SlideShare a Scribd company logo
1 of 92
NEW MATERIALS AND TECHNOLOGIES
USED IN NISM, MUMBAI
DR K M SONI
CHIEF ENGINEER, CPWD, MUMBAI
NISM PATALGANGA, RASAYANI, MUMBAI
 LOCATION: 75 KMS FROM MUMBAI AIRPORT
 AREA OF PLOT: 70 ACRES
 CONSULTANT: HITEN SETHI & ASSOCIATES
 SANCTIONED COST: 315 CRORES
 PROJECT MANAGEMENT AGENCY: CPWD
NISM, PATALGANGA NEAR MUMBAI
FACILITIES
• ORIENTATION BLOCK
• ACADEMIC BLOCKS – 4
• LIBRARY
• OPEN AIR AMPHITHEATRE
• DINING HALL
• AUDITORIUM
• RECREATION BLOCK
• HOSTELS – 4
• RESIDENTIAL BLOCK
• UTILITY BLOCK
• DIRECTOR’S BUNGALOW
GLASS FIBRE REINFORCED CONCRETE PANELS
• GFRC panels have been used in the façade of orientation block. As may
be seen, external surface is curvilinear and thus a material for cladding
was searched which may fit exactly the architectural design envisaged.
Simultaneously, it was the requirement that the material is weather
proof and durable. Due to suitability of GFRC panels, they were adopted
as they could be manufactured in any shape.
• Hot dipped galvanized M.S framework and brackets were used for
supporting the GFRC panels. Minimum thickness of GFRC panels was
adopted as 15 mm whereas thicknesses at return flange/embedded
location was kept as 50 mm. The panels were strengthened by providing
sufficient nos. of horizontal and vertical stiffeners of stainless steel grade
316 of required shape and size as per design requirement.
• The panels consisted of glass fibers of @ 3.5 to 5% by weight, silica,
white cement and admixtures. Water repellant coating was applied on
the panels by dipping panels in required solution to withstand
atmospheric conditions.
POST TENSIONED SLAB
Post tensioned (PT) slabs were used in some portions of
academic blocks. This provided additional headroom for
the services. Additionally such construction has advantages
of higher clear spans, thinner slabs, lighter structure,
reduced cracking and deflections, reduction in storey
height resulting into more storeys in same height, rapid,
quality and skilled construction, and higher loading
performance. It has to be ensured that the slab is not
drilled during lifetime of the structure as it may damage
pre-stressing and lead to failure.
• After placement of steel and tendons, concreting is first
done except at the end from where stressing is done,
excess length cut and grouting carried out around the
tendons.
AAC BLOCKS
• Factory made AAC blocks have been used in
all masonry work. The blocks have low
density (about 550 kg per cum) and are eco-
friendly.
• Are light weight
• Have good acoustic and insulation properties.
• The blocks reduce the weight of structure
and also produce quality construction.
FALSE CEILING AND PANELLING
ORIENTATION BLOCK
ACADEMIC CUM ADMINISTRATIVE BLOCK
ACCOUSTIC FALSE CEILING
• Anutone Salon Slat plus False ceiling
NAMASTE FURNITURE
STAMPED CONCRETE
• Stamped concrete is concrete that is patterned or textured
or embossed to resemble a required pattern may be brick,
stone, slate, tile or wood. It is used for footpaths, walkways,
driveways etc.
• In laying stamped concrete, base was prepared with RCC
though if sub grade is found suitable, it can be provided with
plain concrete also. Over the concrete layer finished to the
grade, colour hardener is added of the required shade in the
fresh concrete as specified, troweled and floated. Approved
release agent is then applied evenly to the troweled surface
before stamping.
• While the concrete is still in plastic stage, required stamping
tools are applied to the surface and curing carried out as
specified.
EXPANDED POLYSTYRENE GEOFOAMBLOCKS
• Such blocks have been used in lecture halls on first and second floors of
the academic blocks for construction of steps. The blocks are very light
and thus help in weight reduction. Due to light weight, their handling
and placing is also easy. In the present case density of the blocks used
was 21.6 kg per cum.
• Despite its light weight, the material’s compressive resistance ranges
from about 15,178 to 128,223 Pa at a one percent strain. When used in
the steps, the thickness of the blocks should be as per the requirements
of the riser and laid accordingly so that riser of the step is sum of
thickness of the block, wire mess and screed concrete including thickness
of flooring if any or carpet as proposed. Over the blocks, wire mesh is
used to tie them, to keep in position and also for better bonding with the
concrete being laid over the blocks. Small thickness of concrete is used
for protection and flooring to be laid as per the architectural
requirements.
• When used in the walling, particularly in partition walls similar
procedure can be adopted except that wire mesh should be provided on
both sides of the wall.
FLOORINGS
GLASS
ACOUSTIC PANELS
ALUMINIUMLOUVERS
Service trenches
• Not a very new concept
• Being adopted in NISM
New materials and technologies used in NISM Mumbai

