Mohmand Dam Hydropower Project
Presentation to the Chairman WAPDA
17 August 2022
DISCUSSION
• Project Brief
• Project Progress
• Project Challenges
• Construction Challenges
• Construction Progress
• Issues and Bottlenecks
• Status of the Contractor’s Extension of Time Claims
1
PROJECT BRIEF
2
Spillway
CFRD Dam
(213 m)
Project Colony
Switchyard
Diversion
Tunnels
Right Bank
Access Road
Left Bank Access Road
Powerhouse
u/s
Coffer Dam
LAYOUT PLAN
Right Bank
Irrigation Intake
Left Bank
Irrigation Intake
Mohmand
Dam
Reservoir
BRIEF PROFILE OF PROJECT
Location:
The project is being constructed across Swat River at a distance of about 48 km from
Peshawar in Mohmand Tribal District, KP.
Objectives:
Hydropower Generation 850 MW
Annual Energy 2.862 Billion units
Gross Storage 1.293 MAF
Irrigated Agricultural Development 16,737 Acres (Revised
18,237)
Drinking Water Supply to Peshawar 470 cusecs (304 MG/day)
Flood Control
Socio-economic uplift of project area
Operation Peaking hydropower with re-regulation
Dam height/ Crest length 213 m high with a crest length of 718 m
Type of Dam Concrete Faced Rockfill Dam
Gross / Live Storage 1.293 / 0.676 MAF
Spillway Capacity 27,427 m3/s PMF
Diversion Tunnels 2 Nos. Each 1.7 km long & 15m diameter
Power Generation
800MW from 4 x 200MW Francis Turbines
and 3,000GWh/year
Irrigation + Water Supply 18,237 Acres + 13 cumecs Peshawar WS
Right Bank Irrigation System 3.6 km Tunnel + 11.7km Canal
Left Bank Irrigation System 4.8 km Tunnel + 12.4 km Canal
PROJECT SALIENT FEATURES
5
Signing of Contract Agreement
March 26, 2019
Accepted Contract Price PKR
224.463 Billion
(Including Foreign Comp. of US$ 716 Million)
Contract Duration after EoT-1 of 215 days
6 Years and 3 months (2285 days)
Contractor’s Mobilization w.e.f April 04, 2019
Commencement Date Sept: 20, 2019
CONTRACTOR: CGGC-DESCON JV
Signing of Consultancy Service Agreement
May 20, 2019
Contract Price
PKR 9.982 Billion
Contract Duration
8 Years & 4 months (100 Months)
Commencement of Consultancy Services
w.e.f May 27, 2019
CONSULTANTS: MOHMAND DAM CONSULTANTS GROUP
JV of NESPAK (Lead Firm)-Pakistan, MWH-USA, SMEC-Australia,
DOLSAR-Turkey, ACE-Pakistan and MM Pakistan in association with 7 Firms
PROJECT PROGRESS
8
CONTRACTOR’S SITE FACILITIES AND
INFRASTRUCTURE
9
Situation:
 Contractor's mobilisation started in
mid – 2019
 Challenges through 1st and 2nd
waves of COVID
Outcomes:
 All site infrastructure now in place
 Works on key work fronts being
executed
Contractor’s Camp and Office
Batching & Crushing Plants
Site Access Roads and Infrastructure
DIVERSION TUNNELS INLET WORKS
10
DIVERSION TUNNELS OUTLET WORKS
11
SPILLWAY
12
Spillway Crest looking downstream
Upper Stilling Basin
Lower Stilling Basin
POWER INTAKE
13
Power Intake – cut slope with high capacity post tensioned anchors
POWERHOUSE AREA
14
Switchyard Platform
Powerhouse cut slope
POWER INTAKE & DT INLET WORKS
15
Main Dam fill stockpile
DT – Inlet Works
Project Colony
Power Intake
Works
Haul Road Bailey Bridge
View from Todobo Quarry
PROJECT CHALLENGES
16
17
Situation:
 5th highest CFRD in the World at 213 m
 Seismically active area
 17M m3 of rockfill required from local sources
 Challenging rate of rock filling required = 23,000
m3 per day
Actions:
 Detailed investigations and testing of rockfill
materials from local quarry
213 m CFRD DAM
Dam Body
 Zoned rockfill dam
 Quartzite and
limestone quarries
available at Project
18
Situation:
 Specialized concreting of dam face slab
 3 stage concreting
Actions:
 Experienced designers:
- Mohale Dam, Lesotho
- KĂĄrahnjĂşkar Dam, Iceland
 Experienced Chinese Contractors (CGGC)
KĂĄrahnjĂşkar Dam, Iceland
Mohmand Dam
213 m CFRD DAM
Situation:
 Deep main grout curtain in complex
geology
Actions:
 Extensive investigations and trials
19
SPILLWAY
Situation:
 PMF Flood capacity = 27,500 cumecs
 Ogee to riverbed = 215m
 Spillway length = 600m long
Actions:
 Double stilling basin arrangement
 Extensive hydraulic model testing at IRI
Nandipur
215m
high
PMF
600m long
Upper Stilling Basin
Lower Stilling Basin
Gated Ogee
20
GEOLOGY
Situation:
 Sequence of tectonically deformed Schist
 strongly developed foliation surfaces, and
 zones of polished graphitic Schist and talc
 little groundwater
Actions:
 Exacting site investigations to understand the
geology and geotechnical parameters:
 Addition borehole campaign
 Spillway crest and CFRD plinth
investigations
 Extensive Hydro jacking testing
 Real-time feedback loop during tunnelling and
surface excavations works to designers
21
DIVERSION TUNNELS – Large diameter in variable geological
conditions Situation:
 2 x 17.0m excavated diameter both 1.7km long
 Encountering weaker zones in foliated Schist
Actions:
 Managed with split-heading excavation
 Prudent real time interpretation of tunnel face
conditions
 Convergence encountered at Inlet due to weak
geology in both tunnels – addition support
measures being installed
Outcome:
 DT-1 header completed - breakthrough Dec
2021
 DT-2 header completed - breakthrough Feb
2022
 Concrete lining in progress – minor excavation
left
22
HIGH CUT SLOPES
Situation:
 High cut slope:
 180m at the Spillway lower stilling basin,
 150m at the Powerhouse
 120m at the Power Intake
 Foliated Schist in seismic area
Actions:
 Heavy slope reinforcement with high capacity
ground anchors
 Real time geological interpretation at each
