SlideShare a Scribd company logo
1 of 32
PMS PRESENTATION
AG14082
AG14090
AG14143
AG14144
SERVICECORRIDORAT connaught place,
NEW DELHI
AERIAL VIEW
AC
FIRE
WATER
IRRIGATION
HT
L
T
FUTURE
EXPANSION
FUTURE
EXPANSION HT
FUTURE
EXPANSION LT
TELECOM
SIZE OF TRAY
 L.H.S : 1500 MM
 R.H.S : 2500
MM
SERVICE CORRIDOR
• Easy identification of services in corridor .
• Continuous monitoring.
• Quick fault detection.
• Ease and cost effectiveness of maintenance.
• Accessibility ensures any time serviceability
• Reduction in breakdown time.
• Future expansion of systems easier.
• Minimum inconvenience to public in case of maintenance.
Contractor and client
 Client : New Delhi Municipal Council (NDMC)
PMC: Engineers India Limited (EIL)
PROJECT INFORMATION
Estimated Cost Rs. 671 Crores
Service Corridor Cost Rs. 70 Crores
EIL Scope Of Work Project Management Consultancy
Project Zero Date 21.05.2008(TURNKEY
CONSULTANCY AGREEMENT
SIGNED BETWEEN NDMC & EIL)
Project Duration 30 Months
Funding Scope Partly By Govt. Of India(under
JNNURM SCHEME) And Partly By
NDMC
Type of contract Amended Turnkey Consultancy Contract
signed on 21.05.2008
Specifications
ITEMS NOS. FUTURE
EXPANSION
HT LINE 4 trays 1
LT CABLES 3 TRAYS 1
Telecom lines 1 tray -
Water supply 2(300mm dia) -
Gas lines - -
Fire water pipes 2(253-300mm dia) -
Air cooling system 1 duct -
SUBWAY & ROAD WORKS
• From B.K.S. Marg To
Panchkuian Road (Upto
DMRC Tunnel): 231m.
• From Panchkuian Road
(After DMRC Tunnel) To
Barakhamba Road:
716m. (Upto DMRC
Tunnel).
• From Barakhamba Road
To Janpath Lane: 223m
(After DMRC Tunnel).
Layout showing Proposed & Existing Subways
EXISTING
PROPOSED
TechnologyUsed
• Open cut method
• Top down method
TOP DOWN METHOD OF CONSTRUCTION
 Service Corridor, being made in Middle Circle of
Connaught Place is a tunnel of rectangular box
section of size (6.3 x 7 mtrs)
 Top Down Method of excavation adopted for the
project as deep excavation was to be carried out very
near to existing buildings
STEPS OF TOP DOWN METHOD
 Identification of Existing Utilities
 Shifting of Utilities & Making of Guide Wall
 Boring for Diaphragm Wall up to the required depth
 Lowering of R/F cage in the Bored Area
 Concreting of the Diaphragm Wall Panel
 Excavation & Chipping of Concrete up to the cut-off level
 RCC Top Slab for the Service Tunnel
 Excavation up to the Bottom Slab
Identificationof ExistingUtilities
 Making of Pre-trench across
the road at regular intervals
to identify the utilities
running along the Proposed
Service Tunnel
 After the utilities were
identified, methodology for
shifting of these utilities were
finalized
Pre – Trench showing the existing utilities
Shifting of Utilities & Making of Guide Wall
 The identified utilities were
diverted temporarily so as to
keep the utilities running & also
to make a guide wall for the
boring
 A Guide Wall was constructed
for a depth of 1.6 m along the
alignment of Service Corridor –
to assist in boring for
Diaphragm Wall & to shift any
unforeseen utilities which are
layed across the road & have
not been identified in the pre-
trench
Boring for Diaphragm Wall
 Boring done up to a depth of
14 m
 Boring done with the help of
bentonite slurry to help
stabilize the walls of the
boring till concreting is done
 The grab is tied to the body
of the crane as a safety
aspect to prevent it from
hitting any existing building
Lowering of R/FCage
• R/F Cage for Diaphragm
Wall Panels of Size (5.0
M) made ready before
boring is commenced
• Each R/F cage weighs
approximately 10.5 MT
Concreting for Diaphragm Wall
 Tremie Concreting done for
Diaphragm Wall
 Each Diaphragm Wall Panel is
56 cum
Excavationup to Bottom of Top Slab
 After the Diaphragm Wall is
casted, Excavation for bottom
of top slab is taken up, so
that the inconvenience to the
public is minimum.
TopSlab
 A top slab of 600 mm is casted,
leaving openings at regular
intervals, so that excavation inside
the tunnel can be carried out
Excavationfor Base Slab
 After the top slab is casted,
excavation inside the tunnel is
started for base slab works
Hindrances
• Existing utilities are a major
hindrance as work has to be
carried out without disturbing
these utilities
• No Drawings for the existing
utilities are available, which
makes the condition even
worse, as it slows down the
pace of the work
Hindrances
• Encroachment in Courtyards
make it difficult to work
• Encroachments exist, which
should be removed before any
work can be done
Hindrances
• Structurally weak columns
have caused the works to
proceed slowly
• Damaged roofs of buildings,
most of them being within
private property
Safety Measures
• Sumps And Pumps Are Proposed To Take Care Of
Instances Of Flooding. Further, No Service Line Has Been
Laid In The First 750mm From The Floor.
• As Far As Cables Are Concerned, Sufficient Fall Back
Space Has Been Provided As Per Relevant Codes Of
Practice.
• Gas Based Fire Fighting Measures Has Also Been
Provided In The Tunnel. Details Of The Fire Detection And
Fire Fighting Shall Be Dealt With Separately.
• Closed Circuit TV Shall Be Installed In The Tunnel For
Surveillance And Security.
Areas of Concern
• Excavation / Digging For Replacement Of Cables /
Other Services Results Can Be Avoided .
• Minimize Inconvenience To Public In Case Of
Maintenance.
• Avoid Traffic Diversions In Case Of Maintenance.
• Reduction In Breakdown Time Of Systems.
• Ease And Cost Effectiveness Of Maintenance.
• Identification Of Services In Tunnel Is Ensured Being
Centralized Systems.
• Future Expansion Of Systems Easier.
• Accordingly After Considering The Time Schedule
Involved In TBM Technology , It Is Proposed To
Construct The Tunnel By Open Cut And Cast In Situ
Method .
Conclusion
Pms presentation

