SlideShare a Scribd company logo
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 1
Cost Engineering Management
Training Course:
Association for the Advancement
of Cost Engineering
2017
LECTURE 4
‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 2
Contact details
moustafa1_ismail@yahoo.com
m.ismail@italconsult.com
https://www.linkedin.com/in/moustafa-ismail-
abu-dief-93798a16/
https://twitter.com/moustafaabudief
https://www.slideshare.net/moustafismail
2017
2017AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 3
Primary
Characteristic
Maturity level of project definition
deliverables expressed as % of
complete definition
Class 5
0-2 %
Class 4
1-15 %
Class 3
10-40 %
Class 2
30-75 %
Class 1
65-100 % Most detailed
Leastdetailed
CCP Certificate Section 2 Cost Estimating Ch. 9
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
42017
Estimating
• Cost estimating framework includes:
 A system for the classification of cost estimating.
 The methodologies used in the preparation of cost estimates.
 Establishing estimating accuracy as it relates to the scope definition.
 he application of risk analysis to contingency.
• Introduction
 Predictive process used to quantify, & price resources for A scope.
 The output of the process is the cost estimate, used for:
 Determining the economic feasibility of a project.
 Evaluating between project alternatives.
 Establishing the project budget.
 Providing a basis for project cost and schedule control.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
5
2017
Estimating
• Estimating steps:
 Understand the scope of activity to quantify the resources required;
 apply costs to the resources;
 apply pricing adjustments; and
 organize output in a structured way that supports decision-making.
Additional steps involve the assessment of risk associated with the estimate, and
review and validation of the estimate.
HINT
 Cost estimate accuracy is crucial in deciding go-not to go or
continue with a project.( increased accuracy is necessary)
 Estimating is iterative process applied (increased) through the project
life cycle as the project scope is defined, modified, and refined.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
6
2017
Estimating
• Estimate Characteristics:
AACE identifies five classes of estimates, 1-5. Class 5 lowest level of
project definition (or project maturity).
For each class, 5 characteristic are used to distinguish one from another.
The 5 used in the AACE Recommended Practice are:
1. degree of project definition
2. end usage of the estimate
3. estimating methodology
4. estimating accuracy
5. effort required to produce the estimate.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
7
2017
Estimate Classifications
SK6 p92Figure 9.1―Generic Cost Estimate Classification Matrix [1]
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
8
2017
Estimate Methodologies
Estimating Methodologies
1. Conceptual estimate( LL of project definition)
2. Deterministic estimate ( H L of project estimate)
1. Conceptual estimate:
 The estimate progress from conceptual (stochastic or factored)
to deterministic methods.
 It involves simple or complex modeling (or factoring), based
on inferred or statistical relationships between costs and other,
typically design related, parameters. Often, subject to
conjecture .(guess)
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
9
2017
Estimate Methodologies
1. Conceptual estimate:– continue
 typically used for Class 5 and Class 4 (sometimes 3) estimates.
 Referred to as ―order-of-magnitude‖ (OOM) in reference to their
typically wide range of estimate accuracy
 Provides a relatively quick method of determining the approximate
probable cost of a project without the benefit of detailed scope
definition.
 These estimates may be used for:
o Establishing an early screening estimate for a project.
o Evaluating the general feasibility of a project.
o Screening project alternatives (such as different locations,
technologies, capacities, etc.).
o Evaluating the cost impacts of design alternatives.
o Establishing a preliminary budget for control purposes during
the design phase of a project.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
10
2017
Estimate Methodologies
1. Conceptual estimate:– continue
Many of conceptual or OOM estimating methodologies are used, the
more commonly used methods are:
i. end product units ii. physical dimensions iii. capacity factor,
iv. ratio or factor methods v. parametric modeling.
1.1 End-Product Units Method
• It is used when data is available from similar projects to relate the
end-product units (capacity units) of a project to its construction
costs. ( plant capacity in KW- Deep well depth- hotel rooms-
hospital rooms- garage no. of parking.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
11
2017
Estimate Methodologies
1.1 End-Product Units Method- continue
 Ex. 1
• A hospital (A) was constructed in Riyadh for a no. of beds equals
200 in 2010 with total cost SAR 80,000,000.00 M. A hospital B
with similar design criteria will be constructed in Makkah in 2017
with no of beds 300. Estimate the expected cost for the hospital B.
• Hospital A SAR 80 M , 200 bed = 80 M/300
• Hospital B 80/200 x 300 = 120 M
• The estimate doesn’t account for location, time, scale- cost indices
may be applied for adjustment. It is used for FEASIBILITY studies
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
12
2017
Estimate Methodologies
1.2 Physical Dimensions Method
It uses item physical dimensions (length, area, volume, etc.) as the
driving factor. For example, a building estimate may be based on
m2/m3 ; water tanks/ gas tanks by m3, pipelines, roadways, or
railroad based on LM. ( ignoring quality factors or specific criteria).
Ex. 2:
Building A 5000 m2 10 M SAR
Building B 1000 m2 = 10 M/5000 X 1000 = SAR 1.0 M
1.3 Capacity Factor Method
Cost of a new facility is derived from the cost of a similar facility of a
known capacity. It relies on the (typical) non-linear relationship
between capacity and cost.
$B/$A=(CapB/CapA)
e
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
13
2017
Estimate Methodologies
1.3 Capacity Factor Method- continue
B= Facility being estimated , e = exponent (proportion) factor 0.5-0.85
Cap & Cap are the capacities of the two facilities.
With e < 1, if capacity increases (say, 20 %), the costs to build the
larger facility increase by less than 20 %.
• It is referred to as the ―scale of operations‖ method, or the ―six
tenth’s factor‖ method.
• If e = 0.6, doubling the capacity increases costs by approximately
50 % - and tripling capacity increases costs approximately 100 %
• In reality, as e increase, it became economical to construct 2 small
buildings than one large buildings.
A B
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4
142017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Ex3 :
100,000 BBL/Day Hydrogen Peroxide unit, to be built in Philadelphia (2004).
A unite 150,000 BBL/Day plant recently completed in Malaysia, with a final
cost of $50 Million in 2002. Our recent history shows a capacity factor (e) of
0.75 is appropriate.
SOLUTION:$B = ($A)(Cap /Cap ) $B = $50MX(100/150) = $36.89 M
We ignored differences in quality (or scope), location, and time.
Ex 3-1:In Malasia (location adjustment)=1.25 - Escalation (timing) 1.06
from 2002 / 2004 - Difference in scope ( Piling) add (-10M)- For pollution
additional cost = 5M
AB
e .75
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 152017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Ex 3-1 – Solution:
150,000 BBL/Day Plant in Malaysia $50M Sequence
Deduct Piling. Tankage, Owner Costs - $10M Less/ add costs N/A
Adjusted Cost for Scope $40M Adjust for
location, scope,
escalate (timing)
Malaysia to Philadelphia Adjustment (X
1.25)
$50M
Escalate to 2002 (X 1.06) $53M
Factor = $53M X (100/150).75 $39M Add capacity factor
Add Pollution Requirements (+$5M) $44M Add any additional
cost specific for
new plant- i.e.
pollution
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 162017
Estimate Methodologies
1.3 Ratio or Factor Methods
X- Used where total cost of an item or facility can be estimated from
cost of a primary component, called ―Equipment Factor‖ estimating.
X- Estimate is class 3 (feasibility), it can be used to show the required
funding for a budget estimate preparation.
X- It counts on on the belief that a ratio or factor exists between an
equipment item costs and costs for the associated non-equipment items
(foundations, piping, electrical, etc.) required for installation.
X-Factors may be used for TIC, total installed cost or direct filed cost
DFC in side the battery limit ISBL.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 172017
Estimate Methodologies
1.3 Ratio or Factor Methods
i. Hans Lang 1947:
Total Plant $ = Total Equipment $ X Equipment Factor
Lang factors based on the type of process plant (see Table below).
Lang’s factors cover (ISBL Costs) and all Offsite Units (OSBL Costs).
Ex. 4:
Total Equipment Cost = $1.5 M
Total Plant Cost =$1.5x 4.74 = $7.11M
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 182017
Estimate Methodologies
1.3 Ratio or Factor Methods
ii. W.E. Hand elaborated (1958). (Hands factors- HF))
X- Proposing different factors for each type of equipment (columns,
vessels, heat exchangers, etc.) excluding