bench
 Engineer and Contractor working together at
each bench for detailed assessment of
support
SPILLWAYS
CONSTRUCTION CHALLENGES
23
24
DIVERSION TUNNELS COMPLETION FOR RIVER DIVERSION
Current Status
• Large Convergence at Inlet structures of DT 1& DT 2.
• Project Management:
• Lack of senior management and senior works technical managers
• No management and coordination of day-to-day material requirement / equipment
requirements
• Construction Management:
• Lack of efficient resources / unspecialized crews for lining works, resulting in
excessive assembly time for Arch shutters, rebar placement, and shutter fixing.
• Frequent material stock shortage for concrete placement including fine and
coarse aggregates
• Concrete temperature – lack of cooling plant facilities to control high concrete
temperatures. Inadequate storage facility for proper material storage.
• The Contractor proposed additional audit to overcome delays due to convergence
25
DIVERSION TUNNELS COMPLETION FOR RIVER DIVERSION
WAY FORWARD:
• Expedite shutter assembly. Improve material forecast and ensure sufficient material
available to meet production needs.
• Mobilize specialized trades. Prepare realistic targets and work as a team to meet
targets and overcome challenges
• Addition of new Access Tunnel to facilitate lining works in the presence of convergence
at Inlet areas in both tunnels.
26
…
NEW ACCESS TUNNEL TO MINIMIZE DELAYS DUE TO CONVERGENCE
27
QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT
SCOPE OF WORK = Quarry Development for Main Dam Fill (17 Million Cum)
Facts:
1. In the contract, the Contractor was required to explore both locations, Todobo and Sappare
2. Contractor claimed that Todobo quarry will be sufficient to meet dam embankment fill quantity
and material specifications. The Engineer required the Contractor to explore both locations.
Todobo Quarry:
1. Contractor geological investigation - results are not reliable due to poor quality of coring
technique.
2. Investigation resulted in Maximum Size 400mm and large sizes may not be obtained from
Todobo.
3. Rockfill trial embankment was initially planned in first week June 2022.
4. 2 out of 10 proposed Trial Blast considered by the Contractor. The last trial blast was done in
March 2022.
5. The access roads to the quarry are still in progress.
28
Current Status - Sappare Quarry:
1. Resource for all aggregates and rockfill on the project as investigated by the Engineer.
2. Client currently drilling investigation holes to prove limestone strength for rockfill.
• Land leasing is delayed. Contractor is facing problems to find the landowner of specific area
where the material shall be tested for trial blast.
• Descon Contractor JV partner has leased 60 acres for aggregates production. CGGC has not
done any coordination for trial blast for filters and rockfill.
• Geological investigation for quarry exploitation by Contractor not started yet as per SP-21.
• Surface investigation done by the Engineer. Material was tested on the surface and tests are
ongoing for UCS and Point Load in site laboratory.
• The Client authorized the geological investigation to confirm the quality of rock for rockfill, due
to inconsistencies in the UCS results reported in the feasibility stage as compared with the
estimated value from Schmidt Hammer tests done on site in April 2022.
• Engineer already approved the laboratory proposed for large scale triaxial test in China
Changjiang Institute.
QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT
29
WAY FORWARD:
• Contractor to expedite Sappare Quarry Development (Access Roads, Blasting, Material
Testing, Stockpiling process which is pre-requisite for Main Dam Fill proposed by Contractor
in their method statement).
• Employer facilitate the Contractor in acquiring land for quarry exploration
• Engineer already approved the laboratory proposed for large scale triaxial test in China
Changjiang Institute.
QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT
CONSTRUCTION PROGRESS
30
COMPONENT WISE PROGRESS (31 JUL 22)
31
OVERALL PROJECT PROGRESS (31 JUL 22)
32
698 days
Attributable
to Contractor
MONTHLY PROGRESS TREND
33
Report
Month
Cumulative
Planned %
Complete
Cumulative
Actual %
Complete
Cumulative
Variance Trend
Period Trend
Nov-21 34.36% 13.43% -20.94% 0.98%
Dec-21 36.94% 14.36% -22.58% 0.93%
Jan-22 39.94% 15.18% -24.76% 0.82%
Feb-22 41.37% 15.94% -25.43 0.76%
Mar-22 42.8 % 16.73% -26.07% 0.79%
Apr-22 43.95 % 17.5% -26.45% 0.77%
May-22 45.24% 18.29% -26.95% 0.79%
Jun-22 46.56% 18.98% -27.58% 0.69%
Jul-22 47.54% 19.55% -27.99% 0.55%
MILESTONE DATES
34
Milestone Description
Contractual Milestone
(EoT-MW-01)
Contractor’s
Monthly Forecast
(Jul 2022)
1. Diversion Tunnels Completion
15 Feb 22
(River Diversion:
17 March 2022)
25 Jun 2023
(River Diversion: 01
Mar 2023)
2. Main Dam - Quarry Investigation 23 Dec 2020 24 Jun 2023
3. Main Dam Completion 20 May 25 26 September 2026
4. Completion of Whole of the Works 21 Dec 25 02 October 2027
DIVERSION TUNNEL LINING PROGRESS
35
DIVERSION TUNNEL LINING PROGRESS
36
DIVERSION TUNNEL LINING PROGRESS
37
MAJOR REASONS FOR DELAYS
38
Milestone Milestone Description
Contractual
Milestone
Consultant's
Forecast
Delayed due to:
A Lot 1 Works
1 Construction of Right Bank Permanent Access Road 17-Mar-20 31-Aug-22* COVID 19/Slow progress
2
