This document provides an overview of cost estimating methodologies. It discusses five classes of cost estimates based on the level of project definition. Conceptual estimates use stochastic or factored methods and are appropriate for early project stages with little definition. Deterministic estimates use more detailed data as projects are better defined. Common conceptual methods described include end product units, physical dimensions, capacity factor, ratio or factor, and parametric modeling. The document provides examples of applying each method.
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10Moustafa Ismail Abu Dief
Cost Management training course, Certified cost professional certification preparation course.
Cost Engineering- Commercial management- tendering and bedding.Process product manufacturing- skills and knowledge of cost engineering
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10Moustafa Ismail Abu Dief
Cost Management training course, Certified cost professional certification preparation course.
Cost Engineering- Commercial management- tendering and bedding.Process product manufacturing- skills and knowledge of cost engineering
Presentation on practical approach of costing in construction industry has been prepared with the objective of spreading and sharing knowledge of flow of costing and key areas among industry, professionals and other related people.
it may be very useful to understand the basic concepts and approach of costing of this fastest growing industry.
Whenever an engineering economic analysis is performed for a major capital investment, the cost-estimating effort for that analysis should be an integral part of a comprehensive planning and design process requiring the active participation of not only engineering designers but also personnel from marketing, manufacturing, finance, and top management
Cost management is the process of planning and controlling the budget of a business. Cost management is a form of management accounting that allows a business to predict impending expenditures to help reduce the chance of going over budget.
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
SAJJAD KHUDHUR ABBAS
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
Presentation focuses on the cost effectiveness of buildings through rationalizing architectural design, opting for green buildings, looking at life cycle cost, promoting professional management, optimising labour, materials, plants time etc to avoid time/cost over-run and to finish the project within defined scope, money and time
Episode 28 : Project Management Contract
most important document for the execution of a project.
project management - know very well, includes all important issues regarding supply and services
Fulfillment of requirements, review the contractual situation, to claim the respective extra costs
project engineers :
mastered the fundamental aspects of the contractual arrangements for negotiated with subcontractor
depends on the relevant information of the team members.
actual contract arrangement - trained and experienced traders and lawyers
Fédération Internationale des Ing é-nieurs - Conseils ” (FIDIC)
take equally into account the interests of Conditions of Contract for Works of Civil Engineering and Construction Conditions of Contract for Electrical an Mechanical Works
jus strictum (binding law) and jus dispositivum (modifiable law).
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
A CCP is an experienced practitioner with advanced knowledge and technical expertise to apply the broad principles and best practices of Total Cost Management (TCM) in the planning, execution and management of any organizational project or program. CCPs also demonstrate the ability to research and communicate aspects of TCM principles and practices to all levels of project or program stakeholders, both internally and externally.
Presentation on practical approach of costing in construction industry has been prepared with the objective of spreading and sharing knowledge of flow of costing and key areas among industry, professionals and other related people.
it may be very useful to understand the basic concepts and approach of costing of this fastest growing industry.
Whenever an engineering economic analysis is performed for a major capital investment, the cost-estimating effort for that analysis should be an integral part of a comprehensive planning and design process requiring the active participation of not only engineering designers but also personnel from marketing, manufacturing, finance, and top management
Cost management is the process of planning and controlling the budget of a business. Cost management is a form of management accounting that allows a business to predict impending expenditures to help reduce the chance of going over budget.
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
SAJJAD KHUDHUR ABBAS
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Episode 27 : Project Management Costs
Cost Method
1. If there is lack of information regarding the existing plant, investment cost can be estimated by using cost factor. It requires the existence of a process concept and the rough layout of the main equipment in order to determine the cost of the main processing unit.
Operating Cost
Consists of (a) Cost of raw material
Utility cost
Labour cost
Maintenance cost
Utility Cost
1. It is quantity based and consisted of electric power, steam and coolant consumption, heating media such as coal and other energy sources like hydrogen.
