SIVOK – RANGPO NEW B.G. RAIL LINE PROJECT
Tunnel T1 & T2
IRCON INTERNATIONAL LIMITED
THE INFRASTRUCTURE COMPANY
Contract Details
Agency M/s. GAMMON
Date of Award 21.08.2019
Completion Period 27 Months
Date of completion 21.11.2021
Contract value Rs. 595.86 cr.
Item Scope
(m)
Excavation Progress
(m)
Lining Progress (m)
Main Tunnel T1 4204 299.6 0.00
Main Tunnel T2 902 120.90 0.00
ADIT Tunnel 800 0.00 0.00
Approach road for
ADIT
320 0.00 0.00
Total
(T1+T2+ADIT)(m)
5906 420.50 0.00
Financial 595.86 Cr. 34.43 Cr
Main Tunnel (L – 4204 m)
2979m
800m
1225m
Gammon Scope
1 in 80
Main tunnel L=902m
T1P2
T1P1
T2P1 T2 P2
290.10
NH-10
Approach road of 320m
length to ADIT Portal
TUNNEL T1 & T2
120.90
Progress of Tunnel T-1 & T-2
9.5
Manpower & Machinery Tunnel no 1 & 2
SN DESIGNATION TO BE DEPLOYED
( As per available
front/face)
DEPLOYED SHORTFALL
1 Project Manager 1 1 0
2 Works Manager 1 1 0
3 QSS Engineer 1 1 0
4 Quality Manager 1 1 0
5 Safety Manager 1 2 0
6 Site Engineer 4 4 0
7 Geologist 1 1 0
8 Surveyor 2 2 0
9 Shift Engineer 6 6 0
10 NATM Foreman 6 6 0
Deployment of key personnel
SN Type of Plants/Equipment TO BE
DEPLOYED
( As per
available
front/face)
Deployed. shortfall Remarks
1 Hydraulic drill jumbo and
basket
4 4 0
2 Sprayed concrete pump 4 4 0
3 Tunnel excavator with
swiveling
3 3 0 Balance will be deployed as the
faces open and during the
execution of concrete lining of
Tunnel
4 Pay loader 3 3 0
5 Transit Mixers 10 6 4
6 Dumper (low profile) 16 16 0 All locally hired
7 Batching Plants 2 2 0
8 Mai Pump 4 5 0
SN Type of Plants/Equipment TO BE
DEPLOYED
( As per
available
front/face)
Deployed. shortfall Remarks
9 Rotor sprayed concrete 2 2 0
10 Working platform with swiveling
basket
4 0 4 Related activities being carried out
by Drill Jumbo basket
11 Excavator 3 3 0
12 Dozer 2 1 1 After handover of Adit
13 Fork lift 1 0 1 After handover of Adit
14 Trailers 2 2 0 All locally hired
15 Concrete pump 6 2 4 Remaining concrete pump will be
deployed as per requirement
16 Stone Crusher Plant 1 0 1 After handover of D.I land
17 Crane 1 1 0
18 Explosive Van 4 4 0 Hired from explosive supplier
19 DG Set 4 7 0 Capacity= 380,365,125x3, 30 & 3 KVA
20 Compactor 1 1 0
21 Mobile concrete mixer low 12 2 10 2 nos B/P set up at each tunnel site
Cavity formation in T1/P1
SIVOK-RANGPO RAIL LINK PROJECT
Introduction-
>Tunnel T1 is a part of Sivok to Rangpo BG Tunnel Project and being
constructed between Sivok Railway Station and Andheri Jhora with a total length
of approx. 4202 meter.
>The south portal of Tunnel T1 (hereby designated as T1P1) is being excavated
by NATM method. A total of 291.3 m from chainage 321.0 m to 612.3 m
(approx.) has been already excavated.
Anticipated Geological L-Section of The
Relevant Part
Tunnel (T1/P1 drive) Face at CH 610.8 m (Apx.) before Cavity Formation
There was no indication of presence of any
shear zone or shale layer at the face and the
face shows only Sandstone which was
medium grained, light gray colored,
generally dry to damp (LHS) in water
condition. The face log of 610.8 m also
attached with this report. The rock class
depicted at 610.8 m was Adv. Class IV. Pic-
1, (RMR=43)
Face log of CH 610.8 m
3D Log of Tunnel T1P1
Tunnel (T1/P1 drive) before Cavity Formation
The cavity material was also
examined and it was found
weak to very weak & sheared &
highly weathered. Two pictures
of collapse material are given
for reference.
Collapse Material
Cavity formed after initial collapse
Initial Treatment
• Cavity formation started during further excavation from CH-610.8 due to sudden
encounter of shear zone. Sealing shotcrete (SFRS) was used as first control measure but
collapse could not controlled and further collapse continued.
Cavity increased up to CH. 608.6 m
• Collapse further continued after
