Capital Gate
Case Study
Presented By:
Jeesmon Babu
S7 CE B
Roll no. -35
Guided By:
Mr. Lins Paul Kuriakose
Assistant Professor
Dept. Of Civil Engg
Capital Gate- Case Study
VISWAJYOTHI COLLEGE OF ENGINEERING
AND TECHNOLOGY, VAZHAKULAM
VISION
“Moulding Engineers par Excellence with Integrity, Fairness and Human Value”
MISSION
 We commit to develop the institution into a Center of Excellence of
International Standards.
 We guide and mould our students in the attainment of intellectual and
professional competence for successfully coping with the rapid and challenging
advancements in technologies and the ever changing world of business,
industry and services.
Capital Gate- Case Study
 We help and support our students in their personal growth shaping them
into mature and responsible individuals.
 We strive to cultivate a sense of social and civic responsibility in our
students, empowering them to serve the humanity.
 We promise to ensure a free environment where quest for the truth is
encouraged.
Capital Gate- Case Study
CIVIL ENGINEERING
DEPARTMENT
VISION
“Building Professionally Competent and Motivated Engineers in the Arena of
Civil Engineering with High Professional Ethics.”
MISSION
 To promote a better teaching learning process through academically
proficient faculties, full fledged laboratories and excellent infrastructure
facilities.
 To equip the graduates with knowledge, research and practical skills in
modern construction practices and techniques.
 To inculcate knowledge of sustainability in various domains of Civil
Engineering.
 To nurture Civil Engineers into ethically strong and responsible leaders to
address global challenges through quality education.
Capital Gate- Case Study
PROGRAM EDUCATIONAL OBJECTIVES
Our Graduates
 Shall tackle the multiple responsibilities of analysis, design and
construction of traditional and modern systems in compliance with various
codes of practices and to meet the current technical challenges.
 Shall be proficient in the use of relevant software packages for planning,
designing, scheduling, executing and controlling of civil engineering
projects, with an urge for life-long learning.
 Shall function effectively with individual capabilities as well as with a
collective strength as a professional team with good communication skills.
Capital Gate- Case Study
PROGRAMME SPECIFIC
OUTCOMES
CIVIL ENGINEERING DEPARTMENT
 Ability to utilize civil engineering principles and software that are appropriate
to solve technical problems, prepare design and construction documents ,create
structural systems; produce drawings, reports and quantity estimates related to
the Civil Engineering domain.
 Ability to utilize modern surveying methods for land measurement and/or
construction layout and to conduct standardized field /laboratory tests related to
Civil Engineering.
Capital Gate- Case Study
Overview
 Introduction
 Design and Aesthetics
 Achievements and awards
 Foundation
 Core
 Diagrids
 Façade
 Splash
 Atrium
 Amenities
 Project Data
 Project Timeline
 conclusion
6
Capital Gate- Case Study
7
Capital Gate- Case Study
Introduction
 Located in Abu Dhabi Capital Centre
 Record lean of 18 degree west
 Centerpiece of ADNEC Complements
the national grandstand
 35 storeys
 160 m tall
 Built up area of 53100 square meter
8
Capital Gate- Case Study
Design and Aesthetics
 Something unique never achieved before
 Inspired from sand dunes of the desert and
waves of the sea
 Dynamic and Fluidic design
 Every element is unique
 No two sections or floor plan are same
9
Courtesy: google
Courtesy: google
Capital Gate- Case Study
10
Courtesy : Pinterest
Capital Gate- Case Study
11
Office Hotel
Capital Gate- Case Study
12
19 roof
Capital Gate- Case Study
Achievements and awards
 Best Commercial High-rise Development at International Property Awards
2015
 "Farthest manmade leaning building“ by Guinness World Records 2010
 Commercial/Mixed-Use Built and Overall Project of the Year Award 2011-
Cityscape Global Awards
 First building to use Pre Cambered Core
 First building to use vertical tensioning in core
13
Capital Gate- Case Study
Foundation
 RRC Raft foundation on top
 6000 cubic meter sand was
removed
 490 piles
 Depth of 20 m –Compression side
600mm dia
 Depth 30 m – Tension side
1000mm dia
14
Capital Gate- Case Study
Core
 Used to transfer building
load to ground
 Pre cambered
 Post tensioned
 Jump forming
