SlideShare a Scribd company logo
1 of 41
VOCATIONAL TRAINING REPORT
STUDY ON CONSTRUCTION OF FLYOVER
OF BRPNNL, PATNA
COSTRUCTION OF FLYOVER FROM
MITHAPUR TO CHIRIYATAND
Submitted by- Under guidance of:
Vishal Prakash Er. Arvind Kumar
Enrol no.-CIV/93/13 Project engineer
Reference no.- NIT/T&P/15/159 Dt.01.10.15 BRPNNL, Patna
National institute of technology, Srinagar
ACKNOWLEDGEMENT
I would like to express my deepest appreciation to all those who
provided me the possibility to complete this report . A special
gratitude I give to project manager Er. Arvind Kumar,( BRPNNL) ,
whose contribution in stimulating suggestions & encouragement,
helped me to coordinate my project especially in writing this report.
Furthermore I would also like to acknowledge with much
appreciation the crucial role of Er. Tanweer siddique(Bridge), Er.
Rishu Singh(Q.S), Er. Ashish Kumar (Survey) and S.P. Singla
construction Pvt. Ltd. Staffs for best possible guidance regarding the
Project.
Lastly, I would like to appreciate the efforts made by BRPNNL, Patna
for providing the professional experience to the us.
Date: 22/01/2016 VISHAL PRAKASH
Place: Patna
BIHAR RAJYA PUL NIRMAN NIGAM
LIMITED, PATNA
CERTIFICATE
This is to certify that the project named “Study on
construction of Flyover from Mithapur to chiriyantand”
submitted by Mr. VISHAL PRAKASH Enrol no.- CIV/93/13 in
partial fulfilment of the requirement for Bachelor of
Technology Degree in Civil Engineering at National
institute of technology, Srinagar
And this work has not Plagiarized from elsewhere to best of
my knowledge.
Date: 22/01/2016 Er. Arvind Kumar
Project Engineer
CONTENT
S.NO TOPIC PAGE NO.
01. INTRODUCTION 05
02. CONSTRUCTION
DETAIL
06
03. EXECUTION OF
PROJECT
07
04. SURVEYING 08-09
05. FOUNDATION 10-13
06. SUBSTRUCTURE 14-26
07. SUPERSTRUCTURE 27-34
08. SPECIFICATIONS 35-36
09. CONCLUSION 37
10. REFERENCES 38
INTRODUCTION
BIHAR RAJYA PUL NIRMAN NIGAM LIMITED, PATNA(BRPNNL)
was established on 11th June 1975 as Govt. Company.
The recent project , flyover from “mithapur to chriyantand” is
also in construction under BRPNNL .
It will reduce the Traffic problems . In Patna due to excess
vehicles and poor traffic system and poor road space i is
necessary to construct flyovers.
The Flyover is 2x2 lane of carriage way 5.5m from Mithapur
R.O.B to chiriyantand via station road (854m. Elevated +207m
ramp) in Patna.
CONSTRUCTION DETAILS
Project title Construction of flyover (2 lane and
1 lane) carriage way (5.5m) from
G.P.O golembur to Chiriyatand
flyover via station road
Project estimated cost 150 crores
Contractor S.P. Singla constructions Pvt.Ltd.
Consultant Stup Association with treetek
Client BRPNNL, Patna
Site Location Station Road
EXECUTION OF PROJECT
 Sequence of construction:
1. Surveying
2. Analysis and design of the structure
3. Piling
a. Drilling
b. Pile cap Construction
4. Construction of Pier shaft and Pier cap
5. Construction of Pedestal and seismic stopper
6. Construction of segments and/or girders
7. Launching and gluing of segments
8. Construction of road over bridge
SURVEYING
TOPOGRAPHICAL SURVEY:
Topography is used to determine the position or any point in
both the horizontal and vertical coordinates( Latitudes,
Longitudes, Altitudes).
Survey includes Reconnaissance. Then
various maps are studied and then detailed
is done by Total station and layouts are
given on AutoCAD.
With the help of this total space for the
construction of the flyover ,no. Of lanes and
total carriage are decided.
TRAFFIC SURVEY:
Is done carry out design improvement traffic system and
management. Traffic forecasts predicts the future traffic levels
on the road. In this flyover design is so made to meet for next
25 yrs.
TRAFFIC MONITORING:
Traffic control includes CCTV and other means for monitoring
traffic by local and state roadways to manage traffic flow and
providing advice concerning traffic congestion.
TRAFFIC CONTROL:
Traffic controllers(T.C) usually known as Lollipop men shows
the their Stop/Slow sign known as STOP. A camera is also