Construction of Wapda Colony (Project Office, Officer and staff
hostels, Category 1 & 2 family houses, mosque and high school)
including roads & utilities
15-Jun-20 31-Aug-22* COVID 19/Slow progress
3 Completion of the whole of the works 17-Mar-21 31 May 23* COVID 19/Slow progress
B Lot 2 Works
1 Completion of Diversion Tunnels 15-Feb-22 23-Oct-23
COVID 19/Slow
progress/Convergence
2
Completion of Control Room in Control House of Dam to install
instrumentation and control facilities
19-Feb-25 9-Dec-26
C Lot 3 Works
1 Completion of Left and Right irrigation Tunnels in all respects 23-Dec-24 7-Dec-26 COVID 19/Slow progress
2 Initial Filling, Testing and Emptying of Canal System 23-Mar-25 29-Sep-26
D
Combined Lot 2 Works and Lot 4 Installation/ Erection, Testing and
Commissioning
1
Ready to reservoir impounding under LOT 2 and LOT4
1) Completion of dry test of all maintenance gates of LLO
2) Completion of Spillway
3) Completion of flushing outlet including dry test of gates and
Stoplogs
20-Apr-25 1-Feb-27 COVID 19/Slow progress
E Overall Completion of Works for Lot 2, Lot3 and Lot 4
1 Completion of whole of the works 21-Dec-25 19-Nov-27
ISSUES AND BOTTLENECKS
39
CRITICAL ISSUES IMPACTING PROGRESS
40
External causes:
• Impact of Covid-19
• Convergence in Diversion Tunnels
• Delayed foreign currency payments
Contractor’s cause:
• Lack of planning and scheduling capability
• Poor submissions of Detailed Time Program /schedules (intentional)
• Lack of Resources (labour & equipment) and inefficient utilization
• Slow work progress on Critical Activities
• Lack of Contract Management/Administration:
• Poor contract understanding resulted in poor submissions: unsubstantiated
claims (intentional)
41
CRITICAL PATH ACTIVITIES – REQUIRING IMMEDIATE FOCUS
• Quarry Development
• DT completion
• QA/QC
• Provide – senior experienced management for overall site management and
coordination
• Provide planning and scheduling capability
• Provide experienced Quarry Management
• Provide experienced QA/QC management
• Provide experienced HSE Management
• Build-up Resources: Manpower & Equipment / Machinery
ACTIONS
42
CONTRACTUAL ACTIONS SUGGESTED FOR THE ENGINEER TO
IMPROVE WORK PROGRESS
Contractor to:
• Submit Detailed Time Program incl. EOT-1 (215 days) as per the Contract
• - Latest submission 29 March 2022 – rejected
• Manage the efficient deployment and utilization of resources.
• Deploy authorized project management and provide Head Office support.
43
STAKEHOLDERS EFFORTS TO IMPROVE PROGRESS.
Employer:-
Facilitating the Contractor with land lease for Quarry development works
Engineer:-
Providing full technical assistance to the Contractor at site
Providing IFC drawings timely to the Contractor to avoid delays
Maintaining the quality of works at site
Contractor:-
Deployed new Management
Submitted acceleration proposal to cover delays due to convergence
Committed to deploy more resources
44
8.3 PROGRAMME
Eight submissions by the Contractor to date.
Last submission by the Contractor was made on 29 Mar 2022 – Engineer’s major
comments were:
• Previous delays, already claimed and determined by the Engineer in EOT 1, still
present in revised schedule.
• Contractual Milestone Dates – not incorporated
• Contractor’s Resources –not provided, their productivities and Planned
durations - not justified
• Unjustified lags
• Unrealistic Total Float due to inaccurate inter-activities relationship
Submissions were rejected and returned for resubmission.
STATUS OF EOT AND CLAIMS
45
STATUS OF EOT CLAIMS
46
Sr. No. Description
Days
claimed
Date of
Submission
Cut-off date Status
1
1st
phase Extension of Time (EOT-
MW-01) for completion of Lot 2,3 &4
808 7 Sep 2020 31 July 2020
Engineer’s determination issued on 15.06.2021
for EOT for 215 days for Lot-2 &4 and 97 days
for Lot-3 after obtaining WAPDA Authority’s
approval on 25.05.2021.
2
Extension of Time for construction of
Right Bank Permanent Access
Roads under Lot-1
1271 3 Mar 2020 11 February 2020
The Contractor’s submission with letter 4471 of
12.3.2022 has been responded by Engineer with
comments, refer Engineer’s letter no. 7239 of
05.05.2022. Contractor’s response is awaited..
3
Extension of Time for construction of
Project Colony (Priority 1 Works)
under Lot-1
1597 15 Aug 2020 1 June 2020
The Engineer has prepared his draft
determination and shall invite the Employer for
review and consultation for finalization.
4
Extension of Time (EOT-PW-03) for
completion of Lot-1 Priority 2 Works
1244 5 Apr 2021 31 January 2021 Under review by the Engineer
5
2nd
Phase of Extension of Time
(EOT-DT-02) for completion of
Diversion Tunnels under Lot-2
234
25 June
2021
31 May 2021
The Engineer has prepared his draft
determination and submitted to the Employer for
review and consultation, ref. our letter no. 7400 of
22.05.2022..
6
Extension of Time for construction of
Right Bank Permanent Access
Roads under Lot-1
427 08 Aug 2021 31 March 2021 Under review by the Engineer
STATUS OF EOT CLAIMS
47
Sr. No. Description
Days
claimed
Date of
Submission
Cut-off date Status
7
Extension of Time for construction of
Project Colony (Priority 1 Works)
under Lot-1
509 24.03.2022 30 November 2021
Under review by the Engineer
8
EOT-3-MW: Completion of Lot-3
works
667 17 July 2021 30 April 2021
The Engineer has prepared his draft determination
