SlideShare a Scribd company logo
1 of 13
Download to read offline
Project Development Handbook
A structured way of developing a project into reality
From idea to commitment
By
Feiko Jager MSc
©Riverlake Solutions SA
Feasibility
study
Concept
definition
Funds &
Permits
Tendering Construction Commissioning
In
operation
Project Development Handbook
Project Development Handbook
A structured way of developing a potential project into reality
Introduction
Developing a potential project is often an iterative process with a long
duration. Large delays compared to initial plans and large cost overruns
compared to optimistic estimates are frequently reasons for
disappointment and difficult decision-making. In our experience this is not
necessary. Although developing something new always has an iterative
character, a structured approach guarantees realistic plans and budgets
and accelerates decision-making. A requirement is that the used approach
is simple and practical and that it is commonly understood and accepted
by all people involved in the project.
This Project Development Handbook provides such an approach.
Limitations
This handbook has been developed primarily for the development of tank
terminals and related infrastructure like jetties and pipelines. It can
however also be applied to the development of other industrial asset
construction projects, e.g. processing plants, power plants or port
installations.
The described project development methodology can be applied to
projects with a capital expenditure between $ 25 and $ 250 million.
Smaller projects can do with a less rigorous approach whilst for larger
projects the described approach will not provide sufficient guarantees
that are required for the magnitude of required investments or impact on
society.
How to use this handbook
This handbook describes the first 4 phases for the development. It ends
with the main financial commitment that is to be made for the project:
the signature under the construction contracts.
The core of this handbook is a matrix of project development phases and
disciplines. The summary of this matrix is provided on the last pages of
the handbook.
The first pages of the handbook provide a description of the principles
behind the methodology. Then, for each phase, two pages provide a
detailed overview of all activities and deliverables of a phase. These pages
are face to face to provide an integral overview of that phase and can be
used as checklist to ensure that all required steps in a phase have been
taken.
Copyright
This handbook has been developed by Riverlake Consultancy SA. You are
not allowed to use this handbook without prior consultation with
Riverlake Consultancy SA.
I wish you success with the realization of your project!
Feiko Jager
©Riverlake Solutions SA Page 2
Methodology
The goal of developing a project is meeting the following pre-requisites:
 The required government permits
 The access to the required plot of land
 The financing of the required investment
 The commercial, financial, technical and operational feasibility
 The safe execution of the project
Reaching the above goals will be done in a structured manner by working
through a matrix of phases and disciplines.
Most disciplines have to be covered during each phase of the project to
guarantee that overlooking one of the disciplines is later reason to iterate
back to an earlier phase. In our experience this is one of the main reasons
for project delay. It is essential to complete a phase consciously prior to
continuing into the next phase. We rather spend one or a few weeks in
completing a phase properly then to discover later that we have to redo a
complete phase which could take months and a large amount of money.
The best way of reaching this way of developing a project is to look at
each step as a separate value creating investment and to make conscious
(investment) decisions for each individual step.
In the next pages we provide for each phase:
 Detailed activities that need to be carried out
 Clearly specified deliverables reflecting the result of the activities
Phases
 Phase 0: Feasibility study
 Phase 1: Concept definition
 Phase 2: Funds & Permits
 Phase 3: Tendering
 Phase 4: Construction
 Phase 5: Commissioning
 Phase 6: In operation
Disciplines
 Location
 Commercial
 Economics
 Finance & taxes
 Scope & management of change
 Permitting
 Engineering
 Procurement
 Planning
 Budget
 Project Management
 HSE
 Insurance
 Operations
 Legal
 External communication
Project Development Handbook
Phase 0: Feasibility study
‘Initiating the project’
Goal: To substantiate an idea or business opportunity
Result: Plot of land identified, basic business idea documented
Costs: 0,1 - 0,2 % of Capex
Duration: A few weeks after location is identified
Disciplines Activities Deliverables
Location Identify one or a few locations that fits the purpose of the business opportunity
well. Talk to the stakeholders (i.e. owners, authorities, neighbors) to ascertain
that they will buy-in to the business idea.
Identified location (drawing, Google Earth picture)
Commercial Describe the basic business idea and identify potential business partners and/or
customers. Quantify roughly which turnover could be generated.
Business plan (commercial part)
Economics Make a rough profitability calculation based on the turnover, cost and Capex
figures provided.
Business plan (economical part)
Finance & taxes Assess if the business idea can be financed by investigating possible funding
structures and potential financiers. Don’t forget to involve applicable tax regimes
in the equation.
Business plan (financing part)
Scope & MoC Write a first description of the functional requirements for the required facilities
and assess if the location fits these requirements. This assessment will be based
on experience figures.
Functional requirements
Permitting Identify the locally required permits and approval procedures as they will have a
large impact on the project schedule and might affect the requirements to the
facility.
Permit overview
Engineering No real engineering is required during this stage, but it will be helpful to engage
experienced engineers to guarantee accurate assumptions on especially scope,
capital expenditure (capex) and schedule.
Procurement Make a pre-selection of potential engineering companies that can provide the
conceptual engineering for the next phase. Select preferred providers, if required
by means of a tender, and prepare for a ready to sign agreement in order to
continue the project immediately when the next phase is approved.
©Riverlake Solutions SA Page 4
Planning &
progress
Make a rough schedule for the total project. At this phase it is sufficient to
estimate the duration of the phases and not of the activities within the phases.
Make a detailed schedule of the activities to be carried out during the next
phase.
 Overall project schedule (high level)
 Detailed schedule for the next phase
Budget Estimate the capex of the total project based on experience figures. This will be a
very rough estimate, typically with a 40% accuracy.
Make a detailed budget for the next phase.
 Overall project capex budget (high level)
 Detailed budget for the next phase
Project
management
Define the approach for the total project. This typically involves dividing the
project in sub-projects and the phasing of the project. Also the project
organization, both internal staff and external advisors and consultants, needs to
be defined.
Define all activities for the next phase in a detailed project plan.
Coordinate the decision-making for the approval of the next phase.
 Overall project plan
 Detailed project plan for the next phase
HSE Not applicable during this phase
Insurance Not applicable during this phase
Operations Quantify roughly what the operation of the facility would annually cost.  Operational cost estimation
Legal Not applicable during this phase
External
communication
Not applicable during this phase
This is the easiest part. Everybody with a bit of funding and some insight in the business can make plan. But out of all feasibility studies made, only 5 or 10%
make it past the next phase……….
Project Development Handbook
Phase 1: Concept definition
‘From rough idea to fixed concept’
