SlideShare a Scribd company logo
TOP DOWN
CONSTRUCTION


  By- Gagan Goswami
Why Top Down Construction
               Required
►    Distance between Boundary wall of Adjacent Existing
    Building and Building Line for New Building is too close and
    the depth of excavation is more than 6 meter and
    possibility of collapse the soil is higher during excavation.
►   Using Top Down Construction more Building and Basement
    Area can use. Suitable for two or more basement.
►   The first base slab level slab will act in such area as a strut
    member and the Retaining wall panels will not allow
    collapse of soil.
►   Water table is too high and difficult to cast Retaining wall,
    Diaphragm wall or Continuous Pile can use as a Retaining
    wall.
METHODOLOGY OF TOP DOWN
          CONSTRUCTION
1.   Setting out for alignment of bore cast in situ of
     piles .
2.   Bore Cast in Situ Piles to be cast and dowels bar
     to be kept for Retaining wall panels. The center
     of piles and Retaining wall panels center line to
     be kept in same line. The Diameter of Piles
     preferred 600 mm, distance between two piles
     center to center preferred 3.33 meters (Suit for
     C/C distance of Columns), Depth of Piles to be
     confirmed by Structural Consultants.
3.   Touching Piles can use as a Retaining wall with
     supporting arrangement during Excavation.
4.   If area of Basement is more and Span is less
     Diaphragm wall can be use as a Retaining wall.
3. Instead of Column C1 to Column C8,Bore
    cast in Situ piles to be cast with dowel
    bars for different level slab and
    connecting Beams, The Diameter of Piles
    (suit as per Columns size),
    Reinforcement details (with dowels for
    Retaining wall and different level slabs
    and Beam), Depth of Piles to be
    confirmed by Structural Consultants.
4. Excavation to be done around 2 meter
   depth and retaining wall panels to be
   cast in stages with dowels bars with
   adjacent piles and dowel bars for next
   Retaining wall panel to be kept .if soil
   between piles collapsed soil nails with
   wire mesh to be kept on earth side to
   retain the same. Retaining wall panels to
   be cast with dowels up to the first base
   slab bottom.
5. Dressing and compaction of soil to be
   done for PCC bed for casting of first base
   slab. 50mm PCC (M15 Grade) to be
   done, the top levels of PCC to be keep
   the base slab level bottom. For beams
   excavation to be done in same alignment
   and dimensions as required and PCC or
   brick work to be done as per beam
   dimensions in Vertical face.
6. After PCC 3mm ply to be laid on PCC
   Surface and PVC sheet to be nailed with
   PCC surface so surface of PCC and
   Surface of Slab Concrete will separate.
7. Reinforcement to be completed as per
   drawings, for beams dowel bar to be
   used from Cast in Situ Piles. Dowel bars
   to be keep for adjacent slabs for Bottom
   Up Construction.
8. Concreting of Slab and Beam to be
    completed.
 9. After 14 days of Concreting, PCC below
    slab to be break/removed excavation to
    be continued and retaining wall panels to
    be cast. Till final level of excavation.
10 Waterproofing to be done and base slab
    to be cast with dowels from Cast in Situ
    Piles.
11.Jacketing of Columns to be done if
    required.
►THANKS
►Ifany query please mail -
 gagangoswami@yahoo.co.in

More Related Content

What's hot

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
Neha Vivek
 
DESIGN OF RCC CULVERT
DESIGN OF  RCC CULVERTDESIGN OF  RCC CULVERT
DESIGN OF RCC CULVERT
Satrudhan11240
 
Table formwork
Table formwork Table formwork
Table formwork
Davis Ciprikis
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
nishant patyal
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
Darshit
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
A Makwana
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
Ghanashyam Prajapati
 
Pile foundation
Pile foundationPile foundation
Pile foundation
Parth Desani
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
Reasat E Noor
 
Manual plastering
Manual plasteringManual plastering
Manual plastering
abhishek_garhwal
 
Steel framing system report
Steel framing system reportSteel framing system report
Steel framing system report
w ss
 
Glass Fiber Reinforced Gypsum (GFRG) Panel
Glass Fiber Reinforced Gypsum (GFRG) Panel Glass Fiber Reinforced Gypsum (GFRG) Panel
Glass Fiber Reinforced Gypsum (GFRG) Panel
M.SAAD ATTARWALA
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
gayathrysatheesan1
 
GFRG PANELS
GFRG PANELSGFRG PANELS
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
Rahul
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 

What's hot (20)

MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
DESIGN OF RCC CULVERT
DESIGN OF  RCC CULVERTDESIGN OF  RCC CULVERT
DESIGN OF RCC CULVERT
 
Table formwork
Table formwork Table formwork
Table formwork
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
Manual plastering
Manual plasteringManual plastering
Manual plastering
 
Steel framing system report
Steel framing system reportSteel framing system report
Steel framing system report
 
Glass Fiber Reinforced Gypsum (GFRG) Panel
Glass Fiber Reinforced Gypsum (GFRG) Panel Glass Fiber Reinforced Gypsum (GFRG) Panel
Glass Fiber Reinforced Gypsum (GFRG) Panel
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
GFRG PANELS
GFRG PANELSGFRG PANELS
GFRG PANELS
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 