 Houses stairways , lifts
and other amenities
15
Capital Gate- Case Study
Pre cambered
 Core is built with a tilt as floors are
stacked its pulled to become straight
 Rebars were set during day and
concrete was placed at night
 Reinforced with 10,000 tons of steel
 Concrete of 250mm slump
 15,000 cubic meters of concrete
16
Capital Gate- Case Study
Post Tensioned
 Usually used in bridge decks
 Vertical ducts are used
 146 steel tendons 20m long spliced
at 5 m
 120 tons of tendons
17
Capital Gate- Case Study
Jump forming
 The formwork is prepared for
the core and that section is
concreted
 The whole form work is lifted
using hydraulic jacks and
above processes is repeated
18
Capital Gate- Case Study
Diagrids
 Each one custom fabricated in
Sharjah
 external shell to transfer loads to
the ground and core
 Egg shell
 More space
19
Capital Gate- Case Study
External Diagrid
 Transfers external load to
ground
 Hollow Square sections
600mmx600mm
 Built of welded steel plates
80mm to 40mm
 RCC ring beam at ground takes
load
20
Courtesy: capitalgate.ae
Capital Gate- Case Study
Internal Diagrid
 In place to transfer load of the atrium
 Transfers loads to the core
 8 m high steel plates connected to core
 Hollow round steel 400mm diameter
 Mirrors the external diagrid
21
Courtesy: Jeff Schofield
Capital Gate- Case Study
Outriggers
 Experiences moderate winds
 Resisted by curved shape
 Used to counter act lateral forces
 Horizontal trusses in the mechanical floor
 Transfers lateral forces from external
structure to the core
22
Capital Gate- Case Study
Façade
 Diamond shaped panels each
custom made
 8mx8m
 12500 Triangular glass panes
 20mm shifts experienced
 Waterproof
23
Capital Gate- Case Study
 The glazing system, called
Cardinal C240, is made of two
silver coatings which are
transparent, increasing its light
transmission.
 Double skin façade
24
Courtesy: capitalgate.ae
Capital Gate- Case Study
Splash
 Built to protect the office sections from direct sunlight
 Serves an aesthetic purpose
25
Courtesy: Jeff Schofield
Courtesy: Jeff Schofield
Capital Gate- Case Study
Atrium
 Funnel shaped opening in hotel section
 To reduce weight on the top floors
 Allows sunlight through a skylight in the roof
26
Courtesy: Jeff Schofield
Capital Gate- Case Study
Amenities
 Infinity pools
 Restaurants
 Helipad
27
Courtesy: capitalgate.ae
Courtesy: capitalgate.ae
Capital Gate- Case Study
 30 meeting rooms
 Conference facilities for 1,200
people
 District cooling system
 Business center on the ground
floor
28
Courtesy: capitalgate.ae
Courtesy: google
Courtesy: google
Capital Gate- Case Study
Project Data
 Cost of the project was $233 million
 600 people labor force from different countries
 400 sub contractors
 Height to Architectural Top: 165 meters
 Total built up Area: 53,100 square meters
 Project Developer: ADNEC Group
 Architect , Structural Engineer, MEP Engineer: RMJM
 Façade Consultant: Hyder Consulting
 Landscape Consultant: Al Khatib Cracknell
 Main Contractor: Al Habtoor Engineering
 Steel Contractor: Eversendai Façade Contractor: Waagner Biro
 Project Manager: Mace
29
Capital Gate- Case Study
Project Timeline
 September 2007 – work commence
 November 2007 – Pile driving starts
 April 2008 – Core wall construction starts
 February 2009 – Façade commences
 May 2009 – Reaches 100 m in height
 June 2009 – Incline starts to take shape
 October 2009 – Attains final height of 160 m
 December 2009 – Completion of exterior core structure
 January 2010 – First phase of splash completed
 February 2010 – Interior fit-out commences
 March 2010 – Commencement of link bridge to Abu Dhabi
National Exhibition Centre
 April 2010 – Commencement of atrium roof
 2011 – Completed construction
 Opening date 21 Dec 2011
30
Capital Gate- Case Study
Conclusion
An engineering marvel that sets an example for upcoming engineers that
nothing is too big to be achieved. It also shows the advanced technologies
used to erect this gravity defying structure.
Use of unconventional methods to get the work done in most efficient and
economic ways set new benchmarks for civil engineering
31
Capital Gate- Case Study
References
 https://www.designbuild-network.com/projects/capital-gate/
 http://www.capitalgate.ae/building.html
 All video courtesy National Geographic Channel –”The Leaning Tower of
Abu Dhabi”
32
Capital Gate- Case Study
33
THANK YOU
ANY QUESTIONS ARE
WELCOMED