Presentation focuses on the cost effectiveness of buildings through rationalizing architectural design, opting for green buildings, looking at life cycle cost, promoting professional management, optimising labour, materials, plants time etc to avoid time/cost over-run and to finish the project within defined scope, money and time
Episode 28 : Project Management Contract
most important document for the execution of a project.
project management - know very well, includes all important issues regarding supply and services
Fulfillment of requirements, review the contractual situation, to claim the respective extra costs
project engineers :
mastered the fundamental aspects of the contractual arrangements for negotiated with subcontractor
depends on the relevant information of the team members.
actual contract arrangement - trained and experienced traders and lawyers
Fédération Internationale des Ing é-nieurs - Conseils ” (FIDIC)
take equally into account the interests of Conditions of Contract for Works of Civil Engineering and Construction Conditions of Contract for Electrical an Mechanical Works
jus strictum (binding law) and jus dispositivum (modifiable law).
SAJJAD KHUDHUR ABBAS
Ceo , Founder & Head of SHacademy
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
A CCP is an experienced practitioner with advanced knowledge and technical expertise to apply the broad principles and best practices of Total Cost Management (TCM) in the planning, execution and management of any organizational project or program. CCPs also demonstrate the ability to research and communicate aspects of TCM principles and practices to all levels of project or program stakeholders, both internally and externally.
80
مبادرة
#تواصل_تطوير
المحاضرة الثمانون من المبادرة مع
المهندس / أحمد سعيد رفاعي
مدير مشاريع وباحث في ادارة المشروعات
بعنوان
" دورة حياة تقدير التكلفة بمشروعات التشييد "
الثامنة والنصف مساء توقيت مكة المكرمة
السابعة والنصف توقيت القاهرة
الإثنين 09 نوفمبر 2020
وذلك عبر تطبيق زووم
Meeting ID: 812 2771 3116
https://us02web.zoom.us/meeting/register/tZUvde6vrzgrG9Jy6qAJj1lOuxbHoNJOE0H-
علما ان هناك بث مباشر للمحاضرة على وقناة يوتيوب
https://www.youtube.com/user/EEAchannal
للتواصل مع إدارة المبادرة عبر قناة تيليجرام
الرابط
https://t.me/EEAKSA
رابط اللينكدان والمكتبة الالكترونية
www.linkedin.com/company/eeaksa-egyptian-engineers-association/
رابط التسجيل العام للمحاضرات
https://forms.gle/vVmw7L187tiATRPw9
Dear students, get latest Solved NMIMS assignments and case study help by professionals.
Mail us at : help.mbaassignments@gmail.com
Call us at : 08263069601
International Journal of Business and Management Invention (IJBMI) is an international journal intended for professionals and researchers in all fields of Business and Management. IJBMI publishes research articles and reviews within the whole field Business and Management, new teaching methods, assessment, validation and the impact of new technologies and it will continue to provide information on the latest trends and developments in this ever-expanding subject. The publications of papers are selected through double peer reviewed to ensure originality, relevance, and readability. The articles published in our journal can be accessed online.
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
In this unit the student will learn:
• The main types of estimation.
• When each type of estimation is used.
• Making approximate estimate to predict the expected cost of a project.
Concept development using Optimization, DFM & CAE - In DFSS Waynsahay
The traditional approach for designing an automotive component or an automobile is to design for performance, design for aesthetics & ergonomics and to design for adequate durability and reliability, so that the performance requirements can be met continuously over the life time of the vehicle.
During the initial design phases, the approach has been to build the factor of safety more than required in certain component or component areas because of the positive and negative interaction effects of casual variables. Thus it can be said that the design is not wholly “optimum”.
This lack of ‘optimum design’ has always given rise to opportunity for further optimization and is popularly known as the value analysis (VA)/value Engineering (VE) approach. The approach has its advantages and many companies have dedicated resources for VA/VE. However on the flip side, it is ‘reactive approach’ and thus can be avoided. In the parlance of six sigma philosophy, it is known as ‘DMAIC (Design, measure, analyze, improve and control) approach’. DMAIC approach solves a problem which has been created.
A more proactive approach known as the DFSS (Design for Six Sigma), which prevents a problem from generating and by using this philosophy it is possible to build ‘value’ and achieve ‘optimization’ in the design phase itself.
