Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 November 2023

Association for Project Management
Association for Project Management Association for Project Management
DEMYSTIFYING INTEGRATED COST &
SCHEDULE RISK ANALYSIS
Robert Balaam
APM Risk SIG webinar
Tuesday 14 November 2023
OVERVIEW
OVERVIEW
• Integrated Cost & Schedule Risk Analysis (ICSRA) provides powerful insight into how a
project’s critical path and cost can deviate when Estimating Uncertainty and Risk are
considered. These insights can be far superior to just using the critical path, or
performing separate Quantitative Schedule Risk Analysis (QSRA) and Quantitative Cost
Risk Analysis (QCRA).
• This talk will provide an overview and demonstrate progressive approaches and
techniques to ICSRA which can be used at various stages throughout a project’s
lifecycle, and using outputs to make better informed decisions and consider additional
actions.
• The session is aimed at project professionals at all levels to demystify a method which is
often thought of as too complicated or unnecessary.
• It is also aimed at corporate and board professionals to express the supplementary
understanding and awareness provided by ICSRA, why it should be executed on major
projects and programmes, and the benefits of implementing ICSRA into projects and
organisations.
INTRODUCTION
PEOPLE - PLANT - PROCESS - PERFORMANCE - PREDICTION
• London, UK > Europe, USA > Canada > London, UK
• PMO, Project Controls, Risk, & IT Projects for 25+ years
• Management Consultant on many major programs/projects:
• Airports: Major Airport New £4Bn Terminal
• Rail: Major Programmes, Portfolio £100Bn
• Nuclear Power: New £15Bn, Major Refurbishments £7Bn
• Defense: Major Air, Land, & Sea £40Bn
• Football, Football (NFL!), Walking, Cycling, Snooker, Tennis
INTRODUCTION
INDUSTRIES & SECTORS
BILLION POUND OPPORTUNITIES
BASE PLATING
• Scarcity of development space
• Shortage of housing / facilities
• “Air Rights” above railway tracks & stations
• Hudson Yards, New York: $25b, own energy supply!
Euston? HS2? Clapham Junction?
https://www.hudsonyardsnewyork.com/about/building-hudson-yards
https://www.theguardian.com/us-news/2019/mar/14/hudson-yards-new-york-city-open-debut
https://www.imdb.com/title/tt9591896/
ICSRA: THE PROBLEM
ICSRA: THE PROBLEM
How do Programme / Project Managers
make decisions to provide best value to
mitigate / recover / expedite / buffer the
schedule, including duration / estimating
uncertainty, risk, and schedule-logic
dependencies and constraints?
TIME CONTINGENCY MANAGEMENT
ICSRA: THE PROBLEM
• No Process
• No Experience
• Risk mapping takes too long
• Schedule & Cost information misalignment
• Software hard to use
• Not detailed enough
• Too detailed
• Don’t get the right results
• No buy-in from leadership
£ £
ICSRA: BENEFITS
• Removes “risk mapping”
• Drives ‘Real’ conversations
• Drives accountability, engagement, behaviours
• Utilises whole team, knowledge, experience
• Greater understanding & awareness of drivers
• Improves Change Management assessments
• Matures schedule and cost estimate
• Joint Confidence Levels (JCL)
• Superior Budget & Cash-Flow forecasting
• Enhanced Change Management & Contingency Management
PROJECT BASICS
PROJECT BASICS
• Scope: Time / Cost / Quality
• Assumption, Exclusions, Dependencies (AED)
• Work Breakdown Structure (WBS): WBS Dictionary
• Organisational Breakdown Structure (OBS)
• Responsibility Assignment Matrix (RAM): Accountability
• Control Accounts (CA): Performance Measurement
• Work Packages (WP): Company
• Activities: Earned Value Technique
• Resources: People / Plant
• Logic & Constraints: Dependencies / Availability
• Decomposition: (Future) Planning Packages
PROJECT BASICS: SCHEDULE
WBS
OBS
CA-1
WP-1.1
WP-1.2
CA-2
WP-2.1
WP-2.2
CA-3
WP-3.1
WP-2.3
QUANTITATIVE RISK ANALYSIS
(QRA) BASICS
QRA BASICS
• Base Estimate
• Estimate Uncertainty (EU): Duration, Cost
• Risks: Threats / Opportunities: Risk Workshops / Risk Interviews
• Distributions: Single Point, Uniform, Triangular…
• Correlation: Matrix, Factors
• Simulation: Scenarios
• Outputs: S-Curves, Percentiles…
• Contingency: Time & Cost!
QUANTITATIVE SCHEDULE
RISK ANALYSIS
(QSRA)
QSRA BASICS
• Base Estimate: Schedule
• Duration Uncertainty (DU)
• Risks: Threats / Opportunities
• Distributions: Single Point, Uniform, Triangular…
• Correlation: Matrix, Factors
• Simulation: Scenarios
• Outputs: S-Curves, Percentiles…
• Contingency: Schedule Buffer / Time Risk Allowance
QSRA: SCHEDULE QUALITY
• APM Schedule Maturity Assessment
• https://www.apm.org.uk/book-shop/the-scheduling-maturity-model/
• DCMA
• https://www.dcma.mil/
• GAO
• https://www.gao.gov/products/gao-16-89g
• NDIA
• https://www.ndia.org/divisions/ipmd/committees/planning-and-scheduling
QSRA: COMPONENTS
Base
Duration
Duration
Uncertainty
Risk
• Duration Uncertainty can have negative element
• Multiple risks can be mapped to one activity
• Risks can be negative (opportunities)
• Correlation also applied to relevant activities
• All elements combine to generate duration for each iteration
• Simulation has x iterations
• Current, Post-Mitigated, Target, simulations
QSRA: BASE
QSRA Iteration Duration
ID Project Base Duration Base Duration
Rank
Duration
Uncertainty
Risk Iteration
Duration
Iteration
Duration Rank
1 Activity 1 40 12 6 25 71 15
2 Activity 2 20 20 2 18 40 20
3 Activity 3 40 12 11 38 89 10
4 Activity 4 80 3 11 22 113 2
5 Activity 5 60 6 11 -5 66 16
