SlideShare a Scribd company logo
Where did it go ‘wrong’?
Jeremy Harrison
Date 04.07.13 2
The journey – directions
• The story
• Accounting for humans
• You know more than you think you do!
• Long term planning
• What can we do differently?
Date 04.07.13 3
The birth and growth of an airport
Date 04.07.13 4
The story…
• …opened 25 November 1999 by the Queen…..
18 months late!
… there by hangs a tale…
Date 04.07.13 5
The station
Date 04.07.13 6
Summary
• Lack of clarity of project objectives, critical success
factors and definition
• Allowed ‘key stakeholders’ to dictate terms; failed to
understand their vested interests
• Lack of appreciation of the complexity of aspects of the
deal – eg. land purchase
• Conventional risk management was applied, however it
did not highlight the significant risks or stop the
problems
• Fixed end date – ie fixed Queen opening date, before
completed all necessary deals
• Be realistic not optimistic!
Date 04.07.13 7
Project Costs..
• Original budget and business case - £12M
– Inherited from the airport operator
– Railways persuaded to take on and advised it was a well developed
scheme
– Land and access deals optimistically explained to be further on than
actually the case
• Outcome
– final cost £29M
– Gold plated car park
Date 04.07.13 8
So what happened?
• Risks not identified?
• Problem not understood or project scope not clear?
• Identify risks but don’t understand them and fail to react
appropriately?
• Distracted by too many risks – inability to prioritise?
Answer – one, some or all of the above
Date 04.07.13 9
Not the only one!
Date 04.07.13 11
Optimism Bias
67% on average
Underestimation of the cost
of Enhancement projects
Or 40% of the Final Cost was ‘unexpected’
at the beginning
Date 04.07.13 12
Optimism Bias – what is it?
• Defined as
–the measure of the extent to which actual project costs
(capital and operating) and duration (time from business case
to benefit delivery and time from contract award to benefit
delivery) exceed those estimated ( for a defined functional
output). It is also a measure of the degree by which the
benefits delivery by the project fall short of the benefits
estimated.
• In short - a way of adding an ‘amount’ for all those things not
thought of or analysed early on in the project life.
Date 04.07.13 13
OB - What is happening?
Cost as
finally
determinedCost
Time – GRIP stages
4/51/2
Optimism Bias
7/8
Predicted AFC
(during life cycle)
Initial Cost
Estimate
Authority Value
Date 04.07.13 14
DfT present values
GRIP Stage 1 3 5
Uplift OB value 66% 40% 6%
Department for Transport
Transport Analysis Guidance (TAG)
Unit 3.5.9
The Estimation and Treatment of Scheme Costs
Date 04.07.13 15
Conclusion
• Despite improving project management processes – the average
underestimation of project costs continues to be between 50-
60%.
• This is an empirically derived ‘average’ value therefore direct
application to a single project will be ‘wrong’
• The appropriate application is to portfolios when looking at
overall funding
• This is an ‘allowance’ for unidentified risks in the early stage
of project development – therefore improving earlier project risk
work reduces the uplift required
• Optimism Bias uplift covers all risks relating to a desired
functional output where as estimating uncertainty is around
the identified construction deliverable
Date 04.07.13 16
A principles approach
1 2 3 4 5 6 7 8
Output Definition Pre-Feasibility Option Selection
Single Option
Development Detailed Design
Construction,
Test and
Commission
Scheme
Handback Project Close Out
Track
Risks Risks Risks Risks Risks Risks Risks Risks
Signalling &
Telecoms
Risks Risks Risks Risks Risks Risks Risks Risks
Civils
Risks Risks Risks Risks Risks Risks Risks Risks
Electrification &
Plant
Risks Risks Risks Risks Risks Risks Risks Risks
Enhancements
Risks Risks Risks Risks Risks Risks Risks Risks
Estates
Risks Risks Risks Risks Risks Risks Risks Risks
Major Projects
Risks Risks Risks Risks Risks Risks Risks Risks
Engineering
Risks Risks Risks Risks Risks Risks Risks Risks
GRIP Lifecycle Stage
Asset
Impact – Cost, Schedule, Outputs, Safety
1 Define objectives
2 Identify risks
3 Analyse risks
4 Evaluate risks
5 Risk treatment
6 Monitor,
review,
communicate and
manage
Risk Register
Impact
Uncertainty
Exposure
Contingency
Date 04.07.13 17
Stakeholders
Risk Management
Principles
Threats/Opportunities
RISK
Stakeholders
Objectives
© Jeremy Harrison
Date 04.07.13 18
The building blocks
Uncertainty
that matters –
the FUTURE
VISION : RISK
Creativity
Knowledge
sharing/
Lessons
Learned
Value
add
© Jeremy Harrison
Date 04.07.13 19
Risk Management Approach
GRIP
Stage
Risk Approach
0 and 1 60% uplift applied to the Point Estimate to cover Optimism
Bias, Estimating Uncertainty and Risk Exposure
2 3 point estimate is made of Estimating Uncertainty and
Risk Exposure
3 Quantitative risk register of threats and opportunities
assessed for probability and impact, covering both
Estimating Uncertainty and Risk Exposure
Min ML Max
Date 00.00.00 Presentation title to go here 2020
Portfolio Effect Savings
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
2
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
3
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
n
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
1
Individual Projects
CP5 Portfolio
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
England & Wales
Scotland
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£300,000 £350,000 £400,000 £450,000 £500,000 £550,000
Correlation
Programme
Risks
Portfolio Impacts Funding Route Totals
Date 04.07.13 21
What questions should we be asking?
• What question, if asked to day, would have the most impact on
the situation?
• What is most important to you here and now? And what makes it
so?
• What are the priorities? What are the criteria for deciding this?
• What are you not thinking of?
• What are you pretending not to know?
Art of Powerful Questions – open and penetrating to the issues
Date 04.07.13 22
Personal reflections
• Never too early to think ‘risk’ – uncertainties that matter!
• You know more than you think you do. What are you doing to tap
into that?
• You are as good as your weakest link – where is it?
• The time line is always longer than you think
• We are what we ‘need’ to be – optimistic or pessimistic