The modern day software tools offer great opportunity to use this philosophy in terms of optimization software, DFM software and validation software of CAE for an optimum concept design.
Automobile field is currently one of most challenging fields with tougher competition between international automotive players in offering light weight, fuel efficient & low emission vehicles of better reliability and durability. In order to stay alive in this competition, it becomes important for Auto players to launch new vehicles in comparatively shorter span of time with less number of prototypes. So new CAE tools and value engineering methods have to be used in the very early stage of development to achieve these goals.
The Topology Optimization is an appropriate method that changes the density and stiffness distributions in an iterative process to achieve a homogeneous stress distribution which defines the concept design of the component in Virtual Vehicle Development Process. The Classical Optimization process considers either minimization of weight or maximization of frequency approach. This paper addresses three aspects of optimization, the Strength aspect and Frequency aspect along with the significant weight reduction during the design. The paper also discusses about the application of the DFM (Design for Manufacturability) concepts to transfer the design proposal in a real manufacturable component.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
3. 2017AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 3
Primary
Characteristic
Maturity level of project definition
deliverables expressed as % of
complete definition
Class 5
0-2 %
Class 4
1-15 %
Class 3
10-40 %
Class 2
30-75 %
Class 1
65-100 % Most detailed
Leastdetailed
CCP Certificate Section 2 Cost Estimating Ch. 9
4. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
42017
Estimating
• Cost estimating framework includes:
A system for the classification of cost estimating.
The methodologies used in the preparation of cost estimates.
Establishing estimating accuracy as it relates to the scope definition.
he application of risk analysis to contingency.
• Introduction
Predictive process used to quantify, & price resources for A scope.
The output of the process is the cost estimate, used for:
Determining the economic feasibility of a project.
Evaluating between project alternatives.
Establishing the project budget.
Providing a basis for project cost and schedule control.
5. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
5
2017
Estimating
• Estimating steps:
Understand the scope of activity to quantify the resources required;
apply costs to the resources;
apply pricing adjustments; and
organize output in a structured way that supports decision-making.
Additional steps involve the assessment of risk associated with the estimate, and
review and validation of the estimate.
HINT
Cost estimate accuracy is crucial in deciding go-not to go or
continue with a project.( increased accuracy is necessary)
Estimating is iterative process applied (increased) through the project
life cycle as the project scope is defined, modified, and refined.
6. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
6
2017
Estimating
• Estimate Characteristics:
AACE identifies five classes of estimates, 1-5. Class 5 lowest level of
project definition (or project maturity).
For each class, 5 characteristic are used to distinguish one from another.
The 5 used in the AACE Recommended Practice are:
1. degree of project definition
2. end usage of the estimate
3. estimating methodology
4. estimating accuracy
5. effort required to produce the estimate.
8. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
8
2017
Estimate Methodologies
Estimating Methodologies
1. Conceptual estimate( LL of project definition)
2. Deterministic estimate ( H L of project estimate)
1. Conceptual estimate:
The estimate progress from conceptual (stochastic or factored)
to deterministic methods.
It involves simple or complex modeling (or factoring), based
on inferred or statistical relationships between costs and other,
typically design related, parameters. Often, subject to
conjecture .(guess)
9. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
9
2017
Estimate Methodologies
1. Conceptual estimate:– continue
typically used for Class 5 and Class 4 (sometimes 3) estimates.
Referred to as ―order-of-magnitude‖ (OOM) in reference to their
typically wide range of estimate accuracy
Provides a relatively quick method of determining the approximate
probable cost of a project without the benefit of detailed scope
definition.
These estimates may be used for:
o Establishing an early screening estimate for a project.
o Evaluating the general feasibility of a project.
o Screening project alternatives (such as different locations,
technologies, capacities, etc.).
o Evaluating the cost impacts of design alternatives.
o Establishing a preliminary budget for control purposes during
the design phase of a project.
10. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
10
2017
Estimate Methodologies
1. Conceptual estimate:– continue
Many of conceptual or OOM estimating methodologies are used, the
more commonly used methods are:
i. end product units ii. physical dimensions iii. capacity factor,
iv. ratio or factor methods v. parametric modeling.