6 Activity 6 90 1 15 4 109 4
7 Activity 7 40 12 17 49 106 5
8 Activity 8 60 6 6 6 72 14
9 Activity 9 50 10 5 -9 46 19
10 Activity 10 80 3 7 12 99 8
11 Activity 11 80 3 17 34 131 1
12 Activity 12 30 18 17 34 81 12
13 Activity 13 40 12 16 47 103 6
14 Activity 14 30 18 2 15 47 18
15 Activity 15 60 6 18 17 95 9
16 Activity 16 40 12 13 47 100 7
17 Activity 17 90 1 4 18 112 3
18 Activity 18 40 12 3 44 87 11
19 Activity 19 50 10 1 15 66 16
20 Activity 20 60 6 5 13 78 13
QSRA: ITERATION 1
Activity Name
QSRA: ITERATION 1
QSRA Iteration Duration
ID Project Base Duration Base Duration
Rank
Duration
Uncertainty
Risk Iteration
Duration
Iteration
Duration Rank
1 Activity 1 40 12 9 20 69 14
2 Activity 2 20 20 4 5 29 20
3 Activity 3 40 12 10 1 51 18
4 Activity 4 80 3 1 36 117 4
5 Activity 5 60 6 8 31 99 7
6 Activity 6 90 1 5 26 121 3
7 Activity 7 40 12 3 45 88 10
8 Activity 8 60 6 3 5 68 15
9 Activity 9 50 10 2 5 57 17
10 Activity 10 80 3 17 46 143 1
11 Activity 11 80 3 13 49 142 2
12 Activity 12 30 18 11 38 79 11
13 Activity 13 40 12 2 32 74 13
14 Activity 14 30 18 4 45 79 11
15 Activity 15 60 6 3 30 93 9
16 Activity 16 40 12 17 -8 49 19
17 Activity 17 90 1 3 2 95 8
18 Activity 18 40 12 20 1 61 16
19 Activity 19 50 10 10 44 104 6
20 Activity 20 60 6 2 46 108 5
QSRA: ITERATION 2
Activity Name
QSRA: ITERATION 2
QSRA: S-CURVE
0
10
20
30
40
50
60
70
80
90
100
01/01/2026
01/04/2026
30/06/2026
28/09/2026
27/12/2026
27/03/2027
25/06/2027
23/09/2027
22/12/2027
21/03/2028
19/06/2028
Percentile
End Date
Activity 20: S-Curve
Percentile Date
0 02/01/2026
5 10/05/2026
10 15/07/2026
15 17/08/2026
20 16/09/2026
25 16/10/2026
30 15/11/2026
35 14/12/2026
40 11/01/2027
45 07/02/2027
50 06/03/2027
55 01/04/2027
60 26/04/2027
65 25/05/2027
70 27/06/2027
75 06/08/2027
80 21/09/2027
85 13/11/2027
90 14/01/2028
95 27/03/2028
100 19/06/2028
• Key Drivers: Which activities / uncertainty / risks most influence end date
• Criticality Index (CI): Probability activity lies on critical path
• Significance Index (SI): Relative duration importance of an activity
• Schedule Sensitivity Index (SSI): SI * CI
• Cruciality Index (CRI): Duration - Total Duration correlation
• Resource Analysis
QSRA OUTPUTS
QUANTITATIVE COST
RISK ANALYSIS
(QCRA)
QCRA BASICS
• Base Estimate: Cost Breakdown Structure
• Cost Uncertainty (CU)
• Risks: Threats / Opportunities: Prolongation Risk
• Distributions: Single Point, Uniform, Triangular…
• Correlation: Matrix, Factors
• Simulation: Scenarios
• Outputs: S-Curves, Percentiles…
• Contingency: Project Contingency, Programme Contingency
QCRA: COMPONENTS
Base Cost Cost Uncertainty Risk
• Cost Uncertainty can have negative element
• Multiple risks can be mapped to one cost element
• Risks can be negative (opportunities)
• Correlation also applied to relevant cost elements
• All elements combine to generate cost for each iteration
• Simulation has x iterations
• Current, Post-Mitigated, Target, simulations
QCRA Iteration Cost
ID Cost Element Base Cost Base Cost Rank Cost Uncertainty Risk Iteration Cost Iteration Cost
Rank
1 Cost Element 1 £ 41,832 17 £ 45,962 £ 77,002 £ 164,796 15
2 Cost Element 2 £ 144,486 2 £ 92,900 £ 125,612 £ 362,998 3
3 Cost Element 3 £ 82,880 10 £ 79,271 £ 153,466 £ 315,617 6
4 Cost Element 4 £ 137,107 4 £ 116,788 £ 82,263 £ 336,158 5
5 Cost Element 5 £ 33,250 19 £ 7,171 £ 22,410 £ 62,831 20
6 Cost Element 6 £ 93,971 8 £ 75,866 £ 139,984 £ 309,821 7
7 Cost Element 7 £ 85,594 9 £ 92,718 £ 94,576 £ 272,888 9
8 Cost Element 8 £ 44,609 16 £ 52,078 £ 81,870 £ 178,557 14
9 Cost Element 9 £ 109,968 5 £ 47,411 £ 123,528 £ 280,907 8
10 Cost Element 10 £ 74,702 12 £ 86,176 £ 102,093 £ 262,971 11
11 Cost Element 11 £ 149,075 1 £ 120,336 £ 290,098 £ 559,509 1
12 Cost Element 12 £ 41,394 18 £ 25,511 £ 48,877 £ 115,782 18
13 Cost Element 13 £ 137,172 3 £ 40,756 £ 228,309 £ 406,237 2
14 Cost Element 14 £ 23,579 20 £ 17,906 £ 33,869 £ 75,354 19
15 Cost Element 15 £ 100,639 7 £ 115,934 £ 130,509 £ 347,082 4
16 Cost Element 16 £ 53,803 14 £ 9,848 £ 96,065 £ 159,716 16
17 Cost Element 17 £ 79,315 11 £ 82,442 £ 105,495 £ 267,252 10
18 Cost Element 18 £ 64,613 13 £ 38,911 £ 119,907 £ 223,431 13
19 Cost Element 19 £ 47,689 15 £ 25,415 £ 65,006 £ 138,110 17
20 Cost Element 20 £ 103,845 6 £ 26,645 £ 124,032 £ 254,522 12
Total £ 1,649,523 £ 1,200,045 £ 2,244,971 £ 5,094,539
QCRA: ITERATION 1
QCRA Iteration Cost
ID Cost Element Base Cost Base Cost Rank Cost Uncertainty Risk Iteration Cost Iteration Cost
Rank
1 Cost Element 1 £ 41,832 17 £ 13,655 £ 31,427 £ 86,914 19
2 Cost Element 2 £ 144,486 2 £ 33,341 £ 279,422 £ 457,249 1
3 Cost Element 3 £ 82,880 10 £ 41,928 £ 111,274 £ 236,082 9
4 Cost Element 4 £ 137,107 4 £ 52,469 £ 142,567 £ 332,143 4
5 Cost Element 5 £ 33,250 19 £ 13,294 £ 60,893 £ 107,437 18
6 Cost Element 6 £ 93,971 8 £ 56,496 £ 153,744 £ 304,211 6
7 Cost Element 7 £ 85,594 9 £ 35,405 £ 82,316 £ 203,315 12
8 Cost Element 8 £ 44,609 16 £ 33,984 £ 63,197 £ 141,790 15
9 Cost Element 9 £ 109,968 5 £ 41,671 £ 148,210 £ 299,849 7
10 Cost Element 10 £ 74,702 12 £ 45,369 £ 90,641 £ 210,712 11
11 Cost Element 11 £ 149,075 1 £ 163,404 £ 106,215 £ 418,694 2
12 Cost Element 12 £ 41,394 18 £ 30,262 £ 46,906 £ 118,562 16
13 Cost Element 13 £ 137,172 3 £ 19,610 £ 74,014 £ 230,796 10
14 Cost Element 14 £ 23,579 20 £ 14,240 £ 42,076 £ 79,895 20
15 Cost Element 15 £ 100,639 7 £ 119,400 £ 110,675 £ 330,714 5
16 Cost Element 16 £ 53,803 14 £ 14,478 £ 76,662 £ 144,943 14
