SERI NALLAH
DIVERSION OF SERI NALLAH AWAY FROM
ATAL TUNNEL ALIGNMENT
GENESIS
 During construction of Atal Tunnel, Seri Nallah fault zone was
encountered
 An Expert committee was formed by MOD which recommended
following: -
 Sealing and strengthening of concrete lining through Grouting
Works inside Atal Tunnel
 Diversion of Seri Nallah
 MoU signed between BRO and NHPC on 25th Jan 2022 for Diversion
of Seri Nallah
 Contract was awarded to M/S Venser by NHPC on 19th June 2022.
 Work started on ground on 01st Sep 2022 but subsequently it was
stopped by DFO due to Forest Clearance(FC)
 FC case was uploaded on Parivesh portal on 15 March 2022 and
uploaded again on 17 march 2023.
 Provisional sanction was granted on 17 July 2023
 Work resumed on 19 July 2023
GOOGLE IMAGERY OF SITE
SERI
NALLAH
Scope of Work Agency
 Diversion of Seri Nallah NHPC
 Construction of approach road to Drainage
Portal – 3.0 Km
BRO
 Construction of internal roads to various
sites of works – 3.80 Km
BRO
SERI NALLAH WORKS
SERI NALA DIVERSION SCHEME – LAYOUT PLAN
DRAINAGE
TUNNEL
GEO TREATMENT OF
SERI NALAH BED WITH
GEOMEMBRANE 450
MTR LENGTH
TRENCH
WEIR
PROPOSED
PRECAST RCC
PIPE WATER
CONDUCT
SYSTEM
ATAL
TUNNEL
SERI NALLAH
SOUTH PORTAL
DRAINAGE
TUNNEL
OUTLET
 Nallah Bed Treatment for 450 m length at Crossing of Seri Nallah area over Atal Tunnel to make the
nallah bed impervious for surface flow.
 A 3.0 m dia 623 long D-shaped unlined Drainage Tunnel to tap and divert part of the underground
seepage affecting Atal Tunnel is proposed above Atal Tunnel between Seri nala bed and Atal Tunnel.
 Trench weir 400 m downstream of outlet portal of drainage tunnel proposed to collect surface water
flow of Seri Nallah and underground seepage from drainage tunnel and divert towards south portal of
Atal tunnel through precast concrete RCC drain pipes of 1.40 m dia for 1050 m length as water
conductor system.
NORTH PORTAL
METHODOLGY PROPOSED FOR DIVERSION WORKS
 Nallah Bed Treament
 Seri nallah crosses above the Atal Tunnel alignment at Chainage 2500 m from South
Portal.
 Treatment of Seri nala bed from 450 m length on Upper reaches from this location
is proposed for bed treatment with Geomembrane and Geotextile with Gabion
mattress and Grouting to make the nallah bed impervious for surface flow and
thereby restricting the penetration of snow melt in the surrounding media.
 Drainage Tunnel
 To tap and divert part of the underground seepage affecting Atal Tunnel, a 3.0 m
diameter, D-shaped unlined drainage tunnel is proposed above Atal Tunnel
between Seri nala bed and Atal tunnel.
 Drainage tunnel has been aligned parallel to the alignment of Atal tunnel in order to
cover the Seri nala fault zone encountered during excavation of Atal tunnel which
might be contributing to seepage in the Atal tunnel.
 The water from drainage tunnel is outlet downstream of the Seri Nallah.
 Trench Wier
 Trench weir 400m downstream of the outlet portal of drainage tunnel has been