1.1 End-Product Units Method
• It is used when data is available from similar projects to relate the
end-product units (capacity units) of a project to its construction
costs. ( plant capacity in KW- Deep well depth- hotel rooms-
hospital rooms- garage no. of parking.
11. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
11
2017
Estimate Methodologies
1.1 End-Product Units Method- continue
Ex. 1
• A hospital (A) was constructed in Riyadh for a no. of beds equals
200 in 2010 with total cost SAR 80,000,000.00 M. A hospital B
with similar design criteria will be constructed in Makkah in 2017
with no of beds 300. Estimate the expected cost for the hospital B.
• Hospital A SAR 80 M , 200 bed = 80 M/300
• Hospital B 80/200 x 300 = 120 M
• The estimate doesn’t account for location, time, scale- cost indices
may be applied for adjustment. It is used for FEASIBILITY studies
12. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
12
2017
Estimate Methodologies
1.2 Physical Dimensions Method
It uses item physical dimensions (length, area, volume, etc.) as the
driving factor. For example, a building estimate may be based on
m2/m3 ; water tanks/ gas tanks by m3, pipelines, roadways, or
railroad based on LM. ( ignoring quality factors or specific criteria).
Ex. 2:
Building A 5000 m2 10 M SAR
Building B 1000 m2 = 10 M/5000 X 1000 = SAR 1.0 M
1.3 Capacity Factor Method
Cost of a new facility is derived from the cost of a similar facility of a
known capacity. It relies on the (typical) non-linear relationship
between capacity and cost.
$B/$A=(CapB/CapA)
e
13. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
13
2017
Estimate Methodologies
1.3 Capacity Factor Method- continue
B= Facility being estimated , e = exponent (proportion) factor 0.5-0.85
Cap & Cap are the capacities of the two facilities.
With e < 1, if capacity increases (say, 20 %), the costs to build the
larger facility increase by less than 20 %.
• It is referred to as the ―scale of operations‖ method, or the ―six
tenth’s factor‖ method.
• If e = 0.6, doubling the capacity increases costs by approximately
50 % - and tripling capacity increases costs approximately 100 %
• In reality, as e increase, it became economical to construct 2 small
buildings than one large buildings.
A B
14. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
142017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Ex3 :
100,000 BBL/Day Hydrogen Peroxide unit, to be built in Philadelphia (2004).
A unite 150,000 BBL/Day plant recently completed in Malaysia, with a final
cost of $50 Million in 2002. Our recent history shows a capacity factor (e) of
0.75 is appropriate.
SOLUTION:$B = ($A)(Cap /Cap ) $B = $50MX(100/150) = $36.89 M
We ignored differences in quality (or scope), location, and time.
Ex 3-1:In Malasia (location adjustment)=1.25 - Escalation (timing) 1.06
from 2002 / 2004 - Difference in scope ( Piling) add (-10M)- For pollution
additional cost = 5M
AB
e .75
15. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 152017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Ex 3-1 – Solution:
150,000 BBL/Day Plant in Malaysia $50M Sequence
Deduct Piling. Tankage, Owner Costs - $10M Less/ add costs N/A
Adjusted Cost for Scope $40M Adjust for
location, scope,
escalate (timing)
Malaysia to Philadelphia Adjustment (X
1.25)
$50M
Escalate to 2002 (X 1.06) $53M
Factor = $53M X (100/150).75 $39M Add capacity factor
Add Pollution Requirements (+$5M) $44M Add any additional
cost specific for
new plant- i.e.
pollution
16. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 162017
Estimate Methodologies
1.3 Ratio or Factor Methods
X- Used where total cost of an item or facility can be estimated from
cost of a primary component, called ―Equipment Factor‖ estimating.
X- Estimate is class 3 (feasibility), it can be used to show the required
funding for a budget estimate preparation.
X- It counts on on the belief that a ratio or factor exists between an
equipment item costs and costs for the associated non-equipment items
(foundations, piping, electrical, etc.) required for installation.
X-Factors may be used for TIC, total installed cost or direct filed cost
DFC in side the battery limit ISBL.
17. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 172017
Estimate Methodologies
1.3 Ratio or Factor Methods
i. Hans Lang 1947:
Total Plant $ = Total Equipment $ X Equipment Factor
Lang factors based on the type of process plant (see Table below).
Lang’s factors cover (ISBL Costs) and all Offsite Units (OSBL Costs).
Ex. 4:
Total Equipment Cost = $1.5 M
Total Plant Cost =$1.5x 4.74 = $7.11M
18. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 182017
Estimate Methodologies
1.3 Ratio or Factor Methods
ii. W.E. Hand elaborated (1958). (Hands factors- HF))
X- Proposing different factors for each type of equipment (columns,
vessels, heat exchangers, etc.) excluding
X- Hands factors 2.0 –3.5, if include instrumentation correlate 2.4 - 4.3
X- HF excluded Indirect Field Costs (IFC), Home Office Costs (HOC),
and the costs for Offsite or Outside Battery Limit (OSBL) facilities.
19. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 192017
Estimate Methodologies
1.3 Ratio or Factor Methods
ii- W.E. Hand (1958)
x
=
x
7,753x 0.3= 2.326
7,753x 0.03= 233
+
.15(9,982+2326+ 233)= 1881 +
1881+233+12308=14,422.0
20. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 202017
Estimate Methodologies
Inside Battery Limits (ISBL) —
• FOR: process plant, it refers to the process units of plant or facility.
• FOR: single piece of equipment, it refers to the piece of equipment
and the associated bulk materials (foundation, piping, electrical,
controls, etc.) directly associated with the piece of equipment. (Dysert)
Outside Battery Limits (OSBL)—
• FOR process plant, it refers to the non‐process facilities of the plant
(i.e., the utility generation facilities, storage facilities, office buildings,
etc.), and are sometimes also referred to as off sites. (Dysert)
21. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 212017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Arthur Miller 1965:
• Miller recognized impact of 3 variables affect the equipment material
cost to a greater degree than they affect the cost of the associated
bulk materials and installation.
1- the size of the major equipment, 2- materials of construction
(metallurgy) of the equipment, 3- operating pressure.
• Miller noted, as the size of a piece of major equipment gets larger, the
amount the amount of bulk materials (foundation, support steel, piping,
instruments, etc.) required for installation does not increase at the same
rate. Thus, as the equipment increases in size, the value of the
equipment factor decreases- same tendency for other 2 variables
22. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 222017
Estimate Methodologies
1.3 Factor Method- continue
Arthur Miller 1965:
• Miller suggested 3 variables could be summarized into a single
attribute ―average unit cost‖ of equipment.
= Total Cost of Process Equipment / Number of Equipment Items
IF the ―average unit cost‖ of equipment increases, then the equipment
factor is scaled smaller. (statistically validated by Rodl and Nushimura .
23. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 232017
Estimate Methodologies
1.4 Parametric method:
o Is an extremely useful tool for preparing early conceptual estimates
when there is little technical data or engineering deliverables.
o Is a mathematical representation of cost relationships that provide a
logical and predictable correlation between the physical or functional
characteristics of a plant (or process system) and its resultant cost.
o is comprised of cost estimating relationships and other parametric
estimating functions that provide logical and repeatable relationships
between independent variables, such as design parameters and the
dependent variable, cost.
24. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 242017
Estimate Methodologies
1.4 Parametric method: continue
• Capacity factor & equipment factors estimates are simple examples of
parametric estimates; however, sophisticated parametric involve
several independent variables or cost drivers.
• Developing a parametric model should generally involve the following
steps [10, 11]:
Cost Model Scope- Determination- intended usage, characteristics
Data Collection – Model quality will not exceed data quality
Data Normalization- Timing(escalation) – location- differences
Data Analysis- linear/nonlinear analysis to get the best model
Data Application- Spread sheets are sufficient
Testing- validation of out puts and its accuracy
Documentation- user manual
25. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 252017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
Detailed estimate, scope definition is quantitatively surveyed and priced
using the most realistic unit prices available.