17 Cost Element 17 £ 79,315 11 £ 89,682 £ 74,785 £ 243,782 8
18 Cost Element 18 £ 64,613 13 £ 7,906 £ 35,107 £ 107,626 17
19 Cost Element 19 £ 47,689 15 £ 21,187 £ 79,925 £ 148,801 13
20 Cost Element 20 £ 103,845 6 £ 99,033 £ 148,932 £ 351,810 3
Total £ 1,649,523 £ 946,814 £ 1,958,988 £ 4,555,325
QCRA: ITERATION 2
0
10
20
30
40
50
60
70
80
90
100
£
1,000,000
£
1,500,000
£
2,000,000
£
2,500,000
£
3,000,000
£
3,500,000
£
4,000,000
£
4,500,000
£
5,000,000
£
5,500,000
£
6,000,000
£
6,500,000
Percentile
Total Cost
Total Cost S-Curve
Percentile Total Cost
0 £ 1,268,332
5 £ 1,405,076
10 £ 1,491,898
15 £ 1,547,023
20 £ 1,599,523
25 £ 1,649,523
30 £ 1,799,523
35 £ 1,957,023
40 £ 2,122,398
45 £ 2,296,042
50 £ 2,478,368
55 £ 2,669,810
60 £ 2,870,824
65 £ 3,102,996
70 £ 3,371,154
75 £ 3,680,877
80 £ 4,038,606
85 £ 4,451,784
90 £ 4,929,005
95 £ 5,480,194
100 £ 6,116,818
QCRA: S-CURVE
INTEGRATED COST &
SCHEDULE RISK ANALYSIS
(ICSRA)
ICSRA: APPROACH
• Organisational / PMO culture key
• Schedule and Cost systems driven by WBS & Control Accounts
• Estimating Uncertainty and Risk assigned to schedule
• Schedule decomposed jointly with cost decomposition
• Activities reviewed wholistically – Time, Cost, & Risk together!
• Application Programme Interfaces (APIs) to reduce errors
ICSRA: COMPONENTS
Activity
Duration
Duration
Uncertainty
Time Risk
Activity
Cost
Cost
Uncertainty
Cost Risk
• Direct conversations and challenges
• Greater understanding of Estimating Uncertainty & Risk
• Accountable elements > drives ownership!
ICSRA: JOINT CONFIDENCE LEVELS
• ISSUE: QSRA & QCRA results don’t reflect combined effects.
• RESULT: Better insight, more accurate estimating & forecasting.
ICSRA: CASH FLOW
• ISSUE: Cash flow forecasting is poor.
• RESULT: More accurate forecasting and insight.
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00
Risk Cost Profile by End Date Series1
Series2
ICSRA ASSURANCE: SCHEDULE HIERARCHY
• ISSUE: Schedule incomprehensible by stakeholders, difficult for scenarios.
• RESULT: Comparative assessments, additional insight.
Initial
Initial
Design
Detailed
Design
Procurement Construction Commissioning Handover
Summary
Schedule
(by Phase)
WBS
Control
Account
Work
Package
Work Package / Activity
(Key areas as required)
ICSRA ASSURANCE: SUMMARY SCHEDULE
• The Summary schedule should be high level, contain 100% of
work, have all phases, key deliverables, key milestones, key
undertakings, key sequences, key paths, identify key
interdependent logic, tactical relationships, be sufficiently
reflective, consistent, and aligned with the detailed schedule.
• Challenge schedule producer with this statement > signature !!
• Tip: Start with detailed Level 3-4 and look for logic across
components.
ICSRA ASSURANCE: PRAGMATIC
• ISSUE: Too many risks to map to schedule.
• RESULT: Pragmatic assessment.
• Red risks
• Red & Amber risks
• Red & Amber & ‘Green Total’ risks
• Risks on / near critical path
• Risks on activities with low float
• Highlights key areas > detailed analysis
ICSRA: BENEFITS
• Removes “risk mapping”
• Drives ‘Real’ conversations
• Drives accountability, engagement, behaviours
• Utilises whole team, knowledge, experience
• Greater understanding & awareness of drivers
• Improves Change Management assessments
• Matures schedule and cost estimate
• Joint Confidence Levels (JCL)
• Superior Budget & Cash-Flow forecasting
• Enhanced Change Management & Contingency Management
THE FUTURE !!
FUTURE OUTPUTS
• ISSUE: Outputs don’t provide decision making information.
• RESULT: Powerful decision making insights.
• Most cost-effective activities (current and future) to expedite / reduce the critical path?
• Which activities most likely to increase the overall cost?
• Which activities most likely to increase the critical path and overall cost?
• Where are the biggest cash flow periods and related values – are they achievable?
• Highest Cost Path / Critical Path
• Highest Labour Cost Path / Critical Path
• Highest Materials Cost Path / Critical Path
COST EFFECTIVE SCHEDULE MANAGEMENT
• ISSUE: Inability to see where schedule & cost problem areas are at once.
• RESULT: Powerful visualisation of key areas to focus on.
RISK ALGORITHMS / AI
• ISSUE: Bias in estimating and lack of historical insight & trending.
• RESULT: Increased insight and forecasting assurance.
• Uses historical information to predict risk
• Can combine data across companies, industries, and countries
• Sometimes just uses text to forecast
• Machine learning provides continuous refinement
• May not suit first-of-a-kind or unique projects
RISK ALGORITHMS / AI
• ISSUE: Bias in estimating and lack of historical insight & trending.
• RESULT: Increased insight and forecasting assurance.
CONCLUSION
CONCLUSION
• Organisational Culture is key!
• Schedule should ALWAYS drive the project
• Decompose Schedule and Cost at the same rate – Schedule first!
• No ‘bad’ simulation – an iterative, engaging, absorbing, insightful, process
• Try to automate – so many potential errors doing manually
• Really look at integrating your schedule, cost, and risk software using APIs
• ICSRA is far more efficient, effective, & insightful, than siloed QSRAs / QCRAs
• It’s a journey not a destination!
EMBRACE.
ENGAGE. EMPOWER.
“THE ONLY THING NECESSARY
FOR THE TRIUMPH OF
COST-DRIVEN PROGRAMMES
IS FOR GOOD
RISK, PMO, PROJECT CONTROLS, & PLANNING
PROFESSIONALS TO DO NOTHING."
THANK YOU
QR CODES
APM EVENTS APM RISK SIG
1 of 53