proposed to collect surface water flow of Seri nala and underground seepage from
drainage tunnel and divert towards south portal of Atal tunnel through precast
concrete RCC drain pipes of 1.40 m dia for 1050 m length.
SERI NALLAH DIVERSION WORKS
Name of Work Diversion of Seri Nallah away from Atal Tunnel,
Rohtang, Himachal Pradesh
Date of Signing of
MoU
25.01.2022
Name of Contractor M/s Vensar Constructions Company Limited,
Banjara Hills, Hyderabad
Letter of Award NH/CCW/CC-I/CO-182/PR11221/Seri Nallah/258/159
dated 19.07.2022
Contract Sum Rs.115,31,44,334/- (Rupees One Hundred Fifteen
Crore Thirty One Lakh Forty Four thousand Three
Hundred Thirty Four Only)
Revised due to change in GST rate from 12% to
18%
Rs.121,49,19,923/- (Rupees One Hundred Twenty
One Crore Forty Nine Lakh Nineteen thousand
Nine Hundred Twenty Three Only)
SERI NALLAH DIVERSION WORKS
Scheduled Date of Start 19.07.2022
Date of Completion
(As per Contract)
30.10.2023 (469 days)
Date of handing over of site to
contractor by NHPC
30.08.2022
(after restoration of access road by BRO).
Actual Date of Start of work 01.09.2022
Date of Completion
(As per revised schedule
submitted by contractor)
29.06.2024
Proposed Date of Completion
(after receipt of Forest Clearance)
04.10.2024
PHYSICAL & FINANCIAL PROGRESS OF WORK
(A) PHYSICAL PROGRESS
S.
N.
Description Date of
Start
Physical
Progress
Remarks
1. DRAINAGE TUNNEL WORK
(a) Excavation of
Drainage
Tunnel
25.07.23 4.8 % Slow progress due to
(a) Delay in handing over of site.
(b) Opening of crown at RD 4.5m to
10m & treatment thereof.
2. SERI NALLAH BED TREATMENT
(a) Excavation 01.11.22 80 % As per schedule.
(b) Concreting 13.09.23 5.9 % Slow progress due to
(a) Cement supply was badly affected
due to blockage of road at
multiple points upto site during
monsoon season.
(b) Stoppage of aggregate supply
due to impose of ban on crusher
plant by State Authority.
PHYSICAL & FINANCIAL PROGRESS OF WORK
S.
N.
Description Date of
Start
Physical
Progress
Remarks
3. CONSTRUCTION OF TRENCH WEIR
(a) Excavation of
Trench Weir
21.08.23 85%
(b) Concreting of
Guide Wall
25.09.23 50%
(c) Excavation for
laying of Pipe
line
21.09.23 28%
(B) FINANCIAL PROGRESS
 10% (approx.) financial progress has been achieved
SERI NALLAH BED TREATMENT – C/S
Geomembrane 1 mm
Geotextile 1 mm
River Bed Level
Geotextile 01 mm
Concrete Bed 300 mm
Gabion Mattress 500 mm
SERI NALLAH BED
GABION MATTRESS
GEOSYNTHETICS MEMBRANE
GEOTEXTILE
CONCRETE BED
DRAINAGE TUNNEL
FOREPOLING EXCAVATION
EXCAVATION REMOVAL OF MUCK
DRAINAGE TUNNEL- FOREPOLING
6m 6m
4m
(10⁰ – 12⁰ )
@150 mm C/C
X
X
X-X View
DRAINAGE TUNNEL X-Sec
3m
3m
TRENCH WEIR PLAN
TRENCH WEIR
Gabion Mattress
Geosynthetics Fibre
TIMELINE CHART
S.No Item Description Unit
BOQ
Qty
(LOA)
BOQ /
Anticipated
Qty
Qty
executed
Balance
Qty
Oct-23
Jun-24
Jul-24
Aug-24
Sep-24
Oct-24
Nov-24
1 2 7 8 8 9 10=8-9
I
Mobilisation & Initial Nallah
Diversion
II Exploratory Drilling Work
1
Drilling of exploratory hole in
Drainage Tunnel (200m)
m 200 200 0 200
40 20 20 60 60
