SlideShare a Scribd company logo
1 of 25
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Close Project or
phase
Chapter 5 ā€“
Project Integration Management
PMP SIXTH EDITION
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
4.7 Close Project or Phase
What is Phase or project closure?
Close Project or Phase process definition
Close Project or Phase - ITTO
Difference between Close Project & close Phase
What are accepted deliverables?
Contract closure Vs. Project closure.
Review
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Integration Management processes
Develop Project
Charter
Develop Project
Management plan
Direct and Manage
Project work
Manage Knowledge
Monitor & Control
Project Work
Perform Integrated
change Control
Close Project or
phase
I P EE
MC CMC
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase -> Overview
Hospital Opening Ceremony
Hospital construction work is completed
Medical equipment installation is completed
Staff has been Training to use medical equipment
Operational Team has been Trained to use/ operate facilities
Project is ready to be Closed.
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
The process of finalizing all activities across all of the PMP Groups to
formally complete the project or phase.
project or phase information is archived, the planned work is
completed, and organizational resources are released.
Close Project or Phase -> Definition
Finalizing
all
activities
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Project Managers focuses on:
Reviewing all prior information from the previous phase
closures.
Reviews scope baseline to ensure completion before
considering the project closed.
Ensure all project work is completed & project has met its
objectives.
Establishes the procedures to investigate & document reasons
for actions taken if a project is terminated before completion.
For successful closure, PM has to engage all concern
stakeholders.
Close Project or Phase -> Administrative closure
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Process includes all planned activities necessary for administrative
closure of the project or phase.
Actions and activities includes:
Satisfying completion or exit criteria.
Transfer projectā€™s products or services to operations.
Collect project or phase records
Audit project success or failure
Gather lessons learned
Archive project information
Close Project or Phase -> Administrative closure
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase->ITTO
Expert Judgment
Data analysis
Meetings
Project Charter
Project Management
plan
Project documents
Accepted deliverables
Business documents
Agreements
Organizational process
assets
Procurement
Documents
Project document
updates
Final product, service
or result transition
Final Report
OPA updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase -> Input
Accepted deliverables Project Charter Business documents Agreements
Project Management
plan
Procurement
Documents
Project documents
Organizational
process assets
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Accepted
deliverables
Any product, deliverable or purchased equipment which is approved by business.
Partial deliverables may also be included for phased or cancelled projects.
Example:
Software build after
UAT
Approved product
specifications (Building
drawing and plan)
Delivery receipts of
equipment
Close Project or Phase -> Input -> Accepted deliverables
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Project Charter
ā€¢ Objective : Verify project/phase has met its objective.
Business documents:
ā€¢ Business case; Benefit management plans
ā€¢ Ensure project has delivered benefits or ready for it.
Agreements:
ā€¢ Contracts may be used as input to verify all contractually
agreed deliverables & milestones are delivered.
Project Management plan
ā€¢ Plans & baselines; closure process
Close Project or Phase -> Input
Business Case
Benefit Management
plan
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Procurement
Documents
To close the contract all procurement documentation is collected, indexed and filed.
Close Project or Phase -> Input -> Procurement Documents
Procurement documents may includes:
ā€œAs-builtā€ plans
/ drawings
ā€œas developedā€
documents
Manuals Troubleshooting
Other technical
documentation
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Project documents
Below project documents may act as input for closure activities:
Close Project or Phase -> Input -> Project documents
Assumption log Issue log Change log
Lessons learned
register
Risk Register Risk Report Milestone list Basis of estimates
Quality control
measurements
Quality reports
Requirements
documentation
Project
communications
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase -> Tools & Techniques
Expert Judgment Data analysis Meetings
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Expert
Judgment
Experts ensures Project or phase closures is performed to appropriate standards.
Close Project or Phase -> Tools & Techniques -> Expert Judgment
Expertise can be used for
Management
control
Audit
Legal and
procurement
Legislation and
regulations
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Meetings
Close Project or Phase -> Tools & Techniques -> Meetings
To confirm the
deliverables have
been accepted
To validate that
the exit criteria
have been met
To formalize the
completion of
the contracts
To evaluate the
satisfaction of
the stakeholders
To gather lessons
learned
To transfer the
knowledge and
information
To celebrate
success
Following meeting may be used:
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Data analysis
Following data analysis techniques are used:
Close Project or Phase -> Tools & Techniques -> Data analysis
Document analysis
ā€¢Finalize project or phase records. Ensure all records are approved.
Regression analysis
ā€¢Involves examining one variable and see effect on dependant
variable. E.g., How Open defects are going to impact operational
cost.
Trend analysis
ā€¢The process of identifying trends is called Trend Analysis. E.g., PM
may analyse delay trend to establish fact that Vendor has used
less resources on project than contractually agreed.
Variance analysis
ā€¢It is an investigation of two comparable data points. There are
three major types of variance reviews: Estimated versus planned,
planned versus actual & Estimated versus actual.
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase -> Output
Final product,
service or result
transition
Final Report
Project document
updates
OPA updates
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Final product, service
or result transition
Refers to Transition of Final product, service to Operational team.
In case of a phase closure, it refers to intermediate product, service of that phase.
Close Project or Phase -> Output -> Final product, service or result transition
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Final Report
Itā€™s phase or project closure reports which start with summary level description.
Scope objectives, criteria to evaluate scope, and the completion evidences.
Quality objectives, criteria to evaluate the project and product quality, and variance information.
Schedule objectives, planned and actual dates, and reasons for variance.
Cost objectives including acceptable cost range, actual costs, and the reasons for variance
Summary of
How benefits
were achieved
How project
achieved the
business needs
identified in the
business plan
How Risk, Issues
were addressed
Close Project or Phase -> Output -> Final Report
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Project document
updates
Project documents:
Operational and support
documents
Project or phase closure
documents
Lessons learned
repository
Close Project or Phase -> Output -> Project document updates
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
OPA updates
ā€¢ PMP; scope, cost, schedule, and project
calendars, risk & other registers;
ā€¢ CM documentation, planned risk
responses, and risk impact.
Project
files:
ā€¢ formal documentation that indicates
completion of the project or phase
ā€¢ Transfer of the completed project or
phase deliverables.
Project or
phase
closure
documents:
ā€¢ Lessons learned that can be
recommended for use, by future
projects.
Historical
information
Close Project or Phase -> Output -> OPA updates
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Close Project or Phase -> Quick Review
What is project or phase closure?
process definition
ITTO
What is successful project closure?
What is Transition of product to operations.
Final Report
PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com)
Integration Management processes
Develop Project
Charter
Develop Project
Management plan
Direct and Manage
Project work
Manage Knowledge
Monitor & Control
Project Work
Perform Integrated
change Control
Close Project or
phase
I P EE
MC CMC
PMBOK Close Project Phase Guide