More Related Content

What's hot

Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Linear Surface Drainage 101: Trench Drain Applications
Linear Surface Drainage 101: Trench Drain ApplicationsLinear Surface Drainage 101: Trench Drain Applications
Linear Surface Drainage 101: Trench Drain ApplicationsCommunications Branding
 
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Communications Branding
 
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...Communications Branding
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Tariq CURRICULUM VITAE
Tariq CURRICULUM VITAETariq CURRICULUM VITAE
Tariq CURRICULUM VITAETariq Bin Riaz
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Fairfax County
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Crosstown TO
 

What's hot (12)

Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Linear Surface Drainage 101: Trench Drain Applications
Linear Surface Drainage 101: Trench Drain ApplicationsLinear Surface Drainage 101: Trench Drain Applications
Linear Surface Drainage 101: Trench Drain Applications
 
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
 
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...
Urbanization and Extreme Weather Effects: How Stormwater Detention, Retention...
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Tariq CURRICULUM VITAE
Tariq CURRICULUM VITAETariq CURRICULUM VITAE
Tariq CURRICULUM VITAE
 
site proj 1
site proj 1site proj 1
site proj 1
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 

Viewers also liked

Visitor Management System
Visitor Management SystemVisitor Management System
Visitor Management SystemRITESH HELONDE
 
Intelligent Visitor Management Solution - LobbyTrac
Intelligent Visitor Management Solution - LobbyTracIntelligent Visitor Management Solution - LobbyTrac
Intelligent Visitor Management Solution - LobbyTracpbindia
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Shobhit Shekhar
 
Inttelix VisTrack - Intelligent Visitor Management System
Inttelix VisTrack - Intelligent Visitor Management SystemInttelix VisTrack - Intelligent Visitor Management System
Inttelix VisTrack - Intelligent Visitor Management SystemInttelix
 
Rfid based vechile parking management system
Rfid based vechile parking management systemRfid based vechile parking management system
Rfid based vechile parking management systemSaurav Suman
 
AUTOMATIC CAR PARKING SYSTEM
AUTOMATIC CAR PARKING SYSTEMAUTOMATIC CAR PARKING SYSTEM
AUTOMATIC CAR PARKING SYSTEMsowmya Sowmya
 