Goal: Fixing the concept and ascertain that it is viable
Result: Clearly defined, viable concept
Costs: 0,2 - 0,4 % of Capex
Duration: 2-3 months
Disciplines Activities Deliverables
Location Engage in discussion with owners and authorities (typically the Port Authority) regarding
the lease or ownership of all required land (and water) for the erection of the facilities on
the main site but also for the marine facilities and underground connecting pipelines.
(option on) lease/ownership agreements for the main site
and other relevant sites like berths/jetties and pipeline
corridors.
Commercial Research the market and find potential launching customers to support the business
idea. Substantiate the business case with a well documented projection of expected
turnover for the first years of operation. Make scenarios, typically an expected one, an
optimistic and a pessimistic one, to test the robustness of the business plan.
 Market report
 Commercial Memorandum of Understanding with
launching customer(s)
 Turnover projection with multiple scenarios
Economics Calculate the business case based on the turnover and operational cost projections and
on the Capex estimation. Test the robustness of the business case by means of scenarios.
Control regularly the expenditure against the budget for this phase and report this in the
project progress reports.
Prepare for the next costly phases by defining the administration and cost control
procedures.
 Business case with multiple scenarios
 Project accounting set-up
Finance & taxes Define the funding structure and engage in discussion with potential financiers and
investors. Organize the funding for the next phase as the project will start to cost serious
money during the next phase.
Define the tax structure for the project execution and future operation of the facility.
 Funding structure proposal
 Funding agreements for the next phase
 Tax structure proposal
Scope & MoC Finalize the description of the functional requirements for the facility and start defining
the operational requirements. Review in detail at the end of the phase if the conceptual
design fits these requirements.
 Functional requirements description (final version)
 Operational requirements description
Permitting Make a plan that states all required activities to apply for the required permits for the
whole project.
Permitting plan
Engineering Make a conceptual design. This design typically consists of a technical description of the
facilities, a lay-out drawing, a Process Flow Diagram (PFD) of the main product pipeline
systems and a description of all required utilities.
Conceptual design consisting typically of:
 Facility description
 Lay-out
 PFD
 Utility description
©Riverlake Solutions SA Page 6
Procurement Define the contracting strategy for the construction. This is necessary as it has a profound
impact on the required level of detail of the basic design.
Make a pre-selection of potential providers of the services required for the next phases.
Select preferred providers, if required by means of a tender, and prepare for ready to
sign agreements in order to continue the project immediately when the next phase is
approved.
 Contracting strategy
 Ready to sign agreements for:
o Engineering the basic design
o The environmental impact assessment
Planning &
progress
Track regularly the progress compared to the schedule for this phase and report this in
the project progress reports.
At the end of the phase, update the high level schedule for the overall project and make a
detailed schedule for the next phase.
 Overall project schedule (update)
 Detailed schedule for next phase
Budget Update the overall Capex budget based on an engineered estimate which is typically 25%
accurate at this stage.
Make a detailed budget for the next phase.
 Overall project Capex budget (update)
 Detailed budget phase 3
Project
management
Organize a kick-off meeting for this phase of the project with all participants in the
project. Coordinate all activities as specified in the project plan of this phase and make
regular progress reports. Identify the risks associated with the project. Define all activities
for the next phase and update the overall project plan according the results of this phase.
Finally coordinate the decision-making for the approval of the next phase.
 Regular (monthly) progress reports
 Risk assessment report with initial risk register
 Detailed project plan phase 2
 Overall project plan update
HSE Identify the main safety hazards of the project HAZID report
Insurance Not applicable during this phase
Operations Make a high level organization scheme and estimate the annual operational costs  High level organization scheme
 Operational cost projection
Legal Investigate the local legal framework for the proposed tax structure.
Review the legal aspects of the agreements for the next phase.
External
communication
Make a PR plan for the project and ask for engineered images of the facility.  Project PR plan
 3D images of the facility
The key to this phase is to find and secure the location, the business and the financing for the project. All three should come simultaneously in order to secure
the funding for the next phase. Without location no business, without business no financing and without financing no location…………
Project Development Handbook
Phase 2: Funds & Permits
‘Committing the stakeholders’
Goal: Fix the required funding and permits
Result: Committed funding & authorized permits
Costs: 0,5 – 1,5 % of Capex
Duration: 6-18 months
Disciplines Activities Deliverables
Location Continue negotiations for all required land lease or ownership contracts. None
Commercial Continue the activities from the previous phase. None
Economics Administer the costs for this phase and control the costs against the budget for
this phase.
Regular reporting of costs against the budget for this
phase.
Finance & taxes Prepare for required funding requests by preparing and discussing a draft
investment proposal. Prepare an initial cash-flow prognosis. Discuss the
investment proposal with investors and capture the results in draft funding
agreements.
 Draft investment proposal documentation
 Initial cash flow projection
 Draft funding agreements
Scope & MoC Finalize the operational requirements for the facility, including maintainability,
automation requirements and the requirements for office space.
Discuss and document how to handle scope changes during the next phases of
the project.
 Operational requirements document
 Management of Change procedure
Permitting Have the environmental impact assessment conducted (assuming that is
required). Maybe other assessments need to be done as well. Compile an
application package for the environmental permit, hand it in to the authorities
and follow-up thoroughly any questions and/or design changes that might need
response in order to obtain the permit as quickly as possible.
 Environmental impact assessment report
 Environmental permit application package
 Environmental permit
Engineering Have a basic design made by a competent engineering firm. Have the design
thoroughly reviewed from the perspective of the other disciplines, especially on
functional and operational requirements and from the permitting perspective.
 Basic design package.
Procurement Start by compiling a long-list of potential contractors that could fit the
contracting strategy as defined in the previous phase. Fathom the interest of
these contractor by sending them a Request for Information (RFI). Make a short-
list of preferred contractors based on an evaluation of the received information.
 Contractor long list
 RFI (Request for Information)
 RFI evaluation document
 Contractor short list(s)
 List of long-lead items
©Riverlake Solutions SA Page 8
Planning &
progress
Monitor the progress of this phase regularly and report this to the stakeholders.
At the end of the phase, make a detailed schedule for the next phase and update
the overall project schedule accordingly.
 Regular progress report against phase 2
schedule
 Overall project schedule (update)
 Detailed schedule phase 3
Budget Update the Capex budget based on a 10% accurate engineering calculation.
Make a detailed budget for the next phase 3
 Overall project Capex budget (update)