More Related Content

What's hot

4. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV0110154. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV011015
Association for Project Management
 
Portfolio management: creating initial building blocks: David Airey, Haringey...
Portfolio management: creating initial building blocks: David Airey, Haringey...Portfolio management: creating initial building blocks: David Airey, Haringey...
Portfolio management: creating initial building blocks: David Airey, Haringey...
Association for Project Management
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
Ibrahim Al-Hudhaif
 
1. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV0110151. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV011015
Association for Project Management
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
Association for Project Management
 
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
Association for Project Management
 
2. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV0110152. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV011015
Association for Project Management
 
Crossrail: lessons in governance
Crossrail: lessons in governanceCrossrail: lessons in governance
Crossrail: lessons in governance
Association for Project Management
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
Association for Project Management
 
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
Association for Project Management
 
3. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV0110153. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV011015
Association for Project Management
 
Preparing to fail by failing to prepare, 25th feb, london
Preparing to fail by failing to prepare, 25th feb, londonPreparing to fail by failing to prepare, 25th feb, london
Preparing to fail by failing to prepare, 25th feb, london
Association for Project Management
 
OGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC deliveryOGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC delivery
Association for Project Management
 
Benefits Summit 2015: one day conference
Benefits Summit 2015: one day conferenceBenefits Summit 2015: one day conference
Benefits Summit 2015: one day conference
Association for Project Management
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Project Controls Expo
 
Enterprise Project Management Solutions - Install and train, job done? by "Da...
Enterprise Project Management Solutions - Install and train, job done? by "Da...Enterprise Project Management Solutions - Install and train, job done? by "Da...
Enterprise Project Management Solutions - Install and train, job done? by "Da...
Project Controls Expo
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...
Association for Project Management
 
Change portfolio management office - Julia Hodkin
Change portfolio management office - Julia HodkinChange portfolio management office - Julia Hodkin
Change portfolio management office - Julia Hodkin
Association for Project Management
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...
Ibrahim Al-Hudhaif
 
Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...
Association for Project Management
 

What's hot (20)

4. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV0110154. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV011015
 
Portfolio management: creating initial building blocks: David Airey, Haringey...
Portfolio management: creating initial building blocks: David Airey, Haringey...Portfolio management: creating initial building blocks: David Airey, Haringey...
Portfolio management: creating initial building blocks: David Airey, Haringey...
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
1. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV0110151. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV011015
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
 
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
Use of Risk Maturity Model to Benchmark Project Health, 26 May 2016
 
2. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV0110152. Amerjit Walia - delivering good governance for p3m GOV011015
2. Amerjit Walia - delivering good governance for p3m GOV011015
 
Crossrail: lessons in governance
Crossrail: lessons in governanceCrossrail: lessons in governance
Crossrail: lessons in governance
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
 
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
Introducing the UK Government’s Project Delivery Standard webinar, 25 October...
 
3. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV0110153. Adrian Pyne - good agile governance (including case studies) GOV011015
3. Adrian Pyne - good agile governance (including case studies) GOV011015
 
Preparing to fail by failing to prepare, 25th feb, london
Preparing to fail by failing to prepare, 25th feb, londonPreparing to fail by failing to prepare, 25th feb, london
Preparing to fail by failing to prepare, 25th feb, london
 
OGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC deliveryOGC gateway process and it's use in Met Office HPC delivery
OGC gateway process and it's use in Met Office HPC delivery
 
Benefits Summit 2015: one day conference
Benefits Summit 2015: one day conferenceBenefits Summit 2015: one day conference
Benefits Summit 2015: one day conference
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Enterprise Project Management Solutions - Install and train, job done? by "Da...
Enterprise Project Management Solutions - Install and train, job done? by "Da...Enterprise Project Management Solutions - Install and train, job done? by "Da...
Enterprise Project Management Solutions - Install and train, job done? by "Da...
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...
 
Change portfolio management office - Julia Hodkin
Change portfolio management office - Julia HodkinChange portfolio management office - Julia Hodkin
Change portfolio management office - Julia Hodkin
 
Excellence through collaboration – the delivery of sustainability in mega pr...
Excellence through collaboration  – the delivery of sustainability in mega pr...Excellence through collaboration  – the delivery of sustainability in mega pr...
Excellence through collaboration – the delivery of sustainability in mega pr...
 
Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...Does your Board exhibit good governance of project and change management?, 22...
Does your Board exhibit good governance of project and change management?, 22...
 

Viewers also liked

An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017
Association for Project Management
 
Becoming an email exemplar Bob Hallewell
Becoming an email exemplar Bob HallewellBecoming an email exemplar Bob Hallewell
Becoming an email exemplar Bob Hallewell
Association for Project Management
 
Newcomers event
Newcomers eventNewcomers event
Cookham Wood Lean & Mean Jane Foulkes
Cookham Wood  Lean & Mean Jane FoulkesCookham Wood  Lean & Mean Jane Foulkes
Cookham Wood Lean & Mean Jane Foulkes
Association for Project Management
 
PMO and Assurance: Skills Funding Agency
PMO and Assurance: Skills Funding AgencyPMO and Assurance: Skills Funding Agency
PMO and Assurance: Skills Funding Agency
Association for Project Management
 
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
Association for Project Management
 
The meaning of communication: Jacqui Gatehouse
The meaning of communication: Jacqui GatehouseThe meaning of communication: Jacqui Gatehouse
The meaning of communication: Jacqui Gatehouse
Association for Project Management
 
Peeling back the covers on government programmes, Richard Bacon MP
Peeling back the covers on government programmes, Richard Bacon MPPeeling back the covers on government programmes, Richard Bacon MP
Peeling back the covers on government programmes, Richard Bacon MP
Association for Project Management
 
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
Association for Project Management
 
Designing projects for success by Tim Banfield
Designing projects for success by Tim BanfieldDesigning projects for success by Tim Banfield
Designing projects for success by Tim Banfield
Association for Project Management
 