Viewers also liked (8)

Visitor Management System
Visitor Management SystemVisitor Management System
Visitor Management System
 
Intelligent Visitor Management Solution - LobbyTrac
Intelligent Visitor Management Solution - LobbyTracIntelligent Visitor Management Solution - LobbyTrac
Intelligent Visitor Management Solution - LobbyTrac
 
Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3Presentation Rev.A 17-Sep-2015 Revision 3
Presentation Rev.A 17-Sep-2015 Revision 3
 
Inttelix VisTrack - Intelligent Visitor Management System
Inttelix VisTrack - Intelligent Visitor Management SystemInttelix VisTrack - Intelligent Visitor Management System
Inttelix VisTrack - Intelligent Visitor Management System
 
eFACiLiTY Visitor Management System
eFACiLiTY Visitor Management SystemeFACiLiTY Visitor Management System
eFACiLiTY Visitor Management System
 
Rfid based vechile parking management system
Rfid based vechile parking management systemRfid based vechile parking management system
Rfid based vechile parking management system
 
AUTOMATIC CAR PARKING SYSTEM
AUTOMATIC CAR PARKING SYSTEMAUTOMATIC CAR PARKING SYSTEM
AUTOMATIC CAR PARKING SYSTEM
 
Rfid presentation
Rfid presentationRfid presentation
Rfid presentation
 

Similar to Pms presentation

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologydinesh sharma
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Hitesh Khanna
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.Himanshu Rao
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional BoringWe-Bore-It
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural WorksBabu Arumugam
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
Precision Directional Drilling - Horizontal Directional Drilling Solutions
Precision Directional Drilling - Horizontal Directional Drilling   SolutionsPrecision Directional Drilling - Horizontal Directional Drilling   Solutions
Precision Directional Drilling - Horizontal Directional Drilling SolutionsPrecision Directional Drilling
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY MD AMANULLAH
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdfpawankumar491710
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...Tobiloba Omitola
 

Similar to Pms presentation (20)

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Civil - Structural Works
Civil - Structural WorksCivil - Structural Works
Civil - Structural Works
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
Precision Directional Drilling - Horizontal Directional Drilling Solutions
Precision Directional Drilling - Horizontal Directional Drilling   SolutionsPrecision Directional Drilling - Horizontal Directional Drilling   Solutions
Precision Directional Drilling - Horizontal Directional Drilling Solutions
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
 
Trenchless technologies comparing thrust boring with horizontal directional ...
Trenchless technologies  comparing thrust boring with horizontal directional ...Trenchless technologies  comparing thrust boring with horizontal directional ...
Trenchless technologies comparing thrust boring with horizontal directional ...
 

Recently uploaded

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 

Recently uploaded (20)

