS & FS in the same setup of the instrument.
Change Point (CP) : The point indicates the shifting of the
instrument.
OR
The point on which both the foresight and back sight are taken
during the operation of levelling is called change point.
Height of Instrument (HI) : When the levelling
instrument is properly levelled, the RL of the line of
collimation is known as the height of instrument.
OR
The elevation of the line of sight with respect to assumed
datum is known as HI. This is obtained by adding the BS
reading to the RL of the BM.
Parallax : The apparent movement of the image relative to
the cross hairs is known as Parallax. This occurs due to
imperfect focussing, when the image does not fall in the
plane of the diaphragm
Types of Levelling Equipments
i) Dumpy level
ii) Tilting level
iii) Automatic level
iv) Digital Auto level
Tilting level
It consists of a telescope attached with a level tube which
can be tilted within few degrees in vertical plane by a tilting
screw.
The Automatic level : The fundamental difference between
automatic and the classic spirit level is that in the former the line
of sight is no longer levelled manually using a tubular spirit level,
but is levelled automatically within a certain tilt range. This is
achieved by compensator in the telescope.
Advantage of automatic level
Much simpler to use
High precision : Mean elevation error on staff
graduated to 5mm division varies between +0.5 to 0.8
mm per km of forward and backward levelling.
High speed : In fly levelling the progress achieved by
various level-wise compared.
Dumpy level : It is simple
compact and stable. The
telescope is rigidly fixed to its
support therefore cannot be
rotated about its longitudinal
axis. A long bubble tube is
attached to the top of
telescope. The instrument is
stable and retains its
permanent adjustment for
long time. This instrument is
commonly used
Diaphram : A frame carrying cross hairs usually made of either
silk thread or platinum wire and placed at the plane at which
vertical image of the object is formed by the objective.
Vertical hair of the diaphram enables the surveyor to check the
verticality of levelling staff whereas horizontal hairs are used to
read the staff graduations.
Components of Dumpy level :
1.Tripod – The tripod stand consist of three legs which may
be solid or framed to support the above three parts of the
level.
2.Levelling head : Levelling head generally consists of two
parallel plates with 3 foot screws. Upper plate is known as
Tribrach and lower plate is trivet which can be screwed on to
the tripod. Levelling head has to perform 3 distant functions :
i) to support the telescope
ii) to attach the level to the tripod
iii) to provide a means for level (foot screws)
to bring the bubble of tube level at the centre of its run.
3. Foot screws : Three foot screws are provided between the
trivet & tribrach. By turning the foot screws the tribrach can be raised
or lowered to bring the bubble to the centre of its run.
4. Telescope : Telescope is an optical instrument used for
magnifying and viewing the images of distant objects. It consists of
two lenses. The lens fitted near the eye is called the eye piece and
the other fitted at the end near to the object is called the objective
lens.
5.Level Tube : Also known as Bubble Tube consists of a
glass tube placed in a brass tube which is sealed with plaster of
paris. The whole of the interior surface or the upper half is
accurately ground so that its longitudinal section, is an arc of a
circle. Level tube is filled with either or alcohol, the remaining
space is occupied by an air bubble. The centre of air bubble
always rest at the highest point of the tube.
Points to be remembered by Staff man
The staff should be made vertical by holding it with
both arms while standing behind it.
The staff should be held on firm ground.
When the telescopic staff is to be extended, care should
be taken so that it is perfectly stretched and properly
fixed on the spring catcher.
The bottom of the staff should be kept clean.
Points to be remembered by Level man
The Levelling instrument should be placed at a position suitable
for the greatest no. of observation to be taken.
The instrument should not be too high or too low.
The Levelling should be done perfectly.
The Levelling instrument should not be placed on the profile
line (i.e. the center line of the project).
The eye-piece should be focused by holding a sheet of white
paper in front of the telescope.
The objective should be focused by pointing the telescope
towards the staff.
The parallax should be eliminated.
The verticality of the staff should be verified by observing the
two vertical hairs & by noting the minimum reading on the
staff when it is moved along the line of sight.
After taking the staff reading, the position of the bubble should
be verified. If it is disturbed, the reading should be taken again.
Temporary Adjustment of Level
1. Selection of suitable position
2. Fixing level with tripod stand
3. Approximate levelling by legs of tripod stand
4. Perfect levelling by foot screws
5. Focussing the eye-piece
6. Focussing the object glass
7. Taking the staff readings
• Selection of suitable position - A sutaible position is selected for setting
the level . From this position , it should be possible to take the greatest
number of observation without difficulty.
• Fixing level with tripod stand – the tripod stand is placed at the required
position with its legs well apart, and pressed firmly into the ground. The
level is fixed on the tripod stand according to the fixing arrangement
provided.
• Approximate levelling by legs of tripod stand- the foot screws are brought
to the center of their run. Two legs of the tripod stand are firmly fixed into
the ground. Then the third leg is moved to the left or right , in or until the
bubble is approximately at the centre of its run.
• Perfect levelling by foot screws – longitudinal bubble on the top of the
telescope. Bubble brought to the center by turning the foot screw equally
either both inward or outward. Then telescope turned through 90 degree.
And brought over the third foot screw , and the bubble is brought to the
center by turning this foot screw clockwise and anticlockwise. The
telescope again brought to its original position. And bubble to the
centered the process repeated several times until bubble remain its
central position.
• Focussing the eye-piece – a piece of white paper is held
in front of the object glass and the eye piece is moved in or
out by turning it clockwise or anticlockwise until the cross
hairs can be seen clearly.
• Focussing the object glass – telescope directed toward
the levelling staff. Looking through the eye piece, the
focusing screw is turned clockwise or antilock wise until the
graduation of staff is visible.