III Seri Nallah Bed Treatmnent
1 Excavation of Seri Nala Bed Cum 102630 102630 66000 36630
25000 11630
2
Concreting/Treatment of Seri
Nala Bed
Cum 14600 11000 340 10660
5000 3500 2160
IV Drainage Tunnel
1 (a) Portal excavation Cum 5625 3213 3213 0
1 (b) Portal Concrete work Cum 50 45.99 45.99 0
2 Excavation of Drainage Tunnel m 610 623 23 600
100
MS-1
(25.07.23)
50 50 150 150 100
MS-4
3
Invert concreting, Drilling of
Drainage hole & Grouting
m 610 623 0 623
200 400 23
V Trench Weir Works
1 Diversion/Protection Dyke
2 Excavation of Trench Weir Cum 5080 13500 11000 2500
2250 250
3 Concreting of Trench Weir Cum 1950 1950 580 1370
800 400 170
MS-2
4 Back Filling Cum 12600 12600 970 11630
5000 2500 4130
5(a) Boulder Wire Crates Cum 382 382 0 382 120 60 60 142
5(b) CC Block Placement Cum 1350 1350 0 1350 400 300 250 400
VI Intake & Silt Flushing Conduit
2
Intake & Silt Flushing Conduit
excavation
Cum 580 1500 0 1500
1000 500
3
Intake & Silt Flushing Conduit
concreting
Cum 1810 1810 0 1810
600 1210
4 Back Filling Cum 9450 9450 0 9450 2500 5000 1950
VII
Precast Concrete Pipes, Drop
Collection Well, Outlet Spill
Channel
1
Excavation of Concrete Pipes,
Drop Collection Well, Outlet
Spill Channel.
Cum 37500 37500 2000 35500
9000 4250 4250 9000 9000
3
Laying of Precast Concrete
Pipes
m 1000 1000 0 1000
140 140 140 280 280 20
4 Other Concreting Works Cum 2700 2700 0 2700
400 350 350 700 700 200
5 Back Filling Cum 15750 15750 0 15750
2500 5000 5000 3250
VIII
HM Works (Design,
Fabrication, Erection &
Testing)
Sets 1 1 0 1
MS-3
Project : Diversion of Seri Nallah away from Atal Tunnel, Rohtang, Himachal Pradesh
Schedule of Construction
Nov-23
Dec-23 -
April-24
May-24
NON
-WORKING
SEASON
NON
-WORKING
SEASON
NON
-WORKING
SEASON
PLAN FOR COMPLETION OF WORK
 Non-working season: 15th Nov 2023 to 14th May 2023
 Milestones:
 MS-1 - Start of Excavation of Drainage Tunnel (25.07.2023)-
Achieved
 MS-2 - Completion of Concreting of Trench Weir (23.05.2024)
 MS-3 - Completion of HM Works (01.08.2024)
 MS-4 - Completion of Excavation of Drainage Tunnel (19-08-2024)
 Completion: 04-10-2024
 Working Season variation: Normally non Working Season has been
considered from 15th Nov to 14th May, however, in this working
season, continuous rainfall caused considerable delay and
hampered progress of work.
ARSN RD 3 KM
CONNECTIVITY
FMN Cl-9
GSB
WBM
BT
Km
0.00
Km
1.00
Km
3.00
Km
2.00
0.400
2.400
2.700
BT WORK ON APPROACH RD
INTERNAL RDS 3.80 KM
 Construction of road to reach the point
from where Seri Nallah will be diverted
(At site of Seri Nallah)
3.80 Km
 Date of Commencement 28 Sep 2022
 Tentative PDC Dec 2023 (W/o BT)
 Physical Progress 14 %
(Fmn cutting appx 2030 m done.
Accessibility granted to Seri
Nallah Bed Treatment work,
Trench weir and Drainage Tnl)
 Financial Progress 8 %
 Work suspended Work suspended due to snow fall
wef Nov 2022 till May 2023
Currently FMN and PMT work is in
progress
ARSN INTERNAL RD 3.80 KM
FMN Cl-9
GSB
WBM
Km
0.00
Km
1.00
Km
3.00
Km
2.00
Km
3.80
THANK YOU

