SlideShare a Scribd company logo
1 of 36
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Chapter 12 –
Project Procurement Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Conduct
Procurement
SIXTH EDITION
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
12.2 Conduct Procurement
Introduction
Conduct Procurement Definition?
Conduct Procurement -> ITTO
What is seller proposals?
Bidder Conference
Proposal Evaluation Techniques
Procurement negotiations
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Procurement Management Processes
Plan Procurement
Management
Conduct Procurement Control Procurement
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
The process of obtaining seller responses, selecting a seller, and
awarding a contract.
It selects a qualified seller and implements the legal agreement
for delivery.
Seller1 Response Seller2 Response
Seller3 Response Seller4 Response
Conduct Procurement
Selected Seller Award Contract
Selection
process
Review
prop.
Evaluate
Seller
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement -> ITTO
Expert Judgment
Data analysis
Advertisement
Bidder Conference
Interpersonal and team skills
Project Management
Plan
Project documents
Procurement
documentation
Sellers Proposals
Enterprise
environmental factors
Organizational process
assets
Selected sellers
Agreements
Change Requests
PMP updates
Project document updates
OPA updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement -> Input
Project Management
Plan
Project documents Sellers Proposals
Procurement
documentation
Enterprise
environmental factors
Organizational
process assets
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Following subsidiary plans & cost baseline will provide key inputs.
Procurement
management Plan
Scope Management
Plan
Requirements
Management Plan
Communication
Management Plan
Risk Management Plan
Configuration
Management plan
Cost Baseline
Conduct Procurement -> Input -> Project Management Plan
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Scope Management Plan
• How the overall scope of work will be managed, including
scope performed by sellers.
Requirements Management Plan
• How seller will manage the requirements agreed in the
agreement.
Communication Management Plan
• How communication between buyer & seller will be
conducted.
Procurement management Plan
• Activities to be undertaken during conduct procurement.
Conduct Procurement -> Input -> Project Management Plan
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Risk Management Plan
• How risk management activities will be structured &
performed for the project.
Configuration Management plan
• Defines the configurable items & list items that
requires formal change control.
• Format & processes for how seller will provide
configuration management consistent with buyers
approach.
Cost Baseline
• Procurement budget .
• Cost associated with managing procurement
processes & sellers.
Conduct Procurement -> Input -> Project Management Plan
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Procurement
Management Plan
Plans describes how goods and services will be acquired from outside.
Procurement processes from developing procurement documents through contract closure.
Make‐or‐buy
decisions
Type of
contract
Team
responsibilities
Evaluation
criteria
Procurement
metrics
Plan Procurement Management-> Output-> Procurement MP
Managing multiple suppliers & coordination
Risk management (Performance bonds/insurance)
Form/format of procurement document
Procurement SOW
Constraints and assumptions
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project documents
Following Project documents will provide key inputs.
Lessons learned register
•Lessons learned with regards to conducting procurement can be applied
to latter phases to improve efficiency.
Project schedule
•Start & end date of procurement activities.
•Contract deliverables due dates.
Requirements documentation
•Technical requirement that seller is required to satisfy.
•Requirements with contractual & legal implications–Health, safety,
security etc.
Risk Register
•Each approved seller comes with its own set of risks.
•e.g., Sellers organization, Contract duration, project delivery method,
contract type, final agreed price etc.
Stakeholder Register
•Details about identified stakeholders.
Conduct Procurement -> Input -> Project documents
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Procurement
Documents
Used to solicit proposals, quotes, and bids from sellers.
Conduct Procurement->Input->Procurement Documents
Bid documents
(RFI, RFP, RFQ)
Procurement
Statement of Work
Independent cost
estimates
Source selection
criteria
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Procurement
Documents