More Related Content

What's hot

High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic BuildingsDania Abdel-aziz
 
Mix use building case Study
Mix use building case Study Mix use building case Study
Mix use building case Study Nitesh Parmar
 
Mixed use building case study
Mixed use building case studyMixed use building case study
Mixed use building case studySimi Sayed
 
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...Anurag Mathur
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Prateek Srivastava
 
Hearst Tower
Hearst TowerHearst Tower
Hearst Towermisschand
 
presentation1Capital Gate Tower.pdf
presentation1Capital Gate Tower.pdfpresentation1Capital Gate Tower.pdf
presentation1Capital Gate Tower.pdfMuhammedJawad6
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studiesSoumitra Smart
 
Heydar Aliyev Centre
Heydar Aliyev CentreHeydar Aliyev Centre
Heydar Aliyev CentreNADEEM AKHTAR
 
World one (Lodha Tower)
World one (Lodha Tower)World one (Lodha Tower)
World one (Lodha Tower)Nikunj Rathod
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREShivangi Saini
 

What's hot (20)

Shanghai tower
Shanghai towerShanghai tower
Shanghai tower
 
High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic Buildings
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Mix use building case Study
Mix use building case Study Mix use building case Study
Mix use building case Study
 
Mixed use building case study
Mixed use building case studyMixed use building case study
Mixed use building case study
 
high rise case study
high rise case studyhigh rise case study
high rise case study
 
The Shard
The ShardThe Shard
The Shard
 
Shard tower
Shard towerShard tower
Shard tower
 
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
Mumbai High Rise Buildings Case studies of Kohinoor Square, Aquaria Grande, K...
 
Hearst Tower
Hearst TowerHearst Tower
Hearst Tower
 
presentation1Capital Gate Tower.pdf
presentation1Capital Gate Tower.pdfpresentation1Capital Gate Tower.pdf
presentation1Capital Gate Tower.pdf
 
Burj Khalifa
Burj KhalifaBurj Khalifa
Burj Khalifa
 
Al Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, KuwaitAl Hamra Firdous Tower, Kuwait
Al Hamra Firdous Tower, Kuwait
 
Tall buildings case studies
Tall buildings   case studiesTall buildings   case studies
Tall buildings case studies
 
Heydar Aliyev Centre
Heydar Aliyev CentreHeydar Aliyev Centre
Heydar Aliyev Centre
 
World one (Lodha Tower)
World one (Lodha Tower)World one (Lodha Tower)
World one (Lodha Tower)
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
 
High rise
High rise High rise
High rise
 

Similar to Capital Gate Case Study

MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for constPradeepPandya1
 
Electrical maintanance
Electrical maintananceElectrical maintanance
Electrical maintananceMadhan Gopal
 
Theodosios Skortsis - Portfolio v5.1
Theodosios Skortsis - Portfolio v5.1Theodosios Skortsis - Portfolio v5.1
Theodosios Skortsis - Portfolio v5.1Theodosios Skortsis
 
designage - Profile-1
designage - Profile-1designage - Profile-1
designage - Profile-1Tushar Patil
 
Company Profile Wah Tung
Company Profile   Wah TungCompany Profile   Wah Tung
Company Profile Wah Tungvipproject
 