Recommended

Advanced project risk reporting webinar, 21 September 2022 by
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Association for Project Management
317 views24 slides
Where did it go wrong? by
Where did it go wrong?Where did it go wrong?
Where did it go wrong?Association for Project Management
1.4K views21 slides
APM QSRA webinar; introduction for risk and planning professionals and decisi... by
APM QSRA webinar; introduction for risk and planning professionals and decisi...APM QSRA webinar; introduction for risk and planning professionals and decisi...
APM QSRA webinar; introduction for risk and planning professionals and decisi...Association for Project Management
6.9K views33 slides
Simon White - Where is the Risk? by
Simon White - Where is the Risk?Simon White - Where is the Risk?
Simon White - Where is the Risk?Association for Project Management
87 views56 slides
Quantiative Risk Analysis for the Aerospace Industry by
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryIntaver Insititute
44 views21 slides

More Related Content

Similar to Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 November 2023

Practical project risk assessment, Simon White by
Practical project risk assessment, Simon WhitePractical project risk assessment, Simon White
Practical project risk assessment, Simon WhiteAssociation for Project Management
2.6K views21 slides
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr... by
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo
796 views17 slides
APM Edinburgh risk management january 2017 final by
APM Edinburgh risk management january 2017 finalAPM Edinburgh risk management january 2017 final
APM Edinburgh risk management january 2017 finalAssociation for Project Management
1K views43 slides
Project Risk Analysis in Aerospace Industry by
Project Risk Analysis in Aerospace IndustryProject Risk Analysis in Aerospace Industry
Project Risk Analysis in Aerospace IndustryIntaver Insititute
1.5K views21 slides
Essentials of Project Management by
Essentials of Project ManagementEssentials of Project Management
Essentials of Project ManagementLiving Online
1.8K views38 slides
Van heeringen estimate faster, cheaper, better by
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, betterHarold van Heeringen
519 views26 slides

Similar to Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 November 2023(20)

Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr... by Project Controls Expo
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Risk Analysis in Aerospace Industry by Intaver Insititute
Project Risk Analysis in Aerospace IndustryProject Risk Analysis in Aerospace Industry
Project Risk Analysis in Aerospace Industry
Intaver Insititute1.5K views
Essentials of Project Management by Living Online
Essentials of Project ManagementEssentials of Project Management
Essentials of Project Management
Living Online1.8K views
Project final report by ALIN BABU
Project final reportProject final report
Project final report
ALIN BABU529 views
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14 by p6academy
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
p6academy1.7K views
Introduction of Secure Software Development Lifecycle by Rishi Kant
Introduction of Secure Software Development LifecycleIntroduction of Secure Software Development Lifecycle
Introduction of Secure Software Development Lifecycle
Rishi Kant356 views
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit... by Project Controls Expo
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
PlacemakAR Application - Software Engineering Discussion by Kanishk Karanawat
PlacemakAR Application - Software Engineering DiscussionPlacemakAR Application - Software Engineering Discussion
PlacemakAR Application - Software Engineering Discussion
Kanishk Karanawat195 views
Implementing Level 5 Metrics Programme @ Capgemini Netherlands by Niteen Kumar
Implementing Level 5 Metrics Programme @ Capgemini NetherlandsImplementing Level 5 Metrics Programme @ Capgemini Netherlands
Implementing Level 5 Metrics Programme @ Capgemini Netherlands
Niteen Kumar1.3K views
Risk Management Processes from Jerry Klanac by PMA Consultants
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
PMA Consultants306 views
Valuing demand response pub by Lucas Finco
Valuing demand response pubValuing demand response pub
Valuing demand response pub
Lucas Finco624 views
CECL Methodology - CRE Loan Pools by Libby Bierman
CECL Methodology - CRE Loan PoolsCECL Methodology - CRE Loan Pools
CECL Methodology - CRE Loan Pools
Libby Bierman260 views