Procurement Statement of Work
•Clearly stated goals, requirements & outcomes for which seller
can provide quantifiable response.
Independent cost estimates
•Developed internally or externally.
•Provide reasonableness check against bidders proposals.
Source selection criteria
•How bidders proposals will be evaluated, including evaluation
criteria & weights.
Conduct Procurement->Input->Procurement Documents
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Seller Proposals
Prepared in response to procurement documents.
Contains the information that will be used by an evaluation team to select one or more successful bidders (sellers).
Its good practice to submit separate technical & financial proposals.
Conduct Procurement->Input->Seller Proposals
Proposal1
Proposal2
Proposal3
Criteria1
Criteria2
Criteria3
Vendor Evaluation
(Source selection criteria)
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
OPA
Listing of preferred sellers that have been prequalified.
Organization policies that influence selection of a seller
Templates, guidelines that determine how agreements are drafted.
Invoicing & payment processes.
Conduct Procurement->Input->OPA
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Enterprise
environmental factors
Local laws & Regulations, e.g., involvement of local sellers
External economic environment; Marketplace conditions
Past experiences with sellers (good & bad)
Prior agreements
Contract management system
Conduct Procurement -> Input -> EEF
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement-> T&T
Expert Judgment Data analysis Advertisement
Bidder Conference
Interpersonal and
team skills
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment
Expert with specialised knowledge:
Conduct Procurement-> T&T->Expert Judgement
Proposal evaluation
Technical or SME
Functional expert
(finance, engineering
etc.)
Industry regulation
environment
Laws, regulation,
compliance
Negotiation
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Advertising
Advertising is communicating with users or potential users of the product or service.
Existing lists of potential sellers can often be expanded by placing advertisements.
Government may require public advertising or online posting of government contracts.
Trade publications Internet Newspapers
Conduct Procurement-> T&T->Advertising
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Bidder Conference
Contractor
conferences
Vendor
conferences
Pre-bid
conferences
Meetings between buyer & sellers
Ensure a clear and complete understanding of requirements
No bidders receive PREFERENTIAL treatment.
Listen to EVERY question and every answer.
Collecting questions from bidders
Arranging field visits
Conduct Procurement-> T&T->Bidder Conference
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Bidder Conference
Contractor
conferences
Vendor
conferences
Pre-bid
conferences
Conduct Procurement-> T&T->Bidder Conference
Important considerations:
Send details technical documents to Vendor, prior to the meeting
Send outline to the vendor & share actual documents during the meeting
Bring all Vendors together in a single room/single meeting
Meet Vendor individually when they are reluctant to share information.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement->T&T->Data analysis->Proposal Evaluation Tech.
Proposal
1
Proposal
2
Proposal
3
Criteria1
Criteria2
Criteria3
Evaluation Team
Screening system
Independent estimate
Past performance history
Weighting system
Proposal
Evaluation
Data analysis
Proposal Evaluation :
•The process of reviewing proposals provided by suppliers.
•Ensure proposals are complete & respond in full to bid documents.
•Selection will be done based on seller responses to selection criteria and
as per buyers procurement policies .
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Seller1 Seller2
Criteria Weight rating Score rating score
1 Company 6 85 510 99 594
2 Technical 9 90 810 90 810
3 Expertise 8 82 656 80 640
4 Cost 7 88 616 75 525
Total 2592 2569
Conduct Procurement->T&T->Data analysis->Proposal Evaluation Tech.
85
99
80
90 90 90
82 80 80
88
75
90
0
20
40
60
80
100
120
Seller1 Seller2 Seller3
Technical Company Expertice Cost
•Eliminate sellers who do no meet minimum requirementScreening system
•Estimation created in‐house or with outside assistanceIndependent estimate
•Use of historical information for selection.Past performance history
•Evaluate by weighting the source selection criteriaWeighting system
Data analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Interpersonal and
team skills
Negotiations:
•Clarify the structure, rights, obligations of parties and other terms of the
purchases to be reflected in Final contract.
•PM & other project management team may present during negotiation to