installed to detect the traffic rule violations, including
speeding of vehicles.
FOUNDATIONS:
Foundations are the structures which are constructed below
existing ground level. It sustains the loads coming from the
sub structures and superstructures.
Bridges had to carry a big load so PILE FOUNDATION are
preferred.
It is a type of foundation which where good soil are at the
depth of 10-15m or soil having low bearing capacity.
In this flyover Group of piles drilled for piling:
for P1 to P14- 10 Piles (140 nos.), for P21, P23, P24, P26, P27,
P29, P30, P32,33& P21A- 4 Piles(40 nos.), for P22, P25, P28,
P31, P22A- 6 Piles(30 nos.), P16 to P19 – 8 Piles(32 nos.)
Total nos. Of piles =242 piles
PILE FOUNDATION
All piles have Dia. =1200mm
Depth =25m (except for P1A, P1B, P1D which have 30m piling)
M35 Grade of concrete
Piles are structure that are made up of steel, concrete, timber.
They are used to build pile foundation, and use of piles is
necessary to ensure safety.
• PILES are divided
in given category:
Steel
piles
Concrete
piles
Wooden(
Timber)
piles
CONCRETE PILES
In this flyover ,Piles used are Concrete cast in-situ piles.
Types of Concrete Piles:
PrecastPiles
These are
prepared by using
ordinary
Reinforcements &
they can be
octagonal
These Piles are
casted to any
Length& cured.
Precisepiles
These are
Prestressed by
use of high
strength steel
cables. Ultimate
Strength= 260ksi.
After curing ,the
cables are cut,
thus producing
high compressive
force on piles.
Castin-situpiles
Piles are built by
making hole in
the ground and
then filling it with
concrete.
Two types – a)
Cased, b)
Uncased
PILE BORING:
Digging in ground for strong foundation is Pile Boring. For
excavation on top soil 2-3 m an instrument named AGAR is
Placed on the top of the digging machine.
Liner is used to maintain the stability of the soil.
SOFT GROUND DIGGING HEAD:
It is being made for digging clay and it is made of heavy duty
high carbon. It is being is done in 3 phases:
A) EXCAVATION- Digging is done by Auger Machine( MAT) up to
28m. After digging flushed Bentonite to prevent the bore hole
from collapse and installing the bottom section of temporary
casing in ground by oscillating and jacking.
B)CONCRETE PLACEMENT:
Concreting is done by transit Mix Truck and it has got ability
to take 7 cubic m of concrete which are casted in foundation
and settled by TREMIE Pipe.
The pile shaft will be concreted by underwater Tremie
technique the pipe is inserted to the bottom of pile leaving
cover of “500mm”. Concrete will be poured by tremie pipe by
using concrete skip.
C) INSTALLATION OF REINFORCEMENT:
After completion of concreting, dowel bars of required length
and nos. Will be installed to pile shaft and down to the
predetermined level before extraction of bottom steel casing.
Reinforcements is done by steel, cage and Liner.
SUBSTRUCTURE
Substructure Pier cap
Pier shaft
Pile cap
Pile cap:
• Formation of pile-
pile cap= R.L of existing ground level-cut off
level
Pile cap is formed by combination of pile and
then binding the steel followed by shuttering
• Dimension of pile caps-
for P1 to P15:
length= 16m, breadth=5.2m, height=1.8m
for P16 to P19:
length= 12.4m, breadth= 5.2m, height= 1.8m
for P21, P23, P24, P26, P27, P29, P30, P32,
P33, P21A, P20A, P23A, P20
length=breadth= 5.2m, height=1.8m
for P22,P25, P28, P28, P31, P22A
length= 8.8m, breadth= 5.2m, height= 1.8m
After piling
completion, soil is
excavated for
construction of pile
cap.
For proper pile cap
P.C.C. Is provided for
separation from
mud. At site 75mm
thick PCC is carried
out for control over
seepage.
• Reinforcement steel in Pile cap
• Grade of concrete used
M35
S.no. BARS
1. 20mm @140mm c/c
2. 16mm @140mm c/c
3. 32mm @90mm c/c
4. 32mm @180mm c/c
5. 16mm @180mm c/c
PIER SHAFT
A pier shaft is a raised structure provided mostly at the centre
of the pile cap which supports the structure and transfer the
several types of load to the foundation.
DIMENSION OF THE SHAFT:
length= 2m, breadth= 2m, height=
and length= 1.5m, breadth= 1.5m, height=
REINFORCEMENTS IN SHAFT:
S.no. BARS