More from Association for Project Management

Presenting with Impact (APM) Oct 2023.pdf by
Presenting with Impact (APM) Oct 2023.pdfPresenting with Impact (APM) Oct 2023.pdf
Presenting with Impact (APM) Oct 2023.pdfAssociation for Project Management
196 views9 slides
Benefits and Value and Governance SIG Conference, Building for Legacy - The L... by
Benefits and Value and Governance SIG Conference, Building for Legacy - The L...Benefits and Value and Governance SIG Conference, Building for Legacy - The L...
Benefits and Value and Governance SIG Conference, Building for Legacy - The L...Association for Project Management
340 views38 slides
Benefits and Value and Governance SIG Conference, Prioritizing sustainability... by
Benefits and Value and Governance SIG Conference, Prioritizing sustainability...Benefits and Value and Governance SIG Conference, Prioritizing sustainability...
Benefits and Value and Governance SIG Conference, Prioritizing sustainability...Association for Project Management
334 views12 slides
Benefits and Value and Governance SIG Conference, The Governance of Sustainab... by
Benefits and Value and Governance SIG Conference, The Governance of Sustainab...Benefits and Value and Governance SIG Conference, The Governance of Sustainab...
Benefits and Value and Governance SIG Conference, The Governance of Sustainab...Association for Project Management
340 views14 slides
Benefits and Value and Governance SIG, Sustainability & Leadership, 10 Octobe... by
Benefits and Value and Governance SIG, Sustainability & Leadership, 10 Octobe...Benefits and Value and Governance SIG, Sustainability & Leadership, 10 Octobe...
Benefits and Value and Governance SIG, Sustainability & Leadership, 10 Octobe...Association for Project Management
336 views17 slides

More from Association for Project Management (20)

Recently uploaded

Presentation_NC_Future now 2006.pdf by
Presentation_NC_Future now 2006.pdfPresentation_NC_Future now 2006.pdf
Presentation_NC_Future now 2006.pdfLora
38 views74 slides
The Picture Of A Photograph by
The Picture Of A PhotographThe Picture Of A Photograph
The Picture Of A PhotographEvelyn Donaldson
38 views81 slides
MercerJesse3.0.pdf by
MercerJesse3.0.pdfMercerJesse3.0.pdf
MercerJesse3.0.pdfjessemercerail
183 views6 slides
GSoC 2024 .pdf by
GSoC 2024 .pdfGSoC 2024 .pdf
GSoC 2024 .pdfShabNaz2
45 views15 slides
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption... by
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...BC Chew
40 views47 slides
Women From 1850 To 1950 Essay by
Women From 1850 To 1950 EssayWomen From 1850 To 1950 Essay
Women From 1850 To 1950 EssayAmy Williams
39 views77 slides

Recently uploaded(20)

Presentation_NC_Future now 2006.pdf by Lora
Presentation_NC_Future now 2006.pdfPresentation_NC_Future now 2006.pdf
Presentation_NC_Future now 2006.pdf
Lora 38 views
GSoC 2024 .pdf by ShabNaz2
GSoC 2024 .pdfGSoC 2024 .pdf
GSoC 2024 .pdf
ShabNaz245 views
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption... by BC Chew
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...
Artificial Intelligence and The Sustainable Development Goals (SDGs) Adoption...
BC Chew40 views
Women From 1850 To 1950 Essay by Amy Williams
Women From 1850 To 1950 EssayWomen From 1850 To 1950 Essay
Women From 1850 To 1950 Essay
Amy Williams39 views
Guidelines & Identification of Early Sepsis DR. NN CHAVAN 02122023.pptx by Niranjan Chavan
Guidelines & Identification of Early Sepsis DR. NN CHAVAN 02122023.pptxGuidelines & Identification of Early Sepsis DR. NN CHAVAN 02122023.pptx
Guidelines & Identification of Early Sepsis DR. NN CHAVAN 02122023.pptx
Niranjan Chavan43 views
Peripheral artery diseases by Dr. Garvit.pptx by garvitnanecha
Peripheral artery diseases by Dr. Garvit.pptxPeripheral artery diseases by Dr. Garvit.pptx
Peripheral artery diseases by Dr. Garvit.pptx
garvitnanecha135 views
Guess Papers ADC 1, Karachi University by Khalid Aziz
Guess Papers ADC 1, Karachi UniversityGuess Papers ADC 1, Karachi University
Guess Papers ADC 1, Karachi University
Khalid Aziz109 views
NodeJS and ExpressJS.pdf by ArthyR3
NodeJS and ExpressJS.pdfNodeJS and ExpressJS.pdf
NodeJS and ExpressJS.pdf
ArthyR353 views
What is Digital Transformation? by Mark Brown
What is Digital Transformation?What is Digital Transformation?
What is Digital Transformation?
Mark Brown46 views
Ask The Expert! Nonprofit Website Tools, Tips, and Technology.pdf by TechSoup
 Ask The Expert! Nonprofit Website Tools, Tips, and Technology.pdf Ask The Expert! Nonprofit Website Tools, Tips, and Technology.pdf
Ask The Expert! Nonprofit Website Tools, Tips, and Technology.pdf
TechSoup 67 views
JRN 362 - Lecture Twenty-Three (Epilogue) by Rich Hanley
JRN 362 - Lecture Twenty-Three (Epilogue)JRN 362 - Lecture Twenty-Three (Epilogue)
JRN 362 - Lecture Twenty-Three (Epilogue)
Rich Hanley44 views
ANGULARJS.pdf by ArthyR3
ANGULARJS.pdfANGULARJS.pdf
ANGULARJS.pdf
ArthyR354 views
Career Building in AI - Technologies, Trends and Opportunities by WebStackAcademy
Career Building in AI - Technologies, Trends and OpportunitiesCareer Building in AI - Technologies, Trends and Opportunities
Career Building in AI - Technologies, Trends and Opportunities
WebStackAcademy51 views
Interaction of microorganisms with vascular plants.pptx by MicrobiologyMicro
Interaction of microorganisms with vascular plants.pptxInteraction of microorganisms with vascular plants.pptx
Interaction of microorganisms with vascular plants.pptx

Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 November 2023

  • 1. DEMYSTIFYING INTEGRATED COST & SCHEDULE RISK ANALYSIS Robert Balaam APM Risk SIG webinar Tuesday 14 November 2023
  • 3. OVERVIEW • Integrated Cost & Schedule Risk Analysis (ICSRA) provides powerful insight into how a project’s critical path and cost can deviate when Estimating Uncertainty and Risk are considered. These insights can be far superior to just using the critical path, or performing separate Quantitative Schedule Risk Analysis (QSRA) and Quantitative Cost Risk Analysis (QCRA). • This talk will provide an overview and demonstrate progressive approaches and techniques to ICSRA which can be used at various stages throughout a project’s lifecycle, and using outputs to make better informed decisions and consider additional actions. • The session is aimed at project professionals at all levels to demystify a method which is often thought of as too complicated or unnecessary. • It is also aimed at corporate and board professionals to express the supplementary understanding and awareness provided by ICSRA, why it should be executed on major projects and programmes, and the benefits of implementing ICSRA into projects and organisations.
  • 5. PEOPLE - PLANT - PROCESS - PERFORMANCE - PREDICTION • London, UK > Europe, USA > Canada > London, UK • PMO, Project Controls, Risk, & IT Projects for 25+ years • Management Consultant on many major programs/projects: • Airports: Major Airport New £4Bn Terminal • Rail: Major Programmes, Portfolio £100Bn • Nuclear Power: New £15Bn, Major Refurbishments £7Bn • Defense: Major Air, Land, & Sea £40Bn • Football, Football (NFL!), Walking, Cycling, Snooker, Tennis INTRODUCTION
  • 8. BASE PLATING • Scarcity of development space • Shortage of housing / facilities • “Air Rights” above railway tracks & stations • Hudson Yards, New York: $25b, own energy supply! Euston? HS2? Clapham Junction? https://www.hudsonyardsnewyork.com/about/building-hudson-yards https://www.theguardian.com/us-news/2019/mar/14/hudson-yards-new-york-city-open-debut https://www.imdb.com/title/tt9591896/
  • 10. ICSRA: THE PROBLEM How do Programme / Project Managers make decisions to provide best value to mitigate / recover / expedite / buffer the schedule, including duration / estimating uncertainty, risk, and schedule-logic dependencies and constraints? TIME CONTINGENCY MANAGEMENT
  • 11. ICSRA: THE PROBLEM • No Process • No Experience • Risk mapping takes too long • Schedule & Cost information misalignment • Software hard to use • Not detailed enough • Too detailed • Don’t get the right results • No buy-in from leadership £ £
  • 12. ICSRA: BENEFITS • Removes “risk mapping” • Drives ‘Real’ conversations • Drives accountability, engagement, behaviours • Utilises whole team, knowledge, experience • Greater understanding & awareness of drivers • Improves Change Management assessments • Matures schedule and cost estimate • Joint Confidence Levels (JCL) • Superior Budget & Cash-Flow forecasting • Enhanced Change Management & Contingency Management
  • 14. PROJECT BASICS • Scope: Time / Cost / Quality • Assumption, Exclusions, Dependencies (AED) • Work Breakdown Structure (WBS): WBS Dictionary • Organisational Breakdown Structure (OBS) • Responsibility Assignment Matrix (RAM): Accountability • Control Accounts (CA): Performance Measurement • Work Packages (WP): Company • Activities: Earned Value Technique • Resources: People / Plant • Logic & Constraints: Dependencies / Availability • Decomposition: (Future) Planning Packages
  • 17. QRA BASICS • Base Estimate • Estimate Uncertainty (EU): Duration, Cost • Risks: Threats / Opportunities: Risk Workshops / Risk Interviews • Distributions: Single Point, Uniform, Triangular… • Correlation: Matrix, Factors • Simulation: Scenarios • Outputs: S-Curves, Percentiles… • Contingency: Time & Cost!
  • 19. QSRA BASICS • Base Estimate: Schedule • Duration Uncertainty (DU) • Risks: Threats / Opportunities • Distributions: Single Point, Uniform, Triangular… • Correlation: Matrix, Factors • Simulation: Scenarios • Outputs: S-Curves, Percentiles… • Contingency: Schedule Buffer / Time Risk Allowance
  • 20. QSRA: SCHEDULE QUALITY • APM Schedule Maturity Assessment • https://www.apm.org.uk/book-shop/the-scheduling-maturity-model/ • DCMA • https://www.dcma.mil/ • GAO • https://www.gao.gov/products/gao-16-89g • NDIA • https://www.ndia.org/divisions/ipmd/committees/planning-and-scheduling
  • 21. QSRA: COMPONENTS Base Duration Duration Uncertainty Risk • Duration Uncertainty can have negative element • Multiple risks can be mapped to one activity • Risks can be negative (opportunities) • Correlation also applied to relevant activities • All elements combine to generate duration for each iteration • Simulation has x iterations • Current, Post-Mitigated, Target, simulations
  • 23. QSRA Iteration Duration ID Project Base Duration Base Duration Rank Duration Uncertainty Risk Iteration Duration Iteration Duration Rank 1 Activity 1 40 12 6 25 71 15 2 Activity 2 20 20 2 18 40 20 3 Activity 3 40 12 11 38 89 10 4 Activity 4 80 3 11 22 113 2 5 Activity 5 60 6 11 -5 66 16 6 Activity 6 90 1 15 4 109 4 7 Activity 7 40 12 17 49 106 5 8 Activity 8 60 6 6 6 72 14 9 Activity 9 50 10 5 -9 46 19 10 Activity 10 80 3 7 12 99 8 11 Activity 11 80 3 17 34 131 1 12 Activity 12 30 18 17 34 81 12 13 Activity 13 40 12 16 47 103 6 14 Activity 14 30 18 2 15 47 18 15 Activity 15 60 6 18 17 95 9 16 Activity 16 40 12 13 47 100 7 17 Activity 17 90 1 4 18 112 3 18 Activity 18 40 12 3 44 87 11 19 Activity 19 50 10 1 15 66 16 20 Activity 20 60 6 5 13 78 13 QSRA: ITERATION 1 Activity Name