first control measure, leading to
increase of cavity upwards and
backwards damaging the LG at
610.1m.
LG Damaged at
610.1m
Fore poles
damaged
Pic-3: LG at 610.1 m got damaged and all forepoles damaged
Cavity increased up to 607.5 m
Seeing that cavity may further extend
and immediate control is required, it
was decided to fill the face by the
muck and seal the same by shotcrete
for further treatment. By the time the
muck filling at face could be
completed, the cavity extended up to
606.8 m (approx.) after damage of LG
shotcrete & wire mesh.
Pic-4: LG at 608.6 m got damaged and all forepoles damaged
Cavity increased up to 606.8 m
Muck Filling at Face
In Surface visit,
a ditch was
found above
Cavity portion.
Therefore, it is
up to approx 34
m.
Possible extent of Cavity
Surface visit at the top of the cavity area.
Video of Ditch found at surface above cavity
Tunnel face filled with muck till 606.0 m. Drilling done to insert pipe to pour
concrete into the cavity.
Remedial Measures (1/13)
• Backfilling and grouting in progress
Remedial Measures (2/13)
Pipe roofing is being done
after concrete filling by 76
mm dia SDR.
Remedial Measures (3/13)
After Pipe roofing temporary rib has been installed at 606.8 m to support the pipe roofing.
Remedial Measures (4/13)
Second temporary rib
installed at 607.3 m.
Remedial Measures (5/13)
Collapse occurred from right side at 607.5 (approx.) while removing the
muck sealing to make space for third rib.
Remedial Measures (6/13)
VIDEO OF COLLAPSE FROM RIGHT SIDE
After collapse from right side
tunnel face packed with muck.
Grouting and backfilling done
by installing 105 mm holes.
Remedial Measures (7/13)
After grouting and
backfilling muck removal
done sequentially for
heading part only and
ISHB 150 ribs being
installed (starting from left
side of the tunnel) up to
612.0 m.
Remedial Measures (8/13)
After installation of ribs at
left side right side part of
the ribs being installed.
Remedial Measures (9/13)
Collapse occurred from
the right side again while
installation of permanent
ribs in right side was
going on.
Remedial Measures (10/13)
Tunnel sealed by muck
after collapse and the
installed ribs supported by
extra ISHB.
Remedial Measures (11/13)
• SDA 32mm dia installed
along the periphery of the
installed ribs at 610.0 m
and grouted.
Remedial Measures (12/13)
After grouting of SDA
sequential muck removal was
done at the right side of the
tunnel and Side Arch part of
the ribs installed one at a time
up to 612.0 m.
Remedial Measures (13/13)
Surface above
the cavity
portion was
traced with the
help of hand
GPS. A ditch
was formed
there which
was approx.
7m X 7m in
horizontal
dimensions &
3-5 m deep.
Effect of Cavity on Surface (1/2)
Weathered and sheared rock mass exposed at one
side of the ditch formed at the surface due to cavity
Monitoring
section at CH
598m & CH.
605.2m showing
deformation
within the safe
limit.
3D MONITORING at CH. 598m & CH. 605.2 m
CH 598 m
CH 605.2 m
• Due to unexpected shear zone the collapse occurred during excavation from CH 610.8 onwards.
Such shears are a common feature in Himalayan geology and exact location & extent is difficult
to map due to lack of outcrops & thick forest cover.
• The overburden cover of this area was determined from L-Section as 34.0 m.
• Tunnel T1 and T2 passes through Mahananda Wild Life Sanctuary in which there are certain
restrictions on free movement for surveying/investigation etc. Hand inspection of collapse
material and by surface visit, a Shear Zone is interpreted as shown in the schematic diagram and
surface photos shown below. This shear zone is considered as main cause of the cavity
formation. The orientation and extent of shear zone can be different from that shown in the
diagram.
Conclusion