1. 4 sides 17 NOS. 32mm
2. 4 sides 10mm @100 c/c
3. 4 sides 10mm @200 c/c
4. 16mm @100 c/c
5. 12mm @200 c/c
6. Links 10mm @200 c/c
PIER CAP-
Pier caps are the topmost structure of the substructure. Above
these the superstructures (segments & girders) are placed.
DIMENSIONS OF PIER CAPS:
For P1 to P14: Length= 6m, Breadth= 3.3m
For P23, P26, P29, P32, P33, P20A : Length= 5.4m,
Breadth= 2.8m
For P21, P24, P27, P30, P31, P21A : Length= 5.4m, Breadth=
1.9m
For P15, P19 : Length= 11.4m, Breadth= 2.8m
For P16 to P18 : Length= 11.4m, Breadth= 2.4m
GRADE OF CONCRETE FOR CASTING
M 35 Except pier 17 ,where M 40 is used.
REINFORCEMENT USED IN PIER CAP
S.no. BARS
1. 12mm @150 c/c
2. 25 nos. 32mm ,top bar
3. 2*5 16mm
4. 12mm @150mm c/c, LV bar
5. 17 nos. 20mm, hunch bar
6. 25mm @125 c/c, Loop
7. 5 nos. 16mm @125mm c/c, Ring
8. 3 nos. 16mm @200mm c/c, Ring
9. 12mm @150mm c/c, bottom bar
10. 24 nos. 20mm @435 c/c in four layers, 6 in each layer
BEARINGS, PEDESTALS, SEISMIC STOPPERS
After the accumulation of all the reinforcements in pier cap a
surface is formed over which Bearings, Pedestals and Seismic
stoppers are provided as per the design.
Seismic stopper: The current designs of seismically designs
as a second line of defence. These structures allow
development of in-service moments of the deck, without
transmitting loads on pier and foundation, while during
earthquake they resist the entire seismic action.
Height of stopper= 1.2m
LV bars are used of 400mm
& 700mm ,16mm dia.
PEDESTALS AND BEARINGS
DIMENSIONS :
• Pedestal: Length= 700mm, Breadth= 700mm, Height= 500mm
• Bearing: Height= 137mm
A bearing is an element of superstructure which provides an
interface between superstructure and sub structure. This is
important because of the deformations and dimensional
changes in superstructure due to Thermal expansion, seismic
forces, wind loads etc. & here use POT PTFE bearing
REINFORCEMENTS :
A mesh of dimension 750mm*850mm is used inside pedestal at
20mm and 100 mm from the top.
8mm @75mm c/c and12mm @100 c/c
MAKING OF PILE AND PIER CAP
PROCESS-
 Messing of Pile caps, pier shafts & pier caps by different
reinforced steel bars.
 Welding by Arc welding method.
 Shuttering and then casting(concreting).
CONCRETING OF STRUCTURES
Concrete is a composite material made up of mainly cement,
water and aggregates in definite proportion as per the grade
of the concrete to achieve the desired physical properties.
After casting of the structures curing is done.
CURING OF THE STRUCTURE:-
For attaining the full strength of the concrete i.e.
Compressive strength curing with water is properly done on
the casted structure. It takes almost 28 to 30 days for a
concrete structure to attain its strength and durability.
DIA. AND DEPTH OF THE BORE HOLES:
• Diameter of the pile =1200mm
• Depth =25m (foundation level)
• Lap length =50D
• Reinforcements : 18 nos. 20mm dia.
& 18mm @150c/c
The 25m of depth consists of following
4 layers:
 clay(7m)
 Gravel & clay mixes(6m)
 Clay(3m)
 Sand gravel mix
SUPERSTRUCTURE
Structures which are above the pier cap and placed on
the bearings are superstructure. Roads are further
constructed over it.
SEGMENTS
• TWO TYPES: A) PIER
SEGMENT, B) NORMAL
SEGMENT
GIRDERS
• Used I –girder in this
project
SEGMENTS:
Placed on the bearing plate. These are used to make a span
of the flyover. Segments are precast made up of M45 GRADE
concrete and FE 500. These structures are posses both
Tension and Compression members, so designs are made by
taking in account both forces on it.
TYPES OF SEGMENT USED:
• Pier segment(P.S)- These are placed at the end of the span on
the pier cap. Length of P.S is smaller than the normal segment
and the anchor hole are inclined. Two P.S are used in making
of the span.
• NORMAL SEGMENT- These are placed in between two P.S for
making the span and anchor hole are straight. Total 9
segments are used in between two pier.
Total length of span= 2*2.35+9*3.25=33.95m
S.NO. SEGMENTS LENGTH
1. PIER SEGMENT 2.35m
2. NORMAL SEGMENT 3.25m
GIRDERS:
Individual beam like structure which are separately placed on