 Detailed budget phase 3
Project
management
Make a detailed plan for the next phase and update the overall project plan
accordingly.
Manage the existing and new risks thoroughly, and keep your internal
stakeholders well informed. Staff next phase (contracting management)
 Overall project plan (update)
 Detailed project plan phase 3
 Update the project risk register
 Monthly progress reports
HSE Conduct a HAZOP study on the basic design when it reaches completion.
Define the way to secure construction safety. The resulting documents will be
part of the contracts with the contractors.
 HAZOP report
 Construction safety goals, KPI’s and procedures
Insurance Not applicable during this phase
Operations Define the organization that will operate the terminal as this becomes necessary
for the design of the office and other personnel facilities, but also to be able to
estimate operational personnel costs.
Conduct an operability review and maintainability review on the basic design
when it reaches completion
 Operations organization chart
 Operability review report
 Maintainability review report
Legal Set-up the required local legal entities Inaugurated legal entities
External
communication
Execute the PR activities as defined in the PR plan to support especially the
permit application.
 Project web site
 Project presentation
 Leaflets etc.
The project starts costing serious money because making a good basic design and conducting an environmental impact assessment requires many
engineering and consultancy hours. A solid project approach is required, especially to stick to the time schedule………
Project Development Handbook
Phase 3: Tendering
‘Finding the right contractors’
Goal: Negotiating value for money construction contracts
Result: Signed construction contract(s)
Costs: 0,5 – 1 % of Capex
Duration: 3-6 months
Disciplines Activities Deliverables
Location Finalize the negotiations for all required land lease or ownership contracts in
order to secure access to the site prior to start construction.
 Signed lease/ownership contracts.
Commercial Finalize the negotiations with launching customers. The contracts need to be
formalized in order to be accepted by the financiers.
Update the turnover projection based on the figures from the launching
contracts.
 Signed customer contracts
 Turnover projection, updated
Economics Review the construction contracts from a financial perspective. Update the
financial business case with the latest Capex budget, the commercial turnover
projection and the Operational expenditure budget.
approval of contracts, PO’s, cost control
 Contractor financial evaluation document
 Regular reporting of costs against the budget for
this phase.
 Business case, update.
Finance & taxes Update cash flow prognosis based on offers, sign funding agreements  Cash flow prognosis, updated
 Funding agreements
Scope & MoC Start the Management of Change (MoC) procedure that was defined during the
previous phase.
 Change request documents
Permitting Apply for construction permits with an application package that is derived from
the basic design that was made during the previous phase.
 Construction permit application
Engineering Have the changes out of the MoC procedure designed and insert these changes
in the permitting and tendering processes.
 Design change specifications
Procurement Write the Request for Proposal (RFP) and send it to the contractors that were
selected during the previous phase. After receiving the proposals from the
contractors, evaluate them and decide on which one to continue with. Then do
the final negotiations and sign the construction contract (s). Do not forget to
procure the long-lead items.
 Request for Proposal
 Tender evaluation document
 Signed construction contract(s)
 Long lead item specifications
©Riverlake Solutions SA Page 10
Planning &
progress
Monitor the progress of this phase against the schedule made during the
previous phase. Make a detailed schedule for the next phase based on the
construction planning provided by the selected contractor. Update the overall
schedule accordingly. update overall schedule.
 Regular progress report against schedule phase
3
 Detailed schedule phase 4
 Overall schedule, update
Budget Update the Capex budget based on the prices provided by the selected
contractor. Do not forget to include all other costs that are required for the
upcoming phases.
 Overall project Capex budget , update
 Budget phase 4
Project
management
Make a detailed plan for the next phase and update the overall project plan
accordingly.
Manage the existing and new risks thoroughly, and keep your internal
stakeholders well informed. Staff the next phase (construction management).
 Overall project plan (update)
 Detailed project plan phase 3
 Update the project risk register
 Monthly progress reports
HSE Conduct a safety evaluation of the proposals from the contractors.  Contractor safety evaluation document
Insurance Review the contractors’ CAR insurance.
Operations Define who of the future operational staff should already be hired to be in place
during construction. Define the detailed Operational expenditure (Opex) budget.
Legal Review the contract terms that will be specified in the RFP and then again of the
final construction contract.
 Legal contract review document
External
communication
Execute the PR activities as defined in the PR plan to support especially the start
of construction.
 Regular website update
 External stakeholder meetings
At the end of this phase you finally know what the project will actually cost exactly. Time has come to commit the majority of the Capex by signing
construction contracts. Thus everything has to be in place: the lease of the land, all required permits, contracts with users of the facility and last but not least
the total funding………Construction can commence!
Project Development Handbook
Summary
Disciplines: Phase 0: Feasibility study Phase 1: Concept definition Phase 2: Funds & Permits Phase 2: Funds & Permits
Location Identify the location Secure the site (lease/buy) - Sign the lease/ownership
contracts
Commercial Define the future business Research the market - Secure part of the future
turnover
Economics Estimate the turnover Calculate the business case Start controlling the costs Do a final update of the
business case
Finance & taxes Align a financing structure Engage funding partners Draft an investment
proposal
Sign the funding
agreements
Scope & Management of
change
Describe the functional
requirements
Finalize the functional
requirements
State the detailed
operational requirements
Start the management of
change procedure
Permitting Identify the required permits Make a permitting plan Assess the environmental
impact
Apply for the construction
permit
Engineering Make a first CAPEX estimate Design a technical concept Engineer a basic design Design the requested
changes
Procurement Select an engineering
provider
Agree on a contracting
strategy
Pre-qualify the
contractors
Tender the construction
contracts
Planning & progress Make an overall schedule Schedule the next phase in
detail
Start monitoring the
progress
Schedule the construction in
detail
Budget Budget the next phase in
detail
Calculate a 25% accurate
budget
Calculate a 10% accurate
budget
Finalize the budget
Project Management Write the project approach
and staff the project
Assess the project risks Bring structure in the
project
Prepare for construction
HSE - Identify the main safety
hazards
Conduct a HAZOP on the
design
Evaluate contractor safety
Insurance - - - Ensure construction
insurance
Operations Quantify the operational costs Prepare a draft organization
scheme
Review the
maintainability
Prepare for first operational
staff hire
Legal - Review the legal entity set-up Inaugurate the legal
entities
Review construction &
funding contracts
External communication - Make a PR plan Present the project Conduct external
stakeholder meetings
©Riverlake Solutions SA Page 12
Few weeks
Phase 0: Feasibility study
Phase 1: Concept definition
Phase 2: Funds & Permits
Phase 3: Tendering
Phase 4: Construction
Phase 5: Commissioning
Phase 6: In operation
2-3 months
6-18 months
3-6 months
½-2 years
1-3 months
Total duration: 1,5 – 4,5 years
SCHEDULE
Typical Time Schedule

