SlideShare a Scribd company logo
TOP DOWN CONSTRUCTION
ADVANTAGES
By
Sai Towers P Ltd.
Why Top Down Construction
Required
• Distance between Boundary wall of Adjacent Existing Building and
Building Line for New Building is too close and the depth of
excavation is more than 6 meter and possibility of collapse the soil
is higher during excavation.
• Using Top Down Construction more Building and Basement Area
can use. Suitable for two or more basement.
• The first base slab level slab will act in such area as a strut member
and the Retaining wall panels will not allow collapse of soil.
• Water table is too high and difficult to cast Retaining wall,
Diaphragm wall or Continuous Pile can use as a Retaining wall.
METHODOLOGY OF TOP DOWN
CONSTRUCTION
• Setting out for alignment of bore cast in situ of piles .
• Bore Cast in Situ Piles to be cast and dowels bar to be kept for
Retaining wall panels. The center of piles and Retaining wall panels
center line to be kept in same line. The Diameter of Piles preferred
600 mm, distance between two piles center to center preferred
3.33 meters (Suit for C/C distance of Columns), Depth of Piles to be
confirmed by Structural Consultants.
• Touching Piles can use as a Retaining wall with supporting
arrangement during Excavation.
• Water table is too high and difficult to cast Retaining wall, Diaphragm
wall or Continuous Pile can use as a Retaining wall.
• Instead of Column C1 to Column C8,Bore cast in Situ piles to be cast with
dowel bars for different level slab and connecting Beams, The Diameter of
Piles (suit as per Columns size), Reinforcement details (with dowels for
Retaining wall and different level slabs and Beam), Depth of Piles to be
confirmed by Structural Consultants.
• Excavation to be done around 2 meter depth and retaining wall panels to
be cast in stages with dowels bars with adjacent piles and dowel bars for
next Retaining wall panel to be kept .if soil between piles collapsed soil
nails with wire mesh to be kept on earth side to retain the same. Retaining
wall panels to be cast with dowels up to the first base slab bottom.
• Dressing and compaction of soil to be done for PCC bed for casting
of first base slab. 50mm PCC (M15 Grade) to be done, the top levels
of PCC to be keep the base slab level bottom. For beams excavation
to be done in same alignment and dimensions as required and PCC
or brick work to be done as per beam dimensions in Vertical face.
• After PCC 3mm ply to be laid on PCC Surface and PVC sheet to be
nailed with PCC surface so surface of PCC and Surface of Slab
Concrete will separate. 7. Reinforcement to be completed as per
drawings, for beams dowel bar to be used from Cast in Situ Piles.
Dowel bars to be keep for adjacent slabs for Bottom Up
Construction.
• Concreting of Slab and Beam to be completed.
• After 14 days of Concreting, PCC below slab to be break/removed
excavation to be continued and retaining wall panels to be cast. Till
final level of excavation.
• Waterproofing to be done and base slab to be cast with dowels
from Cast in Situ Piles.
• Jacketing of Columns to be done if required
If any query please mail – saitowers2000@gmail.com
or visit - sai-towers.com

More Related Content

What's hot

earth support
earth supportearth support
earth support
juwes
 
Top down construction
Top down constructionTop down construction
Top down construction
Amulya Kansal
 
Bored pile-retaining-walls
Bored pile-retaining-wallsBored pile-retaining-walls
Bored pile-retaining-walls
Dr. Naveen BP
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
Davis Ciprikis
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
vietcgxd
 
pile wall
pile wallpile wall
pile wall
SALEM MOHAMMED
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
Kyle Beaudry, P.Eng
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
Thananchayan Theivendra
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinning
Okwera David
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
Nandhaa Veeramani
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Dr.youssef hamida
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 
Underpinning
UnderpinningUnderpinning
Underpinning
Khuzema Olia
 
Underpinning
UnderpinningUnderpinning
Underpinning
YingHongKang
 
Mat foundation
Mat foundationMat foundation
Mat foundation
shuvo293
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
Neha Vivek
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
guasiya
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
John Chakamba
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ANILKUMARMUCHINTALA
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
SALEM MOHAMMED
 

What's hot (20)

earth support
earth supportearth support
earth support
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Bored pile-retaining-walls
Bored pile-retaining-wallsBored pile-retaining-walls
Bored pile-retaining-walls
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
pile wall
pile wallpile wall
pile wall
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinning
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
 

Similar to Top down construction by Sai Towers P Ltd.