  • 25. QSRA Iteration Duration ID Project Base Duration Base Duration Rank Duration Uncertainty Risk Iteration Duration Iteration Duration Rank 1 Activity 1 40 12 9 20 69 14 2 Activity 2 20 20 4 5 29 20 3 Activity 3 40 12 10 1 51 18 4 Activity 4 80 3 1 36 117 4 5 Activity 5 60 6 8 31 99 7 6 Activity 6 90 1 5 26 121 3 7 Activity 7 40 12 3 45 88 10 8 Activity 8 60 6 3 5 68 15 9 Activity 9 50 10 2 5 57 17 10 Activity 10 80 3 17 46 143 1 11 Activity 11 80 3 13 49 142 2 12 Activity 12 30 18 11 38 79 11 13 Activity 13 40 12 2 32 74 13 14 Activity 14 30 18 4 45 79 11 15 Activity 15 60 6 3 30 93 9 16 Activity 16 40 12 17 -8 49 19 17 Activity 17 90 1 3 2 95 8 18 Activity 18 40 12 20 1 61 16 19 Activity 19 50 10 10 44 104 6 20 Activity 20 60 6 2 46 108 5 QSRA: ITERATION 2 Activity Name
  • 27. QSRA: S-CURVE 0 10 20 30 40 50 60 70 80 90 100 01/01/2026 01/04/2026 30/06/2026 28/09/2026 27/12/2026 27/03/2027 25/06/2027 23/09/2027 22/12/2027 21/03/2028 19/06/2028 Percentile End Date Activity 20: S-Curve Percentile Date 0 02/01/2026 5 10/05/2026 10 15/07/2026 15 17/08/2026 20 16/09/2026 25 16/10/2026 30 15/11/2026 35 14/12/2026 40 11/01/2027 45 07/02/2027 50 06/03/2027 55 01/04/2027 60 26/04/2027 65 25/05/2027 70 27/06/2027 75 06/08/2027 80 21/09/2027 85 13/11/2027 90 14/01/2028 95 27/03/2028 100 19/06/2028
  • 28. • Key Drivers: Which activities / uncertainty / risks most influence end date • Criticality Index (CI): Probability activity lies on critical path • Significance Index (SI): Relative duration importance of an activity • Schedule Sensitivity Index (SSI): SI * CI • Cruciality Index (CRI): Duration - Total Duration correlation • Resource Analysis QSRA OUTPUTS
  • 30. QCRA BASICS • Base Estimate: Cost Breakdown Structure • Cost Uncertainty (CU) • Risks: Threats / Opportunities: Prolongation Risk • Distributions: Single Point, Uniform, Triangular… • Correlation: Matrix, Factors • Simulation: Scenarios • Outputs: S-Curves, Percentiles… • Contingency: Project Contingency, Programme Contingency
  • 31. QCRA: COMPONENTS Base Cost Cost Uncertainty Risk • Cost Uncertainty can have negative element • Multiple risks can be mapped to one cost element • Risks can be negative (opportunities) • Correlation also applied to relevant cost elements • All elements combine to generate cost for each iteration • Simulation has x iterations • Current, Post-Mitigated, Target, simulations
  • 32. QCRA Iteration Cost ID Cost Element Base Cost Base Cost Rank Cost Uncertainty Risk Iteration Cost Iteration Cost Rank 1 Cost Element 1 £ 41,832 17 £ 45,962 £ 77,002 £ 164,796 15 2 Cost Element 2 £ 144,486 2 £ 92,900 £ 125,612 £ 362,998 3 3 Cost Element 3 £ 82,880 10 £ 79,271 £ 153,466 £ 315,617 6 4 Cost Element 4 £ 137,107 4 £ 116,788 £ 82,263 £ 336,158 5 5 Cost Element 5 £ 33,250 19 £ 7,171 £ 22,410 £ 62,831 20 6 Cost Element 6 £ 93,971 8 £ 75,866 £ 139,984 £ 309,821 7 7 Cost Element 7 £ 85,594 9 £ 92,718 £ 94,576 £ 272,888 9 8 Cost Element 8 £ 44,609 16 £ 52,078 £ 81,870 £ 178,557 14 9 Cost Element 9 £ 109,968 5 £ 47,411 £ 123,528 £ 280,907 8 10 Cost Element 10 £ 74,702 12 £ 86,176 £ 102,093 £ 262,971 11 11 Cost Element 11 £ 149,075 1 £ 120,336 £ 290,098 £ 559,509 1 12 Cost Element 12 £ 41,394 18 £ 25,511 £ 48,877 £ 115,782 18 13 Cost Element 13 £ 137,172 3 £ 40,756 £ 228,309 £ 406,237 2 14 Cost Element 14 £ 23,579 20 £ 17,906 £ 33,869 £ 75,354 19 15 Cost Element 15 £ 100,639 7 £ 115,934 £ 130,509 £ 347,082 4 16 Cost Element 16 £ 53,803 14 £ 9,848 £ 96,065 £ 159,716 16 17 Cost Element 17 £ 79,315 11 £ 82,442 £ 105,495 £ 267,252 10 18 Cost Element 18 £ 64,613 13 £ 38,911 £ 119,907 £ 223,431 13 19 Cost Element 19 £ 47,689 15 £ 25,415 £ 65,006 £ 138,110 17 20 Cost Element 20 £ 103,845 6 £ 26,645 £ 124,032 £ 254,522 12 Total £ 1,649,523 £ 1,200,045 £ 2,244,971 £ 5,094,539 QCRA: ITERATION 1
  • 33. QCRA Iteration Cost ID Cost Element Base Cost Base Cost Rank Cost Uncertainty Risk Iteration Cost Iteration Cost Rank 1 Cost Element 1 £ 41,832 17 £ 13,655 £ 31,427 £ 86,914 19 2 Cost Element 2 £ 144,486 2 £ 33,341 £ 279,422 £ 457,249 1 3 Cost Element 3 £ 82,880 10 £ 41,928 £ 111,274 £ 236,082 9 4 Cost Element 4 £ 137,107 4 £ 52,469 £ 142,567 £ 332,143 4 5 Cost Element 5 £ 33,250 19 £ 13,294 £ 60,893 £ 107,437 18 6 Cost Element 6 £ 93,971 8 £ 56,496 £ 153,744 £ 304,211 6 7 Cost Element 7 £ 85,594 9 £ 35,405 £ 82,316 £ 203,315 12 8 Cost Element 8 £ 44,609 16 £ 33,984 £ 63,197 £ 141,790 15 9 Cost Element 9 £ 109,968 5 £ 41,671 £ 148,210 £ 299,849 7 10 Cost Element 10 £ 74,702 12 £ 45,369 £ 90,641 £ 210,712 11 11 Cost Element 11 £ 149,075 1 £ 163,404 £ 106,215 £ 418,694 2 12 Cost Element 12 £ 41,394 18 £ 30,262 £ 46,906 £ 118,562 16 13 Cost Element 13 £ 137,172 3 £ 19,610 £ 74,014 £ 230,796 10 14 Cost Element 14 £ 23,579 20 £ 14,240 £ 42,076 £ 79,895 20 15 Cost Element 15 £ 100,639 7 £ 119,400 £ 110,675 £ 330,714 5 16 Cost Element 16 £ 53,803 14 £ 14,478 £ 76,662 £ 144,943 14 17 Cost Element 17 £ 79,315 11 £ 89,682 £ 74,785 £ 243,782 8 18 Cost Element 18 £ 64,613 13 £ 7,906 £ 35,107 £ 107,626 17 19 Cost Element 19 £ 47,689 15 £ 21,187 £ 79,925 £ 148,801 13 20 Cost Element 20 £ 103,845 6 £ 99,033 £ 148,932 £ 351,810 3 Total £ 1,649,523 £ 946,814 £ 1,958,988 £ 4,555,325 QCRA: ITERATION 2