• Taking the staff readings- finally the leveling of the
instrument is verified by turning the telescope in any
direction. When the bubble remain in the central position
for any direction of the telescope.
Types of Levelling operation
1. Simple levelling
2. Differential Levelling
3. Fly Levelling
4. Longitudinal or Profile Levelling
5. Cross-sectional Levelling
6. Check Levelling
Simple levelling : When the difference of level
between two points is determined by setting the
levelling instrument midway between the points, the
process is known as simple levelling.
Differential levelling :
i) If the difference in elevation between them is too
great.
ii) If there are obstacles intervening. In such case it is
necessary to set up the level in several positions and to
work in series of stages.
Differential levelling
This method is also known as compound levelling or
continuous levelling.
Suppose it is required to know the difference of level
between A & B. the level is set up at point O1, O2, O3
etc after temporary adjustment staff reading are taken
at every set up . The point C1, C2, C3 are known as
change points then difference of level between the A &
B is found out.
Fly levelling
When Differential levelling is done in order to connect
a bench mark to the starting point of the alignment of
any project, it is called fly levelling.
Fly levelling is also done to connect the BM to any
intermediate point of the alignment for checking the
accuracy of the work.
Longitudinal or profile levelling
The operation of taking levels along the centre line of
any alignment (road, railway, etc.) at regular intervals is
known as longitudinal levelling. This operation is
undertaken in order to determine the undulations of the
ground surface along the profile line.
Cross Sectional levelling
The operation of taking levels transverse to the
direction of longitudinal levelling is known as cross
sectional levelling. This operation is undertaken in
order to know the nature of the ground across the
centre line of any alignment.
Check levelling
The fly levelling done at end of the day’s work to connect the
finishing point with the starting point on the particular day is
known as check levelling. It is undertaken in order to check the
accuracy of the day’s work.
Reciprocal Levelling
• In this levelling set up on both banks of the river or valley and
two set of staff reading are taken by holding the staff on the
both banks.
• Procedure – Suppose A& B are two points on the opposite
back of river. The level is set up very near A and after proper
temporary adjustment , staff reading are taken at A & B .
Suppose the readings are a1 &b2
• The level is shifted and set up very near B and after proper
adjustment , staff reading are taken at A & B . Suppose the
reading are a2 & b2.
h= true difference between point A & B
• In the first case
correct staff reading at A= a1
correct staff reading at B= b1 – e
True difference of level between A & B
h = a1 – (b1 – e ) …………………(1)
• In second case
Correct staff reading at B = b2
Correct staff reading at A = a2 – e
True difference in level
h =(a2 -e) –b2 ……………(2)
From (1)&(2)
2h = a1 – (b1 - e) + (a2 - e) – b2
= a1 – b1 +e +a2 – e – b2
= (a1 – b1) +(a2 – b2)
h = (a1-b1) + (a2 – b2) / 2
Difficulties faced in levelling
1. When the staff is too near the instrument
2. Levelling across a large pond or lake
3. Levelling across a river
Levelling across a large pond or lake
• We know that the water surface of still lake or pond is
considered to be level.
• Therefore all points on the a water surface have the same R.L.
Two peg A &B fix on opposite bank of the lake or pond.
• The top of the pegs are just flush with the water surface. The
level is set up at O1 and RL of A is determined by taking FS on
A. the RL of B is assume to be equal to that of A .
• Now the level is shifted and set up at O2 . Then by taking a BS
on peg B, levelling is continued.
Levelling across a river
• In case of flowing water , the surface cannot
be considered level, the water level on the
opposite edges will be different. In such case
the method of reciprocoal levelling is aopted.
Two peg A &B are driven in opposite banck of
river.
4. Levelling across a solid wall
Two peg A &B are driven on either side of wall, just touching
it. The level is set up at O1 and a staff reading is taken on A.
let this reading be AC. Then then the height of wall is
measured by staff . Let the height be AE. The HI is found out
by taking a BS on any BM or CP
RL of A = HI – AC
RL of E = RL of A + AE = RL of F
RL of B = RL of F – BF
HI at O2 = RL of B + BD
5. When BM is above line of collimation
this happens when the BM is at the bottom of the
bridge girder or bottom surface of the culvert. And that
it is required to find out RL of A. the level is set up at O
and staff is held inverted on the BM. The staff readig
taken and noted with negative sign. Let BS & FS reading
be – 1.5 and 2.250 respectively.
HI of instrument = 100 – 1.5 = 98.5
RL of A = 98.5 – 2.250 = 95.250
6. Levelling across a rising ground or depression
while levelling across high ground, the level should
not be placed on the top of the ground , but on side
so that the line of collimation just passes through
the apex.
While levelling across a depression the level should
be set up on one side and not at the bottom of the
depression.
Sources of Errors in levelling
 Instrumental errors
 Personal errors
 Errors due to natural causes
Instrumental errors
• The permanent adjustment of the instrument may
not be perfect. i.e. the line of collimation may not
be parallel to the axis of the bubble tube.
• The internal arrangement of the focusing tube is
not perfect.
• The graduation of the levelling staff may not be
perfect.
Personal errors
a) The instrument may not be levelled perfectly.
b) The focusing of the eye-piece & object glass may not be perfect & the
parallax may not be eliminated.
c) The position of the staff may be displaced at the change point at the time
of taking FS & BS readings.
d) The staff may appear inverted when viewed through the telescope. By
mistake, the staff readings may be taken upwards instead of downwards.
e) The reading of the stadia hair rather than the central collimation hair may
be taken by mistake.
f) A wrong entry may be made in the level book.
g) The staff may not be properly & fully extended.
Errors due to natural causes
• When the distance of sight is long, the curvature of
the earth may affect the staff reading.
• The effect of refraction may cause a wrong staff
reading to be taken.
• The effect of high winds & a shining sun may result
in a wrong staff reading.
References
• Surveying and Levelling: N N Basak, Tata McGraw Hill, New
Delhi.
• Surveying: R. Agor, Khanna Publishers.
• http://nptel.iitm.ac.in/courses-contents/IIT Kanpur and IIT
Madras.
• http://www.slideshare.net
• www.scribd.com