More Related Content

What's hot

New Building Materials
New Building MaterialsNew Building Materials
New Building MaterialsDr K M SONI
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSGuy Pomphrey
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSakshiMahadik3
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy constructionMudassir khan
 
Mortarless Masonry_Symposium_2010-03-30
Mortarless Masonry_Symposium_2010-03-30Mortarless Masonry_Symposium_2010-03-30
Mortarless Masonry_Symposium_2010-03-30Mina Gayed
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concreteRajat Nainwal
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTIONRajesh Kolli
 
Precast concrete structures
Precast concrete structuresPrecast concrete structures
Precast concrete structuresAglaia Connect
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesAr Jitendra
 
Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywallDenis Patel
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concreteAshik Ásh
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 
PLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURESPLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURESAjit Sabnis
 

What's hot (20)

New Building Materials
New Building MaterialsNew Building Materials
New Building Materials
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLS
 
national building code
national building codenational building code
national building code
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Rapidwall
RapidwallRapidwall
Rapidwall
 
Forms and materials for speedy construction
Forms and materials for speedy constructionForms and materials for speedy construction
Forms and materials for speedy construction
 
Mortarless system
Mortarless systemMortarless system
Mortarless system
 
Mortarless Masonry_Symposium_2010-03-30
Mortarless Masonry_Symposium_2010-03-30Mortarless Masonry_Symposium_2010-03-30
Mortarless Masonry_Symposium_2010-03-30
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
ALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTIONALTERNATE BUILDING MATERIALS  & TECHNOLOGICAL ALTERNATIVES IN  CONSTRUCTION
ALTERNATE BUILDING MATERIALS & TECHNOLOGICAL ALTERNATIVES IN CONSTRUCTION
 
Precast concrete structures
Precast concrete structuresPrecast concrete structures
Precast concrete structures
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Precast concrete - drywall
Precast  concrete - drywallPrecast  concrete - drywall
Precast concrete - drywall
 
Seminor report
Seminor reportSeminor report
Seminor report
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
 
Precast concrete structures
Precast concrete structuresPrecast concrete structures
Precast concrete structures
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
PLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURESPLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURES
 

Similar to New materials and technologies used in NISM Mumbai

Costrucability approaches and technology
Costrucability approaches and technologyCostrucability approaches and technology
Costrucability approaches and technologyThanigaivel Rajan
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptxdharmveersingh60
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdfNithyashree594058
 
Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides lohwenjun
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxNamanGhevariya
 
Prefabrication system
Prefabrication systemPrefabrication system
Prefabrication systemArun Arun
 
Session 3 low cost housing
Session 3 low cost housingSession 3 low cost housing
Session 3 low cost housingAmol Pawar
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfGourhariBiswas1
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction systemchirag aggarwal
 

Similar to New materials and technologies used in NISM Mumbai (20)

Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 
PPT 12.pptx
PPT 12.pptxPPT 12.pptx
PPT 12.pptx
 
Costrucability approaches and technology
Costrucability approaches and technologyCostrucability approaches and technology
Costrucability approaches and technology
 
DOC-20230626-555..pptx
DOC-20230626-555..pptxDOC-20230626-555..pptx
DOC-20230626-555..pptx
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
Ct3 presentation slides
Ct3 presentation slides Ct3 presentation slides
Ct3 presentation slides
 
Latest ct3
Latest ct3Latest ct3
Latest ct3
 
Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"
 
material ppt
material pptmaterial ppt
material ppt
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
 
Prefabrication system
Prefabrication systemPrefabrication system
Prefabrication system
 
Session 3 low cost housing
Session 3 low cost housingSession 3 low cost housing
Session 3 low cost housing
 
Low cost puneet
Low cost puneetLow cost puneet
Low cost puneet
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Site report
Site reportSite report
Site report
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
 
PREFABRICATION.pdf
PREFABRICATION.pdfPREFABRICATION.pdf
PREFABRICATION.pdf
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Jacketing
JacketingJacketing
Jacketing
 

More from Dr K M SONI

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage ConservationDr K M SONI
 
Project Management
Project ManagementProject Management
Project ManagementDr K M SONI
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leaderDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreementsDr K M SONI
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contractsDr K M SONI
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering worksDr K M SONI
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy buildingDr K M SONI
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste ManagementDr K M SONI
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contractsDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam BlocksDr K M SONI
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through GlassDr K M SONI
 