More Related Content

What's hot

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
Ā 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
Ā 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBSAnand Bobade
Ā 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
Ā 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
Ā 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewAnand Bobade
Ā 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
Ā 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
Ā 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
Ā 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
Ā 
Chap 13.4 Monitor stakeholder
Chap 13.4 Monitor stakeholderChap 13.4 Monitor stakeholder
Chap 13.4 Monitor stakeholderAnand Bobade
Ā 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
Ā 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
Ā 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
Ā 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
Ā 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
Ā 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
Ā 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2Anand Bobade
Ā 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
Ā 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
Ā 

What's hot (20)

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
Ā 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
Ā 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
Ā 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
Ā 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
Ā 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
Ā 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
Ā 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
Ā 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
Ā 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
Ā 
Chap 13.4 Monitor stakeholder
Chap 13.4 Monitor stakeholderChap 13.4 Monitor stakeholder
Chap 13.4 Monitor stakeholder
Ā 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
Ā 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
Ā 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
Ā 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Ā 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
Ā 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
Ā 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2
Ā 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
Ā 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
Ā 

Similar to PMBOK Close Project Phase Guide

Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
Ā 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
Ā 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
Ā 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
Ā 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
Ā 
Program management-steps
Program management-stepsProgram management-steps
Program management-stepsBhawani N Prasad
Ā 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
Ā 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
Ā 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
Ā 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
Ā 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsFlevy.com Best Practices
Ā 
PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015Owen Grant
Ā 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
Ā 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
Ā 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
Ā 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
Ā 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvkGlenn Van_kooijk
Ā 
Software metrics in contracts
Software metrics in contractsSoftware metrics in contracts
Software metrics in contractsNesma
Ā 

Similar to PMBOK Close Project Phase Guide (20)

Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
Ā 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
Ā 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
Ā 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
Ā 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
Ā 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
Ā 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
Ā 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
Ā 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
Ā 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
Ā 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
Ā 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
Ā 
PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015PMO Services Client Annual Review 2015
PMO Services Client Annual Review 2015
Ā 
PM-Project Closing-UiTM Project
PM-Project Closing-UiTM ProjectPM-Project Closing-UiTM Project
PM-Project Closing-UiTM Project
Ā 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
Ā 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
Ā 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
Ā 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
Ā 
Epm dimensys introductie gvk
Epm dimensys introductie gvkEpm dimensys introductie gvk
Epm dimensys introductie gvk
Ā 
Software metrics in contracts
Software metrics in contractsSoftware metrics in contracts
Software metrics in contracts
Ā 

More from Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
Ā 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
Ā 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
Ā 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
Ā 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
Ā 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
Ā 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
Ā 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
Ā 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
Ā 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
Ā 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
Ā 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
Ā 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
Ā 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
Ā 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
Ā 

More from Anand Bobade (15)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
Ā 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
Ā 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
Ā 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
Ā 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
Ā 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
Ā 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
Ā 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
Ā 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
Ā 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
Ā 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
Ā 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
Ā 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
Ā 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
Ā 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
Ā 

Recently uploaded

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
Ā 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
Ā 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
Ā 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
Ā 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Roomdivyansh0kumar0
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
Ā 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
Ā 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
Ā 
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)jennyeacort
Ā 
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁjdkhjh
Ā 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
Ā 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
Ā 

Recently uploaded (17)

LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
Ā 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Ā 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
Ā 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Ā 
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Servicesauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
Ā 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Ā 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Ā 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
Ā 
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)
Call UsšŸ”ā‡›+91-97111šŸ”47426 Call In girls Munirka (DELHI)
Ā 
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ
原ē‰ˆ1:1复刻åƆč„æč„æęƔ大学ęƕäøščƁMississippięƕäøščƁē•™äæ”å­¦åŽ†č®¤čƁ
Ā 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
Ā 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
Ā 

