SlideShare a Scribd company logo
1 of 5
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 1
TSPS /ISPS WORK IN RAJA CANAL
Project details-
In Bangalore water supply sewerage board project, the combined TSPS/ISPS construction work is in
progress near Raja Canal STP. Its include 40 mld terminal sewage pumping station for Raja canal & 20 mld
Intermediate sewage pumping station for Hormavu Sewage treatment plant.
Hurdles while starting the work-
 Sufficient space was not available for construction of TSPS/ISPS structure. After co-ordination with
the client, Raja Canal drain diverted parallel to the rail track by this way; we got the sufficient space
for construction as per the GFC drawing.
Photo showing the diversion ofexistingSWD drain.
 Location of proposed site is near to the existing Raja canal STP (40 mld ), the admin building & the
laboratory building are just 5 to 10 m away from the proposed TSPS & ISPS structure. Also depth of
excavation is 18 to 20 meter from natural ground level as per the GFC drawings, hence it is very
necessary to do proper planning & take proper precautionary measures before starting the
excavation of the proposed TSPS/ISPS structure.
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 2
Photo showing existing Structures arejust side ofexcavation line.
Hence we change the orientation of the structure as per the site condition to avoid any disturbance to
existing structure after proper approval from design team & client.
 Excavation for TSPS/ISPS –
The depth of excavation is 18 to 20 meter from natural ground level. The adjacent SWD drain and
existing STP admin buildings are very near to the line of excavation, hence we recommended to the
contractor to excavate sloping as well as stepping at an interval of every 2 to 4 m vertically, till the
hard strata found. After hard strata found we did the vertical excavation as shown in the
photograph below.
Photo showing-TSPS excavation work.
Every 2-4 m vertical interval 1-1.5 m horizontal step is provided, as shown in figure. It helped us in
the safety point of view. If any sudden collapse will happen the loose soil will slide gradually and
major quantity of soil will stands on the horizontal step provided, also very less quantity of soil will
reach up to the excavation bottom. Sufficient margin (2m to 2.5 m) has provided in between PCC
outer edge & excavation line (Bottom).
After completion of 50 % excavation suddenly collapse happen from the SWD drain side due to
excessive seepage & refilled soil. Hence we suggested to the contractor to do the sheet piling to
retain the loose soil (towards drain side).
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 3
Also sand bags are placed on the bank of drain for strengthening of drain as well as to minimize the
seepage, as shown in the above photograph.
After the sand bags lining on the bank of the drain we got better relief from the collapse as well as
seepage water.
 PCC & Reinforcement of raft-
After completing of PCC work the next challenging work was reinforcement of raft (ISPS/TSPS). As
sufficient space was not available to install the Crain, there is no any alternate to do the
transportation of steel manually at 18 m. depth below the natural ground level. It was done within
8 working days (Day & night), about 150 MT steel shifted for reinforcement of raft by 100 fitters &
helpers during the raining condition. It was the unbelieving experience for all of us, that we did this
work within such a short period.
The photo showing the reinforcement work is in progress.
After raft reinforcement completed
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 4
Casting of the Raft-
After completion of raft reinforcement the next most challenging work for us was, pouring the
concrete. (Quantity- 750 cum.)
While planning the concreting, it was very difficult to us as site RMC plant capacity is only 25
cum/hr. Also there are lots of obstruction to continuous supply of concrete due to traffic
department no entry for period of 8 am to 12 pm & 4 pm to 8 pm (Every day) , as site location is
inside the city, hence there is no any other alternate to complete the concrete work within 8 pm to
next day morning 8 am (within 12 hrs.).
Hence we planned to take the concrete from three different RMC plant vendors (Approved). As
depth of pouring is 18 m from ground level hence we brought 2 static concrete pumps & 2 boom
concrete placer ( truck mounted.) having boom length 36 & 42 m.
Photos showing the pump arrangement made for concreting.
By proper planning & efforts taken by all of us, we completed the raft concreting work within
12 hrs. at a rate of 62.5 cum / hr. It was amazing experience for all of us that such huge quantity
of concrete we did within the short time.
TSPS/ISPSWORK – S1A1 BWSSB.
Prepared By- Ravikiran Chendake Page 5
After completion of raft concrete.

More Related Content

What's hot

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Crosstown TO
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012San Jacinto River Authority
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zachary Maddox
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCrosstown TO
 

What's hot (20)

Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
Keelesdale Station, West Portal and Elevated Guideway Open House - October 2017
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
MANOJ RESUME
MANOJ RESUMEMANOJ RESUME
MANOJ RESUME
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017Eglinton and Mt Pleasant Stations Open House - October 2017
Eglinton and Mt Pleasant Stations Open House - October 2017
 
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
Chaplin & Avenue Stations Construction Liaison Committe Meeting - September 2017
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
AAMIR - PROFILE
AAMIR - PROFILEAAMIR - PROFILE
AAMIR - PROFILE
 
CV Mirani Sb Color
CV Mirani Sb ColorCV Mirani Sb Color
CV Mirani Sb Color
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01Zach Maddox - CV 2016 May 01
Zach Maddox - CV 2016 May 01
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
Ahmd Mahmoud c.v
Ahmd Mahmoud c.vAhmd Mahmoud c.v
Ahmd Mahmoud c.v
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 

Viewers also liked (6)

Rondas
Rondas Rondas
Rondas
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
 
Presentación SlideShare
Presentación SlideSharePresentación SlideShare
Presentación SlideShare
 