the bearings. These structures are shorter in length than
segment and stressing are done precast by using cables
certain in nos. Depends on the design.
In this project I-girder of 3 and 6 span are used.
LAUNCHING OF SEGMENT:
The segments are launched by launching girder or
gantry girder. Beam are connected both end of the
segment and pressure are applied in segments. All
the segments are joined to each other by gluing.
LAUNCHING OF DECK BY LAUNCHING
MACHINE:
Launching machine is used to uplift the segment of
the bridge all the segments are lifted at once by the
use of lifter.
Number of segment between two pier:
no. Of segment= 11
weight of one segment =600T
After placing of the segments Stressing is done by
use of high tensile cables, so that loads came to the
cable & bridge should be stable.
JOINTING OF SEGMENT:
Mixing of both type of chemical (Nitobond Pc base thixotropic
epoxy adhesive& Nitobond Pc 30 harder) is done and every
time two segments are compressed(glued) to each other.
After 24 hours the process checked by flushing water and
leakage in anchor hole.
ANCHOR HOLE-
These are present in entire segment to for stressing of it. 6
nos. Of hole are present at one side of segment. Parabolic
shape.
TENSILE WIRE-
It is a high tensile steel wire inserted in all 11 segment for
stressing. No. Of wire depend on the design(12, 19,25etc.).
Grade of the wire is 19T15.
PRESTRESSING:
Pre-stressing means creating a permanent stress in the
structure. In this process dead end are fixed with life wedge to
hold the tensile wire. And the free end is fixed with hydraulic
jack and force are applied approximately 369 T.
GROUTING:
Grouting involves injection of cemented material in a certain
ratio of cement and water for isolated pore or void space is
often called Simple grouting.
Quantity of material:
o Cement :1 bag
o Water: 22 litres
o Admixtures: cibex 100
SPAN:
The distance between two span is 500mm.
Total span length between two pier varies in this project
P1-P5 =34m, P6-P19=37m and rest have distance= 20m
PRECAUSTION TO BE TAKEN DURING PLACING
CONCRETE
o Water should not be added to concrete during its passage
from mixer to form work.
o The form work(surface) which has to receive the fresh
concrete should be properly watered(cured).
o Concrete should be placed in single thickness.
o Concrete should be tapped in such a way that no honeycomb
surface appear on the surface.
TECHNICAL SPECIFICATION
1) Chiriyatand to Gandhi maidan:
OTHER SPECIFICATION:
o Pile group -4 and 6
o A1-P1- 33.25m, P1-P17- 34m, P17-A2- 33.25m
o Length of flyover= 612 m elevated , approach(RE Panel)= 147m fill.
Diameter of pile 1200mm
Vertical & horizontal loads 250T & 30T
Depth of pile cap 1800mm
Number of Piles 110
Number of pile cap 19
Number of segment 198
2) Station to Mithapur
DIAMETER OF PILES 1800MM
VETICAL& HORIZONTAL LOADS 230T& 20T
CONCRETE USED M35(EXCEPT P17: M40)
DEPTH OF PILE CAP 1.8m
NUMBER OF PILES 267
NUMBER OF PILE CAP 38
NUMBER OF SEGMENT 182
NUMBER OF SHAFT 40
NUMBER OF HAMMER HEAD 37
CONCLUSION
The project report involves construction of flyover and shows
concern over every written word.
Bridges break down separation and foster connectedness
across gulfs and rivers, between people and countries. As far
back as we can see in history, human beings have used new
technology to solve problem and ease their physical burdens.
The distinctiveness of humans as a species is defined by their
use of tools, and bridge are technological tools that aims to
solve the problem of crossing and obstacle in such a way as to
cut down the efforts and time needed to do so.
As the traffic problem arises in the cities due to more vehicles
in the cities because of big population. This flyover change the
face of the city Patna and Paved the way to progress.
REFERENCES:
• Indian bureau of standard and meteorology.
• IS Indian standards.
• IRS Indian road congress( i.e. Recommended code of
practise by IRS)
• ASTM American society of testing and materials.
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)

