4. Cedarvale Station Updates
Recently Complete
• Piles and shallow excavation at the Everden site
• Water main relocation on Eglinton Avenue West at Allen Road North
Ongoing
• Traffic deck, tie-back, and 600mm water main installation at Everden
Upcoming
• Stage 2 shoring on the north side of Eglinton Ave
– South Allen Road realignment
– Planning a weekend closure of SB Allen Road (11pm Friday – 5am Monday)
– July 13-16
8. 8
Forest Hill Station Update
ACTIVITY LOCATION APPROXIMATE DURATION
Summer 2018
Road Reinstatement Works
Eglinton Ave W, west of
Bathurst St
Ongoing through July 2018
Shallow Excavation
Eglinton Ave W, east of
Bathurst St
Ongoing through fall 2018
Wet Utilities Relocation
Bathurst St and Eglinton Ave
W
Ongoing through 2018
Watermain Cut-and-cap
Northside of Eglinton Ave W
between Hilltop Rd and
Bathurst St.
Wednesday July 11, 2018
(overnight)