provide assistance.
•Obtain fair and reasonable price
•Develop good relationship with the seller
Objective of
negotiation:
Conduct Procurement-> T&T->Interpersonal & team skills-> Negotiations
What is
negotiated?
Scope Technical solutions
Technical & business
approaches
Authority to make
changes
Responsibilities
Overall schedule
/Milestones
Price Payment terms
Governing law Proprietary rights Contract financing
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Interpersonal and
team skills
Who should negotiate?
Conduct Procurement-> T&T->Interpersonal & team skills-> Negotiations
Attacks
Personal
insults
Good
guy/bad
guy
Deadline Lying
Limited
authority
Missing
man
Fair
reasonable
Delay
Extreme
demands
Withdrawa
l
PM should not be involved in negotiation.
PM team should not negotiate.
PM & PM team work as supporters & provides clarifications.
Negotiation
tactics
Lead Negotiator
will negotiate
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement->Output
Selected sellers Agreements Change Requests PMP updates
Project document
updates
OPA updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Selected sellers
• Based on the proposal or bid evaluation
Judged:
• A draft contract will become actual contract
when an award is made.
Negotiated:
• For all complex, high‐value, high‐risk
procurements prior to award.
Final senior management approval:
Conduct Procurement->Output->Selected Sellers
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Agreements
Contract is a mutually binding agreement that obligates:
Seller:
• To provide specified product, service or a result.
Buyer:
• To compensate the seller.
Procurement
Statement of work
or deliverables
Schedule,
milestones, date
Performance
reporting
Pricing and
payment terms
Inspection, quality
and acceptance
criteria
Warranty and
future product
support
Incentives and
penalties
Insurance and
performance bonds
Subordinate,
subcontractor
approvals
General terms and
conditions
Change request
handling
Termination clause,
alternative dispute
resolution (ADR)
mechanisms
Conduct Procurement->Output->Agreements
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Change Request due to:
More clarity on the work -> New scope addition.
Project duration/schedule may change based on proposal.
Cost may change based on Vendor proposal.
Conduct Procurement -> Output-> Change Request
Change Requests
Once seller is selected, typically project requires a change request to
adjust schedule, cost, payment milestones etc.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
PMP updates
Following subsidiary plans & baselines may get updated.
Requirements
Management Plan
Quality Management
plan
Communication
Management Plan
Risk Management Plan
Procurement
management Plan
Scope baseline
Schedule baseline Cost Baseline
Conduct Procurement->Output->PMP updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
PMP updates
Requirements Management Plan
• Requirements may change due to changes identified
by seller.
Quality Management plan
• Seller may offer alternative quality standard or solution
that may impact quality approach.
Communication Management Plan
• Updated to incorporate sellers communication needs
& approaches.
Risk Management Plan
• Each agreement & seller has its own set of risks which
may lead to updates.
Procurement management Plan
• Update may require depending on the result of the
contracting & negotiation process.
Conduct Procurement->Output->PMP updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
PMP updates
Scope baseline
• WBS & deliverables document may change during the
procurement process.
Schedule baseline
• Delivery changes created by seller may impact overall
schedule performance.
• baseline need to be updated to reflect current
expectations.
Cost Baseline
• Contractor & material prices can change frequently
due to fluctuating material & labour prices.
• Baseline need to be updated to reflect agreed
contract value.
Conduct Procurement->Output->PMP updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Documents
Updates
Following Project Documents may get updated.
Lessons learned
register
Requirements
documentation
Requirements
Traceability Matrix
Risk Register Stakeholder Register Resource calendars
Conduct Procurement->Output->Project document updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
OPA
Listing of prospective & prequalified sellers
Experience with sellers (Good & bad)
Conduct Procurement->Output ->OPA
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Conduct Procurement -> Review
Conduct Procurement process
Seller proposals
Bidder Conference
Proposal Evaluation Techniques
Independent estimates
Procurement negotiations
Agreements
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)