and shall invite the Employer for review and
consultation for finalization.
9
EOT-4-PW: Completion of
Powerhouse Works
91 12 Oct 2021 13 April 2021
The Engineer shall initiate the consultations with
the parties for has determination.
10
EOT-5-MW: Completion of Lot-3
works
276 18 May 2022 31 Jan 2022 Under review by the Engineer
During a meeting held between the Employer, the Engineer and the Contractor on 04 July 2022, it was agreed by the parties that the Contractor shall
submit his all remaining claims for delaying events for each lot enabling the Engineer to issue his determination lot wise (i.e., combining the submitted
EOTs lot-wise) for all delaying event with following cut-off dates:
Lot-1 – 31 December 2021
Lot-2 – 31 December 2021
Lot-3 – 31 January 2022
The Engineer will proceed for the evaluation of EOTs on receipt of final submissions of remaining delaying events / EOTs which is awaited from the
Contractor.
Variation Orders
48
Sr.
No
Last Submission Date Description Status
1 MDCG/MF/01/7476 30/05/2022
Construction of Multi Cell Box Culverts at Left & Right Bank
Access Roads
VO prepared.
2 MDCG/MF/01/7476 30/05/2022
Variation due to provision of drain at open cut slope of Diversion
Tunnels, Access Tunnel and Power Intake Portals
VO prepared.
3 MDCG/MF/01/7476 30/05/2022 Varied work in the Sewerage System of Project Colony VO prepared.
4 MDCG/MF/01/7606 13/06/2022
Variation due to provision of Overhead Water Tanks at Project
Colony Buildings
The Contractor’s response is
awaited.
5 MDCG/MF/01/4962 30/07/2021
Variation due to Design changes in Boundary/Periphery Wall of
Project Colony
The Contractor’s response is
awaited.
6
CDJV-MDHP-MDCG-
2022-4893
27/05/2022
Variation due to change in foundation of Project Colony
buildings
Contractor’s Design
justifications is under review by
the Engineer for response.
7 MDCG/MF/01/7477 30/05/2022
Variation due to provision of Access Bridge at Power Intake and
Waterway
The Contractor’s proposal is
awaited.
8 MDCG/MF/01/4728 21/06/2021
Variation of surface excavation and rock support for power intake
and power waterway
The Contractor’s response is
awaited
Variation Orders
49
Sr.
No
Last Submission Date Description Status
9 MDCG/MF/01/7049 11/04/2022 Variation of Storm water drainage system in Project Colony
The Contractor’s proposal is
awaited.
10 MDCG/MF/01/6090 08/12/2021 Project Colony Land Development
The Contractor to provide the
breakdown of the Land
Development BOQ item
11
GM&PD/MDHP/TDC-
04/4050-52
04/04/2022 Variation for Provision of Cooking range in Cat-5 buildings
Upon Employer’s confirmation, the
VO has been cancelled.
12 MDCG/MF/01/7834 13/07/2022
Variation due to construction of retaining wall due to level
difference for project colony buildings.
The Contractor’s response is
awaited.
13 MDCG/MF/01/7533 06/06/2022 Variation of stone masonry retaining wall along Access Road
The Contractor’s response is
awaited.
14 MDCG/MF/01/6919 28/03/2022 Variation due to Class-G Concrete Lining in DTs
The Contractor’s response to the
Engineer’s comments is awaited.
15 MDCG/MF/01/4728 21/06/2021
Variation due to Tensioned ground anchors at Power Intake
and Power Waterway
The Contractor’s response to the
Engineer’s comments is awaited.
Variation Orders
50
Sr.
No
Last Submission Date Description Status
16 MDCG/MF/01/6919 28/03/2022 Variation due to Class-G Concrete Lining in DTs
The Contractor’s response to the
Engineer’s comments is awaited.
17 MDCG/MF/01/7830 13/07/2022 Variation regarding the adjustment of generator parameter
The Contractor’s response to the
Engineer’s comments is awaited.
The Employer through his letter no. 4970-74 provided comments from CCC regarding interpretation of Sub-Clause 3.1 (B)
ii of PCC and advised the Engineer to exercise his powers to issue Variation Orders up to 2% of the accepted Contract
price. After further deliberations and correspondence exchanged, the Engineer shall proceed accordingly for issuance of
the VOs.
CONTRACTUAL MATTERS
51
• LOT-2 - DIVERSION TUNNEL COMPLETION - APPLICATION OF LDS
EoT-2 - DT EoT only – preliminary assessment EoT 84 days
EoT assessment to be approved by BOM and Employer
• LOT-3 - RIGHT OF ACCESS TO AND POSSESSION OF SITE
EOT-MW-03 – Preliminary assessment EOT 272 days.
The Engineer’s Draft determination shall invite the Employer for review and consultation for
finalization.
• EXERCISING VO POWERS
The Employer advised the Engineer to exercise his powers to issue Variation Orders up to 2% of the
accepted Contract price.
CONTRACTUAL MATTERS
52
• PANDEMIC CORONA VIRUS (COVID-19)
The Contractor is serving claim notices (EoT & Cost) under force majeure Clause 19 & Employer’s
risk Clause 17.
No entitlement for cost under these clauses:
Clause 19 – not entitled to Cost under Sub-Clauses 19.4. Entitled only for events given in
Sub-Clause 19.1. (ii) – (iv) incl. rebellion, riot, munitions of war.
Clause 17 – Sub-Clause 17.3 & 17.4 - no rectification instructed by the Engineer
• PROJECT COLONY GAS SUPPLY SYSTEM
The Contractor claimed that Gas Supply System is additional to his scope
The Engineer assessed that Gas Supply System is in Contractor’s scope and issued his
Determination under Sub-Clause 3.5 of GCC accordingly.
The Contractor has disputed with the Engineer’s Determination and referred the case to DB
for their decision. DB proceedings are under way.
Thank You
53