How coaching can help you to become an inspirational leader, as well as a gre...
How coaching can help you to become an inspirational leader, as well as a gre...How coaching can help you to become an inspirational leader, as well as a gre...
How coaching can help you to become an inspirational leader, as well as a gre...
Association for Project Management
 
South East Branch Knowledge cafe
South East Branch Knowledge cafe South East Branch Knowledge cafe
South East Branch Knowledge cafe
Association for Project Management
 
Registered Project Professional: What You Need to Know, 6th June 2016
Registered Project Professional: What You Need to Know,  6th June 2016Registered Project Professional: What You Need to Know,  6th June 2016
Registered Project Professional: What You Need to Know, 6th June 2016
Association for Project Management
 
Equipping Programme Managers for Global Success - The evolution of programme ...
Equipping Programme Managers for Global Success - The evolution of programme ...Equipping Programme Managers for Global Success - The evolution of programme ...
Equipping Programme Managers for Global Success - The evolution of programme ...
Association for Project Management
 
Benefits Management: Practice makes perfect?
Benefits Management: Practice makes perfect?Benefits Management: Practice makes perfect?
Benefits Management: Practice makes perfect?
Association for Project Management
 
Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…
Association for Project Management
 
Ngaging your team for success
Ngaging your team for successNgaging your team for success
Ngaging your team for success
Association for Project Management
 
Selecting the right provider for your contract
Selecting the right provider for your contractSelecting the right provider for your contract
Selecting the right provider for your contract
Association for Project Management
 
How do you kill collaboration in organisations by Michael Norton, 9th June 2016
How do you kill collaboration in organisations by Michael Norton, 9th June 2016How do you kill collaboration in organisations by Michael Norton, 9th June 2016
How do you kill collaboration in organisations by Michael Norton, 9th June 2016
Association for Project Management
 
Communicating change - a practical and engaging approach
Communicating change - a practical and engaging approachCommunicating change - a practical and engaging approach
Communicating change - a practical and engaging approach
Association for Project Management
 

Viewers also liked (20)

An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017An introduction to Risk Management, 14 March 2017
An introduction to Risk Management, 14 March 2017
 
Becoming an email exemplar Bob Hallewell
Becoming an email exemplar Bob HallewellBecoming an email exemplar Bob Hallewell
Becoming an email exemplar Bob Hallewell
 
Newcomers event
Newcomers eventNewcomers event
Newcomers event
 
Cookham Wood Lean & Mean Jane Foulkes
Cookham Wood  Lean & Mean Jane FoulkesCookham Wood  Lean & Mean Jane Foulkes
Cookham Wood Lean & Mean Jane Foulkes
 
PMO and Assurance: Skills Funding Agency
PMO and Assurance: Skills Funding AgencyPMO and Assurance: Skills Funding Agency
PMO and Assurance: Skills Funding Agency
 
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
Leading in difficult and uncertain times: The Battle of Britain, Stephen Carv...
 
The meaning of communication: Jacqui Gatehouse
The meaning of communication: Jacqui GatehouseThe meaning of communication: Jacqui Gatehouse
The meaning of communication: Jacqui Gatehouse
 
Peeling back the covers on government programmes, Richard Bacon MP
Peeling back the covers on government programmes, Richard Bacon MPPeeling back the covers on government programmes, Richard Bacon MP
Peeling back the covers on government programmes, Richard Bacon MP
 
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
GRASP: Stakeholders, Prof. Agi Oldfield, 16th June 2016
 
Designing projects for success by Tim Banfield
Designing projects for success by Tim BanfieldDesigning projects for success by Tim Banfield
Designing projects for success by Tim Banfield
 
How coaching can help you to become an inspirational leader, as well as a gre...
How coaching can help you to become an inspirational leader, as well as a gre...How coaching can help you to become an inspirational leader, as well as a gre...
How coaching can help you to become an inspirational leader, as well as a gre...
 