More Related Content

Similar to PPT seri Nallah 19.10.2023.pptx

ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxssuser3797b9
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
Advent Portfolio - Presentation - 2022.pptx
Advent Portfolio - Presentation - 2022.pptxAdvent Portfolio - Presentation - 2022.pptx
Advent Portfolio - Presentation - 2022.pptxShyamPrasadThiraviam
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Hitesh Khanna
 
gammon report by priyanshu kumar, 9608684800
gammon report by priyanshu kumar, 9608684800gammon report by priyanshu kumar, 9608684800
gammon report by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Rajesh Prasad
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Mohammed wahab
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChandra Mohan Lodha
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 

Similar to PPT seri Nallah 19.10.2023.pptx (20)

ANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptxANPARA D FGD PPT 07.06.2023-M (2).pptx
ANPARA D FGD PPT 07.06.2023-M (2).pptx
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
smartparkannb.pdf
smartparkannb.pdfsmartparkannb.pdf
smartparkannb.pdf
 
Project report
Project reportProject report
Project report
 
5878 5
5878 55878 5
5878 5
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Advent Portfolio - Presentation - 2022.pptx
Advent Portfolio - Presentation - 2022.pptxAdvent Portfolio - Presentation - 2022.pptx
Advent Portfolio - Presentation - 2022.pptx
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Muhammad_Aslam_CV
Muhammad_Aslam_CVMuhammad_Aslam_CV
Muhammad_Aslam_CV
 
gammon report by priyanshu kumar, 9608684800
gammon report by priyanshu kumar, 9608684800gammon report by priyanshu kumar, 9608684800
gammon report by priyanshu kumar, 9608684800
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
 
South Jetty
South JettySouth Jetty
South Jetty
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
 
Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014Dcl hdd presentation 9 2-2014
Dcl hdd presentation 9 2-2014
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
mbl
mblmbl
mbl
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Pms presentation
Pms presentationPms presentation
Pms presentation
 

