SlideShare a Scribd company logo
1 of 26
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Monitor Stakeholder
Engagement
Chapter 13 –
Project Stakeholder Management
SIXTH EDITION
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
13.4 Monitor Stakeholder Engagement
Monitor Stakeholder Engagement Definition
Monitor Stakeholder Engagement - ITTO
Interpersonal and team skills
Communication skills
Alternatives analysis
Review
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Project Stakeholder Management
Identify Stakeholders
Plan Stakeholder
Engagement
Manage Stakeholder
Engagement
Monitor Stakeholder
Engagement
I P
E MC
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder Engagement -> Overview
Monitor project
stakeholder
relationships
Tailor strategies
Modify
engagement
strategies
Integrate with
other knowledge
area
Linked to
communication
Maintain/
increases the
efficiency &
effectiveness
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitoring overall project stakeholder relationships and
tailoring strategies and plans for engaging stakeholders.
It will increase efficiency & effectiveness of
stakeholder engagement activities as project evolves.
Monitor Stakeholder Engagement -> Definition
Tailoring strategies and
plans
Engaging stakeholders
Monitoring stakeholder
relationships
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engagement -> ITTO
Data analysis
Decision making
Data Representation
Communication skills
Interpersonal and team skills
Meetings
Work Performance
Information
Change requests
PMP updates
Project document
updates
Inputs Tools & Techniques Outputs
Project Management
Plan
Project documents
Work Performance Data
Enterprise
environmental factors
Organizational process
assets
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engagement -> Inputs
Project Management
Plan
Project documents
Work Performance
Data
Enterprise
environmental factors
Organizational process
assets
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Monitor Stakeholder engagement -> Inputs -> PMP
Stakeholder
engagement plan
Resource
management Plan
Communication
Management plan
Following PMP/subsidiary plans may help in monitoring stakeholder engagement.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Project documents
• Important tool used to manage & resolve issues.
• Helps to monitor stakeholder related issues & disputes.
• Track end to end progress on issue resolutions.
Issue
log:
Monitor Stakeholder engagement -> Inputs -> Project documents
Stakeholder Register Issue log
Project
Communication
Risk Register
Lessons learned
register
Review project document to ensure they support effective stakeholder engagement & management
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Data
It’s a raw observations & measurements identified during Direct and Manage Project work.
Contains data such as which stakeholders has completed or delayed tasks/milestones. CR’s,
issues raised by stakeholders etc
Executing PG ->
Direct and Manage
Project work
Work Performance
Data
Monitoring &
Controlling PG
Monitor
Stakeholder
Engagement.
Monitor Stakeholder Engagement->Input->WPD
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engagement -> ITTO
Data analysis Meetings Decision making Data Representation
Communication skills
Interpersonal and
team skills
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Data analysis
Following data analysis techniques could be used to monitor stakeholder engagement.
Monitor Stakeholder engagement -> ITTO -> Data analysis
Stakeholder Analysis
• It helps determine the current position of
stakeholders with regards to their
engagement level.
Root cause analysis
• It used to determine the underlying reason,
why stakeholder engagement is not yet
getting the expected results..
Alternative analysis
• It is used to evaluate options to respond to
variances in the desired results of stakeholder
engagement.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Decision making
Following Decision making techniques can be used for monitoring stakeholder engagement.
Monitor Stakeholder engagement -> ITTO -> Decision making
Multi-criteria decision analysis
• Several factors for successful stakeholder
engagement are prioritized and weighted.
Voting
• It is used to select the best response for a
variance in stakeholder engagement.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Data Representation
Monitor Stakeholder engagement -> ITTO -> Data Representation
Following Data Representation techniques may help in monitoring stakeholder engagement.
Stakeholder engagement assessment matrix
• Compare current engagement level to planned
level.
• Unaware, Resistant, Neutral, Supportive, Leading
C: Current engagement level