MHA Brochure 2013
MHA Brochure 2013MHA Brochure 2013
MHA Brochure 2013Katie Frost
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typChristian Akl
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typChristian Akl
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian Akl
 
Master Presentation Ali Bassiouny Darwish
Master Presentation Ali Bassiouny Darwish Master Presentation Ali Bassiouny Darwish
Master Presentation Ali Bassiouny Darwish Ali Bassiouny DARWISH
 
Mega prefab company profile
Mega prefab company profileMega prefab company profile
Mega prefab company profilebassamnakfour
 
Facade Consultancy Enveloptechnik
Facade Consultancy EnveloptechnikFacade Consultancy Enveloptechnik
Facade Consultancy EnveloptechnikManjunath Shetty
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docxbrian157854
 
Wetherill Park Planned Major Capital Works
Wetherill Park Planned Major Capital WorksWetherill Park Planned Major Capital Works
Wetherill Park Planned Major Capital WorksMarkus Etting
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016Steve Edgson
 

Similar to Capital Gate Case Study (20)

Mohan 3
Mohan 3Mohan 3
Mohan 3
 
MIVAN CONSTRUCTION TECHNOLOGY for const
MIVAN CONSTRUCTION TECHNOLOGY  for constMIVAN CONSTRUCTION TECHNOLOGY  for const
MIVAN CONSTRUCTION TECHNOLOGY for const
 
Ahmed Abdel Salam 03.2016
Ahmed Abdel Salam 03.2016Ahmed Abdel Salam 03.2016
Ahmed Abdel Salam 03.2016
 
CV.2016
CV.2016CV.2016
CV.2016
 
amir cv
amir cvamir cv
amir cv
 
Electrical maintanance
Electrical maintananceElectrical maintanance
Electrical maintanance
 
Theodosios Skortsis - Portfolio v5.1
Theodosios Skortsis - Portfolio v5.1Theodosios Skortsis - Portfolio v5.1
Theodosios Skortsis - Portfolio v5.1
 
designage - Profile-1
designage - Profile-1designage - Profile-1
designage - Profile-1
 
Company Profile Wah Tung
Company Profile   Wah TungCompany Profile   Wah Tung
Company Profile Wah Tung
 
MHA Brochure 2013
MHA Brochure 2013MHA Brochure 2013
MHA Brochure 2013
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOC
 
Master Presentation Ali Bassiouny Darwish
Master Presentation Ali Bassiouny Darwish Master Presentation Ali Bassiouny Darwish
Master Presentation Ali Bassiouny Darwish
 
IFC
IFCIFC
IFC
 
Mega prefab company profile
Mega prefab company profileMega prefab company profile
Mega prefab company profile
 
Facade Consultancy Enveloptechnik
Facade Consultancy EnveloptechnikFacade Consultancy Enveloptechnik
Facade Consultancy Enveloptechnik
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docx
 
Wetherill Park Planned Major Capital Works
Wetherill Park Planned Major Capital WorksWetherill Park Planned Major Capital Works
Wetherill Park Planned Major Capital Works
 
ICE Case Study 2016
ICE Case Study 2016ICE Case Study 2016
ICE Case Study 2016
 

Recently uploaded

Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationAadityaSharma884161
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 

Recently uploaded (20)

Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint Presentation
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 

