2. 2
Agenda
• Eglinton Crosstown LRT Overview
• Eglinton Maintenance & Storage Facility
• Mount Dennis Station
• Railway Corridor
• West Portal & Elevated Guideway
• Tunnel Fit Out
• Keelesdale Station
• Caledonia Station
3. 3
Eglinton Crosstown LRT
• A 19-kilometre route separated from regular traffic
• 10-kilometres underground in west and central areas; 9-kilometres at surface in east
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• Transit communications system
• Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station
4. 4
Eglinton Crosstown LRT: Key Milestones
Contract signed
and Mobilization
EMSF Ready 1st
LRV Delivery
LRV Delivery Dates
Ready for Testing
and Commissioning
Substantial Completion
November 2018
October 2018
July 2015
March 2020 4
3
2
1
74 Months
5. 5
Maintenance & Storage Facility Concept: Aerial View
*60% rendering
1
2
3
4
1. Vehicle Cleaning Staff Building
2. Vehicle Cleaning & Inspection Facility (VCIF)
3. Maintenance Building
4. Operations Control Center
5
5. Operations Company
(OPSCO)
6. 6
Progress to Date – EMSF
Train WashMaintenance Building
foot print
Eglinton Maintenance and Storage Facility
Staff Building
7. 7
Progress to Date – EMSFProgress to date: EMSF
• Environmental & geotechnical testing
• Foundations for Maintenance, OPSCO, Vechile Cleaning and Staff Buildings
• Site services – dry/wet utilities (ongoing)
• Steel erection for Maintenance Building (started)
8. 8
1
2
3
4
5
6
7
8
Mount Dennis Concept: Aerial View
*60% rendering
1. Bus Loop
2. Main Entrance
3. Second Entrance
4. Building 9 – Third
Entrance
5. Maintenance Building
6. Operations Company
7. New Photography Drive Bridge
8. Rail Corridor
10. 10
Progress to date: Mount Dennis Station
• Foundations – Mount Dennis station box concrete structure – main entrance (ongoing)
• Site services – water main, sanitary and storm sewer placement
• Building 9 foundation
12. 12
Progress to date: West Portal & Elevated Guideway
Ongoing
• Walls and roof formwork and rebar – box tunnel construction
• Utility relocation works for Elevated Guideway
• To follow: Retaining wall and backfilling for Eglinton Avenue West realignment
2000 m3 reinforced concrete poured to date
13. 13
Tunnel Fit Out – Invert Pour
Concrete
slab to be
poured
With the completion of the tunnel boring, we now start the next step for work
in the tunnels with pouring of concrete slabs to ‘invert’ or flatten the tunnel
floor. This must occur prior to the installation of track and transit systems.
14. 14
Tunnel Fit Out – Concrete Pour Overview
• Concrete trucks deliver concrete every 30-60 minutes, depending on how
far down the tunnel the work is occurring
• Trucks park beside the shaft at Cedarvale (Allen Rd. and Eglinton), and
unload 9 m3 of concrete into a large pipe, into one of two mini concrete
trucks (4.5 m3 each) at the shaft floor.
• The mini truck in the shaft then drives down the tunnel to the next section
of tunnel to be inverted.
• The first stage of concrete pour began in tunnel section 1 on April 4, 2017,
and tunnel section 2 on April 17, 2017.
• On average, crews complete a section approximately 80 metres in length
of the concrete slab per day in each tunnel.
15. 15
Tunnel Invert Pour – Stage 1
• Concrete trucks deliver loose concrete to the work area
• Loose concrete mix is used to fill the bottom of the tunnel
• Tunnel Fit Out Crew flatten and smooth it
16. 16
Tunnel Invert Pour – Stage 2
• Workers install welded mesh which functions like rebar to help reinforce the next
layer of concrete
• Higher strength concrete is poured to provide the flat track slab for the rail tracks
• Workers spread the concrete, and a truss screed machine vibrates it into a perfectly
level surface
17. 17
Keelesdale Concept: Aerial View
1
2
3
4
5
1. Main Entrance
2. Third Entrance
3. Second Entrance
4. Traction Power Substation (TPSS)
5. Bus Loop
19. 19
Progress to date: Keelesdale Station
• First station to start construction in March 2016
• Utility relocations
• Shallow Excavation complete on the North Side of intersection
• Excavation at the Traction Power Substation (TPSS), third & main entrance
• North side major utility support beams installed
• North east side deck beams and timber mat installation
• All lanes to re-open to east and westbound traffic end May 2017
20. Caledonia Station Construction Update
Complete
Installation of geotechnical monitoring equipment
Hydro utility relocation work
Bell utility relocation
Traffic signal relocation at Blackthorn Ave and Eglinton Ave W
Piling of the station box
Installation of dewatering system
Shallow excavation to first round of tie-backs
Installation of first round lagging, tie-backs, braces and walers
Tower crane erection
Spring/Summer 2017
• Site service connection to wet utilities (one month)
• Dewatering (ongoing)
• Deep excavation (8 months)
• Monitoring of geotechnical instruments (ongoing)