More Related Content

What's hot

Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying neharajpl
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levellingParimal Jha
 
traversing of survey
traversing of surveytraversing of survey
traversing of surveySelf-employed
 
Total station Surveying
Total station SurveyingTotal station Surveying
Total station SurveyingKiran M
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1Decentumang
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying neharajpl
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying pptNaufil Sayyad
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURINGANAND JIBHKATE
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveyingShikhar Malhotra
 
2. THEODOLITE TRAVERSING (SUR) 3140601 GTU
2. THEODOLITE TRAVERSING (SUR) 3140601 GTU2. THEODOLITE TRAVERSING (SUR) 3140601 GTU
2. THEODOLITE TRAVERSING (SUR) 3140601 GTUVATSAL PATEL
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveyingPhurba Tamang
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouringANAND JIBHKATE
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 

What's hot (20)

Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
Plane Table Surveying PPt
Plane Table Surveying PPtPlane Table Surveying PPt
Plane Table Surveying PPt
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
surveying contouring
surveying contouring surveying contouring
surveying contouring
 
traversing of survey
traversing of surveytraversing of survey
traversing of survey
 
Total station Surveying
Total station SurveyingTotal station Surveying
Total station Surveying
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1
 
Tacheometric surveying
Tacheometric surveying Tacheometric surveying
Tacheometric surveying
 
Surveying
Surveying Surveying
Surveying
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
Triangulation survey
Triangulation surveyTriangulation survey
Triangulation survey
 
Levelling
LevellingLevelling
Levelling
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveying
 