Capital Gate Case Study

  • 1. Capital Gate Case Study Presented By: Jeesmon Babu S7 CE B Roll no. -35 Guided By: Mr. Lins Paul Kuriakose Assistant Professor Dept. Of Civil Engg
  • 2. Capital Gate- Case Study VISWAJYOTHI COLLEGE OF ENGINEERING AND TECHNOLOGY, VAZHAKULAM VISION “Moulding Engineers par Excellence with Integrity, Fairness and Human Value” MISSION  We commit to develop the institution into a Center of Excellence of International Standards.  We guide and mould our students in the attainment of intellectual and professional competence for successfully coping with the rapid and challenging advancements in technologies and the ever changing world of business, industry and services.
  • 3. Capital Gate- Case Study  We help and support our students in their personal growth shaping them into mature and responsible individuals.  We strive to cultivate a sense of social and civic responsibility in our students, empowering them to serve the humanity.  We promise to ensure a free environment where quest for the truth is encouraged.
  • 4. Capital Gate- Case Study CIVIL ENGINEERING DEPARTMENT VISION “Building Professionally Competent and Motivated Engineers in the Arena of Civil Engineering with High Professional Ethics.” MISSION  To promote a better teaching learning process through academically proficient faculties, full fledged laboratories and excellent infrastructure facilities.  To equip the graduates with knowledge, research and practical skills in modern construction practices and techniques.  To inculcate knowledge of sustainability in various domains of Civil Engineering.  To nurture Civil Engineers into ethically strong and responsible leaders to address global challenges through quality education.
  • 5. Capital Gate- Case Study PROGRAM EDUCATIONAL OBJECTIVES Our Graduates  Shall tackle the multiple responsibilities of analysis, design and construction of traditional and modern systems in compliance with various codes of practices and to meet the current technical challenges.  Shall be proficient in the use of relevant software packages for planning, designing, scheduling, executing and controlling of civil engineering projects, with an urge for life-long learning.  Shall function effectively with individual capabilities as well as with a collective strength as a professional team with good communication skills.
  • 6. Capital Gate- Case Study PROGRAMME SPECIFIC OUTCOMES CIVIL ENGINEERING DEPARTMENT  Ability to utilize civil engineering principles and software that are appropriate to solve technical problems, prepare design and construction documents ,create structural systems; produce drawings, reports and quantity estimates related to the Civil Engineering domain.  Ability to utilize modern surveying methods for land measurement and/or construction layout and to conduct standardized field /laboratory tests related to Civil Engineering.
  • 7. Capital Gate- Case Study Overview  Introduction  Design and Aesthetics  Achievements and awards  Foundation  Core  Diagrids  Façade  Splash  Atrium  Amenities  Project Data  Project Timeline  conclusion 6
  • 9. Capital Gate- Case Study Introduction  Located in Abu Dhabi Capital Centre  Record lean of 18 degree west  Centerpiece of ADNEC Complements the national grandstand  35 storeys  160 m tall  Built up area of 53100 square meter 8
  • 10. Capital Gate- Case Study Design and Aesthetics  Something unique never achieved before  Inspired from sand dunes of the desert and waves of the sea  Dynamic and Fluidic design  Every element is unique  No two sections or floor plan are same 9 Courtesy: google Courtesy: google
  • 11. Capital Gate- Case Study 10 Courtesy : Pinterest
  • 12. Capital Gate- Case Study 11 Office Hotel
  • 13. Capital Gate- Case Study 12 19 roof
  • 14. Capital Gate- Case Study Achievements and awards  Best Commercial High-rise Development at International Property Awards 2015  "Farthest manmade leaning building“ by Guinness World Records 2010  Commercial/Mixed-Use Built and Overall Project of the Year Award 2011- Cityscape Global Awards  First building to use Pre Cambered Core  First building to use vertical tensioning in core 13
  • 15. Capital Gate- Case Study Foundation  RRC Raft foundation on top  6000 cubic meter sand was removed  490 piles  Depth of 20 m –Compression side 600mm dia  Depth 30 m – Tension side 1000mm dia 14
  • 16. Capital Gate- Case Study Core  Used to transfer building load to ground  Pre cambered  Post tensioned  Jump forming  Houses stairways , lifts and other amenities 15