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 

Pms presentation

  • 4. SERVICE CORRIDOR • Easy identification of services in corridor . • Continuous monitoring. • Quick fault detection. • Ease and cost effectiveness of maintenance. • Accessibility ensures any time serviceability • Reduction in breakdown time. • Future expansion of systems easier. • Minimum inconvenience to public in case of maintenance.
  • 5. Contractor and client  Client : New Delhi Municipal Council (NDMC) PMC: Engineers India Limited (EIL)
  • 6. PROJECT INFORMATION Estimated Cost Rs. 671 Crores Service Corridor Cost Rs. 70 Crores EIL Scope Of Work Project Management Consultancy Project Zero Date 21.05.2008(TURNKEY CONSULTANCY AGREEMENT SIGNED BETWEEN NDMC & EIL) Project Duration 30 Months Funding Scope Partly By Govt. Of India(under JNNURM SCHEME) And Partly By NDMC Type of contract Amended Turnkey Consultancy Contract signed on 21.05.2008
  • 7. Specifications ITEMS NOS. FUTURE EXPANSION HT LINE 4 trays 1 LT CABLES 3 TRAYS 1 Telecom lines 1 tray - Water supply 2(300mm dia) - Gas lines - - Fire water pipes 2(253-300mm dia) - Air cooling system 1 duct -
  • 8.
  • 9.
  • 10.
  • 11.
  • 12. SUBWAY & ROAD WORKS • From B.K.S. Marg To Panchkuian Road (Upto DMRC Tunnel): 231m. • From Panchkuian Road (After DMRC Tunnel) To Barakhamba Road: 716m. (Upto DMRC Tunnel). • From Barakhamba Road To Janpath Lane: 223m (After DMRC Tunnel). Layout showing Proposed & Existing Subways EXISTING PROPOSED
  • 13.
  • 14. TechnologyUsed • Open cut method • Top down method
  • 15. TOP DOWN METHOD OF CONSTRUCTION  Service Corridor, being made in Middle Circle of Connaught Place is a tunnel of rectangular box section of size (6.3 x 7 mtrs)  Top Down Method of excavation adopted for the project as deep excavation was to be carried out very near to existing buildings
  • 16. STEPS OF TOP DOWN METHOD  Identification of Existing Utilities  Shifting of Utilities & Making of Guide Wall  Boring for Diaphragm Wall up to the required depth  Lowering of R/F cage in the Bored Area  Concreting of the Diaphragm Wall Panel  Excavation & Chipping of Concrete up to the cut-off level  RCC Top Slab for the Service Tunnel  Excavation up to the Bottom Slab
  • 17. Identificationof ExistingUtilities  Making of Pre-trench across the road at regular intervals to identify the utilities running along the Proposed Service Tunnel  After the utilities were identified, methodology for shifting of these utilities were finalized Pre – Trench showing the existing utilities
  • 18. Shifting of Utilities & Making of Guide Wall  The identified utilities were diverted temporarily so as to keep the utilities running & also to make a guide wall for the boring  A Guide Wall was constructed for a depth of 1.6 m along the alignment of Service Corridor – to assist in boring for Diaphragm Wall & to shift any unforeseen utilities which are layed across the road & have not been identified in the pre- trench
  • 19. Boring for Diaphragm Wall  Boring done up to a depth of 14 m  Boring done with the help of bentonite slurry to help stabilize the walls of the boring till concreting is done  The grab is tied to the body of the crane as a safety aspect to prevent it from hitting any existing building
  • 20. Lowering of R/FCage • R/F Cage for Diaphragm Wall Panels of Size (5.0 M) made ready before boring is commenced • Each R/F cage weighs approximately 10.5 MT
  • 21. Concreting for Diaphragm Wall  Tremie Concreting done for Diaphragm Wall  Each Diaphragm Wall Panel is 56 cum
  • 22. Excavationup to Bottom of Top Slab  After the Diaphragm Wall is casted, Excavation for bottom of top slab is taken up, so that the inconvenience to the public is minimum.
  • 23. TopSlab  A top slab of 600 mm is casted, leaving openings at regular intervals, so that excavation inside the tunnel can be carried out
  • 24. Excavationfor Base Slab  After the top slab is casted, excavation inside the tunnel is started for base slab works
  • 25.
  • 26. Hindrances • Existing utilities are a major hindrance as work has to be carried out without disturbing these utilities • No Drawings for the existing utilities are available, which makes the condition even worse, as it slows down the pace of the work
  • 27. Hindrances • Encroachment in Courtyards make it difficult to work • Encroachments exist, which should be removed before any work can be done
  • 28. Hindrances • Structurally weak columns have caused the works to proceed slowly • Damaged roofs of buildings, most of them being within private property
  • 29. Safety Measures • Sumps And Pumps Are Proposed To Take Care Of Instances Of Flooding. Further, No Service Line Has Been Laid In The First 750mm From The Floor. • As Far As Cables Are Concerned, Sufficient Fall Back Space Has Been Provided As Per Relevant Codes Of Practice. • Gas Based Fire Fighting Measures Has Also Been Provided In The Tunnel. Details Of The Fire Detection And Fire Fighting Shall Be Dealt With Separately. • Closed Circuit TV Shall Be Installed In The Tunnel For Surveillance And Security.
  • 30. Areas of Concern • Excavation / Digging For Replacement Of Cables / Other Services Results Can Be Avoided . • Minimize Inconvenience To Public In Case Of Maintenance. • Avoid Traffic Diversions In Case Of Maintenance. • Reduction In Breakdown Time Of Systems. • Ease And Cost Effectiveness Of Maintenance. • Identification Of Services In Tunnel Is Ensured Being Centralized Systems. • Future Expansion Of Systems Easier. • Accordingly After Considering The Time Schedule Involved In TBM Technology , It Is Proposed To Construct The Tunnel By Open Cut And Cast In Situ Method .