Support final budget, bid tenders, project cost control, CO. Class 1-3
Require a substantial amount of time and costs to prepare weeks/ months
Minimum Engineering data includes: drawings data sheets, diagrams,
specifications, technical requirements, layouts, plot plans.
It includes all costs( direct and indirect, and HOC).
Pricing needs: 1. Vendor and Sub-con quotations 2. updated PO’s and
labor rates 3. Project schedule and project plan
• Semi detailed: FOR ISBL detailed costs and for OSBL it is factored
• Forced detailed: Preliminary design is used for detailed quantities.
26. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 262017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
Steps and activities:
1. Prepare project estimate basis and schedule
2. Prepare Direct Field Cost (DFC) estimate
3. Prepare Indirect Field Cost (IFC) estimate
4. Prepare Home Office Cost (HOC) estimate
5. Prepare sales tax/duty estimates
6. Prepare escalation estimates
7. Prepare project fee estimate (for contractors)
8. Prepare cost risk analysis/contingency determination
9. Preview/validate estimate.
27. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 272017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
1. Formal vs. informal prices and quotation( preferable is formal)
2. Implied costs for non BOQ items, tests, soil reports, coting, spare parts,
equipment unloading, equipment accessories., installation, and etc.
3. Consider freight cost, transport, customs, vendors excluded activities,
HINT
28. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 282017
Estimate Methodologies
Take-off
The term take-off is used to refer to the quantities (often known as a
Bill of Quantities).
Take-off involves a detailed examination of the engineering
drawings and deliverables to count the number of each item
appearing on the drawings.
The quantities of like items are then summarized according to the
control structure (WBS/RBS) of the project.
Once the take-off is complete, and total quantities for each like item
summarized, the items can be priced, and the results added together
resulting in the estimated direct field costs for the project.
29. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 292017
Estimate Methodologies
Guidelines for preparing an efficient take-off include:
1. Use pre-printed forms for the orderly sequence of item descriptions,
dimensions, quantities, pricing information, etc.
2. Abbreviate (consistently) whenever possible.
3. Be consistent when listing dimensions (i.e., length X width X height).
4. Use printed dimensions from drawings when available.
5. When possible, add up the printed dimensions for a given item.
6. Measure all dimensions carefully.
7. Use each set of dimensions to calculate multiple quantities where
possible. (Cable length- pipe length)
8. Take advantage of design symmetry or repetition.
30. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 302017
Estimate Methodologies
Guidelines for preparing an efficient take-off continue:
9. List all gross dimensions that can be used again to rough check other
quantities for approximate verifications.
10. Convert imperial dimensions (feet/inch) to decimal equivalents.
11. Do not round until the final summary of quantities.
12. Multiply the large numbers first to reduce rounding errors.
13. Do not convert the units until the final quantities are obtained.
14. Items should be measured/converted to the same units consistently
throughout the take-off.
12. Mark the drawings as quantities are taken off. Use different colors to
identify various types of components or items, as well as to identify items
on hold, etc.
31. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 312017
Estimate Methodologies
Guidelines for preparing an efficient take-off continue:
13. Use approved drawing list to be used with the estimate. Check off
drawings on the drawing list as take-off is completed.
14. Keep similar items together, different items separate.
15. Organize take-off to match the control structure & format of estimate.
16. Identify drawing numbers, section numbers, etc. on the take-off forms
to aid in future checking for completeness, and for incorporating late
changes later on.
17. Consider notes shown on drawings, changes in scale used on different
drawings, zoomed from original size, discrepancies between drawings
and specifications, changes in elevation that may not be obvious, etc.
18. Be careful to quantify all labor operations that may not have a material
component
32. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 322017
Estimate Methodologies
Costing Vs. Pricing
Costing is the process of applying unit costs to the individual
quantities of items associated with the estimate. (labor hours, wage
rates, material costs, and perhaps subcontract costs) which come
from estimating database (either in-house or commercial), vendor
quotes, the procurement department, estimating experience, etc.