South East Branch Knowledge cafe
South East Branch Knowledge cafe South East Branch Knowledge cafe
South East Branch Knowledge cafe
 
Registered Project Professional: What You Need to Know, 6th June 2016
Registered Project Professional: What You Need to Know,  6th June 2016Registered Project Professional: What You Need to Know,  6th June 2016
Registered Project Professional: What You Need to Know, 6th June 2016
 
Equipping Programme Managers for Global Success - The evolution of programme ...
Equipping Programme Managers for Global Success - The evolution of programme ...Equipping Programme Managers for Global Success - The evolution of programme ...
Equipping Programme Managers for Global Success - The evolution of programme ...
 
Benefits Management: Practice makes perfect?
Benefits Management: Practice makes perfect?Benefits Management: Practice makes perfect?
Benefits Management: Practice makes perfect?
 
Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…Project management driven by the top ten critical improvements qu…
Project management driven by the top ten critical improvements qu…
 
Ngaging your team for success
Ngaging your team for successNgaging your team for success
Ngaging your team for success
 
Selecting the right provider for your contract
Selecting the right provider for your contractSelecting the right provider for your contract
Selecting the right provider for your contract
 
How do you kill collaboration in organisations by Michael Norton, 9th June 2016
How do you kill collaboration in organisations by Michael Norton, 9th June 2016How do you kill collaboration in organisations by Michael Norton, 9th June 2016
How do you kill collaboration in organisations by Michael Norton, 9th June 2016
 
Communicating change - a practical and engaging approach
Communicating change - a practical and engaging approachCommunicating change - a practical and engaging approach
Communicating change - a practical and engaging approach
 

Similar to Where did it go wrong?

Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard
Association for Project Management
 
Better Business Cases - APMG
Better Business Cases - APMGBetter Business Cases - APMG
Better Business Cases - APMG
Association for Project Management
 
Project development handbook rl website
Project development handbook rl websiteProject development handbook rl website
Project development handbook rl website
drs. ing. George van Bommel MBE, BSc
 
Project Development Handbook presentation
Project Development Handbook presentationProject Development Handbook presentation
Project Development Handbook presentation
drs. ing. George van Bommel MBE, BSc
 
PROSES ESTIMASI.ppt
PROSES ESTIMASI.pptPROSES ESTIMASI.ppt
PROSES ESTIMASI.ppt
luqmannur3
 
FPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalFPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - Final
Gurin Hanspal
 
Attachment 3
Attachment 3Attachment 3
Opportunity framing
Opportunity framingOpportunity framing
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
PPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsxPPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsx
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
ANGUSMACLEOD21
 
LKG Project Level Presentation FEL in New Energies 2023.ppsx
LKG Project Level Presentation FEL in  New Energies 2023.ppsxLKG Project Level Presentation FEL in  New Energies 2023.ppsx
LKG Project Level Presentation FEL in New Energies 2023.ppsx
AngusMacleod18
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
Kapugantikapuganti Gupta
 
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Association for Project Management
 
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
Kristy Marshall
 
BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
Vijay Pandey
 
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
angusmacleod22
 
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
ANGUSMACLEOD21
 
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsxCAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
ANGUS MACLEOD
 
Atlas Presentation: Birmingham
Atlas Presentation: BirminghamAtlas Presentation: Birmingham
Atlas Presentation: Birmingham
PAS_Team
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
Kinshook Chaturvedi
 
Power plant project finance overview
Power plant project finance overviewPower plant project finance overview
Power plant project finance overview
John Coletti
 

Similar to Where did it go wrong? (20)

Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard
 
Better Business Cases - APMG
Better Business Cases - APMGBetter Business Cases - APMG
Better Business Cases - APMG
 
Project development handbook rl website
Project development handbook rl websiteProject development handbook rl website
Project development handbook rl website
 
Project Development Handbook presentation
Project Development Handbook presentationProject Development Handbook presentation
Project Development Handbook presentation
 
PROSES ESTIMASI.ppt
PROSES ESTIMASI.pptPROSES ESTIMASI.ppt
PROSES ESTIMASI.ppt
 
FPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalFPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - Final
 