Recently uploaded

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

PPT seri Nallah 19.10.2023.pptx

  • 1. SERI NALLAH DIVERSION OF SERI NALLAH AWAY FROM ATAL TUNNEL ALIGNMENT
  • 2. GENESIS  During construction of Atal Tunnel, Seri Nallah fault zone was encountered  An Expert committee was formed by MOD which recommended following: -  Sealing and strengthening of concrete lining through Grouting Works inside Atal Tunnel  Diversion of Seri Nallah  MoU signed between BRO and NHPC on 25th Jan 2022 for Diversion of Seri Nallah  Contract was awarded to M/S Venser by NHPC on 19th June 2022.  Work started on ground on 01st Sep 2022 but subsequently it was stopped by DFO due to Forest Clearance(FC)  FC case was uploaded on Parivesh portal on 15 March 2022 and uploaded again on 17 march 2023.  Provisional sanction was granted on 17 July 2023  Work resumed on 19 July 2023
  • 3. GOOGLE IMAGERY OF SITE SERI NALLAH
  • 4. Scope of Work Agency  Diversion of Seri Nallah NHPC  Construction of approach road to Drainage Portal – 3.0 Km BRO  Construction of internal roads to various sites of works – 3.80 Km BRO SERI NALLAH WORKS
  • 5. SERI NALA DIVERSION SCHEME – LAYOUT PLAN DRAINAGE TUNNEL GEO TREATMENT OF SERI NALAH BED WITH GEOMEMBRANE 450 MTR LENGTH TRENCH WEIR PROPOSED PRECAST RCC PIPE WATER CONDUCT SYSTEM ATAL TUNNEL SERI NALLAH SOUTH PORTAL DRAINAGE TUNNEL OUTLET  Nallah Bed Treatment for 450 m length at Crossing of Seri Nallah area over Atal Tunnel to make the nallah bed impervious for surface flow.  A 3.0 m dia 623 long D-shaped unlined Drainage Tunnel to tap and divert part of the underground seepage affecting Atal Tunnel is proposed above Atal Tunnel between Seri nala bed and Atal Tunnel.  Trench weir 400 m downstream of outlet portal of drainage tunnel proposed to collect surface water flow of Seri Nallah and underground seepage from drainage tunnel and divert towards south portal of Atal tunnel through precast concrete RCC drain pipes of 1.40 m dia for 1050 m length as water conductor system. NORTH PORTAL
  • 6. METHODOLGY PROPOSED FOR DIVERSION WORKS  Nallah Bed Treament  Seri nallah crosses above the Atal Tunnel alignment at Chainage 2500 m from South Portal.  Treatment of Seri nala bed from 450 m length on Upper reaches from this location is proposed for bed treatment with Geomembrane and Geotextile with Gabion mattress and Grouting to make the nallah bed impervious for surface flow and thereby restricting the penetration of snow melt in the surrounding media.  Drainage Tunnel  To tap and divert part of the underground seepage affecting Atal Tunnel, a 3.0 m diameter, D-shaped unlined drainage tunnel is proposed above Atal Tunnel between Seri nala bed and Atal tunnel.  Drainage tunnel has been aligned parallel to the alignment of Atal tunnel in order to cover the Seri nala fault zone encountered during excavation of Atal tunnel which might be contributing to seepage in the Atal tunnel.  The water from drainage tunnel is outlet downstream of the Seri Nallah.  Trench Wier  Trench weir 400m downstream of the outlet portal of drainage tunnel has been proposed to collect surface water flow of Seri nala and underground seepage from drainage tunnel and divert towards south portal of Atal tunnel through precast concrete RCC drain pipes of 1.40 m dia for 1050 m length.
  • 7. SERI NALLAH DIVERSION WORKS Name of Work Diversion of Seri Nallah away from Atal Tunnel, Rohtang, Himachal Pradesh Date of Signing of MoU 25.01.2022 Name of Contractor M/s Vensar Constructions Company Limited, Banjara Hills, Hyderabad Letter of Award NH/CCW/CC-I/CO-182/PR11221/Seri Nallah/258/159 dated 19.07.2022 Contract Sum Rs.115,31,44,334/- (Rupees One Hundred Fifteen Crore Thirty One Lakh Forty Four thousand Three Hundred Thirty Four Only) Revised due to change in GST rate from 12% to 18% Rs.121,49,19,923/- (Rupees One Hundred Twenty One Crore Forty Nine Lakh Nineteen thousand Nine Hundred Twenty Three Only)
  • 8. SERI NALLAH DIVERSION WORKS Scheduled Date of Start 19.07.2022 Date of Completion (As per Contract) 30.10.2023 (469 days) Date of handing over of site to contractor by NHPC 30.08.2022 (after restoration of access road by BRO). Actual Date of Start of work 01.09.2022 Date of Completion (As per revised schedule submitted by contractor) 29.06.2024 Proposed Date of Completion (after receipt of Forest Clearance) 04.10.2024
