Name Muhammad Usman
Roll No 16IT-22
TeacherName Mam-Rafia Naz Memon
SubjectName SPM
Tasks Completed List
Create Project Charter
Work Breakdown Structure
Work Breakdown Structures Dictionary
Create Gantt chart
Create Network Diagram
Create Miles Stone
Create Dependence
Create Resource Sheet
PROJECT CHARTER
Project Tittle: Library Management System.
Project Authorizing Date: 1st
Feb.
Project Start Date: 30 May.
Project Finished Date: 30 Aug.
Project Manager: Muhammad Usman.
Key Schedule: Complete firstversion of softwareby 1st
Feb. Complete the product
version of software 1st
August.
PROJECT OBJECTIVES:
Theobjectiveof LibraryManagementSystemis to providethe
easiness to students or visitors that they can easily take/find the book according to
their choice and read it in the better way. It’s the responsibility of Library
Management Systemthat they providesuch a peaceful environmentthateveryone
learn without disturbance. The firstcharter for the project and the objectives is to
complete the first version of the software for the instrument in 6 month, also
design the project within given constraints.
MAIN PROJECT SUCCESS CRITERIA:
The software must meet all the specification be through
tested and be completed on time. The CEO will formally approvethe project with
advice from other key stack holder.
ROLES & RESPOBSIBILITIES:
Name Role Position email
M.Usman Sponsor CEO khan@gmail.com
Baber Project Manager GM baber@gmail.com
Faisal Team Member Programmer faisal@gmail.com
Junaid Team Member Quality Tester junaid@gmail.com
Sign of Section:
M.usman
Baber
Faisal
Junaid
COMMENTS:
We worked on this project very carefully and we choose such team
members that are expert in their fields, we try to give our best that this project
fulfill user requirements without any difficulties.
WBS DICTIONARY
ID WBS Task Name Description Duration Start End
1 1.0 Library
management
System
Library
Management
System is a
software to
manage, set &
easily deal with
the people
90 days 1-8-18 31-10-18
1.1 Get
Requirement
about Software
Requirement is
basically a wish
of the user that
this software
must have this
type of function
15 Days 1-8-18 15-8-18
1.2 Scope of
Project
Scope of the
project must be
clear for both
developer and
stake holder
7 Days 16-8-18 23-8-18
1.3 Contract sign &
agreement
Before start to
work or
implement the
software
requirement it
is must to sign
contract for
delivery
1 Days 24-8-18 25-8-18
2 2.0 Design &
development
This is process is
necessary,
because design
must be user
friendly that
user understand
easily so for this
first make a
20 Days 25-8-18 14-9-18
prototype to
check the user if
user satisfy then
go to next step
2.1 Front-End
design
Front end
design in such a
way that user
learn easily all
necessary info
put on this
15 Days 10-9-18 25-9-18
2.2 Administrative
design
This is for
Admin, through
this it control
the complete
software
5 Days 26-9-18 1-10-18
2.3 Functional
modules design
Functional
module design
includes serials
management
and standards
integration
5 Days 2-10-18 7-10-18
3 3.0 Documentation
of the software
Documentation
is the most
important part
to develop a
software, it
involves
everything in
document form
about software
14 Days 8-10-18 22-10-18
4 4.0 Finalization of
the software
After complete
the every step
successfully, itis
important that
test the
software again
by some testing
8 Days 23-10-18 31-10-18
method like unit
testing, system
testing, quality
testing etc for
satisfactory

Project Charter in SPM

  • 1.
    Name Muhammad Usman RollNo 16IT-22 TeacherName Mam-Rafia Naz Memon SubjectName SPM
  • 2.
    Tasks Completed List CreateProject Charter Work Breakdown Structure Work Breakdown Structures Dictionary Create Gantt chart Create Network Diagram Create Miles Stone Create Dependence Create Resource Sheet
  • 3.
    PROJECT CHARTER Project Tittle:Library Management System. Project Authorizing Date: 1st Feb. Project Start Date: 30 May. Project Finished Date: 30 Aug. Project Manager: Muhammad Usman. Key Schedule: Complete firstversion of softwareby 1st Feb. Complete the product version of software 1st August. PROJECT OBJECTIVES: Theobjectiveof LibraryManagementSystemis to providethe easiness to students or visitors that they can easily take/find the book according to their choice and read it in the better way. It’s the responsibility of Library Management Systemthat they providesuch a peaceful environmentthateveryone learn without disturbance. The firstcharter for the project and the objectives is to complete the first version of the software for the instrument in 6 month, also design the project within given constraints. MAIN PROJECT SUCCESS CRITERIA: The software must meet all the specification be through tested and be completed on time. The CEO will formally approvethe project with advice from other key stack holder. ROLES & RESPOBSIBILITIES: Name Role Position email M.Usman Sponsor CEO khan@gmail.com Baber Project Manager GM baber@gmail.com Faisal Team Member Programmer faisal@gmail.com
  • 4.
    Junaid Team MemberQuality Tester junaid@gmail.com Sign of Section: M.usman Baber Faisal Junaid COMMENTS: We worked on this project very carefully and we choose such team members that are expert in their fields, we try to give our best that this project fulfill user requirements without any difficulties.
  • 5.
    WBS DICTIONARY ID WBSTask Name Description Duration Start End 1 1.0 Library management System Library Management System is a software to manage, set & easily deal with the people 90 days 1-8-18 31-10-18 1.1 Get Requirement about Software Requirement is basically a wish of the user that this software must have this type of function 15 Days 1-8-18 15-8-18 1.2 Scope of Project Scope of the project must be clear for both developer and stake holder 7 Days 16-8-18 23-8-18 1.3 Contract sign & agreement Before start to work or implement the software requirement it is must to sign contract for delivery 1 Days 24-8-18 25-8-18 2 2.0 Design & development This is process is necessary, because design must be user friendly that user understand easily so for this first make a 20 Days 25-8-18 14-9-18
  • 6.
    prototype to check theuser if user satisfy then go to next step 2.1 Front-End design Front end design in such a way that user learn easily all necessary info put on this 15 Days 10-9-18 25-9-18 2.2 Administrative design This is for Admin, through this it control the complete software 5 Days 26-9-18 1-10-18 2.3 Functional modules design Functional module design includes serials management and standards integration 5 Days 2-10-18 7-10-18 3 3.0 Documentation of the software Documentation is the most important part to develop a software, it involves everything in document form about software 14 Days 8-10-18 22-10-18 4 4.0 Finalization of the software After complete the every step successfully, itis important that test the software again by some testing 8 Days 23-10-18 31-10-18
  • 7.
    method like unit testing,system testing, quality testing etc for satisfactory