  • 17. Capital Gate- Case Study Pre cambered  Core is built with a tilt as floors are stacked its pulled to become straight  Rebars were set during day and concrete was placed at night  Reinforced with 10,000 tons of steel  Concrete of 250mm slump  15,000 cubic meters of concrete 16
  • 18. Capital Gate- Case Study Post Tensioned  Usually used in bridge decks  Vertical ducts are used  146 steel tendons 20m long spliced at 5 m  120 tons of tendons 17
  • 19. Capital Gate- Case Study Jump forming  The formwork is prepared for the core and that section is concreted  The whole form work is lifted using hydraulic jacks and above processes is repeated 18
  • 20. Capital Gate- Case Study Diagrids  Each one custom fabricated in Sharjah  external shell to transfer loads to the ground and core  Egg shell  More space 19
  • 21. Capital Gate- Case Study External Diagrid  Transfers external load to ground  Hollow Square sections 600mmx600mm  Built of welded steel plates 80mm to 40mm  RCC ring beam at ground takes load 20 Courtesy: capitalgate.ae
  • 22. Capital Gate- Case Study Internal Diagrid  In place to transfer load of the atrium  Transfers loads to the core  8 m high steel plates connected to core  Hollow round steel 400mm diameter  Mirrors the external diagrid 21 Courtesy: Jeff Schofield
  • 23. Capital Gate- Case Study Outriggers  Experiences moderate winds  Resisted by curved shape  Used to counter act lateral forces  Horizontal trusses in the mechanical floor  Transfers lateral forces from external structure to the core 22
  • 24. Capital Gate- Case Study Façade  Diamond shaped panels each custom made  8mx8m  12500 Triangular glass panes  20mm shifts experienced  Waterproof 23
  • 25. Capital Gate- Case Study  The glazing system, called Cardinal C240, is made of two silver coatings which are transparent, increasing its light transmission.  Double skin façade 24 Courtesy: capitalgate.ae
  • 26. Capital Gate- Case Study Splash  Built to protect the office sections from direct sunlight  Serves an aesthetic purpose 25 Courtesy: Jeff Schofield Courtesy: Jeff Schofield
  • 27. Capital Gate- Case Study Atrium  Funnel shaped opening in hotel section  To reduce weight on the top floors  Allows sunlight through a skylight in the roof 26 Courtesy: Jeff Schofield
  • 28. Capital Gate- Case Study Amenities  Infinity pools  Restaurants  Helipad 27 Courtesy: capitalgate.ae Courtesy: capitalgate.ae
  • 29. Capital Gate- Case Study  30 meeting rooms  Conference facilities for 1,200 people  District cooling system  Business center on the ground floor 28 Courtesy: capitalgate.ae Courtesy: google Courtesy: google
  • 30. Capital Gate- Case Study Project Data  Cost of the project was $233 million  600 people labor force from different countries  400 sub contractors  Height to Architectural Top: 165 meters  Total built up Area: 53,100 square meters  Project Developer: ADNEC Group  Architect , Structural Engineer, MEP Engineer: RMJM  Façade Consultant: Hyder Consulting  Landscape Consultant: Al Khatib Cracknell  Main Contractor: Al Habtoor Engineering  Steel Contractor: Eversendai Façade Contractor: Waagner Biro  Project Manager: Mace 29
  • 31. Capital Gate- Case Study Project Timeline  September 2007 – work commence  November 2007 – Pile driving starts  April 2008 – Core wall construction starts  February 2009 – Façade commences  May 2009 – Reaches 100 m in height  June 2009 – Incline starts to take shape  October 2009 – Attains final height of 160 m  December 2009 – Completion of exterior core structure  January 2010 – First phase of splash completed  February 2010 – Interior fit-out commences  March 2010 – Commencement of link bridge to Abu Dhabi National Exhibition Centre  April 2010 – Commencement of atrium roof  2011 – Completed construction  Opening date 21 Dec 2011 30
  • 32. Capital Gate- Case Study Conclusion An engineering marvel that sets an example for upcoming engineers that nothing is too big to be achieved. It also shows the advanced technologies used to erect this gravity defying structure. Use of unconventional methods to get the work done in most efficient and economic ways set new benchmarks for civil engineering 31
  • 33. Capital Gate- Case Study References  https://www.designbuild-network.com/projects/capital-gate/  http://www.capitalgate.ae/building.html  All video courtesy National Geographic Channel –”The Leaning Tower of Abu Dhabi” 32
  • 34. Capital Gate- Case Study 33 THANK YOU ANY QUESTIONS ARE WELCOMED