Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 1 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 2 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 3 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 4 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 5 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 6 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 7 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 8 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 9 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 10 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 11 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 12 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 13 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 14 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 15 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 16 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 17 Brentcliffe-Victoria Park CLC Meeting - May 6, 2021 Slide 18
Upcoming SlideShare
What to Upload to SlideShare
Next
Download to read offline and view in fullscreen.

0 Likes

Share

Download to read offline

Brentcliffe-Victoria Park CLC Meeting - May 6, 2021

Download to read offline

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

  • Be the first to like this

Brentcliffe-Victoria Park CLC Meeting - May 6, 2021

  1. 1. May 6, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  2. 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  3. 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration LRV Delivery and Vehicle Testing Brentcliffe – Kennedy Late May Brentcliffe Retaining Wall Construction North side of Eglinton Ave, east of Brentcliffe Rd Underway through June 2021 • Shelter finishing activities • Platform ramps • Platform walls • Handrails Sunnybrook Park Stop Ongoing through May Multi-use path construction: backfill and compaction Serena Gundy Park – West of Leslie St. Ongoing through Spring 2021 Pedestrian staircase installation Parking lot re-opened Backfill on Leslie Trail Eglinton and Leslie St. – South side Completed April Completed April Ongoing through Spring 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  4. 4. EAST TESTING & COMMISSIONING 4 • In late May, light rail vehicles (LRVs) will be delivered to the east end of the alignment to conduct testing and commissioning activities between Brentcliffe Road and Kennedy Road. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue. • The LRVs will follow traffic signals as they cross through intersections. • Prior to testing, the overhead catenary system (OCS) will be energized in order to power the vehicles.
  5. 5. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 5 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Slope stabilization work is now complete and retaining wall construction has resumed • Slope restoration design is in review by CTS and the City of Toronto
  6. 6. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 6 • Construction activities for path construction include: Excavation, backfill and installation of topsoil • Landscaping will take place this year as part of the final restoration plan Mid-July 2020 through Spring 2021
  7. 7. CONSTRUCTION PROGRESS PHOTOS 7 SIDEWALK RESTORATION LESLIE INTERSECTION PEDESTRIAN STAIRCASE LESLIE AND EGLINTON
  8. 8. Science Centre Station
  9. 9. SCIENCE CENTRE STATION UPDATE 9 Activity Location Approx. Date & Duration LRV Delivery and Vehicle Testing Brentcliffe – Kennedy Late May Urban tapestry framework Urban tapestry installation Station box Completed April Ongoing through May Louver Installation Main entrance Completed April Escalator Glazing Station box Ongoing through May Stair Railing Installation Bus Terminal Ongoing through May Ceiling grid & tile installation Station box/Pedestrian tunnel Bus terminal Main entrance Ongoing through Spring 2021 Wall & floor tiling Mechanical and electrical installation Station box Ongoing through Spring 2021 Drywall installation Wall & floor tiling Sliding door installation Bus terminal Ongoing through Spring 2021 Electrical finishes Floor tiling Sliding door installation Main entrance Ongoing through Spring 2021
  10. 10. EAST TESTING & COMMISSIONING 10 • In late May, light rail vehicles (LRVs) will be delivered to the east end of the alignment to conduct testing and commissioning activities between Brentcliffe Road and Kennedy Road. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue. • The LRVs will follow traffic signals as they cross through intersections. • Prior to testing, the overhead catenary system (OCS) will be energized in order to power the vehicles.
  11. 11. SCIENCE CENTRE TRAFFIC CONFIGURATION 11 December 6, 2020 for approx. eight months
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 URBAN TAPESTRY INSTALLATION MAIN ENTRANCE ELECTRICAL WORKS MAIN ENTRANCE
  13. 13. CONSTRUCTION PROGRESS PHOTOS 13 LOUVER WORKS MAIN ENTRANCE CEILING FINISHES BUS TERMINAL
  14. 14. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  15. 15. SECTION TWO AT-GRADE UPDATE 15 Activity Location Approx. Date & Duration LRV Delivery and Vehicle Testing Brentcliffe – Kennedy Late May Road widening Swift Drive to Bermondsey Road Completed in March Barrier curbs East Don River Bridge Completed in March Waterproofing Wynford Bridge East Don River Bridge Completed April Ongoing through May • Shelter finishing activities • Guardrail installation Aga Khan Park & Museum Stop Ongoing through May Retaining walls Swift Drive & Eglinton Ave E Ongoing through May (North wall) • Platform curbs • Handrails • North sidewalk Sloane Stop Ongoing through May • Shelter finishing activities • Platform curbs • Platform ramps O’Connor Stop Ongoing through May
  16. 16. EAST TESTING & COMMISSIONING 16 • In late May, light rail vehicles (LRVs) will be delivered to the east end of the alignment to conduct testing and commissioning activities between Brentcliffe Road and Kennedy Road. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue. • The LRVs will follow traffic signals as they cross through intersections. • Prior to testing, the overhead catenary system (OCS) will be energized in order to power the vehicles.
  17. 17. CONSTRUCTION PROGRESS PHOTOS 17 HANDRAILS INSTALLATION SLOANE STOP WATERPROOFING WYNFORD BRIDGE

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.