More Related Content

Similar to Project Development Handbook presentation

Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016L Douglas Sargent Jr
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
Corporate project management model
Corporate project management modelCorporate project management model
Corporate project management modelLatte Media
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementCatherine Bendell
 
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE  Generally describes the proje.docxPROJECT SCOPE STATEMENTPURPOSE  Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docxtarifarmarie
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxbriancrawford30935
 
Project Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxProject Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxstilliegeorgiana
 
Pm evaluationand selection1
Pm evaluationand selection1Pm evaluationand selection1
Pm evaluationand selection1eshang0904
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef samNermeen gerges
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and controlJanak Singh Chauhan
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overviewcford1973
 
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxProject Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxstilliegeorgiana
 

Similar to Project Development Handbook presentation (20)

Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
Corporate project management model
Corporate project management modelCorporate project management model
Corporate project management model
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
 
Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17 Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17
 
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE  Generally describes the proje.docxPROJECT SCOPE STATEMENTPURPOSE  Generally describes the proje.docx
PROJECT SCOPE STATEMENTPURPOSE Generally describes the proje.docx
 
Measuring project success
Measuring project successMeasuring project success
Measuring project success
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
 
Project Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docxProject Charter V 2.0Project CharterProjec.docx
Project Charter V 2.0Project CharterProjec.docx
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
Pm evaluationand selection1
Pm evaluationand selection1Pm evaluationand selection1
Pm evaluationand selection1
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Resume - Nermeen Atef sam
Resume - Nermeen Atef samResume - Nermeen Atef sam
Resume - Nermeen Atef sam
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and control
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docxProject Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
Project Charter Scoring GuideCRITERIA NON-PERFORMANCE BASI.docx
 