2. THEODOLITE TRAVERSING (SUR) 3140601 GTU
2. THEODOLITE TRAVERSING (SUR) 3140601 GTU2. THEODOLITE TRAVERSING (SUR) 3140601 GTU
2. THEODOLITE TRAVERSING (SUR) 3140601 GTU
 
Curve setting ppt
Curve setting pptCurve setting ppt
Curve setting ppt
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouring
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 

Viewers also liked

Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in SurveyingRAHUL SINHA
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveyingMohammed_82
 
Levelling (Civil Engg)
Levelling (Civil Engg)Levelling (Civil Engg)
Levelling (Civil Engg)Hafiz Hussain
 
Agriculture in pakistan
Agriculture in pakistanAgriculture in pakistan
Agriculture in pakistanSaba96
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Kaushal Mehta
 
Aminoacidos-NIKITA
Aminoacidos-NIKITAAminoacidos-NIKITA
Aminoacidos-NIKITAnikizz
 
Ece(instruction of levelling)
Ece(instruction of levelling)Ece(instruction of levelling)
Ece(instruction of levelling)NIKUL PITHVA
 
MATERIAL TESTING AND PRACTICE by Mostafa Sameer
MATERIAL TESTING AND PRACTICE by Mostafa SameerMATERIAL TESTING AND PRACTICE by Mostafa Sameer
MATERIAL TESTING AND PRACTICE by Mostafa SameerMostafa Sameer
 
Quality control lab
Quality control labQuality control lab
Quality control labRaja Katoch
 
Agriculture in pakistan
Agriculture in pakistanAgriculture in pakistan
Agriculture in pakistangulsheramjad
 
Survey instruments and lab equipments
Survey instruments and lab equipmentsSurvey instruments and lab equipments
Survey instruments and lab equipmentssaibabatraders
 
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...Mr.Allah Dad Khan
 
Trigonometric levelling jithin
Trigonometric levelling   jithinTrigonometric levelling   jithin
Trigonometric levelling jithinJithin Jose
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTGLA University
 
Candy - Construction Estimating & Valuations - rev 2.01
Candy - Construction Estimating & Valuations - rev 2.01Candy - Construction Estimating & Valuations - rev 2.01
Candy - Construction Estimating & Valuations - rev 2.01Jerico Awat
 

Viewers also liked (20)

Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Types of level
Types of levelTypes of level
Types of level
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
 
Levelling (Civil Engg)
Levelling (Civil Engg)Levelling (Civil Engg)
Levelling (Civil Engg)
 
Agriculture in pakistan
Agriculture in pakistanAgriculture in pakistan
Agriculture in pakistan
 
Levelling
LevellingLevelling
Levelling
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
 
Aminoacidos-NIKITA
Aminoacidos-NIKITAAminoacidos-NIKITA
Aminoacidos-NIKITA
 
Ece(instruction of levelling)
Ece(instruction of levelling)Ece(instruction of levelling)
Ece(instruction of levelling)
 
MATERIAL TESTING AND PRACTICE by Mostafa Sameer
MATERIAL TESTING AND PRACTICE by Mostafa SameerMATERIAL TESTING AND PRACTICE by Mostafa Sameer
MATERIAL TESTING AND PRACTICE by Mostafa Sameer
 
surveying ii
surveying iisurveying ii
surveying ii
 
Quality control lab
Quality control labQuality control lab
Quality control lab
 
Agriculture in pakistan
Agriculture in pakistanAgriculture in pakistan
Agriculture in pakistan
 
Pakistan agriculture...
Pakistan agriculture...Pakistan agriculture...
Pakistan agriculture...
 
Survey instruments and lab equipments
Survey instruments and lab equipmentsSurvey instruments and lab equipments
Survey instruments and lab equipments
 
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...
E Agriculture the need of modern technology By Allah Dad Khan Focal Person E ...
 