More Related Content

Similar to PPT CAVITY Tunnel P1 610M--05.02.2021.pptx

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internshipsaibabu48
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Gautam Sharma
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 
coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3Tomasz Najder
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machinerutuldave
 
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent ShaftPeter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent ShaftNSW Environment and Planning
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case studyMD.Suresh Kumar
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...Rajesh Prasad
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptxSubratDash37
 
FINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap StudyFINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap StudyKook Dean
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLMD.Suresh Kumar
 
Paper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanPaper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanSantosh Sati
 

Similar to PPT CAVITY Tunnel P1 610M--05.02.2021.pptx (20)

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Polavaram internship
Polavaram internshipPolavaram internship
Polavaram internship
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)Methodology including all enclosures(modified 18-5-10)
Methodology including all enclosures(modified 18-5-10)
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3
 
PIPE LAYING
PIPE LAYINGPIPE LAYING
PIPE LAYING
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent ShaftPeter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
 
Tech paper guttering-case study
Tech paper guttering-case studyTech paper guttering-case study
Tech paper guttering-case study
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
FINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap StudyFINAL The Owens Lake Turnout Facility End Cap Study
FINAL The Owens Lake Turnout Facility End Cap Study
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
 
Paper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanPaper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutan
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

PPT CAVITY Tunnel P1 610M--05.02.2021.pptx

  • 1. SIVOK – RANGPO NEW B.G. RAIL LINE PROJECT Tunnel T1 & T2 IRCON INTERNATIONAL LIMITED THE INFRASTRUCTURE COMPANY
  • 2. Contract Details Agency M/s. GAMMON Date of Award 21.08.2019 Completion Period 27 Months Date of completion 21.11.2021 Contract value Rs. 595.86 cr. Item Scope (m) Excavation Progress (m) Lining Progress (m) Main Tunnel T1 4204 299.6 0.00 Main Tunnel T2 902 120.90 0.00 ADIT Tunnel 800 0.00 0.00 Approach road for ADIT 320 0.00 0.00 Total (T1+T2+ADIT)(m) 5906 420.50 0.00 Financial 595.86 Cr. 34.43 Cr Main Tunnel (L – 4204 m) 2979m 800m 1225m Gammon Scope 1 in 80 Main tunnel L=902m T1P2 T1P1 T2P1 T2 P2 290.10 NH-10 Approach road of 320m length to ADIT Portal TUNNEL T1 & T2 120.90 Progress of Tunnel T-1 & T-2 9.5
  • 3. Manpower & Machinery Tunnel no 1 & 2 SN DESIGNATION TO BE DEPLOYED ( As per available front/face) DEPLOYED SHORTFALL 1 Project Manager 1 1 0 2 Works Manager 1 1 0 3 QSS Engineer 1 1 0 4 Quality Manager 1 1 0 5 Safety Manager 1 2 0 6 Site Engineer 4 4 0 7 Geologist 1 1 0 8 Surveyor 2 2 0 9 Shift Engineer 6 6 0 10 NATM Foreman 6 6 0 Deployment of key personnel
  • 4. SN Type of Plants/Equipment TO BE DEPLOYED ( As per available front/face) Deployed. shortfall Remarks 1 Hydraulic drill jumbo and basket 4 4 0 2 Sprayed concrete pump 4 4 0 3 Tunnel excavator with swiveling 3 3 0 Balance will be deployed as the faces open and during the execution of concrete lining of Tunnel 4 Pay loader 3 3 0 5 Transit Mixers 10 6 4 6 Dumper (low profile) 16 16 0 All locally hired 7 Batching Plants 2 2 0 8 Mai Pump 4 5 0
  • 5. SN Type of Plants/Equipment TO BE DEPLOYED ( As per available front/face) Deployed. shortfall Remarks 9 Rotor sprayed concrete 2 2 0 10 Working platform with swiveling basket 4 0 4 Related activities being carried out by Drill Jumbo basket 11 Excavator 3 3 0 12 Dozer 2 1 1 After handover of Adit 13 Fork lift 1 0 1 After handover of Adit 14 Trailers 2 2 0 All locally hired 15 Concrete pump 6 2 4 Remaining concrete pump will be deployed as per requirement 16 Stone Crusher Plant 1 0 1 After handover of D.I land 17 Crane 1 1 0 18 Explosive Van 4 4 0 Hired from explosive supplier 19 DG Set 4 7 0 Capacity= 380,365,125x3, 30 & 3 KVA 20 Compactor 1 1 0 21 Mobile concrete mixer low 12 2 10 2 nos B/P set up at each tunnel site
  • 6. Cavity formation in T1/P1 SIVOK-RANGPO RAIL LINK PROJECT
  • 7. Introduction- >Tunnel T1 is a part of Sivok to Rangpo BG Tunnel Project and being constructed between Sivok Railway Station and Andheri Jhora with a total length of approx. 4202 meter. >The south portal of Tunnel T1 (hereby designated as T1P1) is being excavated by NATM method. A total of 291.3 m from chainage 321.0 m to 612.3 m (approx.) has been already excavated.