Best Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWordsBest Practices of Objection Handling in AdWords
Best Practices of Objection Handling in AdWords
 
Nguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logoNguyên tắc-thiết-kế-logo
Nguyên tắc-thiết-kế-logo
 
Conversion Tracking in AdWords
Conversion Tracking in AdWordsConversion Tracking in AdWords
Conversion Tracking in AdWords
 

Similar to Tsps

Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
PPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptxPPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptxSaketChandra4
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM Hemant Thakur
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptxAmirShafiq25
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChandra Mohan Lodha
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPrerak Ka.Patel
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 

Similar to Tsps (20)

1 sethi
1 sethi1 sethi
1 sethi
 
injo slip update
injo slip updateinjo slip update
injo slip update
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
bridge design
 bridge design bridge design
bridge design
 
PPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptxPPT seri Nallah 19.10.2023.pptx
PPT seri Nallah 19.10.2023.pptx
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
REPAIR OF THE SPILLWAY AT PANDOH DAM
REPAIR OF THE  SPILLWAY AT PANDOH DAM REPAIR OF THE  SPILLWAY AT PANDOH DAM
REPAIR OF THE SPILLWAY AT PANDOH DAM
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Summer training report
Summer training reportSummer training report
Summer training report
 
SACHIN CIVIL.docx
SACHIN CIVIL.docxSACHIN CIVIL.docx
SACHIN CIVIL.docx
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Update for pending works
Update for pending worksUpdate for pending works
Update for pending works
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Tsps

  • 1. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 1 TSPS /ISPS WORK IN RAJA CANAL Project details- In Bangalore water supply sewerage board project, the combined TSPS/ISPS construction work is in progress near Raja Canal STP. Its include 40 mld terminal sewage pumping station for Raja canal & 20 mld Intermediate sewage pumping station for Hormavu Sewage treatment plant. Hurdles while starting the work-  Sufficient space was not available for construction of TSPS/ISPS structure. After co-ordination with the client, Raja Canal drain diverted parallel to the rail track by this way; we got the sufficient space for construction as per the GFC drawing. Photo showing the diversion ofexistingSWD drain.  Location of proposed site is near to the existing Raja canal STP (40 mld ), the admin building & the laboratory building are just 5 to 10 m away from the proposed TSPS & ISPS structure. Also depth of excavation is 18 to 20 meter from natural ground level as per the GFC drawings, hence it is very necessary to do proper planning & take proper precautionary measures before starting the excavation of the proposed TSPS/ISPS structure.
  • 2. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 2 Photo showing existing Structures arejust side ofexcavation line. Hence we change the orientation of the structure as per the site condition to avoid any disturbance to existing structure after proper approval from design team & client.  Excavation for TSPS/ISPS – The depth of excavation is 18 to 20 meter from natural ground level. The adjacent SWD drain and existing STP admin buildings are very near to the line of excavation, hence we recommended to the contractor to excavate sloping as well as stepping at an interval of every 2 to 4 m vertically, till the hard strata found. After hard strata found we did the vertical excavation as shown in the photograph below. Photo showing-TSPS excavation work. Every 2-4 m vertical interval 1-1.5 m horizontal step is provided, as shown in figure. It helped us in the safety point of view. If any sudden collapse will happen the loose soil will slide gradually and major quantity of soil will stands on the horizontal step provided, also very less quantity of soil will reach up to the excavation bottom. Sufficient margin (2m to 2.5 m) has provided in between PCC outer edge & excavation line (Bottom). After completion of 50 % excavation suddenly collapse happen from the SWD drain side due to excessive seepage & refilled soil. Hence we suggested to the contractor to do the sheet piling to retain the loose soil (towards drain side).
  • 3. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 3 Also sand bags are placed on the bank of drain for strengthening of drain as well as to minimize the seepage, as shown in the above photograph. After the sand bags lining on the bank of the drain we got better relief from the collapse as well as seepage water.  PCC & Reinforcement of raft- After completing of PCC work the next challenging work was reinforcement of raft (ISPS/TSPS). As sufficient space was not available to install the Crain, there is no any alternate to do the transportation of steel manually at 18 m. depth below the natural ground level. It was done within 8 working days (Day & night), about 150 MT steel shifted for reinforcement of raft by 100 fitters & helpers during the raining condition. It was the unbelieving experience for all of us, that we did this work within such a short period. The photo showing the reinforcement work is in progress. After raft reinforcement completed
  • 4. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 4 Casting of the Raft- After completion of raft reinforcement the next most challenging work for us was, pouring the concrete. (Quantity- 750 cum.) While planning the concreting, it was very difficult to us as site RMC plant capacity is only 25 cum/hr. Also there are lots of obstruction to continuous supply of concrete due to traffic department no entry for period of 8 am to 12 pm & 4 pm to 8 pm (Every day) , as site location is inside the city, hence there is no any other alternate to complete the concrete work within 8 pm to next day morning 8 am (within 12 hrs.). Hence we planned to take the concrete from three different RMC plant vendors (Approved). As depth of pouring is 18 m from ground level hence we brought 2 static concrete pumps & 2 boom concrete placer ( truck mounted.) having boom length 36 & 42 m. Photos showing the pump arrangement made for concreting. By proper planning & efforts taken by all of us, we completed the raft concreting work within 12 hrs. at a rate of 62.5 cum / hr. It was amazing experience for all of us that such huge quantity of concrete we did within the short time.
  • 5. TSPS/ISPSWORK – S1A1 BWSSB. Prepared By- Ravikiran Chendake Page 5 After completion of raft concrete.