X- Hands factors 2.0 –3.5, if include instrumentation correlate 2.4 - 4.3
X- HF excluded Indirect Field Costs (IFC), Home Office Costs (HOC),
and the costs for Offsite or Outside Battery Limit (OSBL) facilities.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 192017
Estimate Methodologies
1.3 Ratio or Factor Methods
ii- W.E. Hand (1958)
x
=
x
7,753x 0.3= 2.326
7,753x 0.03= 233
+
.15(9,982+2326+ 233)= 1881 +
1881+233+12308=14,422.0
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 202017
Estimate Methodologies
Inside Battery Limits (ISBL) —
• FOR: process plant, it refers to the process units of plant or facility.
• FOR: single piece of equipment, it refers to the piece of equipment
and the associated bulk materials (foundation, piping, electrical,
controls, etc.) directly associated with the piece of equipment. (Dysert)
Outside Battery Limits (OSBL)—
• FOR process plant, it refers to the non‐process facilities of the plant
(i.e., the utility generation facilities, storage facilities, office buildings,
etc.), and are sometimes also referred to as off sites. (Dysert)
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 212017
Estimate Methodologies
1.3 Capacity Factor Method- continue
Arthur Miller 1965:
• Miller recognized impact of 3 variables affect the equipment material
cost to a greater degree than they affect the cost of the associated
bulk materials and installation.
1- the size of the major equipment, 2- materials of construction
(metallurgy) of the equipment, 3- operating pressure.
• Miller noted, as the size of a piece of major equipment gets larger, the
amount the amount of bulk materials (foundation, support steel, piping,
instruments, etc.) required for installation does not increase at the same
rate. Thus, as the equipment increases in size, the value of the
equipment factor decreases- same tendency for other 2 variables
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 222017
Estimate Methodologies
1.3 Factor Method- continue
Arthur Miller 1965:
• Miller suggested 3 variables could be summarized into a single
attribute ―average unit cost‖ of equipment.
= Total Cost of Process Equipment / Number of Equipment Items
IF the ―average unit cost‖ of equipment increases, then the equipment
factor is scaled smaller. (statistically validated by Rodl and Nushimura .
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 232017
Estimate Methodologies
1.4 Parametric method:
o Is an extremely useful tool for preparing early conceptual estimates
when there is little technical data or engineering deliverables.
o Is a mathematical representation of cost relationships that provide a
logical and predictable correlation between the physical or functional
characteristics of a plant (or process system) and its resultant cost.
o is comprised of cost estimating relationships and other parametric
estimating functions that provide logical and repeatable relationships
between independent variables, such as design parameters and the
dependent variable, cost.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 242017
Estimate Methodologies
1.4 Parametric method: continue
• Capacity factor & equipment factors estimates are simple examples of
parametric estimates; however, sophisticated parametric involve
several independent variables or cost drivers.
• Developing a parametric model should generally involve the following
steps [10, 11]:
 Cost Model Scope- Determination- intended usage, characteristics
 Data Collection – Model quality will not exceed data quality
 Data Normalization- Timing(escalation) – location- differences
 Data Analysis- linear/nonlinear analysis to get the best model
 Data Application- Spread sheets are sufficient
 Testing- validation of out puts and its accuracy
 Documentation- user manual
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 252017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
 Detailed estimate, scope definition is quantitatively surveyed and priced
using the most realistic unit prices available.
 Support final budget, bid tenders, project cost control, CO. Class 1-3
 Require a substantial amount of time and costs to prepare weeks/ months
 Minimum Engineering data includes: drawings data sheets, diagrams,
specifications, technical requirements, layouts, plot plans.
 It includes all costs( direct and indirect, and HOC).
 Pricing needs: 1. Vendor and Sub-con quotations 2. updated PO’s and
labor rates 3. Project schedule and project plan
• Semi detailed: FOR ISBL detailed costs and for OSBL it is factored
• Forced detailed: Preliminary design is used for detailed quantities.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 262017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
 Steps and activities:
1. Prepare project estimate basis and schedule
2. Prepare Direct Field Cost (DFC) estimate
3. Prepare Indirect Field Cost (IFC) estimate
4. Prepare Home Office Cost (HOC) estimate
5. Prepare sales tax/duty estimates
6. Prepare escalation estimates
7. Prepare project fee estimate (for contractors)
8. Prepare cost risk analysis/contingency determination
9. Preview/validate estimate.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 272017
Estimate Methodologies
2. Deterministic
• Detailed – high level of project definition
1. Formal vs. informal prices and quotation( preferable is formal)
2. Implied costs for non BOQ items, tests, soil reports, coting, spare parts,
equipment unloading, equipment accessories., installation, and etc.
3. Consider freight cost, transport, customs, vendors excluded activities,
HINT
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 282017
Estimate Methodologies
 Take-off
 The term take-off is used to refer to the quantities (often known as a
Bill of Quantities).
 Take-off involves a detailed examination of the engineering
drawings and deliverables to count the number of each item
appearing on the drawings.
 The quantities of like items are then summarized according to the
control structure (WBS/RBS) of the project.
 Once the take-off is complete, and total quantities for each like item
summarized, the items can be priced, and the results added together
resulting in the estimated direct field costs for the project.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 292017
Estimate Methodologies
 Guidelines for preparing an efficient take-off include:
1. Use pre-printed forms for the orderly sequence of item descriptions,
dimensions, quantities, pricing information, etc.
2. Abbreviate (consistently) whenever possible.
3. Be consistent when listing dimensions (i.e., length X width X height).
4. Use printed dimensions from drawings when available.
5. When possible, add up the printed dimensions for a given item.
6. Measure all dimensions carefully.
7. Use each set of dimensions to calculate multiple quantities where
possible. (Cable length- pipe length)
8. Take advantage of design symmetry or repetition.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 302017
Estimate Methodologies
 Guidelines for preparing an efficient take-off continue:
9. List all gross dimensions that can be used again to rough check other
quantities for approximate verifications.
10. Convert imperial dimensions (feet/inch) to decimal equivalents.
11. Do not round until the final summary of quantities.
12. Multiply the large numbers first to reduce rounding errors.
13. Do not convert the units until the final quantities are obtained.
14. Items should be measured/converted to the same units consistently
throughout the take-off.
12. Mark the drawings as quantities are taken off. Use different colors to
identify various types of components or items, as well as to identify items
on hold, etc.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 312017
Estimate Methodologies
 Guidelines for preparing an efficient take-off continue:
13. Use approved drawing list to be used with the estimate. Check off
drawings on the drawing list as take-off is completed.
14. Keep similar items together, different items separate.
15. Organize take-off to match the control structure & format of estimate.
16. Identify drawing numbers, section numbers, etc. on the take-off forms
to aid in future checking for completeness, and for incorporating late
changes later on.
17. Consider notes shown on drawings, changes in scale used on different
drawings, zoomed from original size, discrepancies between drawings
and specifications, changes in elevation that may not be obvious, etc.
18. Be careful to quantify all labor operations that may not have a material
component
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 322017
Estimate Methodologies
 Costing Vs. Pricing
 Costing is the process of applying unit costs to the individual
quantities of items associated with the estimate. (labor hours, wage
rates, material costs, and perhaps subcontract costs) which come
from estimating database (either in-house or commercial), vendor
quotes, the procurement department, estimating experience, etc.
 Pricing, is adjusting the costs that have been applied for specific
project conditions, and commercial terms. It includes adjustments to
cost to allow for overhead and profit, to improve cash flow, or
otherwise serve the business interests of the party preparing the
estimate. Thus, the pricing strategy depends on the particular party
preparing the estimate.(contractor/ investor/ developer)