More Related Content

What's hot

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBSAnand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 

What's hot (20)

Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 

Similar to Chap 12.2 Conduct Procurement

Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewAnand Bobade
 
Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 
Overview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxOverview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxabiytk
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptxDoctorOkelloBen
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersAnand Bobade
 
Vendor selection
Vendor selectionVendor selection
Vendor selectionjanessa24
 
Software metrics in contracts
Software metrics in contractsSoftware metrics in contracts
Software metrics in contractsNesma
 

Similar to Chap 12.2 Conduct Procurement (20)

Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management Overview
 
Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholder
 
procurement overview
procurement overviewprocurement overview
procurement overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
Overview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxOverview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptx
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholders
 
Vendor selection
Vendor selectionVendor selection
Vendor selection
 
Software metrics in contracts
Software metrics in contractsSoftware metrics in contracts
Software metrics in contracts
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 

More from Anand Bobade (17)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 

Recently uploaded

Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 

Recently uploaded (16)

Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 

Chap 12.2 Conduct Procurement

  • 1. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Chapter 12 – Project Procurement Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Conduct Procurement SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 12.2 Conduct Procurement Introduction Conduct Procurement Definition? Conduct Procurement -> ITTO What is seller proposals? Bidder Conference Proposal Evaluation Techniques Procurement negotiations Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Procurement Management Processes Plan Procurement Management Conduct Procurement Control Procurement
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) The process of obtaining seller responses, selecting a seller, and awarding a contract. It selects a qualified seller and implements the legal agreement for delivery. Seller1 Response Seller2 Response Seller3 Response Seller4 Response Conduct Procurement Selected Seller Award Contract Selection process Review prop. Evaluate Seller
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement -> ITTO Expert Judgment Data analysis Advertisement Bidder Conference Interpersonal and team skills Project Management Plan Project documents Procurement documentation Sellers Proposals Enterprise environmental factors Organizational process assets Selected sellers Agreements Change Requests PMP updates Project document updates OPA updates Inputs Tools & Techniques Outputs
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement -> Input Project Management Plan Project documents Sellers Proposals Procurement documentation Enterprise environmental factors Organizational process assets
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Following subsidiary plans & cost baseline will provide key inputs. Procurement management Plan Scope Management Plan Requirements Management Plan Communication Management Plan Risk Management Plan Configuration Management plan Cost Baseline Conduct Procurement -> Input -> Project Management Plan
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Scope Management Plan • How the overall scope of work will be managed, including scope performed by sellers. Requirements Management Plan • How seller will manage the requirements agreed in the agreement. Communication Management Plan • How communication between buyer & seller will be conducted. Procurement management Plan • Activities to be undertaken during conduct procurement. Conduct Procurement -> Input -> Project Management Plan
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management Plan Risk Management Plan • How risk management activities will be structured & performed for the project. Configuration Management plan • Defines the configurable items & list items that requires formal change control. • Format & processes for how seller will provide configuration management consistent with buyers approach. Cost Baseline • Procurement budget . • Cost associated with managing procurement processes & sellers. Conduct Procurement -> Input -> Project Management Plan
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Procurement Management Plan Plans describes how goods and services will be acquired from outside. Procurement processes from developing procurement documents through contract closure. Make‐or‐buy decisions Type of contract Team responsibilities Evaluation criteria Procurement metrics Plan Procurement Management-> Output-> Procurement MP Managing multiple suppliers & coordination Risk management (Performance bonds/insurance) Form/format of procurement document Procurement SOW Constraints and assumptions