Pricing, is adjusting the costs that have been applied for specific
project conditions, and commercial terms. It includes adjustments to
cost to allow for overhead and profit, to improve cash flow, or
otherwise serve the business interests of the party preparing the
estimate. Thus, the pricing strategy depends on the particular party
preparing the estimate.(contractor/ investor/ developer)
33. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 332017
Estimate Methodologies
Estimating allowances:
Included in an estimate to account for the predictable but indefinable
costs associated with project scope in detailed estimates.
It is simply not cost effective to quantify and cost every small item
included with the project, so to account for these situations, allowance
for costs associated with these items may be included in the estimate.
Included in the estimate as a percentage of some detailed cost
component. Typical examples are:
• design allowance for engineered equipment
• material take-off allowance
• overbuy allowance
• unrecoverable shipping damage allowance
• allowance for undefined major items
34. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 342017
Estimate Methodologies
Estimating allowances:
Category % Description
design allowance for
engineered equipment
2-5% equ.
cost
Accounts for continue design
after PO.
material take-off allowance 2-15 % cost
of discipline
undefined material such as
concrete accessories
overbuy allowance 2-10 % Incomplete utilization of
material waste, theft, misuse.
unrecoverable shipping
damage allowance
Case
dependent
covers the uncovered part by
insurance
undefined major items Case
depende
Design does not cover/
complte some parts but shall
be estimated.
35. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 352017
Estimate Methodologies
Estimating accuracy:
Accuracy is affected by the following:
Project definition
Information and data used quality
Technology level
Estimator competency and used techniques.
Purpose of the estimate
Available time and recourses
36. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 362017
Estimate Methodologies
Contingency and Risk Analysis
• Corporate management think of requests for contingency as
―padding‖ the estimate.
• Is an amount used in the estimate to deal with the uncertainties
inherent in the estimating process.
• The estimator regards contingency as the funds added to the
originally derived point estimate to achieve a given probability of
not overrunning the estimate.
• Contingency includes: difference in wages, errors, design shortage,
inflation in material price, labor productivity variances, skills.
37. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 372017
Estimate Methodologies
Contingency and Risk Analysis
Contingency specifically excludes:
• Significant changes in scope.
• Major unexpected work stoppages (strikes, etc.).
• Disasters (hurricanes, tornadoes, etc.).
• Excessive, unexpected inflation.
• Excessive, unexpected currency fluctuations.
Contingency reduces level of risk but
doesn’t increase accuracy.
38. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 382017
Estimate Methodologies
Risk Analysis
Is a process used to understand the probability of over/under running
It provides a level of certainty to complete a project for the specified
estimate value.
Two types of risk analysis are commonly used:
1. Strategic risk analysis models that evaluate the level of project
definition and project technical complexity in determining the overall
risk to project cost. And,
2. Detailed risk analysis models that evaluate the accuracy range for
individual or groups of estimate components in determining the
overall risk to project cost.
39. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 392017
Risk Analysis- example
To achieve a 50 % probability
of u/overrun – fund project at
$25.4 million. - meaning
contingency $2.1 million.
, equivalent to nine % of the
original point value of the
estimate.
If we wanted to provide a 70%
probability of not exceeding
our project funding, -
Fund project at $26.6 million,
meaning cont. of $3.3 million.
equivalent to 14.2%.
40. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 402017
Structuring the Estimate
• WBS- RBS. the structure will vary with the size and complexity of
the project.
• To maintain some kind of order in the estimate, segregate costs into
various these categories:
1. Material vs. Labor vs. Subcontracts
2. Direct Costs vs. Indirect Costs vs. Home Office Costs
3. Concrete vs. Structural Steel vs. Piping vs. Other Construction
Disciplines
Ch: 9 Estimating
41. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 412017
Structuring the Estimate- Project Breakdown System
X- The matrix of the WBS and RBS forms the full Project Control
Structure or Project Breakdown System (PBS). The intersection points of
the WBS and RBS structures is called a ―cost center‖ which is identified
through a numbering system. (Fig 9.15 SK6)
X- It must reveal project execution &how costs summarized & reporting.