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 332017
Estimate Methodologies
 Estimating allowances:
 Included in an estimate to account for the predictable but indefinable
costs associated with project scope in detailed estimates.
 It is simply not cost effective to quantify and cost every small item
included with the project, so to account for these situations, allowance
for costs associated with these items may be included in the estimate.
 Included in the estimate as a percentage of some detailed cost
component. Typical examples are:
• design allowance for engineered equipment
• material take-off allowance
• overbuy allowance
• unrecoverable shipping damage allowance
• allowance for undefined major items
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 342017
Estimate Methodologies
 Estimating allowances:
Category % Description
design allowance for
engineered equipment
2-5% equ.
cost
Accounts for continue design
after PO.
material take-off allowance 2-15 % cost
of discipline
undefined material such as
concrete accessories
overbuy allowance 2-10 % Incomplete utilization of
material waste, theft, misuse.
unrecoverable shipping
damage allowance
Case
dependent
covers the uncovered part by
insurance
undefined major items Case
depende
Design does not cover/
complte some parts but shall
be estimated.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 352017
Estimate Methodologies
 Estimating accuracy:
Accuracy is affected by the following:
 Project definition
 Information and data used quality
 Technology level
 Estimator competency and used techniques.
 Purpose of the estimate
 Available time and recourses
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 362017
Estimate Methodologies
Contingency and Risk Analysis
• Corporate management think of requests for contingency as
―padding‖ the estimate.
• Is an amount used in the estimate to deal with the uncertainties
inherent in the estimating process.
• The estimator regards contingency as the funds added to the
originally derived point estimate to achieve a given probability of
not overrunning the estimate.
• Contingency includes: difference in wages, errors, design shortage,
inflation in material price, labor productivity variances, skills.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 372017
Estimate Methodologies
Contingency and Risk Analysis
 Contingency specifically excludes:
• Significant changes in scope.
• Major unexpected work stoppages (strikes, etc.).
• Disasters (hurricanes, tornadoes, etc.).
• Excessive, unexpected inflation.
• Excessive, unexpected currency fluctuations.
Contingency reduces level of risk but
doesn’t increase accuracy.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 382017
Estimate Methodologies
 Risk Analysis
 Is a process used to understand the probability of over/under running
 It provides a level of certainty to complete a project for the specified
estimate value.
 Two types of risk analysis are commonly used:
1. Strategic risk analysis models that evaluate the level of project
definition and project technical complexity in determining the overall
risk to project cost. And,
2. Detailed risk analysis models that evaluate the accuracy range for
individual or groups of estimate components in determining the
overall risk to project cost.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 392017
 Risk Analysis- example
To achieve a 50 % probability
of u/overrun – fund project at
$25.4 million. - meaning
contingency $2.1 million.
, equivalent to nine % of the
original point value of the
estimate.
If we wanted to provide a 70%
probability of not exceeding
our project funding, -
Fund project at $26.6 million,
meaning cont. of $3.3 million.
equivalent to 14.2%.
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 402017
 Structuring the Estimate
• WBS- RBS. the structure will vary with the size and complexity of
the project.
• To maintain some kind of order in the estimate, segregate costs into
various these categories:
1. Material vs. Labor vs. Subcontracts
2. Direct Costs vs. Indirect Costs vs. Home Office Costs
3. Concrete vs. Structural Steel vs. Piping vs. Other Construction
Disciplines
Ch: 9 Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 412017
 Structuring the Estimate- Project Breakdown System
X- The matrix of the WBS and RBS forms the full Project Control
Structure or Project Breakdown System (PBS). The intersection points of
the WBS and RBS structures is called a ―cost center‖ which is identified
through a numbering system. (Fig 9.15 SK6)
X- It must reveal project execution &how costs summarized & reporting.
Ch: 9 - Estimating
(Fig 9.15 SK6)
(Fig 9.16 SK6)
Ex: the labor to pour concrete in the
hydrocracker unit, the cost code would
be: 01-02-C-2-003-1 (Onsite-
Hydrocracker-Construction-Concrete-
Pour-Labor).
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 422017
 Estimate/Cost/Schedule Integration
 One to One approach
• Effective project M.& control integrate cost estimate+schedule + c cont
• Estimate to the level of schedule activities to achieve detailed and efficient
cost and schedule control, but it may face some difficulties:
 Costing detailed schedule activities is generally not feasible.
 Activities are subject to frequent change within the project than cost codes.
 Tracking bulk material costs by activity is tough task.
 Determine an appropriate level of detail to correlate cost and schedule,
balanced between C estimate and schedule by keeping the estimate and
schedule structures the identical to a certain level of WBS
Ch: 9 - Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 432017
 Estimate/Cost/Schedule Integration
Fig. 9.17 cost estimate WBS
the cost and schedule WBS
structures will diverge to meet each structure’s
particular control needs.
Estimate provides L. hours, to evaluate durations
and resources.
Ch: 9 - Estimating
Fig. 9.18 Schedule WBS
Schedule provides dates needed for escalation,
cash flow
SK6
SK6
diverge
diverge
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 442017
 Estimate/Cost/Schedule Integration
• The estimator and scheduler should determine the levels at which cost items and schedule
activities can be correlated. ( high level of WBS).
• The cost and schedule breakdown can be aligned at some level as it is not essential compatible
• Estimation is sensitive to the schedule and correlated to it.
• Changes to the plan that have time impact significantly affect project cost considering the
basis estimating algorithm: Total $ = (Qty. X Unit Material $) +(Qty. X Unit Labor Hours X Wage Rate)
• Unit Material $ ( inflation), Unit Labor Hours (seasonal availability, and Wage Rate (
inflation, seasonal, plan changes) dependent on the schedule.
• Weather can affect productivity, seasonal variation, and execution plan changes (affecting
overtime and/or shift premiums).
• Many costs in a project are dependent on the duration and when executed in the calendar year
( inflation- cost of time- over head- indirect cost).
Ch: 9 - Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 452017
 Estimate Review
• estimate should contain all the required information and is understandable
to all interested .
• The estimate review process is usually comprised of a series of estimate
reviews, internal estimating department reviews, engineering reviews,
project team reviews, and by various levels of management, depending on
the importance of the project.
1. Estimating Team/Estimating Department Review
• Check the Math((extensions of pricing are correct, summaries add up,..)
2. Basis of Estimate- BOE
• Design Basis: Overall scope, details for each area/unit/work
package, specific inclusions, and even more importantly, specific
exclusions of items or facilities should be documented. Scope
assumptions, equipment lists, drawings lists& specification
Ch: 9 - Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 462017
BOE - continue
• Planning Basis: project plan, mile stones resources, labor rotation,
shifts, calendar
 Cost of major equipment (referencing quotes or PO’s), labor rates,
Basis: source of all pricing used, source of all bulk material pricing,
pricing all labor work-hours should be documented, assumptions for
productivities. Identify allowances the estimate , basis for cost
escalation included in the estimate.
• Risk Basis: estimate is a prediction of probable costs so it involves
Uncertainty & risk then Contingency is included and to be documented.
 Estimating Department Guidelines, review with check list,
procedures, codes, techniques, formats, allowances, factors.
Ch.: 9 - Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 472017
BOE - continue
• Engineering/Design Review
 Completeness of Engineering Deliverables - review the listing of all
drawings, sketches, specifications, and other engineering deliverables
 check bases of the estimate.- Design risk, design cost,
• Project Manager/Project Team Review- to gain the entire project
team’s support of the estimate.
• Management Reviews- by various levels of corporate management.
• Presenting the Estimate- Present to customer, not just a list of
numbers, describe as:
Basis of Estimate (BOE) Estimate Summaries
Estimate Detail Estimate Benchmarking Report
Estimate Reconciliation Report Estimate Backup
Ch.: 9 - Estimating
AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 48
Cost Engineering Management
2017