  • 34. 0 10 20 30 40 50 60 70 80 90 100 £ 1,000,000 £ 1,500,000 £ 2,000,000 £ 2,500,000 £ 3,000,000 £ 3,500,000 £ 4,000,000 £ 4,500,000 £ 5,000,000 £ 5,500,000 £ 6,000,000 £ 6,500,000 Percentile Total Cost Total Cost S-Curve Percentile Total Cost 0 £ 1,268,332 5 £ 1,405,076 10 £ 1,491,898 15 £ 1,547,023 20 £ 1,599,523 25 £ 1,649,523 30 £ 1,799,523 35 £ 1,957,023 40 £ 2,122,398 45 £ 2,296,042 50 £ 2,478,368 55 £ 2,669,810 60 £ 2,870,824 65 £ 3,102,996 70 £ 3,371,154 75 £ 3,680,877 80 £ 4,038,606 85 £ 4,451,784 90 £ 4,929,005 95 £ 5,480,194 100 £ 6,116,818 QCRA: S-CURVE
  • 35. INTEGRATED COST & SCHEDULE RISK ANALYSIS (ICSRA)
  • 36. ICSRA: APPROACH • Organisational / PMO culture key • Schedule and Cost systems driven by WBS & Control Accounts • Estimating Uncertainty and Risk assigned to schedule • Schedule decomposed jointly with cost decomposition • Activities reviewed wholistically – Time, Cost, & Risk together! • Application Programme Interfaces (APIs) to reduce errors
  • 37. ICSRA: COMPONENTS Activity Duration Duration Uncertainty Time Risk Activity Cost Cost Uncertainty Cost Risk • Direct conversations and challenges • Greater understanding of Estimating Uncertainty & Risk • Accountable elements > drives ownership!
  • 38. ICSRA: JOINT CONFIDENCE LEVELS • ISSUE: QSRA & QCRA results don’t reflect combined effects. • RESULT: Better insight, more accurate estimating & forecasting.
  • 39. ICSRA: CASH FLOW • ISSUE: Cash flow forecasting is poor. • RESULT: More accurate forecasting and insight. 0 100,000 200,000 300,000 400,000 500,000 600,000 700,000 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Jan-00 Risk Cost Profile by End Date Series1 Series2
  • 40. ICSRA ASSURANCE: SCHEDULE HIERARCHY • ISSUE: Schedule incomprehensible by stakeholders, difficult for scenarios. • RESULT: Comparative assessments, additional insight. Initial Initial Design Detailed Design Procurement Construction Commissioning Handover Summary Schedule (by Phase) WBS Control Account Work Package Work Package / Activity (Key areas as required)
  • 41. ICSRA ASSURANCE: SUMMARY SCHEDULE • The Summary schedule should be high level, contain 100% of work, have all phases, key deliverables, key milestones, key undertakings, key sequences, key paths, identify key interdependent logic, tactical relationships, be sufficiently reflective, consistent, and aligned with the detailed schedule. • Challenge schedule producer with this statement > signature !! • Tip: Start with detailed Level 3-4 and look for logic across components.
  • 42. ICSRA ASSURANCE: PRAGMATIC • ISSUE: Too many risks to map to schedule. • RESULT: Pragmatic assessment. • Red risks • Red & Amber risks • Red & Amber & ‘Green Total’ risks • Risks on / near critical path • Risks on activities with low float • Highlights key areas > detailed analysis
  • 43. ICSRA: BENEFITS • Removes “risk mapping” • Drives ‘Real’ conversations • Drives accountability, engagement, behaviours • Utilises whole team, knowledge, experience • Greater understanding & awareness of drivers • Improves Change Management assessments • Matures schedule and cost estimate • Joint Confidence Levels (JCL) • Superior Budget & Cash-Flow forecasting • Enhanced Change Management & Contingency Management
  • 45. FUTURE OUTPUTS • ISSUE: Outputs don’t provide decision making information. • RESULT: Powerful decision making insights. • Most cost-effective activities (current and future) to expedite / reduce the critical path? • Which activities most likely to increase the overall cost? • Which activities most likely to increase the critical path and overall cost? • Where are the biggest cash flow periods and related values – are they achievable? • Highest Cost Path / Critical Path • Highest Labour Cost Path / Critical Path • Highest Materials Cost Path / Critical Path
  • 46. COST EFFECTIVE SCHEDULE MANAGEMENT • ISSUE: Inability to see where schedule & cost problem areas are at once. • RESULT: Powerful visualisation of key areas to focus on.
  • 47. RISK ALGORITHMS / AI • ISSUE: Bias in estimating and lack of historical insight & trending. • RESULT: Increased insight and forecasting assurance. • Uses historical information to predict risk • Can combine data across companies, industries, and countries • Sometimes just uses text to forecast • Machine learning provides continuous refinement • May not suit first-of-a-kind or unique projects
  • 48. RISK ALGORITHMS / AI • ISSUE: Bias in estimating and lack of historical insight & trending. • RESULT: Increased insight and forecasting assurance.
  • 50. CONCLUSION • Organisational Culture is key! • Schedule should ALWAYS drive the project • Decompose Schedule and Cost at the same rate – Schedule first! • No ‘bad’ simulation – an iterative, engaging, absorbing, insightful, process • Try to automate – so many potential errors doing manually • Really look at integrating your schedule, cost, and risk software using APIs • ICSRA is far more efficient, effective, & insightful, than siloed QSRAs / QCRAs • It’s a journey not a destination! EMBRACE. ENGAGE. EMPOWER.
  • 51. “THE ONLY THING NECESSARY FOR THE TRIUMPH OF COST-DRIVEN PROGRAMMES IS FOR GOOD RISK, PMO, PROJECT CONTROLS, & PLANNING PROFESSIONALS TO DO NOTHING."
  • 53. QR CODES APM EVENTS APM RISK SIG