Trigonometric levelling jithin
Trigonometric levelling   jithinTrigonometric levelling   jithin
Trigonometric levelling jithin
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECT
 
Corporate farming pakistan
Corporate farming pakistanCorporate farming pakistan
Corporate farming pakistan
 
Candy - Construction Estimating & Valuations - rev 2.01
Candy - Construction Estimating & Valuations - rev 2.01Candy - Construction Estimating & Valuations - rev 2.01
Candy - Construction Estimating & Valuations - rev 2.01
 

Similar to Levelling

Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingMir Zafarullah
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingRai University
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingRai University
 
Lecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfLecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfPranayaKishoreRaycho
 
3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptxMartin Murimi
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfAlwandBarzani
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Sunilkumar Mandal
 
LEVELLING METHODS AND INSTRUMENTS IN SURVEYING
LEVELLING METHODS AND INSTRUMENTS IN SURVEYINGLEVELLING METHODS AND INSTRUMENTS IN SURVEYING
LEVELLING METHODS AND INSTRUMENTS IN SURVEYINGATHIRA B K
 
surveying.levelling ppt.ppt
surveying.levelling ppt.pptsurveying.levelling ppt.ppt
surveying.levelling ppt.pptivargarud
 
Project report1 of levelling in pdf2
Project report1 of levelling in pdf2Project report1 of levelling in pdf2
Project report1 of levelling in pdf2Ramesh Ranjan
 
WHAT IS DUMPY LEVEL IN SURVEYING
WHAT IS DUMPY LEVEL IN SURVEYINGWHAT IS DUMPY LEVEL IN SURVEYING
WHAT IS DUMPY LEVEL IN SURVEYINGpwhite91
 
Mass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptMass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptNITINSURESH30
 
chapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdfchapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdfsandipanpaul16
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in SurveyingPhurba Tamang
 

Similar to Levelling (20)

UNIT FOUR.pptx
UNIT FOUR.pptxUNIT FOUR.pptx
UNIT FOUR.pptx
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levelling
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
Lecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfLecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdf
 
3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx
 
Levelling
LevellingLevelling
Levelling
 
Leveling
LevelingLeveling
Leveling
 
Unit 3
Unit 3Unit 3
Unit 3
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01
 
LEVELLING METHODS AND INSTRUMENTS IN SURVEYING
LEVELLING METHODS AND INSTRUMENTS IN SURVEYINGLEVELLING METHODS AND INSTRUMENTS IN SURVEYING
LEVELLING METHODS AND INSTRUMENTS IN SURVEYING
 
Mohammed kareem
Mohammed kareemMohammed kareem
Mohammed kareem
 
surveying.levelling ppt.ppt
surveying.levelling ppt.pptsurveying.levelling ppt.ppt
surveying.levelling ppt.ppt
 
Project report1 of levelling in pdf2
Project report1 of levelling in pdf2Project report1 of levelling in pdf2
Project report1 of levelling in pdf2
 
WHAT IS DUMPY LEVEL IN SURVEYING
WHAT IS DUMPY LEVEL IN SURVEYINGWHAT IS DUMPY LEVEL IN SURVEYING
WHAT IS DUMPY LEVEL IN SURVEYING
 
Mass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptMass diagram and its characeristics .ppt
Mass diagram and its characeristics .ppt
 
Module-IV SURVEYING-I [BTCVC304]
Module-IV SURVEYING-I [BTCVC304]Module-IV SURVEYING-I [BTCVC304]
Module-IV SURVEYING-I [BTCVC304]
 
chapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdfchapter 3 levelling @etconp.pdf
chapter 3 levelling @etconp.pdf
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 