More Related Content

Similar to Mohmand Dam Hydropower Project Update

CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)Sachin Chitnis
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
78-83-NovDec12
78-83-NovDec1278-83-NovDec12
78-83-NovDec12Simon Devetak
 
City Council March 19, 2013 Hickory update
City Council March 19, 2013 Hickory updateCity Council March 19, 2013 Hickory update
City Council March 19, 2013 Hickory updateCity of San Angelo Texas
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of damssarojkhadka059
 
Project Management Challenges in an Effluent Treatment Plant Construction
Project Management  Challenges in an Effluent Treatment Plant Construction Project Management  Challenges in an Effluent Treatment Plant Construction
Project Management Challenges in an Effluent Treatment Plant Construction PRABHASH GOKARN
 
Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Shammy Puri
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013 carsoncorporation
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveFairfax County
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...IEI GSC
 
Peter McGough CV 2010
Peter McGough CV 2010Peter McGough CV 2010
Peter McGough CV 2010pmcgough
 

Similar to Mohmand Dam Hydropower Project Update (20)

CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)CV  -Sachin Madhukar Chitnis  -( Civil Roads, Utility,infra,metro rail ,)
CV -Sachin Madhukar Chitnis -( Civil Roads, Utility,infra,metro rail ,)
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
78-83-NovDec12
78-83-NovDec1278-83-NovDec12
78-83-NovDec12
 
City Council March 19, 2013 Hickory update
City Council March 19, 2013 Hickory updateCity Council March 19, 2013 Hickory update
City Council March 19, 2013 Hickory update
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 
Project Management Challenges in an Effluent Treatment Plant Construction
Project Management  Challenges in an Effluent Treatment Plant Construction Project Management  Challenges in an Effluent Treatment Plant Construction
Project Management Challenges in an Effluent Treatment Plant Construction
 
Cv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas TulabotCv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas Tulabot
 
Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011
 
site proj 1
site proj 1site proj 1
site proj 1
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013
 
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr DriveStorm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
Storm Pipe Rehabilitation at Cider Barrel Circle and Orr Drive
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
 
Peter McGough CV 2010
Peter McGough CV 2010Peter McGough CV 2010
Peter McGough CV 2010
 
ANP DAM PPT Dt 30-10-2022 EE.pptx
ANP DAM PPT Dt 30-10-2022 EE.pptxANP DAM PPT Dt 30-10-2022 EE.pptx
ANP DAM PPT Dt 30-10-2022 EE.pptx
 

Recently uploaded

Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造kbdhl05e
 
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiSuhani Kapoor
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130Suhani Kapoor
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)jennyeacort
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Narsimha murthy
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 

Recently uploaded (20)

Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造
 
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 

Mohmand Dam Hydropower Project Update

  • 1. Mohmand Dam Hydropower Project Presentation to the Chairman WAPDA 17 August 2022
  • 2. DISCUSSION • Project Brief • Project Progress • Project Challenges • Construction Challenges • Construction Progress • Issues and Bottlenecks • Status of the Contractor’s Extension of Time Claims 1
  • 4. Spillway CFRD Dam (213 m) Project Colony Switchyard Diversion Tunnels Right Bank Access Road Left Bank Access Road Powerhouse u/s Coffer Dam LAYOUT PLAN Right Bank Irrigation Intake Left Bank Irrigation Intake Mohmand Dam Reservoir
  • 5. BRIEF PROFILE OF PROJECT Location: The project is being constructed across Swat River at a distance of about 48 km from Peshawar in Mohmand Tribal District, KP. Objectives: Hydropower Generation 850 MW Annual Energy 2.862 Billion units Gross Storage 1.293 MAF Irrigated Agricultural Development 16,737 Acres (Revised 18,237) Drinking Water Supply to Peshawar 470 cusecs (304 MG/day) Flood Control Socio-economic uplift of project area
  • 6. Operation Peaking hydropower with re-regulation Dam height/ Crest length 213 m high with a crest length of 718 m Type of Dam Concrete Faced Rockfill Dam Gross / Live Storage 1.293 / 0.676 MAF Spillway Capacity 27,427 m3/s PMF Diversion Tunnels 2 Nos. Each 1.7 km long & 15m diameter Power Generation 800MW from 4 x 200MW Francis Turbines and 3,000GWh/year Irrigation + Water Supply 18,237 Acres + 13 cumecs Peshawar WS Right Bank Irrigation System 3.6 km Tunnel + 11.7km Canal Left Bank Irrigation System 4.8 km Tunnel + 12.4 km Canal PROJECT SALIENT FEATURES 5
  • 7. Signing of Contract Agreement March 26, 2019 Accepted Contract Price PKR 224.463 Billion (Including Foreign Comp. of US$ 716 Million) Contract Duration after EoT-1 of 215 days 6 Years and 3 months (2285 days) Contractor’s Mobilization w.e.f April 04, 2019 Commencement Date Sept: 20, 2019 CONTRACTOR: CGGC-DESCON JV
  • 8. Signing of Consultancy Service Agreement May 20, 2019 Contract Price PKR 9.982 Billion Contract Duration 8 Years & 4 months (100 Months) Commencement of Consultancy Services w.e.f May 27, 2019 CONSULTANTS: MOHMAND DAM CONSULTANTS GROUP JV of NESPAK (Lead Firm)-Pakistan, MWH-USA, SMEC-Australia, DOLSAR-Turkey, ACE-Pakistan and MM Pakistan in association with 7 Firms
  • 10. CONTRACTOR’S SITE FACILITIES AND INFRASTRUCTURE 9 Situation:  Contractor's mobilisation started in mid – 2019  Challenges through 1st and 2nd waves of COVID Outcomes:  All site infrastructure now in place  Works on key work fronts being executed Contractor’s Camp and Office Batching & Crushing Plants Site Access Roads and Infrastructure
  • 13. SPILLWAY 12 Spillway Crest looking downstream Upper Stilling Basin Lower Stilling Basin
  • 14. POWER INTAKE 13 Power Intake – cut slope with high capacity post tensioned anchors
  • 16. POWER INTAKE & DT INLET WORKS 15 Main Dam fill stockpile DT – Inlet Works Project Colony Power Intake Works Haul Road Bailey Bridge View from Todobo Quarry
  • 18. 17 Situation:  5th highest CFRD in the World at 213 m  Seismically active area  17M m3 of rockfill required from local sources  Challenging rate of rock filling required = 23,000 m3 per day Actions:  Detailed investigations and testing of rockfill materials from local quarry 213 m CFRD DAM Dam Body  Zoned rockfill dam  Quartzite and limestone quarries available at Project
  • 19. 18 Situation:  Specialized concreting of dam face slab  3 stage concreting Actions:  Experienced designers: - Mohale Dam, Lesotho - KĂĄrahnjĂşkar Dam, Iceland  Experienced Chinese Contractors (CGGC) KĂĄrahnjĂşkar Dam, Iceland Mohmand Dam 213 m CFRD DAM Situation:  Deep main grout curtain in complex geology Actions:  Extensive investigations and trials
  • 20. 19 SPILLWAY Situation:  PMF Flood capacity = 27,500 cumecs  Ogee to riverbed = 215m  Spillway length = 600m long Actions:  Double stilling basin arrangement  Extensive hydraulic model testing at IRI Nandipur 215m high PMF 600m long Upper Stilling Basin Lower Stilling Basin Gated Ogee
  • 21. 20 GEOLOGY Situation:  Sequence of tectonically deformed Schist  strongly developed foliation surfaces, and  zones of polished graphitic Schist and talc  little groundwater Actions:  Exacting site investigations to understand the geology and geotechnical parameters:  Addition borehole campaign  Spillway crest and CFRD plinth investigations  Extensive Hydro jacking testing  Real-time feedback loop during tunnelling and surface excavations works to designers
  • 22. 21 DIVERSION TUNNELS – Large diameter in variable geological conditions Situation:  2 x 17.0m excavated diameter both 1.7km long  Encountering weaker zones in foliated Schist Actions:  Managed with split-heading excavation  Prudent real time interpretation of tunnel face conditions  Convergence encountered at Inlet due to weak geology in both tunnels – addition support measures being installed Outcome:  DT-1 header completed - breakthrough Dec 2021  DT-2 header completed - breakthrough Feb 2022  Concrete lining in progress – minor excavation left
  • 23. 22 HIGH CUT SLOPES Situation:  High cut slope:  180m at the Spillway lower stilling basin,  150m at the Powerhouse  120m at the Power Intake  Foliated Schist in seismic area Actions:  Heavy slope reinforcement with high capacity ground anchors  Real time geological interpretation at each bench  Engineer and Contractor working together at each bench for detailed assessment of support SPILLWAYS
  • 25. 24 DIVERSION TUNNELS COMPLETION FOR RIVER DIVERSION Current Status • Large Convergence at Inlet structures of DT 1& DT 2. • Project Management: • Lack of senior management and senior works technical managers • No management and coordination of day-to-day material requirement / equipment requirements • Construction Management: • Lack of efficient resources / unspecialized crews for lining works, resulting in excessive assembly time for Arch shutters, rebar placement, and shutter fixing. • Frequent material stock shortage for concrete placement including fine and coarse aggregates • Concrete temperature – lack of cooling plant facilities to control high concrete temperatures. Inadequate storage facility for proper material storage. • The Contractor proposed additional audit to overcome delays due to convergence
  • 26. 25 DIVERSION TUNNELS COMPLETION FOR RIVER DIVERSION WAY FORWARD: • Expedite shutter assembly. Improve material forecast and ensure sufficient material available to meet production needs. • Mobilize specialized trades. Prepare realistic targets and work as a team to meet targets and overcome challenges • Addition of new Access Tunnel to facilitate lining works in the presence of convergence at Inlet areas in both tunnels.
  • 27. 26 … NEW ACCESS TUNNEL TO MINIMIZE DELAYS DUE TO CONVERGENCE