Attachment 3
Attachment 3Attachment 3
Attachment 3
 
Opportunity framing
Opportunity framingOpportunity framing
Opportunity framing
 
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
PPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsxPPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsx
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
 
LKG Project Level Presentation FEL in New Energies 2023.ppsx
LKG Project Level Presentation FEL in  New Energies 2023.ppsxLKG Project Level Presentation FEL in  New Energies 2023.ppsx
LKG Project Level Presentation FEL in New Energies 2023.ppsx
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
 
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
 
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
8. Nicole Player, MGT - Creating a Mine with Datamine Scenario Planning and S...
 
BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
 
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
 
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
 
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsxCAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
 
Atlas Presentation: Birmingham
Atlas Presentation: BirminghamAtlas Presentation: Birmingham
Atlas Presentation: Birmingham
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Power plant project finance overview
Power plant project finance overviewPower plant project finance overview
Power plant project finance overview
 

More from Association for Project Management

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
Association for Project Management
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
Association for Project Management
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
Association for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
Association for Project Management
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
Association for Project Management
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
Association for Project Management
 

More from Association for Project Management (20)

Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 

Recently uploaded

amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
marketing317746
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
WilliamRodrigues148
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
JeremyPeirce1
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
thesiliconleaders
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
Aggregage
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
my Pandit
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
NZSG
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
fisherameliaisabella
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 

Recently uploaded (20)

amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05amptalk_RecruitingDeck_english_2024.06.05
amptalk_RecruitingDeck_english_2024.06.05
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Training my puppy and implementation in this story
Training my puppy and implementation in this storyTraining my puppy and implementation in this story
Training my puppy and implementation in this story
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Top mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptxTop mailing list providers in the USA.pptx
Top mailing list providers in the USA.pptx
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 
-- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month ---- June 2024 is National Volunteer Month --
-- June 2024 is National Volunteer Month --
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdfModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
ModelingMarketingStrategiesMKS.CollumbiaUniversitypdf
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 

Where did it go wrong?