Ch: 9 - Estimating
(Fig 9.15 SK6)
(Fig 9.16 SK6)
Ex: the labor to pour concrete in the
hydrocracker unit, the cost code would
be: 01-02-C-2-003-1 (Onsite-
Hydrocracker-Construction-Concrete-
Pour-Labor).
42. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 422017
Estimate/Cost/Schedule Integration
One to One approach
• Effective project M.& control integrate cost estimate+schedule + c cont
• Estimate to the level of schedule activities to achieve detailed and efficient
cost and schedule control, but it may face some difficulties:
Costing detailed schedule activities is generally not feasible.
Activities are subject to frequent change within the project than cost codes.
Tracking bulk material costs by activity is tough task.
Determine an appropriate level of detail to correlate cost and schedule,
balanced between C estimate and schedule by keeping the estimate and
schedule structures the identical to a certain level of WBS
Ch: 9 - Estimating
43. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 432017
Estimate/Cost/Schedule Integration
Fig. 9.17 cost estimate WBS
the cost and schedule WBS
structures will diverge to meet each structure’s
particular control needs.
Estimate provides L. hours, to evaluate durations
and resources.
Ch: 9 - Estimating
Fig. 9.18 Schedule WBS
Schedule provides dates needed for escalation,
cash flow
SK6
SK6
diverge
diverge
44. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 442017
Estimate/Cost/Schedule Integration
• The estimator and scheduler should determine the levels at which cost items and schedule
activities can be correlated. ( high level of WBS).
• The cost and schedule breakdown can be aligned at some level as it is not essential compatible
• Estimation is sensitive to the schedule and correlated to it.
• Changes to the plan that have time impact significantly affect project cost considering the
basis estimating algorithm: Total $ = (Qty. X Unit Material $) +(Qty. X Unit Labor Hours X Wage Rate)
• Unit Material $ ( inflation), Unit Labor Hours (seasonal availability, and Wage Rate (
inflation, seasonal, plan changes) dependent on the schedule.
• Weather can affect productivity, seasonal variation, and execution plan changes (affecting
overtime and/or shift premiums).
• Many costs in a project are dependent on the duration and when executed in the calendar year
( inflation- cost of time- over head- indirect cost).
Ch: 9 - Estimating
45. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 452017
Estimate Review
• estimate should contain all the required information and is understandable
to all interested .
• The estimate review process is usually comprised of a series of estimate
reviews, internal estimating department reviews, engineering reviews,
project team reviews, and by various levels of management, depending on
the importance of the project.
1. Estimating Team/Estimating Department Review
• Check the Math((extensions of pricing are correct, summaries add up,..)
2. Basis of Estimate- BOE
• Design Basis: Overall scope, details for each area/unit/work
package, specific inclusions, and even more importantly, specific
exclusions of items or facilities should be documented. Scope
assumptions, equipment lists, drawings lists& specification
Ch: 9 - Estimating
46. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 462017
BOE - continue
• Planning Basis: project plan, mile stones resources, labor rotation,
shifts, calendar
Cost of major equipment (referencing quotes or PO’s), labor rates,
Basis: source of all pricing used, source of all bulk material pricing,
pricing all labor work-hours should be documented, assumptions for
productivities. Identify allowances the estimate , basis for cost
escalation included in the estimate.
• Risk Basis: estimate is a prediction of probable costs so it involves
Uncertainty & risk then Contingency is included and to be documented.
Estimating Department Guidelines, review with check list,
procedures, codes, techniques, formats, allowances, factors.
Ch.: 9 - Estimating
47. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 472017
BOE - continue
• Engineering/Design Review
Completeness of Engineering Deliverables - review the listing of all
drawings, sketches, specifications, and other engineering deliverables
check bases of the estimate.- Design risk, design cost,
• Project Manager/Project Team Review- to gain the entire project
team’s support of the estimate.
• Management Reviews- by various levels of corporate management.
• Presenting the Estimate- Present to customer, not just a list of
numbers, describe as:
Basis of Estimate (BOE) Estimate Summaries
Estimate Detail Estimate Benchmarking Report
Estimate Reconciliation Report Estimate Backup
Ch.: 9 - Estimating
48. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 48
Cost Engineering Management
2017