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project documents Following Project documents will provide key inputs. Lessons learned register •Lessons learned with regards to conducting procurement can be applied to latter phases to improve efficiency. Project schedule •Start & end date of procurement activities. •Contract deliverables due dates. Requirements documentation •Technical requirement that seller is required to satisfy. •Requirements with contractual & legal implications–Health, safety, security etc. Risk Register •Each approved seller comes with its own set of risks. •e.g., Sellers organization, Contract duration, project delivery method, contract type, final agreed price etc. Stakeholder Register •Details about identified stakeholders. Conduct Procurement -> Input -> Project documents
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Procurement Documents Used to solicit proposals, quotes, and bids from sellers. Conduct Procurement->Input->Procurement Documents Bid documents (RFI, RFP, RFQ) Procurement Statement of Work Independent cost estimates Source selection criteria
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Procurement Documents Procurement Statement of Work •Clearly stated goals, requirements & outcomes for which seller can provide quantifiable response. Independent cost estimates •Developed internally or externally. •Provide reasonableness check against bidders proposals. Source selection criteria •How bidders proposals will be evaluated, including evaluation criteria & weights. Conduct Procurement->Input->Procurement Documents
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Seller Proposals Prepared in response to procurement documents. Contains the information that will be used by an evaluation team to select one or more successful bidders (sellers). Its good practice to submit separate technical & financial proposals. Conduct Procurement->Input->Seller Proposals Proposal1 Proposal2 Proposal3 Criteria1 Criteria2 Criteria3 Vendor Evaluation (Source selection criteria)
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) OPA Listing of preferred sellers that have been prequalified. Organization policies that influence selection of a seller Templates, guidelines that determine how agreements are drafted. Invoicing & payment processes. Conduct Procurement->Input->OPA
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Enterprise environmental factors Local laws & Regulations, e.g., involvement of local sellers External economic environment; Marketplace conditions Past experiences with sellers (good & bad) Prior agreements Contract management system Conduct Procurement -> Input -> EEF
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement-> T&T Expert Judgment Data analysis Advertisement Bidder Conference Interpersonal and team skills
  • 18. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Expert Judgment Expert with specialised knowledge: Conduct Procurement-> T&T->Expert Judgement Proposal evaluation Technical or SME Functional expert (finance, engineering etc.) Industry regulation environment Laws, regulation, compliance Negotiation
  • 19. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Advertising Advertising is communicating with users or potential users of the product or service. Existing lists of potential sellers can often be expanded by placing advertisements. Government may require public advertising or online posting of government contracts. Trade publications Internet Newspapers Conduct Procurement-> T&T->Advertising
  • 20. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Bidder Conference Contractor conferences Vendor conferences Pre-bid conferences Meetings between buyer & sellers Ensure a clear and complete understanding of requirements No bidders receive PREFERENTIAL treatment. Listen to EVERY question and every answer. Collecting questions from bidders Arranging field visits Conduct Procurement-> T&T->Bidder Conference
  • 21. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Bidder Conference Contractor conferences Vendor conferences Pre-bid conferences Conduct Procurement-> T&T->Bidder Conference Important considerations: Send details technical documents to Vendor, prior to the meeting Send outline to the vendor & share actual documents during the meeting Bring all Vendors together in a single room/single meeting Meet Vendor individually when they are reluctant to share information.
  • 22. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement->T&T->Data analysis->Proposal Evaluation Tech. Proposal 1 Proposal 2 Proposal 3 Criteria1 Criteria2 Criteria3 Evaluation Team Screening system Independent estimate Past performance history Weighting system Proposal Evaluation Data analysis Proposal Evaluation : •The process of reviewing proposals provided by suppliers. •Ensure proposals are complete & respond in full to bid documents. •Selection will be done based on seller responses to selection criteria and as per buyers procurement policies .
  • 23. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Seller1 Seller2 Criteria Weight rating Score rating score 1 Company 6 85 510 99 594 2 Technical 9 90 810 90 810 3 Expertise 8 82 656 80 640 4 Cost 7 88 616 75 525 Total 2592 2569 Conduct Procurement->T&T->Data analysis->Proposal Evaluation Tech. 85 99 80 90 90 90 82 80 80 88 75 90 0 20 40 60 80 100 120 Seller1 Seller2 Seller3 Technical Company Expertice Cost •Eliminate sellers who do no meet minimum requirementScreening system •Estimation created in‐house or with outside assistanceIndependent estimate •Use of historical information for selection.Past performance history •Evaluate by weighting the source selection criteriaWeighting system Data analysis