Project report
Project reportProject report
Project report
 

More from drs. ing. George van Bommel MBE, BSc

More from drs. ing. George van Bommel MBE, BSc (20)

haldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup documenthaldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup document
 
La Luz Port Nautical Chart detailed information
La Luz Port Nautical Chart detailed informationLa Luz Port Nautical Chart detailed information
La Luz Port Nautical Chart detailed information
 
RivSol_article_2_-_Engineering_process.pdf
RivSol_article_2_-_Engineering_process.pdfRivSol_article_2_-_Engineering_process.pdf
RivSol_article_2_-_Engineering_process.pdf
 
bunker fuels ISO specs 8217 2010.pdf
bunker fuels ISO specs 8217 2010.pdfbunker fuels ISO specs 8217 2010.pdf
bunker fuels ISO specs 8217 2010.pdf
 
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdftopsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
 
Commissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdfCommissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdf
 
Large_Pellet_Plants.pdf
Large_Pellet_Plants.pdfLarge_Pellet_Plants.pdf
Large_Pellet_Plants.pdf
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Bunker fuels iso specs 8217 2010
Bunker fuels iso specs 8217 2010Bunker fuels iso specs 8217 2010
Bunker fuels iso specs 8217 2010
 
Project development handbook rl website
Project development handbook rl websiteProject development handbook rl website
Project development handbook rl website
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Training program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukhTraining program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukh
 
VMT 11 - Artikel BioValGroup
VMT 11 - Artikel BioValGroupVMT 11 - Artikel BioValGroup
VMT 11 - Artikel BioValGroup
 
Fertilizer Product Quality GVB
Fertilizer Product Quality GVBFertilizer Product Quality GVB
Fertilizer Product Quality GVB
 
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology 2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
 
Pöyry is biocoal_a_bioenergy_game_changer
Pöyry is biocoal_a_bioenergy_game_changerPöyry is biocoal_a_bioenergy_game_changer
Pöyry is biocoal_a_bioenergy_game_changer
 
Iea bioenergy t32_torrefaction_review (overview of technologies)
Iea bioenergy t32_torrefaction_review (overview of technologies)Iea bioenergy t32_torrefaction_review (overview of technologies)
Iea bioenergy t32_torrefaction_review (overview of technologies)
 
Fertilizer manual (unido and ifdc)
Fertilizer manual (unido and ifdc)Fertilizer manual (unido and ifdc)
Fertilizer manual (unido and ifdc)
 
Biomass tar properties
Biomass tar propertiesBiomass tar properties
Biomass tar properties
 
Ash correlations on hhv
Ash correlations on hhvAsh correlations on hhv
Ash correlations on hhv
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Project Development Handbook presentation