Recently uploaded

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Levelling

  • 2. Levelling The art of determining relative heights of different points on or below the surface of the earth is called LEVELLING, deals with measurements in the vertical plane. For execution of Engineering Projects it is very necessary to determine elevations of different points along the alignment of proposed project.
  • 3. Uses or purpose of Levelling 1. To prepare a contour map for fixing sites for reservoirs, dams etc. & to fix the alignment of roads, railways, irrigation canals etc. 2. To determine the altitudes of different important points on a hill or to reduced levels of different points on or below the surface of the earth. 3. To prepare a longitudinal & cross section of a project (roads, railways, irrigation canals etc) in order to determine the volume of earth work. 4. To prepare a layout map for water supply , sanitary or drainage schemes.
  • 4. Terms used in Levelling Level Surface : The surface which is parallel to the mean spheroidal surface of the earth is known as level surface. Level line – any line lying on a level surface is called a level line.
  • 5. Datum Surface or line : This is an imaginary level surface or level line from which the vertical distances of different points (above or below this line) are measured. Mean Sea Level (M.S.L.) : M.S.L. is obtained by making hourly observations of the tides at any place over a period of 19 years. MSL adopted by Survey of India is now Bombay which was Karachi earlier. Reduced Level (RL) : The vertical distances or Height or depth of a point above or below the assumed datum is called Reduced level. It may be positive or negative.
  • 6.
  • 7. Line of Collimation : It is the imaginary line passing through the intersection of the cross hairs at the diaphragm and the optical center of the object glass and its extensions, it is also called line of sight or collimation. Axis of the Telescope : This axis is an imaginary line passing through the optical center of the object glass and the optical centre of the eye piece.
  • 8. • Bench Mark (BM) :These are fixed reference point or marks of known elevation or RL determined with reference to the datum line. These are very important marks. They serve as reference points for finding the RL of new points or for conducting levelling operations in projects involving roads, railways, etc. • GTS Bench mark (Great Trigonometrical Survey ): These Bench marks are established by national agency like Survey of India Department at a large interval all over the country ( 100 km. interval). They are established with highest precision. Their position and elevation above MSL is given in a special catalogue known as GTS Maps.
  • 9. Permanent Bench Mark : These are fixed points or marks established by Government departments like PWD, Railway, Irrigation, etc. RLs of these points are determined with reference to GTS Bench mark (10 km. interval) & are kept on permanent points like the plinth of building, parapet of bridge or culvert etc.
  • 10. Arbitrary Bench mark : When the RLs of some fixed points are assumed, they are termed arbitrary bench-marks. These are adopted in small survey operations. Temporary Bench mark : When the Bench marks are established temporarily at the end of a day’s work, they are said to be temporary Bench mark . They are generally made on the root of tree, the parapet of a nearby culvert etc.
  • 11. Back sight (B.S.) : This is the first staff reading taken in any setup of the instrument after the levelling has been perfectly done. This reading is always taken on a point of known RL, i.e. on a bench mark or change point. Fore Sight (F.S.) : It is the last staff reading in any setup of the instrument, and indicates the shifting of the instrument.
  • 12. Intermediate Sight (IS) : It is any other staff reading between the BS & FS in the same setup of the instrument. Change Point (CP) : The point indicates the shifting of the instrument. OR The point on which both the foresight and back sight are taken during the operation of levelling is called change point.
  • 13. Height of Instrument (HI) : When the levelling instrument is properly levelled, the RL of the line of collimation is known as the height of instrument. OR The elevation of the line of sight with respect to assumed datum is known as HI. This is obtained by adding the BS reading to the RL of the BM. Parallax : The apparent movement of the image relative to the cross hairs is known as Parallax. This occurs due to imperfect focussing, when the image does not fall in the plane of the diaphragm
  • 14. Types of Levelling Equipments i) Dumpy level ii) Tilting level iii) Automatic level iv) Digital Auto level
  • 15. Tilting level It consists of a telescope attached with a level tube which can be tilted within few degrees in vertical plane by a tilting screw.
  • 16. The Automatic level : The fundamental difference between automatic and the classic spirit level is that in the former the line of sight is no longer levelled manually using a tubular spirit level, but is levelled automatically within a certain tilt range. This is achieved by compensator in the telescope.
  • 17. Advantage of automatic level Much simpler to use High precision : Mean elevation error on staff graduated to 5mm division varies between +0.5 to 0.8 mm per km of forward and backward levelling. High speed : In fly levelling the progress achieved by various level-wise compared.
  • 18. Dumpy level : It is simple compact and stable. The telescope is rigidly fixed to its support therefore cannot be rotated about its longitudinal axis. A long bubble tube is attached to the top of telescope. The instrument is stable and retains its permanent adjustment for long time. This instrument is commonly used
  • 19.