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

New materials and technologies used in NISM Mumbai

  • 1. NEW MATERIALS AND TECHNOLOGIES USED IN NISM, MUMBAI DR K M SONI CHIEF ENGINEER, CPWD, MUMBAI
  • 2. NISM PATALGANGA, RASAYANI, MUMBAI  LOCATION: 75 KMS FROM MUMBAI AIRPORT  AREA OF PLOT: 70 ACRES  CONSULTANT: HITEN SETHI & ASSOCIATES  SANCTIONED COST: 315 CRORES  PROJECT MANAGEMENT AGENCY: CPWD
  • 3.
  • 5. FACILITIES • ORIENTATION BLOCK • ACADEMIC BLOCKS – 4 • LIBRARY • OPEN AIR AMPHITHEATRE • DINING HALL • AUDITORIUM • RECREATION BLOCK • HOSTELS – 4 • RESIDENTIAL BLOCK • UTILITY BLOCK • DIRECTOR’S BUNGALOW
  • 6.
  • 7.
  • 8.
  • 9. GLASS FIBRE REINFORCED CONCRETE PANELS • GFRC panels have been used in the façade of orientation block. As may be seen, external surface is curvilinear and thus a material for cladding was searched which may fit exactly the architectural design envisaged. Simultaneously, it was the requirement that the material is weather proof and durable. Due to suitability of GFRC panels, they were adopted as they could be manufactured in any shape. • Hot dipped galvanized M.S framework and brackets were used for supporting the GFRC panels. Minimum thickness of GFRC panels was adopted as 15 mm whereas thicknesses at return flange/embedded location was kept as 50 mm. The panels were strengthened by providing sufficient nos. of horizontal and vertical stiffeners of stainless steel grade 316 of required shape and size as per design requirement. • The panels consisted of glass fibers of @ 3.5 to 5% by weight, silica, white cement and admixtures. Water repellant coating was applied on the panels by dipping panels in required solution to withstand atmospheric conditions.
  • 10.
  • 11. POST TENSIONED SLAB Post tensioned (PT) slabs were used in some portions of academic blocks. This provided additional headroom for the services. Additionally such construction has advantages of higher clear spans, thinner slabs, lighter structure, reduced cracking and deflections, reduction in storey height resulting into more storeys in same height, rapid, quality and skilled construction, and higher loading performance. It has to be ensured that the slab is not drilled during lifetime of the structure as it may damage pre-stressing and lead to failure. • After placement of steel and tendons, concreting is first done except at the end from where stressing is done, excess length cut and grouting carried out around the tendons.
  • 12.
  • 13.
  • 14. AAC BLOCKS • Factory made AAC blocks have been used in all masonry work. The blocks have low density (about 550 kg per cum) and are eco- friendly. • Are light weight • Have good acoustic and insulation properties. • The blocks reduce the weight of structure and also produce quality construction.
  • 15.
  • 16. FALSE CEILING AND PANELLING
  • 18.
  • 19.
  • 20.
  • 21.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. ACCOUSTIC FALSE CEILING • Anutone Salon Slat plus False ceiling
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 40.
  • 41.
  • 42.
  • 43.
  • 45. • Stamped concrete is concrete that is patterned or textured or embossed to resemble a required pattern may be brick, stone, slate, tile or wood. It is used for footpaths, walkways, driveways etc. • In laying stamped concrete, base was prepared with RCC though if sub grade is found suitable, it can be provided with plain concrete also. Over the concrete layer finished to the grade, colour hardener is added of the required shade in the fresh concrete as specified, troweled and floated. Approved release agent is then applied evenly to the troweled surface before stamping. • While the concrete is still in plastic stage, required stamping tools are applied to the surface and curing carried out as specified.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52. EXPANDED POLYSTYRENE GEOFOAMBLOCKS • Such blocks have been used in lecture halls on first and second floors of the academic blocks for construction of steps. The blocks are very light and thus help in weight reduction. Due to light weight, their handling and placing is also easy. In the present case density of the blocks used was 21.6 kg per cum. • Despite its light weight, the material’s compressive resistance ranges from about 15,178 to 128,223 Pa at a one percent strain. When used in the steps, the thickness of the blocks should be as per the requirements of the riser and laid accordingly so that riser of the step is sum of thickness of the block, wire mess and screed concrete including thickness of flooring if any or carpet as proposed. Over the blocks, wire mesh is used to tie them, to keep in position and also for better bonding with the concrete being laid over the blocks. Small thickness of concrete is used for protection and flooring to be laid as per the architectural requirements. • When used in the walling, particularly in partition walls similar procedure can be adopted except that wire mesh should be provided on both sides of the wall.
  • 53.
  • 54.
  • 55.
  • 56.
  • 58.
  • 59.
  • 60.
  • 61.
  • 62.
  • 63.
  • 64.
  • 65.
  • 66. GLASS
  • 67.
  • 68.
  • 69.
  • 70.
  • 71.
  • 72.
  • 73.
  • 74.
  • 75.
  • 76.
  • 77.
  • 78.
  • 80.
  • 81.
  • 83.
  • 84.
  • 85.
  • 86.
  • 87.
  • 88.
  • 89.
  • 90.
  • 91. Service trenches • Not a very new concept • Being adopted in NISM