D: Desired engagement level
Develop a plan to change
engagement level from
Current to Desired.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Communication
skills
Following Communication skills may help in monitoring stakeholder engagement.
Presentation:
• It provide clear information to stakeholders.
• More effective than e-mails, newsletters
• Provide an opportunity for real-time reaction
from stakeholders
Feedback
• Feedback is used to ensure that the
information to stakeholders is received and
understood.
Monitor Stakeholder engagement -> ITTO -> Communication skills
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engag. -> ITTO -> Interpersonal & team skills
Interpersonal and
team skills
Following Interpersonal and team skills may help in monitoring stakeholder engagement.
Active listening Cultural awareness Leadership Networking Political awareness
• Reduces misunderstandings and miscommunication
Active
listening
• Help plan communications based on the cultural differences
and requirements of stakeholders and team members.
Cultural
awareness
• Help communicate the vision of project & inspire them to
support project.
Leadership
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engag. -> ITTO -> Interpersonal & team skills
Interpersonal and
team skills
Following Interpersonal and team skills may help in monitoring stakeholder engagement.
Active listening Cultural awareness Leadership Networking Political awareness
• Helps PM to learn about levels of engagement of stakeholders.Networking
• Help understand organization strategies
• Understand which stakeholder uses power and influence.
• Helps develop an ability to communicate with these stakeholders.
Political
awareness
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Meetings:
are used to assess current stakeholder engagement levels and compare them
to planned levels.
Status / Stand-up
meetings
Retrospectives Steering committees Risk/ Issues review
Meetings
Monitor Stakeholder Engagement->T&T-> Meetings
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder engagement -> Outputs
Work Performance
Information
Change requests PMP updates
Project document
updates
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Information
WPI represents the current status of stakeholder engagement.
E.g., Current level of stakeholder support to the project, as compared to the desired levels.
Further WPI is contextualized with WPI from other control processes to generate reports.
Monitor Stakeholder Engagement->Outputs->WPI
Monitoring & Controlling PG
-> Monitor & control project
work
WPI
Monitor Stakeholder
Engagement
T&T:
Stakeholder
engagement
assessment matrix
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
CR may be raised to change the Stakeholder engagement plan to include
new engagement strategy or update existing.
Corrective actions
• Lead to improve stakeholder engagement
Preventive actions
• Reduce stakeholder issues
Monitor Stakeholder Engagement->Outputs->Change Request
Change requests
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
PMP updates
Following PMP/ subsidiary plans may get updated
Monitor Stakeholder engag. -> Output -> PMP updates
Stakeholder engagement plan
• Any updates regarding information about
stakeholders
• Update to engagement strategy.
Resource management Plan
• The project team’s responsibilities for
stakeholder engagement activities.
Communication Management plan:
• The communication strategies for engaging
stakeholders may need to be updated.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Project document
updates
Following project documents may get updated
Monitor Stakeholder engag. -> Output -> Project document updates
Stakeholder Register
• new information about stakeholders is updated.
Issue log
• Change in stakeholders attitudes towards any of
the existing issues in the issue log.
Lessons learned register
• Lessons learned about challenges and how they
could have been avoided.
Risk Register
• Stakeholders specific Risks need to be updated as
a result of interaction with the stakeholders.
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Monitor Stakeholder Engagement -> Review
Monitor Stakeholder Engagement Definition
Monitor Stakeholder Engagement - ITTO
Data analysis - Root cause & Alternative analysis
Decision making – Voting & MCDA
Interpersonal and team skills
Communication skills: Presentation, Feedback
PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com)
Project Stakeholder Management -> Complete review
Identify Stakeholders
Plan Stakeholder
Engagement
Manage Stakeholder
Engagement
Monitor Stakeholder
Engagement
I P
E MC
No one will believe in you until you believe in
you.
Robin Sharma