  • 1. Project Development Handbook A structured way of developing a project into reality From idea to commitment By Feiko Jager MSc ©Riverlake Solutions SA Feasibility study Concept definition Funds & Permits Tendering Construction Commissioning In operation
  • 2. Project Development Handbook Project Development Handbook A structured way of developing a potential project into reality Introduction Developing a potential project is often an iterative process with a long duration. Large delays compared to initial plans and large cost overruns compared to optimistic estimates are frequently reasons for disappointment and difficult decision-making. In our experience this is not necessary. Although developing something new always has an iterative character, a structured approach guarantees realistic plans and budgets and accelerates decision-making. A requirement is that the used approach is simple and practical and that it is commonly understood and accepted by all people involved in the project. This Project Development Handbook provides such an approach. Limitations This handbook has been developed primarily for the development of tank terminals and related infrastructure like jetties and pipelines. It can however also be applied to the development of other industrial asset construction projects, e.g. processing plants, power plants or port installations. The described project development methodology can be applied to projects with a capital expenditure between $ 25 and $ 250 million. Smaller projects can do with a less rigorous approach whilst for larger projects the described approach will not provide sufficient guarantees that are required for the magnitude of required investments or impact on society. How to use this handbook This handbook describes the first 4 phases for the development. It ends with the main financial commitment that is to be made for the project: the signature under the construction contracts. The core of this handbook is a matrix of project development phases and disciplines. The summary of this matrix is provided on the last pages of the handbook. The first pages of the handbook provide a description of the principles behind the methodology. Then, for each phase, two pages provide a detailed overview of all activities and deliverables of a phase. These pages are face to face to provide an integral overview of that phase and can be used as checklist to ensure that all required steps in a phase have been taken. Copyright This handbook has been developed by Riverlake Consultancy SA. You are not allowed to use this handbook without prior consultation with Riverlake Consultancy SA. I wish you success with the realization of your project! Feiko Jager
  • 3. ©Riverlake Solutions SA Page 2 Methodology The goal of developing a project is meeting the following pre-requisites:  The required government permits  The access to the required plot of land  The financing of the required investment  The commercial, financial, technical and operational feasibility  The safe execution of the project Reaching the above goals will be done in a structured manner by working through a matrix of phases and disciplines. Most disciplines have to be covered during each phase of the project to guarantee that overlooking one of the disciplines is later reason to iterate back to an earlier phase. In our experience this is one of the main reasons for project delay. It is essential to complete a phase consciously prior to continuing into the next phase. We rather spend one or a few weeks in completing a phase properly then to discover later that we have to redo a complete phase which could take months and a large amount of money. The best way of reaching this way of developing a project is to look at each step as a separate value creating investment and to make conscious (investment) decisions for each individual step. In the next pages we provide for each phase:  Detailed activities that need to be carried out  Clearly specified deliverables reflecting the result of the activities Phases  Phase 0: Feasibility study  Phase 1: Concept definition  Phase 2: Funds & Permits  Phase 3: Tendering  Phase 4: Construction  Phase 5: Commissioning  Phase 6: In operation Disciplines  Location  Commercial  Economics  Finance & taxes  Scope & management of change  Permitting  Engineering  Procurement  Planning  Budget  Project Management  HSE  Insurance  Operations  Legal  External communication
  • 4. Project Development Handbook Phase 0: Feasibility study ‘Initiating the project’ Goal: To substantiate an idea or business opportunity Result: Plot of land identified, basic business idea documented Costs: 0,1 - 0,2 % of Capex Duration: A few weeks after location is identified Disciplines Activities Deliverables Location Identify one or a few locations that fits the purpose of the business opportunity well. Talk to the stakeholders (i.e. owners, authorities, neighbors) to ascertain that they will buy-in to the business idea. Identified location (drawing, Google Earth picture) Commercial Describe the basic business idea and identify potential business partners and/or customers. Quantify roughly which turnover could be generated. Business plan (commercial part) Economics Make a rough profitability calculation based on the turnover, cost and Capex figures provided. Business plan (economical part) Finance & taxes Assess if the business idea can be financed by investigating possible funding structures and potential financiers. Don’t forget to involve applicable tax regimes in the equation. Business plan (financing part) Scope & MoC Write a first description of the functional requirements for the required facilities and assess if the location fits these requirements. This assessment will be based on experience figures. Functional requirements Permitting Identify the locally required permits and approval procedures as they will have a large impact on the project schedule and might affect the requirements to the facility. Permit overview Engineering No real engineering is required during this stage, but it will be helpful to engage experienced engineers to guarantee accurate assumptions on especially scope, capital expenditure (capex) and schedule. Procurement Make a pre-selection of potential engineering companies that can provide the conceptual engineering for the next phase. Select preferred providers, if required by means of a tender, and prepare for a ready to sign agreement in order to continue the project immediately when the next phase is approved.
  • 5. ©Riverlake Solutions SA Page 4 Planning & progress Make a rough schedule for the total project. At this phase it is sufficient to estimate the duration of the phases and not of the activities within the phases. Make a detailed schedule of the activities to be carried out during the next phase.  Overall project schedule (high level)  Detailed schedule for the next phase Budget Estimate the capex of the total project based on experience figures. This will be a very rough estimate, typically with a 40% accuracy. Make a detailed budget for the next phase.  Overall project capex budget (high level)  Detailed budget for the next phase Project management Define the approach for the total project. This typically involves dividing the project in sub-projects and the phasing of the project. Also the project organization, both internal staff and external advisors and consultants, needs to be defined. Define all activities for the next phase in a detailed project plan. Coordinate the decision-making for the approval of the next phase.  Overall project plan  Detailed project plan for the next phase HSE Not applicable during this phase Insurance Not applicable during this phase Operations Quantify roughly what the operation of the facility would annually cost.  Operational cost estimation Legal Not applicable during this phase External communication Not applicable during this phase This is the easiest part. Everybody with a bit of funding and some insight in the business can make plan. But out of all feasibility studies made, only 5 or 10% make it past the next phase……….