  • 24. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Interpersonal and team skills Negotiations: •Clarify the structure, rights, obligations of parties and other terms of the purchases to be reflected in Final contract. •PM & other project management team may present during negotiation to provide assistance. •Obtain fair and reasonable price •Develop good relationship with the seller Objective of negotiation: Conduct Procurement-> T&T->Interpersonal & team skills-> Negotiations What is negotiated? Scope Technical solutions Technical & business approaches Authority to make changes Responsibilities Overall schedule /Milestones Price Payment terms Governing law Proprietary rights Contract financing
  • 25. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Interpersonal and team skills Who should negotiate? Conduct Procurement-> T&T->Interpersonal & team skills-> Negotiations Attacks Personal insults Good guy/bad guy Deadline Lying Limited authority Missing man Fair reasonable Delay Extreme demands Withdrawa l PM should not be involved in negotiation. PM team should not negotiate. PM & PM team work as supporters & provides clarifications. Negotiation tactics Lead Negotiator will negotiate
  • 26. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement->Output Selected sellers Agreements Change Requests PMP updates Project document updates OPA updates
  • 27. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Selected sellers • Based on the proposal or bid evaluation Judged: • A draft contract will become actual contract when an award is made. Negotiated: • For all complex, high‐value, high‐risk procurements prior to award. Final senior management approval: Conduct Procurement->Output->Selected Sellers
  • 28. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Agreements Contract is a mutually binding agreement that obligates: Seller: • To provide specified product, service or a result. Buyer: • To compensate the seller. Procurement Statement of work or deliverables Schedule, milestones, date Performance reporting Pricing and payment terms Inspection, quality and acceptance criteria Warranty and future product support Incentives and penalties Insurance and performance bonds Subordinate, subcontractor approvals General terms and conditions Change request handling Termination clause, alternative dispute resolution (ADR) mechanisms Conduct Procurement->Output->Agreements
  • 29. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Change Request due to: More clarity on the work -> New scope addition. Project duration/schedule may change based on proposal. Cost may change based on Vendor proposal. Conduct Procurement -> Output-> Change Request Change Requests Once seller is selected, typically project requires a change request to adjust schedule, cost, payment milestones etc.
  • 30. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) PMP updates Following subsidiary plans & baselines may get updated. Requirements Management Plan Quality Management plan Communication Management Plan Risk Management Plan Procurement management Plan Scope baseline Schedule baseline Cost Baseline Conduct Procurement->Output->PMP updates
  • 31. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) PMP updates Requirements Management Plan • Requirements may change due to changes identified by seller. Quality Management plan • Seller may offer alternative quality standard or solution that may impact quality approach. Communication Management Plan • Updated to incorporate sellers communication needs & approaches. Risk Management Plan • Each agreement & seller has its own set of risks which may lead to updates. Procurement management Plan • Update may require depending on the result of the contracting & negotiation process. Conduct Procurement->Output->PMP updates
  • 32. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) PMP updates Scope baseline • WBS & deliverables document may change during the procurement process. Schedule baseline • Delivery changes created by seller may impact overall schedule performance. • baseline need to be updated to reflect current expectations. Cost Baseline • Contractor & material prices can change frequently due to fluctuating material & labour prices. • Baseline need to be updated to reflect agreed contract value. Conduct Procurement->Output->PMP updates
  • 33. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Documents Updates Following Project Documents may get updated. Lessons learned register Requirements documentation Requirements Traceability Matrix Risk Register Stakeholder Register Resource calendars Conduct Procurement->Output->Project document updates
  • 34. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) OPA Listing of prospective & prequalified sellers Experience with sellers (Good & bad) Conduct Procurement->Output ->OPA
  • 35. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Conduct Procurement -> Review Conduct Procurement process Seller proposals Bidder Conference Proposal Evaluation Techniques Independent estimates Procurement negotiations Agreements
  • 36. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)