Viewers also liked

Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessonscoen_van_der_vliet
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
Sathish Kumar
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Hamed Zarei
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
Durgesh Kumar Yadav
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
Austrian Standards
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
Hamed Zarei
 
Tunneling
Tunneling Tunneling
Tunneling
ila vamsi krishna
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
richardbieniawski
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
Narendra Kumar Dewangan
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
luisaam
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
1971995
 
Dam PPT
Dam PPTDam PPT
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
SHUBHAM DABHADE
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Mohit Shukla
 
Bridges precast
Bridges precastBridges precast
Bridges precast
Dr Fereidoun Dejahang
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
Strukturas
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
Communications Branding
 

Viewers also liked (20)

Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
 
Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
 
Bridge 91 Design
Bridge 91 DesignBridge 91 Design
Bridge 91 Design
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
NATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in TunnelingNATM (New Austrian Tunneling Method ) in Tunneling
NATM (New Austrian Tunneling Method ) in Tunneling
 
Tunneling
Tunneling Tunneling
Tunneling
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Casting yard
Casting yardCasting yard
Casting yard
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 

Similar to Top Down Construction Presentation.

Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
Sai Towers P Ltd.
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Dr.youssef hamida
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
Bhargava Ram
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
kristenjames
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
kristenjames
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
SALEM MOHAMMED
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
VATSAL PATEL
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
Ishwar Chauhan
 
Guidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexGuidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexPriya Raj
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
sydneyaugust1
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
Shivananda Roy
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
ShahbazKhan379018
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
aman kumar
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
Work check list
Work check listWork check list
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
bct%20final.pptx
bct%20final.pptxbct%20final.pptx
bct%20final.pptx
AnshumiTanna
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wallkristenjames
 

Similar to Top Down Construction Presentation. (20)

Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
 
Guidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporexGuidelines for construction of masonry with siporex
Guidelines for construction of masonry with siporex
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Work check list
Work check listWork check list
Work check list
 
Form Work
Form Work Form Work
Form Work
 
bct%20final.pptx
bct%20final.pptxbct%20final.pptx
bct%20final.pptx
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wall
 
construction study project sjce ctm
construction study project sjce ctmconstruction study project sjce ctm
construction study project sjce ctm
 

Top Down Construction Presentation.

  • 1. TOP DOWN CONSTRUCTION By- Gagan Goswami
  • 2. Why Top Down Construction Required ► Distance between Boundary wall of Adjacent Existing Building and Building Line for New Building is too close and the depth of excavation is more than 6 meter and possibility of collapse the soil is higher during excavation. ► Using Top Down Construction more Building and Basement Area can use. Suitable for two or more basement. ► The first base slab level slab will act in such area as a strut member and the Retaining wall panels will not allow collapse of soil. ► Water table is too high and difficult to cast Retaining wall, Diaphragm wall or Continuous Pile can use as a Retaining wall.
  • 3. METHODOLOGY OF TOP DOWN CONSTRUCTION 1. Setting out for alignment of bore cast in situ of piles . 2. Bore Cast in Situ Piles to be cast and dowels bar to be kept for Retaining wall panels. The center of piles and Retaining wall panels center line to be kept in same line. The Diameter of Piles preferred 600 mm, distance between two piles center to center preferred 3.33 meters (Suit for C/C distance of Columns), Depth of Piles to be confirmed by Structural Consultants. 3. Touching Piles can use as a Retaining wall with supporting arrangement during Excavation. 4. If area of Basement is more and Span is less Diaphragm wall can be use as a Retaining wall.
  • 4.
  • 5. 3. Instead of Column C1 to Column C8,Bore cast in Situ piles to be cast with dowel bars for different level slab and connecting Beams, The Diameter of Piles (suit as per Columns size), Reinforcement details (with dowels for Retaining wall and different level slabs and Beam), Depth of Piles to be confirmed by Structural Consultants.
  • 6. 4. Excavation to be done around 2 meter depth and retaining wall panels to be cast in stages with dowels bars with adjacent piles and dowel bars for next Retaining wall panel to be kept .if soil between piles collapsed soil nails with wire mesh to be kept on earth side to retain the same. Retaining wall panels to be cast with dowels up to the first base slab bottom.
  • 7.
  • 8. 5. Dressing and compaction of soil to be done for PCC bed for casting of first base slab. 50mm PCC (M15 Grade) to be done, the top levels of PCC to be keep the base slab level bottom. For beams excavation to be done in same alignment and dimensions as required and PCC or brick work to be done as per beam dimensions in Vertical face.
  • 9.
  • 10. 6. After PCC 3mm ply to be laid on PCC Surface and PVC sheet to be nailed with PCC surface so surface of PCC and Surface of Slab Concrete will separate. 7. Reinforcement to be completed as per drawings, for beams dowel bar to be used from Cast in Situ Piles. Dowel bars to be keep for adjacent slabs for Bottom Up Construction.
  • 11.
  • 12. 8. Concreting of Slab and Beam to be completed. 9. After 14 days of Concreting, PCC below slab to be break/removed excavation to be continued and retaining wall panels to be cast. Till final level of excavation. 10 Waterproofing to be done and base slab to be cast with dowels from Cast in Situ Piles. 11.Jacketing of Columns to be done if required.
  • 13. ►THANKS ►Ifany query please mail - gagangoswami@yahoo.co.in