  • 1. Where did it go ‘wrong’? Jeremy Harrison
  • 2. Date 04.07.13 2 The journey – directions • The story • Accounting for humans • You know more than you think you do! • Long term planning • What can we do differently?
  • 3. Date 04.07.13 3 The birth and growth of an airport
  • 4. Date 04.07.13 4 The story… • …opened 25 November 1999 by the Queen….. 18 months late! … there by hangs a tale…
  • 6. Date 04.07.13 6 Summary • Lack of clarity of project objectives, critical success factors and definition • Allowed ‘key stakeholders’ to dictate terms; failed to understand their vested interests • Lack of appreciation of the complexity of aspects of the deal – eg. land purchase • Conventional risk management was applied, however it did not highlight the significant risks or stop the problems • Fixed end date – ie fixed Queen opening date, before completed all necessary deals • Be realistic not optimistic!
  • 7. Date 04.07.13 7 Project Costs.. • Original budget and business case - £12M – Inherited from the airport operator – Railways persuaded to take on and advised it was a well developed scheme – Land and access deals optimistically explained to be further on than actually the case • Outcome – final cost £29M – Gold plated car park
  • 8. Date 04.07.13 8 So what happened? • Risks not identified? • Problem not understood or project scope not clear? • Identify risks but don’t understand them and fail to react appropriately? • Distracted by too many risks – inability to prioritise? Answer – one, some or all of the above
  • 9. Date 04.07.13 9 Not the only one!
  • 10. Date 04.07.13 11 Optimism Bias 67% on average Underestimation of the cost of Enhancement projects Or 40% of the Final Cost was ‘unexpected’ at the beginning
  • 11. Date 04.07.13 12 Optimism Bias – what is it? • Defined as –the measure of the extent to which actual project costs (capital and operating) and duration (time from business case to benefit delivery and time from contract award to benefit delivery) exceed those estimated ( for a defined functional output). It is also a measure of the degree by which the benefits delivery by the project fall short of the benefits estimated. • In short - a way of adding an ‘amount’ for all those things not thought of or analysed early on in the project life.
  • 12. Date 04.07.13 13 OB - What is happening? Cost as finally determinedCost Time – GRIP stages 4/51/2 Optimism Bias 7/8 Predicted AFC (during life cycle) Initial Cost Estimate Authority Value
  • 13. Date 04.07.13 14 DfT present values GRIP Stage 1 3 5 Uplift OB value 66% 40% 6% Department for Transport Transport Analysis Guidance (TAG) Unit 3.5.9 The Estimation and Treatment of Scheme Costs
  • 14. Date 04.07.13 15 Conclusion • Despite improving project management processes – the average underestimation of project costs continues to be between 50- 60%. • This is an empirically derived ‘average’ value therefore direct application to a single project will be ‘wrong’ • The appropriate application is to portfolios when looking at overall funding • This is an ‘allowance’ for unidentified risks in the early stage of project development – therefore improving earlier project risk work reduces the uplift required • Optimism Bias uplift covers all risks relating to a desired functional output where as estimating uncertainty is around the identified construction deliverable
  • 15. Date 04.07.13 16 A principles approach 1 2 3 4 5 6 7 8 Output Definition Pre-Feasibility Option Selection Single Option Development Detailed Design Construction, Test and Commission Scheme Handback Project Close Out Track Risks Risks Risks Risks Risks Risks Risks Risks Signalling & Telecoms Risks Risks Risks Risks Risks Risks Risks Risks Civils Risks Risks Risks Risks Risks Risks Risks Risks Electrification & Plant Risks Risks Risks Risks Risks Risks Risks Risks Enhancements Risks Risks Risks Risks Risks Risks Risks Risks Estates Risks Risks Risks Risks Risks Risks Risks Risks Major Projects Risks Risks Risks Risks Risks Risks Risks Risks Engineering Risks Risks Risks Risks Risks Risks Risks Risks GRIP Lifecycle Stage Asset Impact – Cost, Schedule, Outputs, Safety 1 Define objectives 2 Identify risks 3 Analyse risks 4 Evaluate risks 5 Risk treatment 6 Monitor, review, communicate and manage Risk Register Impact Uncertainty Exposure Contingency
  • 16. Date 04.07.13 17 Stakeholders Risk Management Principles Threats/Opportunities RISK Stakeholders Objectives © Jeremy Harrison
  • 17. Date 04.07.13 18 The building blocks Uncertainty that matters – the FUTURE VISION : RISK Creativity Knowledge sharing/ Lessons Learned Value add © Jeremy Harrison
  • 18. Date 04.07.13 19 Risk Management Approach GRIP Stage Risk Approach 0 and 1 60% uplift applied to the Point Estimate to cover Optimism Bias, Estimating Uncertainty and Risk Exposure 2 3 point estimate is made of Estimating Uncertainty and Risk Exposure 3 Quantitative risk register of threats and opportunities assessed for probability and impact, covering both Estimating Uncertainty and Risk Exposure Min ML Max
  • 19. Date 00.00.00 Presentation title to go here 2020 Portfolio Effect Savings 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 2 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 3 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 n 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 1 Individual Projects CP5 Portfolio 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 England & Wales Scotland 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% £300,000 £350,000 £400,000 £450,000 £500,000 £550,000 Correlation Programme Risks Portfolio Impacts Funding Route Totals
  • 20. Date 04.07.13 21 What questions should we be asking? • What question, if asked to day, would have the most impact on the situation? • What is most important to you here and now? And what makes it so? • What are the priorities? What are the criteria for deciding this? • What are you not thinking of? • What are you pretending not to know? Art of Powerful Questions – open and penetrating to the issues
  • 21. Date 04.07.13 22 Personal reflections • Never too early to think ‘risk’ – uncertainties that matter! • You know more than you think you do. What are you doing to tap into that? • You are as good as your weakest link – where is it? • The time line is always longer than you think • We are what we ‘need’ to be – optimistic or pessimistic