  • 9. PHYSICAL & FINANCIAL PROGRESS OF WORK (A) PHYSICAL PROGRESS S. N. Description Date of Start Physical Progress Remarks 1. DRAINAGE TUNNEL WORK (a) Excavation of Drainage Tunnel 25.07.23 4.8 % Slow progress due to (a) Delay in handing over of site. (b) Opening of crown at RD 4.5m to 10m & treatment thereof. 2. SERI NALLAH BED TREATMENT (a) Excavation 01.11.22 80 % As per schedule. (b) Concreting 13.09.23 5.9 % Slow progress due to (a) Cement supply was badly affected due to blockage of road at multiple points upto site during monsoon season. (b) Stoppage of aggregate supply due to impose of ban on crusher plant by State Authority.
  • 10. PHYSICAL & FINANCIAL PROGRESS OF WORK S. N. Description Date of Start Physical Progress Remarks 3. CONSTRUCTION OF TRENCH WEIR (a) Excavation of Trench Weir 21.08.23 85% (b) Concreting of Guide Wall 25.09.23 50% (c) Excavation for laying of Pipe line 21.09.23 28% (B) FINANCIAL PROGRESS  10% (approx.) financial progress has been achieved
  • 11. SERI NALLAH BED TREATMENT – C/S Geomembrane 1 mm Geotextile 1 mm River Bed Level Geotextile 01 mm Concrete Bed 300 mm Gabion Mattress 500 mm
  • 12. SERI NALLAH BED GABION MATTRESS GEOSYNTHETICS MEMBRANE GEOTEXTILE CONCRETE BED
  • 14. DRAINAGE TUNNEL- FOREPOLING 6m 6m 4m (10⁰ – 12⁰ ) @150 mm C/C X X X-X View DRAINAGE TUNNEL X-Sec 3m 3m
  • 17. TIMELINE CHART S.No Item Description Unit BOQ Qty (LOA) BOQ / Anticipated Qty Qty executed Balance Qty Oct-23 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 1 2 7 8 8 9 10=8-9 I Mobilisation & Initial Nallah Diversion II Exploratory Drilling Work 1 Drilling of exploratory hole in Drainage Tunnel (200m) m 200 200 0 200 40 20 20 60 60 III Seri Nallah Bed Treatmnent 1 Excavation of Seri Nala Bed Cum 102630 102630 66000 36630 25000 11630 2 Concreting/Treatment of Seri Nala Bed Cum 14600 11000 340 10660 5000 3500 2160 IV Drainage Tunnel 1 (a) Portal excavation Cum 5625 3213 3213 0 1 (b) Portal Concrete work Cum 50 45.99 45.99 0 2 Excavation of Drainage Tunnel m 610 623 23 600 100 MS-1 (25.07.23) 50 50 150 150 100 MS-4 3 Invert concreting, Drilling of Drainage hole & Grouting m 610 623 0 623 200 400 23 V Trench Weir Works 1 Diversion/Protection Dyke 2 Excavation of Trench Weir Cum 5080 13500 11000 2500 2250 250 3 Concreting of Trench Weir Cum 1950 1950 580 1370 800 400 170 MS-2 4 Back Filling Cum 12600 12600 970 11630 5000 2500 4130 5(a) Boulder Wire Crates Cum 382 382 0 382 120 60 60 142 5(b) CC Block Placement Cum 1350 1350 0 1350 400 300 250 400 VI Intake & Silt Flushing Conduit 2 Intake & Silt Flushing Conduit excavation Cum 580 1500 0 1500 1000 500 3 Intake & Silt Flushing Conduit concreting Cum 1810 1810 0 1810 600 1210 4 Back Filling Cum 9450 9450 0 9450 2500 5000 1950 VII Precast Concrete Pipes, Drop Collection Well, Outlet Spill Channel 1 Excavation of Concrete Pipes, Drop Collection Well, Outlet Spill Channel. Cum 37500 37500 2000 35500 9000 4250 4250 9000 9000 3 Laying of Precast Concrete Pipes m 1000 1000 0 1000 140 140 140 280 280 20 4 Other Concreting Works Cum 2700 2700 0 2700 400 350 350 700 700 200 5 Back Filling Cum 15750 15750 0 15750 2500 5000 5000 3250 VIII HM Works (Design, Fabrication, Erection & Testing) Sets 1 1 0 1 MS-3 Project : Diversion of Seri Nallah away from Atal Tunnel, Rohtang, Himachal Pradesh Schedule of Construction Nov-23 Dec-23 - April-24 May-24 NON -WORKING SEASON NON -WORKING SEASON NON -WORKING SEASON
  • 18. PLAN FOR COMPLETION OF WORK  Non-working season: 15th Nov 2023 to 14th May 2023  Milestones:  MS-1 - Start of Excavation of Drainage Tunnel (25.07.2023)- Achieved  MS-2 - Completion of Concreting of Trench Weir (23.05.2024)  MS-3 - Completion of HM Works (01.08.2024)  MS-4 - Completion of Excavation of Drainage Tunnel (19-08-2024)  Completion: 04-10-2024  Working Season variation: Normally non Working Season has been considered from 15th Nov to 14th May, however, in this working season, continuous rainfall caused considerable delay and hampered progress of work.
  • 19. ARSN RD 3 KM CONNECTIVITY FMN Cl-9 GSB WBM BT Km 0.00 Km 1.00 Km 3.00 Km 2.00 0.400 2.400 2.700
  • 20. BT WORK ON APPROACH RD
  • 21. INTERNAL RDS 3.80 KM  Construction of road to reach the point from where Seri Nallah will be diverted (At site of Seri Nallah) 3.80 Km  Date of Commencement 28 Sep 2022  Tentative PDC Dec 2023 (W/o BT)  Physical Progress 14 % (Fmn cutting appx 2030 m done. Accessibility granted to Seri Nallah Bed Treatment work, Trench weir and Drainage Tnl)  Financial Progress 8 %  Work suspended Work suspended due to snow fall wef Nov 2022 till May 2023 Currently FMN and PMT work is in progress
  • 22. ARSN INTERNAL RD 3.80 KM FMN Cl-9 GSB WBM Km 0.00 Km 1.00 Km 3.00 Km 2.00 Km 3.80