9. 9
Fairbank Station Update
ACTIVITY LOCATION START DATE APPROX DURATION
SPRING 2018
Support of Excavation – Piling South side of Eglinton Ave W Began Feb 8, 2018 Through Late May 2018
Wet Utilities Relocation Dufferin St and Eglinton Ave W Ongoing Through Spring 2018
Geotechnical Equipment
Installation
Southwest corner on sidewalk Ongoing Until early June 2018
Overnight Water Shut-off
Eglinton Ave between Dufferin
St and Northcliffe Blvd
Tuesday May 22, 2018 9:00 p.m. – 5:00 a.m.
Support of Excavation –
Shallow Excavation & Tie-backs
Main Entrance Late March 2018 Through Summer 2018
Support of Excavation –
Shallow Excavation
Southeast Station Box Mid-May 2018 Through Summer 2018
Support of Excavation –
Shallow Excavation
Southwest Station Box Late May Through Fall 2018
14. 14
Construction Activities Area & Impacts Timing Duration
Mining
- Underground excavation
underway for next few
weeks
- Work to increase depth of
main shaft mid-late May
• Main Entrance
• North side work zone
Underway - 24
hours
End of 2019
Monitoring instruments, incl.
leak detection (installations,
surveying and monitoring)
• Crews move from location
to location around the
station area between
Times Road and east of
Oakwood.
Ongoing Ongoing
Excavation at Secondary
Entrance
• Increase in truck traffic
removing soil from site
• No additional traffic
impacts anticipated at this
time.
Early June TBC
Oakwood Station: What to Expect