More Related Content

What's hot

PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
Manish Kandpal
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
Sadegh Yazdani
 
5. cost estimation
5. cost estimation5. cost estimation
5. cost estimation
Eduardo Alves
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
SHAZEBALIKHAN1
 
Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in construction
Saravana murthy
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
VancityInstitute
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
MUHAMMAD KHURSHID AHMAD
 
cost-estimation-tutorial
cost-estimation-tutorialcost-estimation-tutorial
cost-estimation-tutorial
shopnohin_shopnobalok
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01web
GABISA DEMISIE
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
Yudi Setiawan
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
Martin van Vliet
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimatingAli Juma Albahrani
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
Amit Kumar Senapati, PMP®
 
Estimation and project costing training module
Estimation and project costing training moduleEstimation and project costing training module
Estimation and project costing training modulekhalid noman husainy
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
Nagma Modi
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
SAJJAD KHUDHUR ABBAS
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
SAJJAD KHUDHUR ABBAS
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in Buildings
JIT KUMAR GUPTA
 
Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering IntroductionLeendertdegeus
 
Episode 28 : Project Management Contract
Episode 28 :  Project Management ContractEpisode 28 :  Project Management Contract
Episode 28 : Project Management Contract
SAJJAD KHUDHUR ABBAS
 

What's hot (20)

PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
 
5. cost estimation
5. cost estimation5. cost estimation
5. cost estimation
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in construction
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
cost-estimation-tutorial
cost-estimation-tutorialcost-estimation-tutorial
cost-estimation-tutorial
 
Engineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01webEngineering design guildline_general_plant_cost_estimating_rev01web
Engineering design guildline_general_plant_cost_estimating_rev01web
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
Estimation and project costing training module
Estimation and project costing training moduleEstimation and project costing training module
Estimation and project costing training module
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
Episode 27 : Project Management Costs
Episode 27 : Project Management Costs Episode 27 : Project Management Costs
Episode 27 : Project Management Costs
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in Buildings
 
Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering Introduction
 
Episode 28 : Project Management Contract
Episode 28 :  Project Management ContractEpisode 28 :  Project Management Contract
Episode 28 : Project Management Contract
 

Similar to Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9

CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skills
AnjumNaveed12
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Moustafa Ismail Abu Dief
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
SudipBalLama
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
Egyptian Engineers Association
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
ArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
ArvinThamsir1
 
Project management
Project managementProject management
Project management
smumbahelp
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
hlksd
 
B0342014027
B0342014027B0342014027
B0342014027
inventionjournals
 
IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
IRJET Journal
 
Integration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemIntegration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemLaurent Carlander
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET Journal
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
Muthanna Abbu
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practicalAbada Saad
 
Concept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS WayConcept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS Way
nsahay
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
Minn Lwin
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
IRJET Journal
 

Similar to Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9 (20)

CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Sharpen your cost_estimating_skills
Sharpen your cost_estimating_skillsSharpen your cost_estimating_skills
Sharpen your cost_estimating_skills
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
Project management
Project managementProject management
Project management
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
B0342014027
B0342014027B0342014027
B0342014027
 
IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
Integration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance systemIntegration of cost-risk within an intelligent maintenance system
Integration of cost-risk within an intelligent maintenance system
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practical
 
Value Value
Value Value Value Value
Value Value
 
Concept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS WayConcept development using Optimization, DFM & CAE - In DFSS Way
Concept development using Optimization, DFM & CAE - In DFSS Way
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 

More from Moustafa Ismail Abu Dief

Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
Moustafa Ismail Abu Dief
 
Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
Moustafa Ismail Abu Dief
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
Moustafa Ismail Abu Dief
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
Moustafa Ismail Abu Dief
 
CMC certification
CMC certificationCMC certification
CMC certification
Moustafa Ismail Abu Dief
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Moustafa Ismail Abu Dief
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
Moustafa Ismail Abu Dief
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
Moustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Moustafa Ismail Abu Dief
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Moustafa Ismail Abu Dief
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
Moustafa Ismail Abu Dief
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Moustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 

More from Moustafa Ismail Abu Dief (18)

Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
 
CMC certification
CMC certificationCMC certification
CMC certification
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 

