SlideShare a Scribd company logo
1 of 17
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Trainer: Anand Bobade
PMP
PMBOK 6th Edition, 2019, All rights reserved.
Chapter 6 –
Project Schedule Management
Plan Schedule
management
Define Activities
Sequence
Activities
Estimate Activity
Duration
Develop
Schedule
Control
Schedule
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
6. Project Schedule Management
Overview
Trends & emerging practices
Tailoring considerations
Considerations for agile/adaptive environments
Schedule management processes
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Schedule Management-> Overview
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Trends & emerging practices
Single process
• Define activity
• Sequencing activities
• Durations estimations
• Developing a schedule
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Iterative scheduling with a backlog
• A form of rolling wave planning for predictive / agile approach to
product development.
Trends & emerging practices
Requirements - user
stories, then prioritized
time-boxed periods.
(2 to 4 weeks)
deliver the
incremental value
welcomes changes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
On-demand scheduling.
• This approach is used in Kanban system and it is based on the theory-of-constraints
and pull-based scheduling concepts of lean manufacturing
Kanban System
Trends & emerging practices
Theory of
constraints
pull-based
scheduling
Lean
manufacturing
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Kanban:
• Method for visualizing the flow of work, in order to balance demand with available
capacity and spot bottlenecks
Trends & emerging practices -> Kanban
Work items are
visualized
Participants can view of
progress
Team
members pull work as
capacity permits
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Pull-based scheduling
• Pull work from backlog and do it as soon as resources are available
Trends & emerging practices
Limit teams work in progress to
balance demand with delivery
Tasks are similar in size, as in
operations
Does not rely on a schedule that
was developed previously
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Theory of constraints
• Used in lean manufacturing.
• Identify the most important limiting factor and Systematically improve it.
Trends & emerging practices
Theory of
constraints
Identify the
Constraint
Exploit the
Constraint
Subordinate &
synchronize to
the constraint
Elevate
Repeat the
process
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Lifecycle approach
Resource availability
(Resources, Productivity)
Project dimensions
(Complexity, innovation)
Technology support
(PMIS)
Tailoring considerations
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Scaling factors like team size,
technical complexity
Multiple approaches
(traditional, agile, hybrid) can
be mixed
Adaptive approach - Iterative
scheduling
Role of Project Manager
- Not changing in Agile
Considerations for agile/adaptive environments
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Considerations for agile/adaptive environments
Adaptive approach - Iterative scheduling
Product Vision Product backlog Shippable
product
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Considerations for agile/adaptive environments
Role of Project Manager - Not changing in Agile
Project Manager
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Plan Schedule management:
• Establishing policies, procedures, &
documentation the project schedule
Define Activities:
• Identifying and documenting the specific actions
to produce the deliverables.
Sequence Activities:
• Iidentifying and documenting relationships among
the project activities.
Project Schedule Management processes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration:
• Estimating the number of work periods needed to
complete activities with estimated resources
Develop Schedule:
• Analysing activity sequences, durations, resource
requirements & constraints to create schedule
Control Schedule:
• Monitoring the status of project activities to
update project progress and manage changes
Project Schedule Management processes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Schedule Management -> Review
Overview
Trends & emerging practices
Tailoring considerations
Considerations for agile/adaptive environments
Schedule management processes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)

More Related Content

What's hot

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 

What's hot (20)

Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 

Similar to Chap 6.0 Schedule Management Overview

PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?

Similar to Chap 6.0 Schedule Management Overview (20)

Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Sage Project Management
Sage Project Management Sage Project Management
Sage Project Management
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 

More from Anand Bobade

More from Anand Bobade (12)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

Recently uploaded

Recently uploaded (12)

Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importance
 
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out PackagingW.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garg
 
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdfNurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholars
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Review
 

Chap 6.0 Schedule Management Overview

  • 1. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Trainer: Anand Bobade PMP PMBOK 6th Edition, 2019, All rights reserved. Chapter 6 – Project Schedule Management Plan Schedule management Define Activities Sequence Activities Estimate Activity Duration Develop Schedule Control Schedule
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 6. Project Schedule Management Overview Trends & emerging practices Tailoring considerations Considerations for agile/adaptive environments Schedule management processes Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Schedule Management-> Overview
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Trends & emerging practices Single process • Define activity • Sequencing activities • Durations estimations • Developing a schedule
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Iterative scheduling with a backlog • A form of rolling wave planning for predictive / agile approach to product development. Trends & emerging practices Requirements - user stories, then prioritized time-boxed periods. (2 to 4 weeks) deliver the incremental value welcomes changes
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) On-demand scheduling. • This approach is used in Kanban system and it is based on the theory-of-constraints and pull-based scheduling concepts of lean manufacturing Kanban System Trends & emerging practices Theory of constraints pull-based scheduling Lean manufacturing
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Kanban: • Method for visualizing the flow of work, in order to balance demand with available capacity and spot bottlenecks Trends & emerging practices -> Kanban Work items are visualized Participants can view of progress Team members pull work as capacity permits
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Pull-based scheduling • Pull work from backlog and do it as soon as resources are available Trends & emerging practices Limit teams work in progress to balance demand with delivery Tasks are similar in size, as in operations Does not rely on a schedule that was developed previously
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Theory of constraints • Used in lean manufacturing. • Identify the most important limiting factor and Systematically improve it. Trends & emerging practices Theory of constraints Identify the Constraint Exploit the Constraint Subordinate & synchronize to the constraint Elevate Repeat the process
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Lifecycle approach Resource availability (Resources, Productivity) Project dimensions (Complexity, innovation) Technology support (PMIS) Tailoring considerations
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Scaling factors like team size, technical complexity Multiple approaches (traditional, agile, hybrid) can be mixed Adaptive approach - Iterative scheduling Role of Project Manager - Not changing in Agile Considerations for agile/adaptive environments
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Considerations for agile/adaptive environments Adaptive approach - Iterative scheduling Product Vision Product backlog Shippable product
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Considerations for agile/adaptive environments Role of Project Manager - Not changing in Agile Project Manager
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Plan Schedule management: • Establishing policies, procedures, & documentation the project schedule Define Activities: • Identifying and documenting the specific actions to produce the deliverables. Sequence Activities: • Iidentifying and documenting relationships among the project activities. Project Schedule Management processes
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration: • Estimating the number of work periods needed to complete activities with estimated resources Develop Schedule: • Analysing activity sequences, durations, resource requirements & constraints to create schedule Control Schedule: • Monitoring the status of project activities to update project progress and manage changes Project Schedule Management processes
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Schedule Management -> Review Overview Trends & emerging practices Tailoring considerations Considerations for agile/adaptive environments Schedule management processes
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)