  • 28. 27 QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT SCOPE OF WORK = Quarry Development for Main Dam Fill (17 Million Cum) Facts: 1. In the contract, the Contractor was required to explore both locations, Todobo and Sappare 2. Contractor claimed that Todobo quarry will be sufficient to meet dam embankment fill quantity and material specifications. The Engineer required the Contractor to explore both locations. Todobo Quarry: 1. Contractor geological investigation - results are not reliable due to poor quality of coring technique. 2. Investigation resulted in Maximum Size 400mm and large sizes may not be obtained from Todobo. 3. Rockfill trial embankment was initially planned in first week June 2022. 4. 2 out of 10 proposed Trial Blast considered by the Contractor. The last trial blast was done in March 2022. 5. The access roads to the quarry are still in progress.
  • 29. 28 Current Status - Sappare Quarry: 1. Resource for all aggregates and rockfill on the project as investigated by the Engineer. 2. Client currently drilling investigation holes to prove limestone strength for rockfill. • Land leasing is delayed. Contractor is facing problems to find the landowner of specific area where the material shall be tested for trial blast. • Descon Contractor JV partner has leased 60 acres for aggregates production. CGGC has not done any coordination for trial blast for filters and rockfill. • Geological investigation for quarry exploitation by Contractor not started yet as per SP-21. • Surface investigation done by the Engineer. Material was tested on the surface and tests are ongoing for UCS and Point Load in site laboratory. • The Client authorized the geological investigation to confirm the quality of rock for rockfill, due to inconsistencies in the UCS results reported in the feasibility stage as compared with the estimated value from Schmidt Hammer tests done on site in April 2022. • Engineer already approved the laboratory proposed for large scale triaxial test in China Changjiang Institute. QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT
  • 30. 29 WAY FORWARD: • Contractor to expedite Sappare Quarry Development (Access Roads, Blasting, Material Testing, Stockpiling process which is pre-requisite for Main Dam Fill proposed by Contractor in their method statement). • Employer facilitate the Contractor in acquiring land for quarry exploration • Engineer already approved the laboratory proposed for large scale triaxial test in China Changjiang Institute. QUARRY DEVELOPMENT FOR MAIN DAM EMBANKMENT
  • 32. COMPONENT WISE PROGRESS (31 JUL 22) 31
  • 33. OVERALL PROJECT PROGRESS (31 JUL 22) 32 698 days Attributable to Contractor
  • 34. MONTHLY PROGRESS TREND 33 Report Month Cumulative Planned % Complete Cumulative Actual % Complete Cumulative Variance Trend Period Trend Nov-21 34.36% 13.43% -20.94% 0.98% Dec-21 36.94% 14.36% -22.58% 0.93% Jan-22 39.94% 15.18% -24.76% 0.82% Feb-22 41.37% 15.94% -25.43 0.76% Mar-22 42.8 % 16.73% -26.07% 0.79% Apr-22 43.95 % 17.5% -26.45% 0.77% May-22 45.24% 18.29% -26.95% 0.79% Jun-22 46.56% 18.98% -27.58% 0.69% Jul-22 47.54% 19.55% -27.99% 0.55%
  • 35. MILESTONE DATES 34 Milestone Description Contractual Milestone (EoT-MW-01) Contractor’s Monthly Forecast (Jul 2022) 1. Diversion Tunnels Completion 15 Feb 22 (River Diversion: 17 March 2022) 25 Jun 2023 (River Diversion: 01 Mar 2023) 2. Main Dam - Quarry Investigation 23 Dec 2020 24 Jun 2023 3. Main Dam Completion 20 May 25 26 September 2026 4. Completion of Whole of the Works 21 Dec 25 02 October 2027
  • 36. DIVERSION TUNNEL LINING PROGRESS 35
  • 37. DIVERSION TUNNEL LINING PROGRESS 36
  • 38. DIVERSION TUNNEL LINING PROGRESS 37
  • 39. MAJOR REASONS FOR DELAYS 38 Milestone Milestone Description Contractual Milestone Consultant's Forecast Delayed due to: A Lot 1 Works 1 Construction of Right Bank Permanent Access Road 17-Mar-20 31-Aug-22* COVID 19/Slow progress 2 Construction of Wapda Colony (Project Office, Officer and staff hostels, Category 1 & 2 family houses, mosque and high school) including roads & utilities 15-Jun-20 31-Aug-22* COVID 19/Slow progress 3 Completion of the whole of the works 17-Mar-21 31 May 23* COVID 19/Slow progress B Lot 2 Works 1 Completion of Diversion Tunnels 15-Feb-22 23-Oct-23 COVID 19/Slow progress/Convergence 2 Completion of Control Room in Control House of Dam to install instrumentation and control facilities 19-Feb-25 9-Dec-26 C Lot 3 Works 1 Completion of Left and Right irrigation Tunnels in all respects 23-Dec-24 7-Dec-26 COVID 19/Slow progress 2 Initial Filling, Testing and Emptying of Canal System 23-Mar-25 29-Sep-26 D Combined Lot 2 Works and Lot 4 Installation/ Erection, Testing and Commissioning 1 Ready to reservoir impounding under LOT 2 and LOT4 1) Completion of dry test of all maintenance gates of LLO 2) Completion of Spillway 3) Completion of flushing outlet including dry test of gates and Stoplogs 20-Apr-25 1-Feb-27 COVID 19/Slow progress E Overall Completion of Works for Lot 2, Lot3 and Lot 4 1 Completion of whole of the works 21-Dec-25 19-Nov-27
  • 41. CRITICAL ISSUES IMPACTING PROGRESS 40 External causes: • Impact of Covid-19 • Convergence in Diversion Tunnels • Delayed foreign currency payments Contractor’s cause: • Lack of planning and scheduling capability • Poor submissions of Detailed Time Program /schedules (intentional) • Lack of Resources (labour & equipment) and inefficient utilization • Slow work progress on Critical Activities • Lack of Contract Management/Administration: • Poor contract understanding resulted in poor submissions: unsubstantiated claims (intentional)
  • 42. 41 CRITICAL PATH ACTIVITIES – REQUIRING IMMEDIATE FOCUS • Quarry Development • DT completion • QA/QC • Provide – senior experienced management for overall site management and coordination • Provide planning and scheduling capability • Provide experienced Quarry Management • Provide experienced QA/QC management • Provide experienced HSE Management • Build-up Resources: Manpower & Equipment / Machinery ACTIONS
  • 43. 42 CONTRACTUAL ACTIONS SUGGESTED FOR THE ENGINEER TO IMPROVE WORK PROGRESS Contractor to: • Submit Detailed Time Program incl. EOT-1 (215 days) as per the Contract • - Latest submission 29 March 2022 – rejected • Manage the efficient deployment and utilization of resources. • Deploy authorized project management and provide Head Office support.
  • 44. 43 STAKEHOLDERS EFFORTS TO IMPROVE PROGRESS. Employer:- Facilitating the Contractor with land lease for Quarry development works Engineer:- Providing full technical assistance to the Contractor at site Providing IFC drawings timely to the Contractor to avoid delays Maintaining the quality of works at site Contractor:- Deployed new Management Submitted acceleration proposal to cover delays due to convergence Committed to deploy more resources
  • 45. 44 8.3 PROGRAMME Eight submissions by the Contractor to date. Last submission by the Contractor was made on 29 Mar 2022 – Engineer’s major comments were: • Previous delays, already claimed and determined by the Engineer in EOT 1, still present in revised schedule. • Contractual Milestone Dates – not incorporated • Contractor’s Resources –not provided, their productivities and Planned durations - not justified • Unjustified lags • Unrealistic Total Float due to inaccurate inter-activities relationship Submissions were rejected and returned for resubmission.
  • 46. STATUS OF EOT AND CLAIMS 45