Recently uploaded

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9

  • 1. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 1 Cost Engineering Management Training Course: Association for the Advancement of Cost Engineering 2017 LECTURE 4 ‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬
  • 2. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 2 Contact details moustafa1_ismail@yahoo.com m.ismail@italconsult.com https://www.linkedin.com/in/moustafa-ismail- abu-dief-93798a16/ https://twitter.com/moustafaabudief https://www.slideshare.net/moustafismail 2017
  • 3. 2017AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 3 Primary Characteristic Maturity level of project definition deliverables expressed as % of complete definition Class 5 0-2 % Class 4 1-15 % Class 3 10-40 % Class 2 30-75 % Class 1 65-100 % Most detailed Leastdetailed CCP Certificate Section 2 Cost Estimating Ch. 9
  • 4. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 42017 Estimating • Cost estimating framework includes:  A system for the classification of cost estimating.  The methodologies used in the preparation of cost estimates.  Establishing estimating accuracy as it relates to the scope definition.  he application of risk analysis to contingency. • Introduction  Predictive process used to quantify, & price resources for A scope.  The output of the process is the cost estimate, used for:  Determining the economic feasibility of a project.  Evaluating between project alternatives.  Establishing the project budget.  Providing a basis for project cost and schedule control.
  • 5. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 5 2017 Estimating • Estimating steps:  Understand the scope of activity to quantify the resources required;  apply costs to the resources;  apply pricing adjustments; and  organize output in a structured way that supports decision-making. Additional steps involve the assessment of risk associated with the estimate, and review and validation of the estimate. HINT  Cost estimate accuracy is crucial in deciding go-not to go or continue with a project.( increased accuracy is necessary)  Estimating is iterative process applied (increased) through the project life cycle as the project scope is defined, modified, and refined.
  • 6. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 6 2017 Estimating • Estimate Characteristics: AACE identifies five classes of estimates, 1-5. Class 5 lowest level of project definition (or project maturity). For each class, 5 characteristic are used to distinguish one from another. The 5 used in the AACE Recommended Practice are: 1. degree of project definition 2. end usage of the estimate 3. estimating methodology 4. estimating accuracy 5. effort required to produce the estimate.
  • 7. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 7 2017 Estimate Classifications SK6 p92Figure 9.1―Generic Cost Estimate Classification Matrix [1]
  • 8. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 8 2017 Estimate Methodologies Estimating Methodologies 1. Conceptual estimate( LL of project definition) 2. Deterministic estimate ( H L of project estimate) 1. Conceptual estimate:  The estimate progress from conceptual (stochastic or factored) to deterministic methods.  It involves simple or complex modeling (or factoring), based on inferred or statistical relationships between costs and other, typically design related, parameters. Often, subject to conjecture .(guess)
  • 9. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 9 2017 Estimate Methodologies 1. Conceptual estimate:– continue  typically used for Class 5 and Class 4 (sometimes 3) estimates.  Referred to as ―order-of-magnitude‖ (OOM) in reference to their typically wide range of estimate accuracy  Provides a relatively quick method of determining the approximate probable cost of a project without the benefit of detailed scope definition.  These estimates may be used for: o Establishing an early screening estimate for a project. o Evaluating the general feasibility of a project. o Screening project alternatives (such as different locations, technologies, capacities, etc.). o Evaluating the cost impacts of design alternatives. o Establishing a preliminary budget for control purposes during the design phase of a project.
  • 10. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 10 2017 Estimate Methodologies 1. Conceptual estimate:– continue Many of conceptual or OOM estimating methodologies are used, the more commonly used methods are: i. end product units ii. physical dimensions iii. capacity factor, iv. ratio or factor methods v. parametric modeling. 1.1 End-Product Units Method • It is used when data is available from similar projects to relate the end-product units (capacity units) of a project to its construction costs. ( plant capacity in KW- Deep well depth- hotel rooms- hospital rooms- garage no. of parking.
  • 11. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 11 2017 Estimate Methodologies 1.1 End-Product Units Method- continue  Ex. 1 • A hospital (A) was constructed in Riyadh for a no. of beds equals 200 in 2010 with total cost SAR 80,000,000.00 M. A hospital B with similar design criteria will be constructed in Makkah in 2017 with no of beds 300. Estimate the expected cost for the hospital B. • Hospital A SAR 80 M , 200 bed = 80 M/300 • Hospital B 80/200 x 300 = 120 M • The estimate doesn’t account for location, time, scale- cost indices may be applied for adjustment. It is used for FEASIBILITY studies
  • 12. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 12 2017 Estimate Methodologies 1.2 Physical Dimensions Method It uses item physical dimensions (length, area, volume, etc.) as the driving factor. For example, a building estimate may be based on m2/m3 ; water tanks/ gas tanks by m3, pipelines, roadways, or railroad based on LM. ( ignoring quality factors or specific criteria). Ex. 2: Building A 5000 m2 10 M SAR Building B 1000 m2 = 10 M/5000 X 1000 = SAR 1.0 M 1.3 Capacity Factor Method Cost of a new facility is derived from the cost of a similar facility of a known capacity. It relies on the (typical) non-linear relationship between capacity and cost. $B/$A=(CapB/CapA) e
  • 13. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 13 2017 Estimate Methodologies 1.3 Capacity Factor Method- continue B= Facility being estimated , e = exponent (proportion) factor 0.5-0.85 Cap & Cap are the capacities of the two facilities. With e < 1, if capacity increases (say, 20 %), the costs to build the larger facility increase by less than 20 %. • It is referred to as the ―scale of operations‖ method, or the ―six tenth’s factor‖ method. • If e = 0.6, doubling the capacity increases costs by approximately 50 % - and tripling capacity increases costs approximately 100 % • In reality, as e increase, it became economical to construct 2 small buildings than one large buildings. A B
  • 14. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 142017 Estimate Methodologies 1.3 Capacity Factor Method- continue Ex3 : 100,000 BBL/Day Hydrogen Peroxide unit, to be built in Philadelphia (2004). A unite 150,000 BBL/Day plant recently completed in Malaysia, with a final cost of $50 Million in 2002. Our recent history shows a capacity factor (e) of 0.75 is appropriate. SOLUTION:$B = ($A)(Cap /Cap ) $B = $50MX(100/150) = $36.89 M We ignored differences in quality (or scope), location, and time. Ex 3-1:In Malasia (location adjustment)=1.25 - Escalation (timing) 1.06 from 2002 / 2004 - Difference in scope ( Piling) add (-10M)- For pollution additional cost = 5M AB e .75
  • 15. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 152017 Estimate Methodologies 1.3 Capacity Factor Method- continue Ex 3-1 – Solution: 150,000 BBL/Day Plant in Malaysia $50M Sequence Deduct Piling. Tankage, Owner Costs - $10M Less/ add costs N/A Adjusted Cost for Scope $40M Adjust for location, scope, escalate (timing) Malaysia to Philadelphia Adjustment (X 1.25) $50M Escalate to 2002 (X 1.06) $53M Factor = $53M X (100/150).75 $39M Add capacity factor Add Pollution Requirements (+$5M) $44M Add any additional cost specific for new plant- i.e. pollution
  • 16. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 162017 Estimate Methodologies 1.3 Ratio or Factor Methods X- Used where total cost of an item or facility can be estimated from cost of a primary component, called ―Equipment Factor‖ estimating. X- Estimate is class 3 (feasibility), it can be used to show the required funding for a budget estimate preparation. X- It counts on on the belief that a ratio or factor exists between an equipment item costs and costs for the associated non-equipment items (foundations, piping, electrical, etc.) required for installation. X-Factors may be used for TIC, total installed cost or direct filed cost DFC in side the battery limit ISBL.
  • 17. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 172017 Estimate Methodologies 1.3 Ratio or Factor Methods i. Hans Lang 1947: Total Plant $ = Total Equipment $ X Equipment Factor Lang factors based on the type of process plant (see Table below). Lang’s factors cover (ISBL Costs) and all Offsite Units (OSBL Costs). Ex. 4: Total Equipment Cost = $1.5 M Total Plant Cost =$1.5x 4.74 = $7.11M
  • 18. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 182017 Estimate Methodologies 1.3 Ratio or Factor Methods ii. W.E. Hand elaborated (1958). (Hands factors- HF)) X- Proposing different factors for each type of equipment (columns, vessels, heat exchangers, etc.) excluding X- Hands factors 2.0 –3.5, if include instrumentation correlate 2.4 - 4.3 X- HF excluded Indirect Field Costs (IFC), Home Office Costs (HOC), and the costs for Offsite or Outside Battery Limit (OSBL) facilities.