PMBOK Close Project Phase Guide

  • 1. Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Close Project or phase Chapter 5 ā€“ Project Integration Management PMP SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) 4.7 Close Project or Phase What is Phase or project closure? Close Project or Phase process definition Close Project or Phase - ITTO Difference between Close Project & close Phase What are accepted deliverables? Contract closure Vs. Project closure. Review
  • 3. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Integration Management processes Develop Project Charter Develop Project Management plan Direct and Manage Project work Manage Knowledge Monitor & Control Project Work Perform Integrated change Control Close Project or phase I P EE MC CMC
  • 4. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase -> Overview Hospital Opening Ceremony Hospital construction work is completed Medical equipment installation is completed Staff has been Training to use medical equipment Operational Team has been Trained to use/ operate facilities Project is ready to be Closed.
  • 5. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) The process of finalizing all activities across all of the PMP Groups to formally complete the project or phase. project or phase information is archived, the planned work is completed, and organizational resources are released. Close Project or Phase -> Definition Finalizing all activities
  • 6. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Project Managers focuses on: Reviewing all prior information from the previous phase closures. Reviews scope baseline to ensure completion before considering the project closed. Ensure all project work is completed & project has met its objectives. Establishes the procedures to investigate & document reasons for actions taken if a project is terminated before completion. For successful closure, PM has to engage all concern stakeholders. Close Project or Phase -> Administrative closure
  • 7. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Process includes all planned activities necessary for administrative closure of the project or phase. Actions and activities includes: Satisfying completion or exit criteria. Transfer projectā€™s products or services to operations. Collect project or phase records Audit project success or failure Gather lessons learned Archive project information Close Project or Phase -> Administrative closure
  • 8. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase->ITTO Expert Judgment Data analysis Meetings Project Charter Project Management plan Project documents Accepted deliverables Business documents Agreements Organizational process assets Procurement Documents Project document updates Final product, service or result transition Final Report OPA updates Inputs Tools & Techniques Outputs
  • 9. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase -> Input Accepted deliverables Project Charter Business documents Agreements Project Management plan Procurement Documents Project documents Organizational process assets
  • 10. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Accepted deliverables Any product, deliverable or purchased equipment which is approved by business. Partial deliverables may also be included for phased or cancelled projects. Example: Software build after UAT Approved product specifications (Building drawing and plan) Delivery receipts of equipment Close Project or Phase -> Input -> Accepted deliverables
  • 11. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Project Charter ā€¢ Objective : Verify project/phase has met its objective. Business documents: ā€¢ Business case; Benefit management plans ā€¢ Ensure project has delivered benefits or ready for it. Agreements: ā€¢ Contracts may be used as input to verify all contractually agreed deliverables & milestones are delivered. Project Management plan ā€¢ Plans & baselines; closure process Close Project or Phase -> Input Business Case Benefit Management plan
  • 12. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Procurement Documents To close the contract all procurement documentation is collected, indexed and filed. Close Project or Phase -> Input -> Procurement Documents Procurement documents may includes: ā€œAs-builtā€ plans / drawings ā€œas developedā€ documents Manuals Troubleshooting Other technical documentation
  • 13. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Project documents Below project documents may act as input for closure activities: Close Project or Phase -> Input -> Project documents Assumption log Issue log Change log Lessons learned register Risk Register Risk Report Milestone list Basis of estimates Quality control measurements Quality reports Requirements documentation Project communications
  • 14. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase -> Tools & Techniques Expert Judgment Data analysis Meetings
  • 15. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Expert Judgment Experts ensures Project or phase closures is performed to appropriate standards. Close Project or Phase -> Tools & Techniques -> Expert Judgment Expertise can be used for Management control Audit Legal and procurement Legislation and regulations
  • 16. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Meetings Close Project or Phase -> Tools & Techniques -> Meetings To confirm the deliverables have been accepted To validate that the exit criteria have been met To formalize the completion of the contracts To evaluate the satisfaction of the stakeholders To gather lessons learned To transfer the knowledge and information To celebrate success Following meeting may be used:
  • 17. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Data analysis Following data analysis techniques are used: Close Project or Phase -> Tools & Techniques -> Data analysis Document analysis ā€¢Finalize project or phase records. Ensure all records are approved. Regression analysis ā€¢Involves examining one variable and see effect on dependant variable. E.g., How Open defects are going to impact operational cost. Trend analysis ā€¢The process of identifying trends is called Trend Analysis. E.g., PM may analyse delay trend to establish fact that Vendor has used less resources on project than contractually agreed. Variance analysis ā€¢It is an investigation of two comparable data points. There are three major types of variance reviews: Estimated versus planned, planned versus actual & Estimated versus actual.
  • 18. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase -> Output Final product, service or result transition Final Report Project document updates OPA updates
  • 19. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Final product, service or result transition Refers to Transition of Final product, service to Operational team. In case of a phase closure, it refers to intermediate product, service of that phase. Close Project or Phase -> Output -> Final product, service or result transition
  • 20. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Final Report Itā€™s phase or project closure reports which start with summary level description. Scope objectives, criteria to evaluate scope, and the completion evidences. Quality objectives, criteria to evaluate the project and product quality, and variance information. Schedule objectives, planned and actual dates, and reasons for variance. Cost objectives including acceptable cost range, actual costs, and the reasons for variance Summary of How benefits were achieved How project achieved the business needs identified in the business plan How Risk, Issues were addressed Close Project or Phase -> Output -> Final Report
  • 21. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Project document updates Project documents: Operational and support documents Project or phase closure documents Lessons learned repository Close Project or Phase -> Output -> Project document updates
  • 22. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) OPA updates ā€¢ PMP; scope, cost, schedule, and project calendars, risk & other registers; ā€¢ CM documentation, planned risk responses, and risk impact. Project files: ā€¢ formal documentation that indicates completion of the project or phase ā€¢ Transfer of the completed project or phase deliverables. Project or phase closure documents: ā€¢ Lessons learned that can be recommended for use, by future projects. Historical information Close Project or Phase -> Output -> OPA updates
  • 23. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Close Project or Phase -> Quick Review What is project or phase closure? process definition ITTO What is successful project closure? What is Transition of product to operations. Final Report
  • 24. PMBOK 6 - All rights reserved 2019, By: Anand Bobade (nmbobade@gmail.com) Integration Management processes Develop Project Charter Develop Project Management plan Direct and Manage Project work Manage Knowledge Monitor & Control Project Work Perform Integrated change Control Close Project or phase I P EE MC CMC