  • 6. Project Development Handbook Phase 1: Concept definition ‘From rough idea to fixed concept’ Goal: Fixing the concept and ascertain that it is viable Result: Clearly defined, viable concept Costs: 0,2 - 0,4 % of Capex Duration: 2-3 months Disciplines Activities Deliverables Location Engage in discussion with owners and authorities (typically the Port Authority) regarding the lease or ownership of all required land (and water) for the erection of the facilities on the main site but also for the marine facilities and underground connecting pipelines. (option on) lease/ownership agreements for the main site and other relevant sites like berths/jetties and pipeline corridors. Commercial Research the market and find potential launching customers to support the business idea. Substantiate the business case with a well documented projection of expected turnover for the first years of operation. Make scenarios, typically an expected one, an optimistic and a pessimistic one, to test the robustness of the business plan.  Market report  Commercial Memorandum of Understanding with launching customer(s)  Turnover projection with multiple scenarios Economics Calculate the business case based on the turnover and operational cost projections and on the Capex estimation. Test the robustness of the business case by means of scenarios. Control regularly the expenditure against the budget for this phase and report this in the project progress reports. Prepare for the next costly phases by defining the administration and cost control procedures.  Business case with multiple scenarios  Project accounting set-up Finance & taxes Define the funding structure and engage in discussion with potential financiers and investors. Organize the funding for the next phase as the project will start to cost serious money during the next phase. Define the tax structure for the project execution and future operation of the facility.  Funding structure proposal  Funding agreements for the next phase  Tax structure proposal Scope & MoC Finalize the description of the functional requirements for the facility and start defining the operational requirements. Review in detail at the end of the phase if the conceptual design fits these requirements.  Functional requirements description (final version)  Operational requirements description Permitting Make a plan that states all required activities to apply for the required permits for the whole project. Permitting plan Engineering Make a conceptual design. This design typically consists of a technical description of the facilities, a lay-out drawing, a Process Flow Diagram (PFD) of the main product pipeline systems and a description of all required utilities. Conceptual design consisting typically of:  Facility description  Lay-out  PFD  Utility description
  • 7. ©Riverlake Solutions SA Page 6 Procurement Define the contracting strategy for the construction. This is necessary as it has a profound impact on the required level of detail of the basic design. Make a pre-selection of potential providers of the services required for the next phases. Select preferred providers, if required by means of a tender, and prepare for ready to sign agreements in order to continue the project immediately when the next phase is approved.  Contracting strategy  Ready to sign agreements for: o Engineering the basic design o The environmental impact assessment Planning & progress Track regularly the progress compared to the schedule for this phase and report this in the project progress reports. At the end of the phase, update the high level schedule for the overall project and make a detailed schedule for the next phase.  Overall project schedule (update)  Detailed schedule for next phase Budget Update the overall Capex budget based on an engineered estimate which is typically 25% accurate at this stage. Make a detailed budget for the next phase.  Overall project Capex budget (update)  Detailed budget phase 3 Project management Organize a kick-off meeting for this phase of the project with all participants in the project. Coordinate all activities as specified in the project plan of this phase and make regular progress reports. Identify the risks associated with the project. Define all activities for the next phase and update the overall project plan according the results of this phase. Finally coordinate the decision-making for the approval of the next phase.  Regular (monthly) progress reports  Risk assessment report with initial risk register  Detailed project plan phase 2  Overall project plan update HSE Identify the main safety hazards of the project HAZID report Insurance Not applicable during this phase Operations Make a high level organization scheme and estimate the annual operational costs  High level organization scheme  Operational cost projection Legal Investigate the local legal framework for the proposed tax structure. Review the legal aspects of the agreements for the next phase. External communication Make a PR plan for the project and ask for engineered images of the facility.  Project PR plan  3D images of the facility The key to this phase is to find and secure the location, the business and the financing for the project. All three should come simultaneously in order to secure the funding for the next phase. Without location no business, without business no financing and without financing no location…………
  • 8. Project Development Handbook Phase 2: Funds & Permits ‘Committing the stakeholders’ Goal: Fix the required funding and permits Result: Committed funding & authorized permits Costs: 0,5 – 1,5 % of Capex Duration: 6-18 months Disciplines Activities Deliverables Location Continue negotiations for all required land lease or ownership contracts. None Commercial Continue the activities from the previous phase. None Economics Administer the costs for this phase and control the costs against the budget for this phase. Regular reporting of costs against the budget for this phase. Finance & taxes Prepare for required funding requests by preparing and discussing a draft investment proposal. Prepare an initial cash-flow prognosis. Discuss the investment proposal with investors and capture the results in draft funding agreements.  Draft investment proposal documentation  Initial cash flow projection  Draft funding agreements Scope & MoC Finalize the operational requirements for the facility, including maintainability, automation requirements and the requirements for office space. Discuss and document how to handle scope changes during the next phases of the project.  Operational requirements document  Management of Change procedure Permitting Have the environmental impact assessment conducted (assuming that is required). Maybe other assessments need to be done as well. Compile an application package for the environmental permit, hand it in to the authorities and follow-up thoroughly any questions and/or design changes that might need response in order to obtain the permit as quickly as possible.  Environmental impact assessment report  Environmental permit application package  Environmental permit Engineering Have a basic design made by a competent engineering firm. Have the design thoroughly reviewed from the perspective of the other disciplines, especially on functional and operational requirements and from the permitting perspective.  Basic design package. Procurement Start by compiling a long-list of potential contractors that could fit the contracting strategy as defined in the previous phase. Fathom the interest of these contractor by sending them a Request for Information (RFI). Make a short- list of preferred contractors based on an evaluation of the received information.  Contractor long list  RFI (Request for Information)  RFI evaluation document  Contractor short list(s)  List of long-lead items