  • 19. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 192017 Estimate Methodologies 1.3 Ratio or Factor Methods ii- W.E. Hand (1958) x = x 7,753x 0.3= 2.326 7,753x 0.03= 233 + .15(9,982+2326+ 233)= 1881 + 1881+233+12308=14,422.0
  • 20. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 202017 Estimate Methodologies Inside Battery Limits (ISBL) — • FOR: process plant, it refers to the process units of plant or facility. • FOR: single piece of equipment, it refers to the piece of equipment and the associated bulk materials (foundation, piping, electrical, controls, etc.) directly associated with the piece of equipment. (Dysert) Outside Battery Limits (OSBL)— • FOR process plant, it refers to the non‐process facilities of the plant (i.e., the utility generation facilities, storage facilities, office buildings, etc.), and are sometimes also referred to as off sites. (Dysert)
  • 21. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 212017 Estimate Methodologies 1.3 Capacity Factor Method- continue Arthur Miller 1965: • Miller recognized impact of 3 variables affect the equipment material cost to a greater degree than they affect the cost of the associated bulk materials and installation. 1- the size of the major equipment, 2- materials of construction (metallurgy) of the equipment, 3- operating pressure. • Miller noted, as the size of a piece of major equipment gets larger, the amount the amount of bulk materials (foundation, support steel, piping, instruments, etc.) required for installation does not increase at the same rate. Thus, as the equipment increases in size, the value of the equipment factor decreases- same tendency for other 2 variables
  • 22. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 222017 Estimate Methodologies 1.3 Factor Method- continue Arthur Miller 1965: • Miller suggested 3 variables could be summarized into a single attribute ―average unit cost‖ of equipment. = Total Cost of Process Equipment / Number of Equipment Items IF the ―average unit cost‖ of equipment increases, then the equipment factor is scaled smaller. (statistically validated by Rodl and Nushimura .
  • 23. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 232017 Estimate Methodologies 1.4 Parametric method: o Is an extremely useful tool for preparing early conceptual estimates when there is little technical data or engineering deliverables. o Is a mathematical representation of cost relationships that provide a logical and predictable correlation between the physical or functional characteristics of a plant (or process system) and its resultant cost. o is comprised of cost estimating relationships and other parametric estimating functions that provide logical and repeatable relationships between independent variables, such as design parameters and the dependent variable, cost.
  • 24. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 242017 Estimate Methodologies 1.4 Parametric method: continue • Capacity factor & equipment factors estimates are simple examples of parametric estimates; however, sophisticated parametric involve several independent variables or cost drivers. • Developing a parametric model should generally involve the following steps [10, 11]:  Cost Model Scope- Determination- intended usage, characteristics  Data Collection – Model quality will not exceed data quality  Data Normalization- Timing(escalation) – location- differences  Data Analysis- linear/nonlinear analysis to get the best model  Data Application- Spread sheets are sufficient  Testing- validation of out puts and its accuracy  Documentation- user manual
  • 25. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 252017 Estimate Methodologies 2. Deterministic • Detailed – high level of project definition  Detailed estimate, scope definition is quantitatively surveyed and priced using the most realistic unit prices available.  Support final budget, bid tenders, project cost control, CO. Class 1-3  Require a substantial amount of time and costs to prepare weeks/ months  Minimum Engineering data includes: drawings data sheets, diagrams, specifications, technical requirements, layouts, plot plans.  It includes all costs( direct and indirect, and HOC).  Pricing needs: 1. Vendor and Sub-con quotations 2. updated PO’s and labor rates 3. Project schedule and project plan • Semi detailed: FOR ISBL detailed costs and for OSBL it is factored • Forced detailed: Preliminary design is used for detailed quantities.
  • 26. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 262017 Estimate Methodologies 2. Deterministic • Detailed – high level of project definition  Steps and activities: 1. Prepare project estimate basis and schedule 2. Prepare Direct Field Cost (DFC) estimate 3. Prepare Indirect Field Cost (IFC) estimate 4. Prepare Home Office Cost (HOC) estimate 5. Prepare sales tax/duty estimates 6. Prepare escalation estimates 7. Prepare project fee estimate (for contractors) 8. Prepare cost risk analysis/contingency determination 9. Preview/validate estimate.
  • 27. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 272017 Estimate Methodologies 2. Deterministic • Detailed – high level of project definition 1. Formal vs. informal prices and quotation( preferable is formal) 2. Implied costs for non BOQ items, tests, soil reports, coting, spare parts, equipment unloading, equipment accessories., installation, and etc. 3. Consider freight cost, transport, customs, vendors excluded activities, HINT
  • 28. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 282017 Estimate Methodologies  Take-off  The term take-off is used to refer to the quantities (often known as a Bill of Quantities).  Take-off involves a detailed examination of the engineering drawings and deliverables to count the number of each item appearing on the drawings.  The quantities of like items are then summarized according to the control structure (WBS/RBS) of the project.  Once the take-off is complete, and total quantities for each like item summarized, the items can be priced, and the results added together resulting in the estimated direct field costs for the project.
  • 29. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 292017 Estimate Methodologies  Guidelines for preparing an efficient take-off include: 1. Use pre-printed forms for the orderly sequence of item descriptions, dimensions, quantities, pricing information, etc. 2. Abbreviate (consistently) whenever possible. 3. Be consistent when listing dimensions (i.e., length X width X height). 4. Use printed dimensions from drawings when available. 5. When possible, add up the printed dimensions for a given item. 6. Measure all dimensions carefully. 7. Use each set of dimensions to calculate multiple quantities where possible. (Cable length- pipe length) 8. Take advantage of design symmetry or repetition.
  • 30. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 302017 Estimate Methodologies  Guidelines for preparing an efficient take-off continue: 9. List all gross dimensions that can be used again to rough check other quantities for approximate verifications. 10. Convert imperial dimensions (feet/inch) to decimal equivalents. 11. Do not round until the final summary of quantities. 12. Multiply the large numbers first to reduce rounding errors. 13. Do not convert the units until the final quantities are obtained. 14. Items should be measured/converted to the same units consistently throughout the take-off. 12. Mark the drawings as quantities are taken off. Use different colors to identify various types of components or items, as well as to identify items on hold, etc.
  • 31. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 312017 Estimate Methodologies  Guidelines for preparing an efficient take-off continue: 13. Use approved drawing list to be used with the estimate. Check off drawings on the drawing list as take-off is completed. 14. Keep similar items together, different items separate. 15. Organize take-off to match the control structure & format of estimate. 16. Identify drawing numbers, section numbers, etc. on the take-off forms to aid in future checking for completeness, and for incorporating late changes later on. 17. Consider notes shown on drawings, changes in scale used on different drawings, zoomed from original size, discrepancies between drawings and specifications, changes in elevation that may not be obvious, etc. 18. Be careful to quantify all labor operations that may not have a material component
  • 32. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 322017 Estimate Methodologies  Costing Vs. Pricing  Costing is the process of applying unit costs to the individual quantities of items associated with the estimate. (labor hours, wage rates, material costs, and perhaps subcontract costs) which come from estimating database (either in-house or commercial), vendor quotes, the procurement department, estimating experience, etc.  Pricing, is adjusting the costs that have been applied for specific project conditions, and commercial terms. It includes adjustments to cost to allow for overhead and profit, to improve cash flow, or otherwise serve the business interests of the party preparing the estimate. Thus, the pricing strategy depends on the particular party preparing the estimate.(contractor/ investor/ developer)