  • 20. Diaphram : A frame carrying cross hairs usually made of either silk thread or platinum wire and placed at the plane at which vertical image of the object is formed by the objective. Vertical hair of the diaphram enables the surveyor to check the verticality of levelling staff whereas horizontal hairs are used to read the staff graduations.
  • 21. Components of Dumpy level : 1.Tripod – The tripod stand consist of three legs which may be solid or framed to support the above three parts of the level. 2.Levelling head : Levelling head generally consists of two parallel plates with 3 foot screws. Upper plate is known as Tribrach and lower plate is trivet which can be screwed on to the tripod. Levelling head has to perform 3 distant functions : i) to support the telescope ii) to attach the level to the tripod iii) to provide a means for level (foot screws) to bring the bubble of tube level at the centre of its run.
  • 22. 3. Foot screws : Three foot screws are provided between the trivet & tribrach. By turning the foot screws the tribrach can be raised or lowered to bring the bubble to the centre of its run. 4. Telescope : Telescope is an optical instrument used for magnifying and viewing the images of distant objects. It consists of two lenses. The lens fitted near the eye is called the eye piece and the other fitted at the end near to the object is called the objective lens. 5.Level Tube : Also known as Bubble Tube consists of a glass tube placed in a brass tube which is sealed with plaster of paris. The whole of the interior surface or the upper half is accurately ground so that its longitudinal section, is an arc of a circle. Level tube is filled with either or alcohol, the remaining space is occupied by an air bubble. The centre of air bubble always rest at the highest point of the tube.
  • 23. Points to be remembered by Staff man The staff should be made vertical by holding it with both arms while standing behind it. The staff should be held on firm ground. When the telescopic staff is to be extended, care should be taken so that it is perfectly stretched and properly fixed on the spring catcher. The bottom of the staff should be kept clean.
  • 24. Points to be remembered by Level man The Levelling instrument should be placed at a position suitable for the greatest no. of observation to be taken. The instrument should not be too high or too low. The Levelling should be done perfectly. The Levelling instrument should not be placed on the profile line (i.e. the center line of the project). The eye-piece should be focused by holding a sheet of white paper in front of the telescope.
  • 25. The objective should be focused by pointing the telescope towards the staff. The parallax should be eliminated. The verticality of the staff should be verified by observing the two vertical hairs & by noting the minimum reading on the staff when it is moved along the line of sight. After taking the staff reading, the position of the bubble should be verified. If it is disturbed, the reading should be taken again.
  • 26. Temporary Adjustment of Level 1. Selection of suitable position 2. Fixing level with tripod stand 3. Approximate levelling by legs of tripod stand 4. Perfect levelling by foot screws 5. Focussing the eye-piece 6. Focussing the object glass 7. Taking the staff readings
  • 27. • Selection of suitable position - A sutaible position is selected for setting the level . From this position , it should be possible to take the greatest number of observation without difficulty. • Fixing level with tripod stand – the tripod stand is placed at the required position with its legs well apart, and pressed firmly into the ground. The level is fixed on the tripod stand according to the fixing arrangement provided. • Approximate levelling by legs of tripod stand- the foot screws are brought to the center of their run. Two legs of the tripod stand are firmly fixed into the ground. Then the third leg is moved to the left or right , in or until the bubble is approximately at the centre of its run. • Perfect levelling by foot screws – longitudinal bubble on the top of the telescope. Bubble brought to the center by turning the foot screw equally either both inward or outward. Then telescope turned through 90 degree. And brought over the third foot screw , and the bubble is brought to the center by turning this foot screw clockwise and anticlockwise. The telescope again brought to its original position. And bubble to the centered the process repeated several times until bubble remain its central position.
  • 28.
  • 29. • Focussing the eye-piece – a piece of white paper is held in front of the object glass and the eye piece is moved in or out by turning it clockwise or anticlockwise until the cross hairs can be seen clearly. • Focussing the object glass – telescope directed toward the levelling staff. Looking through the eye piece, the focusing screw is turned clockwise or antilock wise until the graduation of staff is visible. • Taking the staff readings- finally the leveling of the instrument is verified by turning the telescope in any direction. When the bubble remain in the central position for any direction of the telescope.
  • 30. Types of Levelling operation 1. Simple levelling 2. Differential Levelling 3. Fly Levelling 4. Longitudinal or Profile Levelling 5. Cross-sectional Levelling 6. Check Levelling
  • 31. Simple levelling : When the difference of level between two points is determined by setting the levelling instrument midway between the points, the process is known as simple levelling.
  • 32. Differential levelling : i) If the difference in elevation between them is too great. ii) If there are obstacles intervening. In such case it is necessary to set up the level in several positions and to work in series of stages.
  • 33. Differential levelling This method is also known as compound levelling or continuous levelling. Suppose it is required to know the difference of level between A & B. the level is set up at point O1, O2, O3 etc after temporary adjustment staff reading are taken at every set up . The point C1, C2, C3 are known as change points then difference of level between the A & B is found out.