  • 8. Anticipated Geological L-Section of The Relevant Part
  • 9. Tunnel (T1/P1 drive) Face at CH 610.8 m (Apx.) before Cavity Formation There was no indication of presence of any shear zone or shale layer at the face and the face shows only Sandstone which was medium grained, light gray colored, generally dry to damp (LHS) in water condition. The face log of 610.8 m also attached with this report. The rock class depicted at 610.8 m was Adv. Class IV. Pic- 1, (RMR=43)
  • 10. Face log of CH 610.8 m
  • 11. 3D Log of Tunnel T1P1
  • 12. Tunnel (T1/P1 drive) before Cavity Formation
  • 13. The cavity material was also examined and it was found weak to very weak & sheared & highly weathered. Two pictures of collapse material are given for reference. Collapse Material
  • 14. Cavity formed after initial collapse
  • 15. Initial Treatment • Cavity formation started during further excavation from CH-610.8 due to sudden encounter of shear zone. Sealing shotcrete (SFRS) was used as first control measure but collapse could not controlled and further collapse continued.
  • 16. Cavity increased up to CH. 608.6 m
  • 17. • Collapse further continued after first control measure, leading to increase of cavity upwards and backwards damaging the LG at 610.1m. LG Damaged at 610.1m Fore poles damaged Pic-3: LG at 610.1 m got damaged and all forepoles damaged
  • 18. Cavity increased up to 607.5 m
  • 19. Seeing that cavity may further extend and immediate control is required, it was decided to fill the face by the muck and seal the same by shotcrete for further treatment. By the time the muck filling at face could be completed, the cavity extended up to 606.8 m (approx.) after damage of LG shotcrete & wire mesh. Pic-4: LG at 608.6 m got damaged and all forepoles damaged
  • 20. Cavity increased up to 606.8 m
  • 22. In Surface visit, a ditch was found above Cavity portion. Therefore, it is up to approx 34 m. Possible extent of Cavity
  • 23. Surface visit at the top of the cavity area. Video of Ditch found at surface above cavity
  • 24. Tunnel face filled with muck till 606.0 m. Drilling done to insert pipe to pour concrete into the cavity. Remedial Measures (1/13)
  • 25. • Backfilling and grouting in progress Remedial Measures (2/13)
  • 26. Pipe roofing is being done after concrete filling by 76 mm dia SDR. Remedial Measures (3/13)
  • 27. After Pipe roofing temporary rib has been installed at 606.8 m to support the pipe roofing. Remedial Measures (4/13)
  • 28. Second temporary rib installed at 607.3 m. Remedial Measures (5/13)
  • 29. Collapse occurred from right side at 607.5 (approx.) while removing the muck sealing to make space for third rib. Remedial Measures (6/13) VIDEO OF COLLAPSE FROM RIGHT SIDE
  • 30. After collapse from right side tunnel face packed with muck. Grouting and backfilling done by installing 105 mm holes. Remedial Measures (7/13)
  • 31. After grouting and backfilling muck removal done sequentially for heading part only and ISHB 150 ribs being installed (starting from left side of the tunnel) up to 612.0 m. Remedial Measures (8/13)
  • 32. After installation of ribs at left side right side part of the ribs being installed. Remedial Measures (9/13)
  • 33. Collapse occurred from the right side again while installation of permanent ribs in right side was going on. Remedial Measures (10/13)
  • 34. Tunnel sealed by muck after collapse and the installed ribs supported by extra ISHB. Remedial Measures (11/13)
  • 35. • SDA 32mm dia installed along the periphery of the installed ribs at 610.0 m and grouted. Remedial Measures (12/13)
  • 36. After grouting of SDA sequential muck removal was done at the right side of the tunnel and Side Arch part of the ribs installed one at a time up to 612.0 m. Remedial Measures (13/13)
  • 37. Surface above the cavity portion was traced with the help of hand GPS. A ditch was formed there which was approx. 7m X 7m in horizontal dimensions & 3-5 m deep. Effect of Cavity on Surface (1/2) Weathered and sheared rock mass exposed at one side of the ditch formed at the surface due to cavity
  • 38. Monitoring section at CH 598m & CH. 605.2m showing deformation within the safe limit. 3D MONITORING at CH. 598m & CH. 605.2 m CH 598 m CH 605.2 m
  • 39. • Due to unexpected shear zone the collapse occurred during excavation from CH 610.8 onwards. Such shears are a common feature in Himalayan geology and exact location & extent is difficult to map due to lack of outcrops & thick forest cover. • The overburden cover of this area was determined from L-Section as 34.0 m. • Tunnel T1 and T2 passes through Mahananda Wild Life Sanctuary in which there are certain restrictions on free movement for surveying/investigation etc. Hand inspection of collapse material and by surface visit, a Shear Zone is interpreted as shown in the schematic diagram and surface photos shown below. This shear zone is considered as main cause of the cavity formation. The orientation and extent of shear zone can be different from that shown in the diagram. Conclusion