  • 33. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 332017 Estimate Methodologies  Estimating allowances:  Included in an estimate to account for the predictable but indefinable costs associated with project scope in detailed estimates.  It is simply not cost effective to quantify and cost every small item included with the project, so to account for these situations, allowance for costs associated with these items may be included in the estimate.  Included in the estimate as a percentage of some detailed cost component. Typical examples are: • design allowance for engineered equipment • material take-off allowance • overbuy allowance • unrecoverable shipping damage allowance • allowance for undefined major items
  • 34. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 342017 Estimate Methodologies  Estimating allowances: Category % Description design allowance for engineered equipment 2-5% equ. cost Accounts for continue design after PO. material take-off allowance 2-15 % cost of discipline undefined material such as concrete accessories overbuy allowance 2-10 % Incomplete utilization of material waste, theft, misuse. unrecoverable shipping damage allowance Case dependent covers the uncovered part by insurance undefined major items Case depende Design does not cover/ complte some parts but shall be estimated.
  • 35. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 352017 Estimate Methodologies  Estimating accuracy: Accuracy is affected by the following:  Project definition  Information and data used quality  Technology level  Estimator competency and used techniques.  Purpose of the estimate  Available time and recourses
  • 36. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 362017 Estimate Methodologies Contingency and Risk Analysis • Corporate management think of requests for contingency as ―padding‖ the estimate. • Is an amount used in the estimate to deal with the uncertainties inherent in the estimating process. • The estimator regards contingency as the funds added to the originally derived point estimate to achieve a given probability of not overrunning the estimate. • Contingency includes: difference in wages, errors, design shortage, inflation in material price, labor productivity variances, skills.
  • 37. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 372017 Estimate Methodologies Contingency and Risk Analysis  Contingency specifically excludes: • Significant changes in scope. • Major unexpected work stoppages (strikes, etc.). • Disasters (hurricanes, tornadoes, etc.). • Excessive, unexpected inflation. • Excessive, unexpected currency fluctuations. Contingency reduces level of risk but doesn’t increase accuracy.
  • 38. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 382017 Estimate Methodologies  Risk Analysis  Is a process used to understand the probability of over/under running  It provides a level of certainty to complete a project for the specified estimate value.  Two types of risk analysis are commonly used: 1. Strategic risk analysis models that evaluate the level of project definition and project technical complexity in determining the overall risk to project cost. And, 2. Detailed risk analysis models that evaluate the accuracy range for individual or groups of estimate components in determining the overall risk to project cost.
  • 39. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 392017  Risk Analysis- example To achieve a 50 % probability of u/overrun – fund project at $25.4 million. - meaning contingency $2.1 million. , equivalent to nine % of the original point value of the estimate. If we wanted to provide a 70% probability of not exceeding our project funding, - Fund project at $26.6 million, meaning cont. of $3.3 million. equivalent to 14.2%.
  • 40. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 402017  Structuring the Estimate • WBS- RBS. the structure will vary with the size and complexity of the project. • To maintain some kind of order in the estimate, segregate costs into various these categories: 1. Material vs. Labor vs. Subcontracts 2. Direct Costs vs. Indirect Costs vs. Home Office Costs 3. Concrete vs. Structural Steel vs. Piping vs. Other Construction Disciplines Ch: 9 Estimating
  • 41. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 412017  Structuring the Estimate- Project Breakdown System X- The matrix of the WBS and RBS forms the full Project Control Structure or Project Breakdown System (PBS). The intersection points of the WBS and RBS structures is called a ―cost center‖ which is identified through a numbering system. (Fig 9.15 SK6) X- It must reveal project execution &how costs summarized & reporting. Ch: 9 - Estimating (Fig 9.15 SK6) (Fig 9.16 SK6) Ex: the labor to pour concrete in the hydrocracker unit, the cost code would be: 01-02-C-2-003-1 (Onsite- Hydrocracker-Construction-Concrete- Pour-Labor).
  • 42. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 422017  Estimate/Cost/Schedule Integration  One to One approach • Effective project M.& control integrate cost estimate+schedule + c cont • Estimate to the level of schedule activities to achieve detailed and efficient cost and schedule control, but it may face some difficulties:  Costing detailed schedule activities is generally not feasible.  Activities are subject to frequent change within the project than cost codes.  Tracking bulk material costs by activity is tough task.  Determine an appropriate level of detail to correlate cost and schedule, balanced between C estimate and schedule by keeping the estimate and schedule structures the identical to a certain level of WBS Ch: 9 - Estimating
  • 43. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 432017  Estimate/Cost/Schedule Integration Fig. 9.17 cost estimate WBS the cost and schedule WBS structures will diverge to meet each structure’s particular control needs. Estimate provides L. hours, to evaluate durations and resources. Ch: 9 - Estimating Fig. 9.18 Schedule WBS Schedule provides dates needed for escalation, cash flow SK6 SK6 diverge diverge
  • 44. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 442017  Estimate/Cost/Schedule Integration • The estimator and scheduler should determine the levels at which cost items and schedule activities can be correlated. ( high level of WBS). • The cost and schedule breakdown can be aligned at some level as it is not essential compatible • Estimation is sensitive to the schedule and correlated to it. • Changes to the plan that have time impact significantly affect project cost considering the basis estimating algorithm: Total $ = (Qty. X Unit Material $) +(Qty. X Unit Labor Hours X Wage Rate) • Unit Material $ ( inflation), Unit Labor Hours (seasonal availability, and Wage Rate ( inflation, seasonal, plan changes) dependent on the schedule. • Weather can affect productivity, seasonal variation, and execution plan changes (affecting overtime and/or shift premiums). • Many costs in a project are dependent on the duration and when executed in the calendar year ( inflation- cost of time- over head- indirect cost). Ch: 9 - Estimating
  • 45. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 452017  Estimate Review • estimate should contain all the required information and is understandable to all interested . • The estimate review process is usually comprised of a series of estimate reviews, internal estimating department reviews, engineering reviews, project team reviews, and by various levels of management, depending on the importance of the project. 1. Estimating Team/Estimating Department Review • Check the Math((extensions of pricing are correct, summaries add up,..) 2. Basis of Estimate- BOE • Design Basis: Overall scope, details for each area/unit/work package, specific inclusions, and even more importantly, specific exclusions of items or facilities should be documented. Scope assumptions, equipment lists, drawings lists& specification Ch: 9 - Estimating
  • 46. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 462017 BOE - continue • Planning Basis: project plan, mile stones resources, labor rotation, shifts, calendar  Cost of major equipment (referencing quotes or PO’s), labor rates, Basis: source of all pricing used, source of all bulk material pricing, pricing all labor work-hours should be documented, assumptions for productivities. Identify allowances the estimate , basis for cost escalation included in the estimate. • Risk Basis: estimate is a prediction of probable costs so it involves Uncertainty & risk then Contingency is included and to be documented.  Estimating Department Guidelines, review with check list, procedures, codes, techniques, formats, allowances, factors. Ch.: 9 - Estimating
  • 47. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 472017 BOE - continue • Engineering/Design Review  Completeness of Engineering Deliverables - review the listing of all drawings, sketches, specifications, and other engineering deliverables  check bases of the estimate.- Design risk, design cost, • Project Manager/Project Team Review- to gain the entire project team’s support of the estimate. • Management Reviews- by various levels of corporate management. • Presenting the Estimate- Present to customer, not just a list of numbers, describe as: Basis of Estimate (BOE) Estimate Summaries Estimate Detail Estimate Benchmarking Report Estimate Reconciliation Report Estimate Backup Ch.: 9 - Estimating
  • 48. AACE-AGS CCP Cost Engineering Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- 4 48 Cost Engineering Management 2017