  • 47. STATUS OF EOT CLAIMS 46 Sr. No. Description Days claimed Date of Submission Cut-off date Status 1 1st phase Extension of Time (EOT- MW-01) for completion of Lot 2,3 &4 808 7 Sep 2020 31 July 2020 Engineer’s determination issued on 15.06.2021 for EOT for 215 days for Lot-2 &4 and 97 days for Lot-3 after obtaining WAPDA Authority’s approval on 25.05.2021. 2 Extension of Time for construction of Right Bank Permanent Access Roads under Lot-1 1271 3 Mar 2020 11 February 2020 The Contractor’s submission with letter 4471 of 12.3.2022 has been responded by Engineer with comments, refer Engineer’s letter no. 7239 of 05.05.2022. Contractor’s response is awaited.. 3 Extension of Time for construction of Project Colony (Priority 1 Works) under Lot-1 1597 15 Aug 2020 1 June 2020 The Engineer has prepared his draft determination and shall invite the Employer for review and consultation for finalization. 4 Extension of Time (EOT-PW-03) for completion of Lot-1 Priority 2 Works 1244 5 Apr 2021 31 January 2021 Under review by the Engineer 5 2nd Phase of Extension of Time (EOT-DT-02) for completion of Diversion Tunnels under Lot-2 234 25 June 2021 31 May 2021 The Engineer has prepared his draft determination and submitted to the Employer for review and consultation, ref. our letter no. 7400 of 22.05.2022.. 6 Extension of Time for construction of Right Bank Permanent Access Roads under Lot-1 427 08 Aug 2021 31 March 2021 Under review by the Engineer
  • 48. STATUS OF EOT CLAIMS 47 Sr. No. Description Days claimed Date of Submission Cut-off date Status 7 Extension of Time for construction of Project Colony (Priority 1 Works) under Lot-1 509 24.03.2022 30 November 2021 Under review by the Engineer 8 EOT-3-MW: Completion of Lot-3 works 667 17 July 2021 30 April 2021 The Engineer has prepared his draft determination and shall invite the Employer for review and consultation for finalization. 9 EOT-4-PW: Completion of Powerhouse Works 91 12 Oct 2021 13 April 2021 The Engineer shall initiate the consultations with the parties for has determination. 10 EOT-5-MW: Completion of Lot-3 works 276 18 May 2022 31 Jan 2022 Under review by the Engineer During a meeting held between the Employer, the Engineer and the Contractor on 04 July 2022, it was agreed by the parties that the Contractor shall submit his all remaining claims for delaying events for each lot enabling the Engineer to issue his determination lot wise (i.e., combining the submitted EOTs lot-wise) for all delaying event with following cut-off dates: Lot-1 – 31 December 2021 Lot-2 – 31 December 2021 Lot-3 – 31 January 2022 The Engineer will proceed for the evaluation of EOTs on receipt of final submissions of remaining delaying events / EOTs which is awaited from the Contractor.
  • 49. Variation Orders 48 Sr. No Last Submission Date Description Status 1 MDCG/MF/01/7476 30/05/2022 Construction of Multi Cell Box Culverts at Left & Right Bank Access Roads VO prepared. 2 MDCG/MF/01/7476 30/05/2022 Variation due to provision of drain at open cut slope of Diversion Tunnels, Access Tunnel and Power Intake Portals VO prepared. 3 MDCG/MF/01/7476 30/05/2022 Varied work in the Sewerage System of Project Colony VO prepared. 4 MDCG/MF/01/7606 13/06/2022 Variation due to provision of Overhead Water Tanks at Project Colony Buildings The Contractor’s response is awaited. 5 MDCG/MF/01/4962 30/07/2021 Variation due to Design changes in Boundary/Periphery Wall of Project Colony The Contractor’s response is awaited. 6 CDJV-MDHP-MDCG- 2022-4893 27/05/2022 Variation due to change in foundation of Project Colony buildings Contractor’s Design justifications is under review by the Engineer for response. 7 MDCG/MF/01/7477 30/05/2022 Variation due to provision of Access Bridge at Power Intake and Waterway The Contractor’s proposal is awaited. 8 MDCG/MF/01/4728 21/06/2021 Variation of surface excavation and rock support for power intake and power waterway The Contractor’s response is awaited
  • 50. Variation Orders 49 Sr. No Last Submission Date Description Status 9 MDCG/MF/01/7049 11/04/2022 Variation of Storm water drainage system in Project Colony The Contractor’s proposal is awaited. 10 MDCG/MF/01/6090 08/12/2021 Project Colony Land Development The Contractor to provide the breakdown of the Land Development BOQ item 11 GM&PD/MDHP/TDC- 04/4050-52 04/04/2022 Variation for Provision of Cooking range in Cat-5 buildings Upon Employer’s confirmation, the VO has been cancelled. 12 MDCG/MF/01/7834 13/07/2022 Variation due to construction of retaining wall due to level difference for project colony buildings. The Contractor’s response is awaited. 13 MDCG/MF/01/7533 06/06/2022 Variation of stone masonry retaining wall along Access Road The Contractor’s response is awaited. 14 MDCG/MF/01/6919 28/03/2022 Variation due to Class-G Concrete Lining in DTs The Contractor’s response to the Engineer’s comments is awaited. 15 MDCG/MF/01/4728 21/06/2021 Variation due to Tensioned ground anchors at Power Intake and Power Waterway The Contractor’s response to the Engineer’s comments is awaited.
  • 51. Variation Orders 50 Sr. No Last Submission Date Description Status 16 MDCG/MF/01/6919 28/03/2022 Variation due to Class-G Concrete Lining in DTs The Contractor’s response to the Engineer’s comments is awaited. 17 MDCG/MF/01/7830 13/07/2022 Variation regarding the adjustment of generator parameter The Contractor’s response to the Engineer’s comments is awaited. The Employer through his letter no. 4970-74 provided comments from CCC regarding interpretation of Sub-Clause 3.1 (B) ii of PCC and advised the Engineer to exercise his powers to issue Variation Orders up to 2% of the accepted Contract price. After further deliberations and correspondence exchanged, the Engineer shall proceed accordingly for issuance of the VOs.
  • 52. CONTRACTUAL MATTERS 51 • LOT-2 - DIVERSION TUNNEL COMPLETION - APPLICATION OF LDS EoT-2 - DT EoT only – preliminary assessment EoT 84 days EoT assessment to be approved by BOM and Employer • LOT-3 - RIGHT OF ACCESS TO AND POSSESSION OF SITE EOT-MW-03 – Preliminary assessment EOT 272 days. The Engineer’s Draft determination shall invite the Employer for review and consultation for finalization. • EXERCISING VO POWERS The Employer advised the Engineer to exercise his powers to issue Variation Orders up to 2% of the accepted Contract price.
  • 53. CONTRACTUAL MATTERS 52 • PANDEMIC CORONA VIRUS (COVID-19) The Contractor is serving claim notices (EoT & Cost) under force majeure Clause 19 & Employer’s risk Clause 17. No entitlement for cost under these clauses: Clause 19 – not entitled to Cost under Sub-Clauses 19.4. Entitled only for events given in Sub-Clause 19.1. (ii) – (iv) incl. rebellion, riot, munitions of war. Clause 17 – Sub-Clause 17.3 & 17.4 - no rectification instructed by the Engineer • PROJECT COLONY GAS SUPPLY SYSTEM The Contractor claimed that Gas Supply System is additional to his scope The Engineer assessed that Gas Supply System is in Contractor’s scope and issued his Determination under Sub-Clause 3.5 of GCC accordingly. The Contractor has disputed with the Engineer’s Determination and referred the case to DB for their decision. DB proceedings are under way.