More Related Content

What's hot

Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaJoshua Render
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Project communication management
Project communication managementProject communication management
Project communication managementDikshant Ghimire
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Project communication management
Project communication managementProject communication management
Project communication managementTakudzwa Chatora
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewAnand Bobade
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off PresentationEbru Seiwert
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP) Ahmad Maharma, PMP,RMP
 

What's hot (20)

Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge Area
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 

Similar to Chap 13.4 Monitor stakeholder

Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderAnand Bobade
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledgeAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
2013 PMRG Member Survey
2013 PMRG Member Survey2013 PMRG Member Survey
2013 PMRG Member SurveyAdrian Ho
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Webinar: Stakeholder Management Engaging The Organisation For Results
Webinar: Stakeholder Management Engaging The Organisation For ResultsWebinar: Stakeholder Management Engaging The Organisation For Results
Webinar: Stakeholder Management Engaging The Organisation For ResultsAli Zeeshan
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 

Similar to Chap 13.4 Monitor stakeholder (20)

Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholder
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholders
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
2013 PMRG Member Survey
2013 PMRG Member Survey2013 PMRG Member Survey
2013 PMRG Member Survey
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Webinar: Stakeholder Management Engaging The Organisation For Results
Webinar: Stakeholder Management Engaging The Organisation For ResultsWebinar: Stakeholder Management Engaging The Organisation For Results
Webinar: Stakeholder Management Engaging The Organisation For Results
 
2019 Agile ^ Scrum
2019 Agile ^ Scrum2019 Agile ^ Scrum
2019 Agile ^ Scrum
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Proving Project Value
Proving Project ValueProving Project Value
Proving Project Value
 

More from Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 

More from Anand Bobade (15)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 

Recently uploaded

原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 

Recently uploaded (17)