More Related Content

What's hot

Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaNarayan Gupta
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Summer traning report
Summer traning reportSummer traning report
Summer traning reportAmit Raj
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their designBhavya Jaiswal
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadampradip dangar
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction projectAxay Sharma
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavementBhavya Jaiswal
 
final year Project (civil)
final year Project (civil)final year Project (civil)
final year Project (civil)Alankar jaiswal
 

What's hot (20)

Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL Patna
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Summer traning report
Summer traning reportSummer traning report
Summer traning report
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Spine and wing method for box girders
Spine and wing method for box girdersSpine and wing method for box girders
Spine and wing method for box girders
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Flyover Bridge construction project
Flyover Bridge construction projectFlyover Bridge construction project
Flyover Bridge construction project
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Stress ribbon-bridges
Stress ribbon-bridgesStress ribbon-bridges
Stress ribbon-bridges
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
final year Project (civil)
final year Project (civil)final year Project (civil)
final year Project (civil)
 

Similar to TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
Industrial training seminar PPT
Industrial training seminar PPTIndustrial training seminar PPT
Industrial training seminar PPTAbhishek Makwana
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITEDWater Birds (Ali)
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentationATUL SHUKLA
 
Summer training presentation from BRPNNL by Randhir Kumar(1503050)
Summer training presentation from BRPNNL by Randhir Kumar(1503050)Summer training presentation from BRPNNL by Randhir Kumar(1503050)
Summer training presentation from BRPNNL by Randhir Kumar(1503050)RandhirKumar172
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 

Similar to TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR) (20)

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Field work
Field workField work
Field work
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Industrial training seminar PPT
Industrial training seminar PPTIndustrial training seminar PPT
Industrial training seminar PPT
 
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITEDCIVIL CONSTRUCTION INFATIMA FERTILIZER COMPANY LIMITED
CIVIL CONSTRUCTION IN FATIMA FERTILIZER COMPANY LIMITED
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
lmrc presentation
lmrc presentationlmrc presentation
lmrc presentation
 
Summer training presentation from BRPNNL by Randhir Kumar(1503050)
Summer training presentation from BRPNNL by Randhir Kumar(1503050)Summer training presentation from BRPNNL by Randhir Kumar(1503050)
Summer training presentation from BRPNNL by Randhir Kumar(1503050)
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
Training
TrainingTraining
Training
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
 

Recently uploaded

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 

Recently uploaded (20)

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 

TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)