  • 9. ©Riverlake Solutions SA Page 8 Planning & progress Monitor the progress of this phase regularly and report this to the stakeholders. At the end of the phase, make a detailed schedule for the next phase and update the overall project schedule accordingly.  Regular progress report against phase 2 schedule  Overall project schedule (update)  Detailed schedule phase 3 Budget Update the Capex budget based on a 10% accurate engineering calculation. Make a detailed budget for the next phase 3  Overall project Capex budget (update)  Detailed budget phase 3 Project management Make a detailed plan for the next phase and update the overall project plan accordingly. Manage the existing and new risks thoroughly, and keep your internal stakeholders well informed. Staff next phase (contracting management)  Overall project plan (update)  Detailed project plan phase 3  Update the project risk register  Monthly progress reports HSE Conduct a HAZOP study on the basic design when it reaches completion. Define the way to secure construction safety. The resulting documents will be part of the contracts with the contractors.  HAZOP report  Construction safety goals, KPI’s and procedures Insurance Not applicable during this phase Operations Define the organization that will operate the terminal as this becomes necessary for the design of the office and other personnel facilities, but also to be able to estimate operational personnel costs. Conduct an operability review and maintainability review on the basic design when it reaches completion  Operations organization chart  Operability review report  Maintainability review report Legal Set-up the required local legal entities Inaugurated legal entities External communication Execute the PR activities as defined in the PR plan to support especially the permit application.  Project web site  Project presentation  Leaflets etc. The project starts costing serious money because making a good basic design and conducting an environmental impact assessment requires many engineering and consultancy hours. A solid project approach is required, especially to stick to the time schedule………
  • 10. Project Development Handbook Phase 3: Tendering ‘Finding the right contractors’ Goal: Negotiating value for money construction contracts Result: Signed construction contract(s) Costs: 0,5 – 1 % of Capex Duration: 3-6 months Disciplines Activities Deliverables Location Finalize the negotiations for all required land lease or ownership contracts in order to secure access to the site prior to start construction.  Signed lease/ownership contracts. Commercial Finalize the negotiations with launching customers. The contracts need to be formalized in order to be accepted by the financiers. Update the turnover projection based on the figures from the launching contracts.  Signed customer contracts  Turnover projection, updated Economics Review the construction contracts from a financial perspective. Update the financial business case with the latest Capex budget, the commercial turnover projection and the Operational expenditure budget. approval of contracts, PO’s, cost control  Contractor financial evaluation document  Regular reporting of costs against the budget for this phase.  Business case, update. Finance & taxes Update cash flow prognosis based on offers, sign funding agreements  Cash flow prognosis, updated  Funding agreements Scope & MoC Start the Management of Change (MoC) procedure that was defined during the previous phase.  Change request documents Permitting Apply for construction permits with an application package that is derived from the basic design that was made during the previous phase.  Construction permit application Engineering Have the changes out of the MoC procedure designed and insert these changes in the permitting and tendering processes.  Design change specifications Procurement Write the Request for Proposal (RFP) and send it to the contractors that were selected during the previous phase. After receiving the proposals from the contractors, evaluate them and decide on which one to continue with. Then do the final negotiations and sign the construction contract (s). Do not forget to procure the long-lead items.  Request for Proposal  Tender evaluation document  Signed construction contract(s)  Long lead item specifications
  • 11. ©Riverlake Solutions SA Page 10 Planning & progress Monitor the progress of this phase against the schedule made during the previous phase. Make a detailed schedule for the next phase based on the construction planning provided by the selected contractor. Update the overall schedule accordingly. update overall schedule.  Regular progress report against schedule phase 3  Detailed schedule phase 4  Overall schedule, update Budget Update the Capex budget based on the prices provided by the selected contractor. Do not forget to include all other costs that are required for the upcoming phases.  Overall project Capex budget , update  Budget phase 4 Project management Make a detailed plan for the next phase and update the overall project plan accordingly. Manage the existing and new risks thoroughly, and keep your internal stakeholders well informed. Staff the next phase (construction management).  Overall project plan (update)  Detailed project plan phase 3  Update the project risk register  Monthly progress reports HSE Conduct a safety evaluation of the proposals from the contractors.  Contractor safety evaluation document Insurance Review the contractors’ CAR insurance. Operations Define who of the future operational staff should already be hired to be in place during construction. Define the detailed Operational expenditure (Opex) budget. Legal Review the contract terms that will be specified in the RFP and then again of the final construction contract.  Legal contract review document External communication Execute the PR activities as defined in the PR plan to support especially the start of construction.  Regular website update  External stakeholder meetings At the end of this phase you finally know what the project will actually cost exactly. Time has come to commit the majority of the Capex by signing construction contracts. Thus everything has to be in place: the lease of the land, all required permits, contracts with users of the facility and last but not least the total funding………Construction can commence!
  • 12. Project Development Handbook Summary Disciplines: Phase 0: Feasibility study Phase 1: Concept definition Phase 2: Funds & Permits Phase 2: Funds & Permits Location Identify the location Secure the site (lease/buy) - Sign the lease/ownership contracts Commercial Define the future business Research the market - Secure part of the future turnover Economics Estimate the turnover Calculate the business case Start controlling the costs Do a final update of the business case Finance & taxes Align a financing structure Engage funding partners Draft an investment proposal Sign the funding agreements Scope & Management of change Describe the functional requirements Finalize the functional requirements State the detailed operational requirements Start the management of change procedure Permitting Identify the required permits Make a permitting plan Assess the environmental impact Apply for the construction permit Engineering Make a first CAPEX estimate Design a technical concept Engineer a basic design Design the requested changes Procurement Select an engineering provider Agree on a contracting strategy Pre-qualify the contractors Tender the construction contracts Planning & progress Make an overall schedule Schedule the next phase in detail Start monitoring the progress Schedule the construction in detail Budget Budget the next phase in detail Calculate a 25% accurate budget Calculate a 10% accurate budget Finalize the budget Project Management Write the project approach and staff the project Assess the project risks Bring structure in the project Prepare for construction HSE - Identify the main safety hazards Conduct a HAZOP on the design Evaluate contractor safety Insurance - - - Ensure construction insurance Operations Quantify the operational costs Prepare a draft organization scheme Review the maintainability Prepare for first operational staff hire Legal - Review the legal entity set-up Inaugurate the legal entities Review construction & funding contracts External communication - Make a PR plan Present the project Conduct external stakeholder meetings
  • 13. ©Riverlake Solutions SA Page 12 Few weeks Phase 0: Feasibility study Phase 1: Concept definition Phase 2: Funds & Permits Phase 3: Tendering Phase 4: Construction Phase 5: Commissioning Phase 6: In operation 2-3 months 6-18 months 3-6 months ½-2 years 1-3 months Total duration: 1,5 – 4,5 years SCHEDULE Typical Time Schedule