原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 

Chap 13.4 Monitor stakeholder

  • 1. PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Monitor Stakeholder Engagement Chapter 13 – Project Stakeholder Management SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) 13.4 Monitor Stakeholder Engagement Monitor Stakeholder Engagement Definition Monitor Stakeholder Engagement - ITTO Interpersonal and team skills Communication skills Alternatives analysis Review
  • 3. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Project Stakeholder Management Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement I P E MC
  • 4. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder Engagement -> Overview Monitor project stakeholder relationships Tailor strategies Modify engagement strategies Integrate with other knowledge area Linked to communication Maintain/ increases the efficiency & effectiveness
  • 5. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitoring overall project stakeholder relationships and tailoring strategies and plans for engaging stakeholders. It will increase efficiency & effectiveness of stakeholder engagement activities as project evolves. Monitor Stakeholder Engagement -> Definition Tailoring strategies and plans Engaging stakeholders Monitoring stakeholder relationships
  • 6. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engagement -> ITTO Data analysis Decision making Data Representation Communication skills Interpersonal and team skills Meetings Work Performance Information Change requests PMP updates Project document updates Inputs Tools & Techniques Outputs Project Management Plan Project documents Work Performance Data Enterprise environmental factors Organizational process assets
  • 7. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engagement -> Inputs Project Management Plan Project documents Work Performance Data Enterprise environmental factors Organizational process assets
  • 8. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Monitor Stakeholder engagement -> Inputs -> PMP Stakeholder engagement plan Resource management Plan Communication Management plan Following PMP/subsidiary plans may help in monitoring stakeholder engagement.
  • 9. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Project documents • Important tool used to manage & resolve issues. • Helps to monitor stakeholder related issues & disputes. • Track end to end progress on issue resolutions. Issue log: Monitor Stakeholder engagement -> Inputs -> Project documents Stakeholder Register Issue log Project Communication Risk Register Lessons learned register Review project document to ensure they support effective stakeholder engagement & management
  • 10. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Work Performance Data It’s a raw observations & measurements identified during Direct and Manage Project work. Contains data such as which stakeholders has completed or delayed tasks/milestones. CR’s, issues raised by stakeholders etc Executing PG -> Direct and Manage Project work Work Performance Data Monitoring & Controlling PG Monitor Stakeholder Engagement. Monitor Stakeholder Engagement->Input->WPD
  • 11. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engagement -> ITTO Data analysis Meetings Decision making Data Representation Communication skills Interpersonal and team skills
  • 12. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Data analysis Following data analysis techniques could be used to monitor stakeholder engagement. Monitor Stakeholder engagement -> ITTO -> Data analysis Stakeholder Analysis • It helps determine the current position of stakeholders with regards to their engagement level. Root cause analysis • It used to determine the underlying reason, why stakeholder engagement is not yet getting the expected results.. Alternative analysis • It is used to evaluate options to respond to variances in the desired results of stakeholder engagement.
  • 13. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Decision making Following Decision making techniques can be used for monitoring stakeholder engagement. Monitor Stakeholder engagement -> ITTO -> Decision making Multi-criteria decision analysis • Several factors for successful stakeholder engagement are prioritized and weighted. Voting • It is used to select the best response for a variance in stakeholder engagement.
  • 14. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Data Representation Monitor Stakeholder engagement -> ITTO -> Data Representation Following Data Representation techniques may help in monitoring stakeholder engagement. Stakeholder engagement assessment matrix • Compare current engagement level to planned level. • Unaware, Resistant, Neutral, Supportive, Leading C: Current engagement level D: Desired engagement level Develop a plan to change engagement level from Current to Desired.
  • 15. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Communication skills Following Communication skills may help in monitoring stakeholder engagement. Presentation: • It provide clear information to stakeholders. • More effective than e-mails, newsletters • Provide an opportunity for real-time reaction from stakeholders Feedback • Feedback is used to ensure that the information to stakeholders is received and understood. Monitor Stakeholder engagement -> ITTO -> Communication skills
  • 16. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engag. -> ITTO -> Interpersonal & team skills Interpersonal and team skills Following Interpersonal and team skills may help in monitoring stakeholder engagement. Active listening Cultural awareness Leadership Networking Political awareness • Reduces misunderstandings and miscommunication Active listening • Help plan communications based on the cultural differences and requirements of stakeholders and team members. Cultural awareness • Help communicate the vision of project & inspire them to support project. Leadership
  • 17. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engag. -> ITTO -> Interpersonal & team skills Interpersonal and team skills Following Interpersonal and team skills may help in monitoring stakeholder engagement. Active listening Cultural awareness Leadership Networking Political awareness • Helps PM to learn about levels of engagement of stakeholders.Networking • Help understand organization strategies • Understand which stakeholder uses power and influence. • Helps develop an ability to communicate with these stakeholders. Political awareness
  • 18. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Meetings: are used to assess current stakeholder engagement levels and compare them to planned levels. Status / Stand-up meetings Retrospectives Steering committees Risk/ Issues review Meetings Monitor Stakeholder Engagement->T&T-> Meetings
  • 19. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder engagement -> Outputs Work Performance Information Change requests PMP updates Project document updates
  • 20. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Work Performance Information WPI represents the current status of stakeholder engagement. E.g., Current level of stakeholder support to the project, as compared to the desired levels. Further WPI is contextualized with WPI from other control processes to generate reports. Monitor Stakeholder Engagement->Outputs->WPI Monitoring & Controlling PG -> Monitor & control project work WPI Monitor Stakeholder Engagement T&T: Stakeholder engagement assessment matrix
  • 21. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) CR may be raised to change the Stakeholder engagement plan to include new engagement strategy or update existing. Corrective actions • Lead to improve stakeholder engagement Preventive actions • Reduce stakeholder issues Monitor Stakeholder Engagement->Outputs->Change Request Change requests
  • 22. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) PMP updates Following PMP/ subsidiary plans may get updated Monitor Stakeholder engag. -> Output -> PMP updates Stakeholder engagement plan • Any updates regarding information about stakeholders • Update to engagement strategy. Resource management Plan • The project team’s responsibilities for stakeholder engagement activities. Communication Management plan: • The communication strategies for engaging stakeholders may need to be updated.
  • 23. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Project document updates Following project documents may get updated Monitor Stakeholder engag. -> Output -> Project document updates Stakeholder Register • new information about stakeholders is updated. Issue log • Change in stakeholders attitudes towards any of the existing issues in the issue log. Lessons learned register • Lessons learned about challenges and how they could have been avoided. Risk Register • Stakeholders specific Risks need to be updated as a result of interaction with the stakeholders.
  • 24. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Monitor Stakeholder Engagement -> Review Monitor Stakeholder Engagement Definition Monitor Stakeholder Engagement - ITTO Data analysis - Root cause & Alternative analysis Decision making – Voting & MCDA Interpersonal and team skills Communication skills: Presentation, Feedback
  • 25. PMBOK 6 - All rights reserved – 2019, By: Anand Bobade (nmbobade@gmail.com) Project Stakeholder Management -> Complete review Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement I P E MC
  • 26. No one will believe in you until you believe in you. Robin Sharma