  • 1. VOCATIONAL TRAINING REPORT STUDY ON CONSTRUCTION OF FLYOVER OF BRPNNL, PATNA COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND Submitted by- Under guidance of: Vishal Prakash Er. Arvind Kumar Enrol no.-CIV/93/13 Project engineer Reference no.- NIT/T&P/15/159 Dt.01.10.15 BRPNNL, Patna National institute of technology, Srinagar
  • 2. ACKNOWLEDGEMENT I would like to express my deepest appreciation to all those who provided me the possibility to complete this report . A special gratitude I give to project manager Er. Arvind Kumar,( BRPNNL) , whose contribution in stimulating suggestions & encouragement, helped me to coordinate my project especially in writing this report. Furthermore I would also like to acknowledge with much appreciation the crucial role of Er. Tanweer siddique(Bridge), Er. Rishu Singh(Q.S), Er. Ashish Kumar (Survey) and S.P. Singla construction Pvt. Ltd. Staffs for best possible guidance regarding the Project. Lastly, I would like to appreciate the efforts made by BRPNNL, Patna for providing the professional experience to the us. Date: 22/01/2016 VISHAL PRAKASH Place: Patna
  • 3. BIHAR RAJYA PUL NIRMAN NIGAM LIMITED, PATNA CERTIFICATE This is to certify that the project named “Study on construction of Flyover from Mithapur to chiriyantand” submitted by Mr. VISHAL PRAKASH Enrol no.- CIV/93/13 in partial fulfilment of the requirement for Bachelor of Technology Degree in Civil Engineering at National institute of technology, Srinagar And this work has not Plagiarized from elsewhere to best of my knowledge. Date: 22/01/2016 Er. Arvind Kumar Project Engineer
  • 4. CONTENT S.NO TOPIC PAGE NO. 01. INTRODUCTION 05 02. CONSTRUCTION DETAIL 06 03. EXECUTION OF PROJECT 07 04. SURVEYING 08-09 05. FOUNDATION 10-13 06. SUBSTRUCTURE 14-26 07. SUPERSTRUCTURE 27-34 08. SPECIFICATIONS 35-36 09. CONCLUSION 37 10. REFERENCES 38
  • 5. INTRODUCTION BIHAR RAJYA PUL NIRMAN NIGAM LIMITED, PATNA(BRPNNL) was established on 11th June 1975 as Govt. Company. The recent project , flyover from “mithapur to chriyantand” is also in construction under BRPNNL . It will reduce the Traffic problems . In Patna due to excess vehicles and poor traffic system and poor road space i is necessary to construct flyovers. The Flyover is 2x2 lane of carriage way 5.5m from Mithapur R.O.B to chiriyantand via station road (854m. Elevated +207m ramp) in Patna.
  • 6. CONSTRUCTION DETAILS Project title Construction of flyover (2 lane and 1 lane) carriage way (5.5m) from G.P.O golembur to Chiriyatand flyover via station road Project estimated cost 150 crores Contractor S.P. Singla constructions Pvt.Ltd. Consultant Stup Association with treetek Client BRPNNL, Patna Site Location Station Road
  • 7. EXECUTION OF PROJECT  Sequence of construction: 1. Surveying 2. Analysis and design of the structure 3. Piling a. Drilling b. Pile cap Construction 4. Construction of Pier shaft and Pier cap 5. Construction of Pedestal and seismic stopper 6. Construction of segments and/or girders 7. Launching and gluing of segments 8. Construction of road over bridge
  • 8. SURVEYING TOPOGRAPHICAL SURVEY: Topography is used to determine the position or any point in both the horizontal and vertical coordinates( Latitudes, Longitudes, Altitudes). Survey includes Reconnaissance. Then various maps are studied and then detailed is done by Total station and layouts are given on AutoCAD. With the help of this total space for the construction of the flyover ,no. Of lanes and total carriage are decided.
  • 9. TRAFFIC SURVEY: Is done carry out design improvement traffic system and management. Traffic forecasts predicts the future traffic levels on the road. In this flyover design is so made to meet for next 25 yrs. TRAFFIC MONITORING: Traffic control includes CCTV and other means for monitoring traffic by local and state roadways to manage traffic flow and providing advice concerning traffic congestion. TRAFFIC CONTROL: Traffic controllers(T.C) usually known as Lollipop men shows the their Stop/Slow sign known as STOP. A camera is also installed to detect the traffic rule violations, including speeding of vehicles.
  • 10. FOUNDATIONS: Foundations are the structures which are constructed below existing ground level. It sustains the loads coming from the sub structures and superstructures. Bridges had to carry a big load so PILE FOUNDATION are preferred. It is a type of foundation which where good soil are at the depth of 10-15m or soil having low bearing capacity. In this flyover Group of piles drilled for piling: for P1 to P14- 10 Piles (140 nos.), for P21, P23, P24, P26, P27, P29, P30, P32,33& P21A- 4 Piles(40 nos.), for P22, P25, P28, P31, P22A- 6 Piles(30 nos.), P16 to P19 – 8 Piles(32 nos.) Total nos. Of piles =242 piles
  • 11. PILE FOUNDATION All piles have Dia. =1200mm Depth =25m (except for P1A, P1B, P1D which have 30m piling) M35 Grade of concrete Piles are structure that are made up of steel, concrete, timber. They are used to build pile foundation, and use of piles is necessary to ensure safety. • PILES are divided in given category: Steel piles Concrete piles Wooden( Timber) piles
  • 12. CONCRETE PILES In this flyover ,Piles used are Concrete cast in-situ piles. Types of Concrete Piles: PrecastPiles These are prepared by using ordinary Reinforcements & they can be octagonal These Piles are casted to any Length& cured. Precisepiles These are Prestressed by use of high strength steel cables. Ultimate Strength= 260ksi. After curing ,the cables are cut, thus producing high compressive force on piles. Castin-situpiles Piles are built by making hole in the ground and then filling it with concrete. Two types – a) Cased, b) Uncased