  • 34. Fly levelling When Differential levelling is done in order to connect a bench mark to the starting point of the alignment of any project, it is called fly levelling. Fly levelling is also done to connect the BM to any intermediate point of the alignment for checking the accuracy of the work.
  • 35. Longitudinal or profile levelling The operation of taking levels along the centre line of any alignment (road, railway, etc.) at regular intervals is known as longitudinal levelling. This operation is undertaken in order to determine the undulations of the ground surface along the profile line.
  • 36. Cross Sectional levelling The operation of taking levels transverse to the direction of longitudinal levelling is known as cross sectional levelling. This operation is undertaken in order to know the nature of the ground across the centre line of any alignment.
  • 37. Check levelling The fly levelling done at end of the day’s work to connect the finishing point with the starting point on the particular day is known as check levelling. It is undertaken in order to check the accuracy of the day’s work.
  • 38.
  • 39. Reciprocal Levelling • In this levelling set up on both banks of the river or valley and two set of staff reading are taken by holding the staff on the both banks. • Procedure – Suppose A& B are two points on the opposite back of river. The level is set up very near A and after proper temporary adjustment , staff reading are taken at A & B . Suppose the readings are a1 &b2 • The level is shifted and set up very near B and after proper adjustment , staff reading are taken at A & B . Suppose the reading are a2 & b2.
  • 40. h= true difference between point A & B • In the first case correct staff reading at A= a1 correct staff reading at B= b1 – e True difference of level between A & B h = a1 – (b1 – e ) …………………(1) • In second case Correct staff reading at B = b2 Correct staff reading at A = a2 – e True difference in level h =(a2 -e) –b2 ……………(2) From (1)&(2) 2h = a1 – (b1 - e) + (a2 - e) – b2 = a1 – b1 +e +a2 – e – b2 = (a1 – b1) +(a2 – b2) h = (a1-b1) + (a2 – b2) / 2
  • 41. Difficulties faced in levelling 1. When the staff is too near the instrument 2. Levelling across a large pond or lake 3. Levelling across a river
  • 42. Levelling across a large pond or lake • We know that the water surface of still lake or pond is considered to be level. • Therefore all points on the a water surface have the same R.L. Two peg A &B fix on opposite bank of the lake or pond. • The top of the pegs are just flush with the water surface. The level is set up at O1 and RL of A is determined by taking FS on A. the RL of B is assume to be equal to that of A . • Now the level is shifted and set up at O2 . Then by taking a BS on peg B, levelling is continued.
  • 43. Levelling across a river • In case of flowing water , the surface cannot be considered level, the water level on the opposite edges will be different. In such case the method of reciprocoal levelling is aopted. Two peg A &B are driven in opposite banck of river.
  • 44. 4. Levelling across a solid wall Two peg A &B are driven on either side of wall, just touching it. The level is set up at O1 and a staff reading is taken on A. let this reading be AC. Then then the height of wall is measured by staff . Let the height be AE. The HI is found out by taking a BS on any BM or CP RL of A = HI – AC RL of E = RL of A + AE = RL of F RL of B = RL of F – BF HI at O2 = RL of B + BD
  • 45. 5. When BM is above line of collimation this happens when the BM is at the bottom of the bridge girder or bottom surface of the culvert. And that it is required to find out RL of A. the level is set up at O and staff is held inverted on the BM. The staff readig taken and noted with negative sign. Let BS & FS reading be – 1.5 and 2.250 respectively. HI of instrument = 100 – 1.5 = 98.5 RL of A = 98.5 – 2.250 = 95.250
  • 46. 6. Levelling across a rising ground or depression while levelling across high ground, the level should not be placed on the top of the ground , but on side so that the line of collimation just passes through the apex. While levelling across a depression the level should be set up on one side and not at the bottom of the depression.
  • 47. Sources of Errors in levelling  Instrumental errors  Personal errors  Errors due to natural causes
  • 48. Instrumental errors • The permanent adjustment of the instrument may not be perfect. i.e. the line of collimation may not be parallel to the axis of the bubble tube. • The internal arrangement of the focusing tube is not perfect. • The graduation of the levelling staff may not be perfect.
  • 49. Personal errors a) The instrument may not be levelled perfectly. b) The focusing of the eye-piece & object glass may not be perfect & the parallax may not be eliminated. c) The position of the staff may be displaced at the change point at the time of taking FS & BS readings. d) The staff may appear inverted when viewed through the telescope. By mistake, the staff readings may be taken upwards instead of downwards. e) The reading of the stadia hair rather than the central collimation hair may be taken by mistake. f) A wrong entry may be made in the level book. g) The staff may not be properly & fully extended.
  • 50. Errors due to natural causes • When the distance of sight is long, the curvature of the earth may affect the staff reading. • The effect of refraction may cause a wrong staff reading to be taken. • The effect of high winds & a shining sun may result in a wrong staff reading.
  • 51. References • Surveying and Levelling: N N Basak, Tata McGraw Hill, New Delhi. • Surveying: R. Agor, Khanna Publishers. • http://nptel.iitm.ac.in/courses-contents/IIT Kanpur and IIT Madras. • http://www.slideshare.net • www.scribd.com