  • 13. PILE BORING: Digging in ground for strong foundation is Pile Boring. For excavation on top soil 2-3 m an instrument named AGAR is Placed on the top of the digging machine. Liner is used to maintain the stability of the soil. SOFT GROUND DIGGING HEAD: It is being made for digging clay and it is made of heavy duty high carbon. It is being is done in 3 phases: A) EXCAVATION- Digging is done by Auger Machine( MAT) up to 28m. After digging flushed Bentonite to prevent the bore hole from collapse and installing the bottom section of temporary casing in ground by oscillating and jacking.
  • 14. B)CONCRETE PLACEMENT: Concreting is done by transit Mix Truck and it has got ability to take 7 cubic m of concrete which are casted in foundation and settled by TREMIE Pipe. The pile shaft will be concreted by underwater Tremie technique the pipe is inserted to the bottom of pile leaving cover of “500mm”. Concrete will be poured by tremie pipe by using concrete skip. C) INSTALLATION OF REINFORCEMENT: After completion of concreting, dowel bars of required length and nos. Will be installed to pile shaft and down to the predetermined level before extraction of bottom steel casing. Reinforcements is done by steel, cage and Liner.
  • 15.
  • 17. Pile cap: • Formation of pile- pile cap= R.L of existing ground level-cut off level Pile cap is formed by combination of pile and then binding the steel followed by shuttering • Dimension of pile caps- for P1 to P15: length= 16m, breadth=5.2m, height=1.8m for P16 to P19: length= 12.4m, breadth= 5.2m, height= 1.8m for P21, P23, P24, P26, P27, P29, P30, P32, P33, P21A, P20A, P23A, P20 length=breadth= 5.2m, height=1.8m for P22,P25, P28, P28, P31, P22A length= 8.8m, breadth= 5.2m, height= 1.8m After piling completion, soil is excavated for construction of pile cap. For proper pile cap P.C.C. Is provided for separation from mud. At site 75mm thick PCC is carried out for control over seepage.
  • 18. • Reinforcement steel in Pile cap • Grade of concrete used M35 S.no. BARS 1. 20mm @140mm c/c 2. 16mm @140mm c/c 3. 32mm @90mm c/c 4. 32mm @180mm c/c 5. 16mm @180mm c/c
  • 19. PIER SHAFT A pier shaft is a raised structure provided mostly at the centre of the pile cap which supports the structure and transfer the several types of load to the foundation. DIMENSION OF THE SHAFT: length= 2m, breadth= 2m, height= and length= 1.5m, breadth= 1.5m, height= REINFORCEMENTS IN SHAFT: S.no. BARS 1. 4 sides 17 NOS. 32mm 2. 4 sides 10mm @100 c/c 3. 4 sides 10mm @200 c/c 4. 16mm @100 c/c 5. 12mm @200 c/c 6. Links 10mm @200 c/c
  • 20. PIER CAP- Pier caps are the topmost structure of the substructure. Above these the superstructures (segments & girders) are placed. DIMENSIONS OF PIER CAPS: For P1 to P14: Length= 6m, Breadth= 3.3m For P23, P26, P29, P32, P33, P20A : Length= 5.4m, Breadth= 2.8m For P21, P24, P27, P30, P31, P21A : Length= 5.4m, Breadth= 1.9m For P15, P19 : Length= 11.4m, Breadth= 2.8m For P16 to P18 : Length= 11.4m, Breadth= 2.4m GRADE OF CONCRETE FOR CASTING M 35 Except pier 17 ,where M 40 is used.
  • 21. REINFORCEMENT USED IN PIER CAP S.no. BARS 1. 12mm @150 c/c 2. 25 nos. 32mm ,top bar 3. 2*5 16mm 4. 12mm @150mm c/c, LV bar 5. 17 nos. 20mm, hunch bar 6. 25mm @125 c/c, Loop 7. 5 nos. 16mm @125mm c/c, Ring 8. 3 nos. 16mm @200mm c/c, Ring 9. 12mm @150mm c/c, bottom bar 10. 24 nos. 20mm @435 c/c in four layers, 6 in each layer
  • 22.
  • 23. BEARINGS, PEDESTALS, SEISMIC STOPPERS After the accumulation of all the reinforcements in pier cap a surface is formed over which Bearings, Pedestals and Seismic stoppers are provided as per the design. Seismic stopper: The current designs of seismically designs as a second line of defence. These structures allow development of in-service moments of the deck, without transmitting loads on pier and foundation, while during earthquake they resist the entire seismic action. Height of stopper= 1.2m LV bars are used of 400mm & 700mm ,16mm dia.
  • 25. DIMENSIONS : • Pedestal: Length= 700mm, Breadth= 700mm, Height= 500mm • Bearing: Height= 137mm A bearing is an element of superstructure which provides an interface between superstructure and sub structure. This is important because of the deformations and dimensional changes in superstructure due to Thermal expansion, seismic forces, wind loads etc. & here use POT PTFE bearing REINFORCEMENTS : A mesh of dimension 750mm*850mm is used inside pedestal at 20mm and 100 mm from the top. 8mm @75mm c/c and12mm @100 c/c
  • 26. MAKING OF PILE AND PIER CAP PROCESS-  Messing of Pile caps, pier shafts & pier caps by different reinforced steel bars.  Welding by Arc welding method.  Shuttering and then casting(concreting). CONCRETING OF STRUCTURES Concrete is a composite material made up of mainly cement, water and aggregates in definite proportion as per the grade of the concrete to achieve the desired physical properties. After casting of the structures curing is done.
  • 27. CURING OF THE STRUCTURE:- For attaining the full strength of the concrete i.e. Compressive strength curing with water is properly done on the casted structure. It takes almost 28 to 30 days for a concrete structure to attain its strength and durability.
  • 28. DIA. AND DEPTH OF THE BORE HOLES: • Diameter of the pile =1200mm • Depth =25m (foundation level) • Lap length =50D • Reinforcements : 18 nos. 20mm dia. & 18mm @150c/c The 25m of depth consists of following 4 layers:  clay(7m)  Gravel & clay mixes(6m)  Clay(3m)  Sand gravel mix
  • 29. SUPERSTRUCTURE Structures which are above the pier cap and placed on the bearings are superstructure. Roads are further constructed over it. SEGMENTS • TWO TYPES: A) PIER SEGMENT, B) NORMAL SEGMENT GIRDERS • Used I –girder in this project
  • 30. SEGMENTS: Placed on the bearing plate. These are used to make a span of the flyover. Segments are precast made up of M45 GRADE concrete and FE 500. These structures are posses both Tension and Compression members, so designs are made by taking in account both forces on it.
  • 31. TYPES OF SEGMENT USED: • Pier segment(P.S)- These are placed at the end of the span on the pier cap. Length of P.S is smaller than the normal segment and the anchor hole are inclined. Two P.S are used in making of the span. • NORMAL SEGMENT- These are placed in between two P.S for making the span and anchor hole are straight. Total 9 segments are used in between two pier. Total length of span= 2*2.35+9*3.25=33.95m S.NO. SEGMENTS LENGTH 1. PIER SEGMENT 2.35m 2. NORMAL SEGMENT 3.25m
  • 32. GIRDERS: Individual beam like structure which are separately placed on the bearings. These structures are shorter in length than segment and stressing are done precast by using cables certain in nos. Depends on the design. In this project I-girder of 3 and 6 span are used.
  • 33. LAUNCHING OF SEGMENT: The segments are launched by launching girder or gantry girder. Beam are connected both end of the segment and pressure are applied in segments. All the segments are joined to each other by gluing. LAUNCHING OF DECK BY LAUNCHING MACHINE: Launching machine is used to uplift the segment of the bridge all the segments are lifted at once by the use of lifter. Number of segment between two pier: no. Of segment= 11 weight of one segment =600T After placing of the segments Stressing is done by use of high tensile cables, so that loads came to the cable & bridge should be stable.
  • 34. JOINTING OF SEGMENT: Mixing of both type of chemical (Nitobond Pc base thixotropic epoxy adhesive& Nitobond Pc 30 harder) is done and every time two segments are compressed(glued) to each other. After 24 hours the process checked by flushing water and leakage in anchor hole. ANCHOR HOLE- These are present in entire segment to for stressing of it. 6 nos. Of hole are present at one side of segment. Parabolic shape. TENSILE WIRE- It is a high tensile steel wire inserted in all 11 segment for stressing. No. Of wire depend on the design(12, 19,25etc.). Grade of the wire is 19T15.
  • 35. PRESTRESSING: Pre-stressing means creating a permanent stress in the structure. In this process dead end are fixed with life wedge to hold the tensile wire. And the free end is fixed with hydraulic jack and force are applied approximately 369 T. GROUTING: Grouting involves injection of cemented material in a certain ratio of cement and water for isolated pore or void space is often called Simple grouting. Quantity of material: o Cement :1 bag o Water: 22 litres o Admixtures: cibex 100
  • 36. SPAN: The distance between two span is 500mm. Total span length between two pier varies in this project P1-P5 =34m, P6-P19=37m and rest have distance= 20m PRECAUSTION TO BE TAKEN DURING PLACING CONCRETE o Water should not be added to concrete during its passage from mixer to form work. o The form work(surface) which has to receive the fresh concrete should be properly watered(cured). o Concrete should be placed in single thickness. o Concrete should be tapped in such a way that no honeycomb surface appear on the surface.
  • 37. TECHNICAL SPECIFICATION 1) Chiriyatand to Gandhi maidan: OTHER SPECIFICATION: o Pile group -4 and 6 o A1-P1- 33.25m, P1-P17- 34m, P17-A2- 33.25m o Length of flyover= 612 m elevated , approach(RE Panel)= 147m fill. Diameter of pile 1200mm Vertical & horizontal loads 250T & 30T Depth of pile cap 1800mm Number of Piles 110 Number of pile cap 19 Number of segment 198
  • 38. 2) Station to Mithapur DIAMETER OF PILES 1800MM VETICAL& HORIZONTAL LOADS 230T& 20T CONCRETE USED M35(EXCEPT P17: M40) DEPTH OF PILE CAP 1.8m NUMBER OF PILES 267 NUMBER OF PILE CAP 38 NUMBER OF SEGMENT 182 NUMBER OF SHAFT 40 NUMBER OF HAMMER HEAD 37
  • 39. CONCLUSION The project report involves construction of flyover and shows concern over every written word. Bridges break down separation and foster connectedness across gulfs and rivers, between people and countries. As far back as we can see in history, human beings have used new technology to solve problem and ease their physical burdens. The distinctiveness of humans as a species is defined by their use of tools, and bridge are technological tools that aims to solve the problem of crossing and obstacle in such a way as to cut down the efforts and time needed to do so. As the traffic problem arises in the cities due to more vehicles in the cities because of big population. This flyover change the face of the city Patna and Paved the way to progress.
  • 40. REFERENCES: • Indian bureau of standard and meteorology. • IS Indian standards. • IRS Indian road congress( i.e. Recommended code of practise by IRS) • ASTM American society of testing and materials.