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
VATSAL PATEL
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
aman kumar
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
ShahbazKhan379018
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs bihar
Vaishnav Mishra
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
Shivananda Roy
 
Disaster Resistant Building Introduction
Disaster Resistant Building IntroductionDisaster Resistant Building Introduction
Disaster Resistant Building Introduction
TanmoyDatta15
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
ssuser480182
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
kristenjames
 
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
dilip patidar
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
practicalanswerssl
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
kristenjames
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
AbhinavSahu45
 
house construction
house constructionhouse construction
house construction
Abhinav Saha
 
Work check list
Work check listWork check list
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
Akshay Gawade
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Deepak Verma
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
DivineGraceFernando
 

Similar to Top down construction by Sai Towers P Ltd. (20)

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs bihar
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Disaster Resistant Building Introduction
Disaster Resistant Building IntroductionDisaster Resistant Building Introduction
Disaster Resistant Building Introduction
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
 
Form Work
Form Work Form Work
Form Work
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
 
house construction
house constructionhouse construction
house construction
 
Work check list
Work check listWork check list
Work check list
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
 

Recently uploaded

Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptxAnilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
neilahuja668
 
Gianluigi Torzi | Managing Director and Head of Capital Markets
Gianluigi Torzi | Managing Director and Head of Capital MarketsGianluigi Torzi | Managing Director and Head of Capital Markets
Gianluigi Torzi | Managing Director and Head of Capital Markets
Gianluigi Torzi
 
Why is Revit MEP Outsourcing considered an as good option for construction pr...
Why is Revit MEP Outsourcing considered an as good option for construction pr...Why is Revit MEP Outsourcing considered an as good option for construction pr...
Why is Revit MEP Outsourcing considered an as good option for construction pr...
MarsBIM1
 
Selling your home can be easy. Our team helps make it happen.
Selling your home can be easy. Our team helps make it happen.Selling your home can be easy. Our team helps make it happen.
Selling your home can be easy. Our team helps make it happen.
Eric B. Slifkin, PA
 
The Slifkin Real Estate Team Listing Presentation
The Slifkin Real Estate Team Listing PresentationThe Slifkin Real Estate Team Listing Presentation
The Slifkin Real Estate Team Listing Presentation
Eric B. Slifkin, PA
 
SVN Live 6.17.24 Weekly Property Broadcast
SVN Live 6.17.24 Weekly Property BroadcastSVN Live 6.17.24 Weekly Property Broadcast
SVN Live 6.17.24 Weekly Property Broadcast
SVN International Corp.
 
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdfGUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
ProexportColombia1
 
Listing Turkey - Piyalepasa Istanbul Catalog
Listing Turkey -  Piyalepasa Istanbul CatalogListing Turkey -  Piyalepasa Istanbul Catalog
Listing Turkey - Piyalepasa Istanbul Catalog
Listing Turkey
 
Living in an UBER World - June '24 Sales Meeting
Living in an UBER World - June '24 Sales MeetingLiving in an UBER World - June '24 Sales Meeting
Living in an UBER World - June '24 Sales Meeting
Tom Blefko
 
Sunrise Infra Properties Company Profile Pradeep.pdf
Sunrise Infra Properties Company Profile Pradeep.pdfSunrise Infra Properties Company Profile Pradeep.pdf
Sunrise Infra Properties Company Profile Pradeep.pdf
babugunda75
 
Marbo Medic Real Estate - Belgrade City.pdf
Marbo Medic Real Estate - Belgrade City.pdfMarbo Medic Real Estate - Belgrade City.pdf
Marbo Medic Real Estate - Belgrade City.pdf
IrinaKovacevic4
 
Office Building for Sale - 2810 City View Drive, Madison, WI
Office Building for Sale - 2810 City View Drive, Madison, WIOffice Building for Sale - 2810 City View Drive, Madison, WI
Office Building for Sale - 2810 City View Drive, Madison, WI
Lee & Associates of Madison, WI
 
Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!
shuilykhatunnil
 
Future of andhra pradesh real estate.pdf
Future of andhra pradesh real estate.pdfFuture of andhra pradesh real estate.pdf
Future of andhra pradesh real estate.pdf
narinav14
 
Signature Global TITANIUM SPR | 3.5 & 4.5BHK High rise Apartments in Gurgaon
Signature Global TITANIUM SPR  | 3.5 & 4.5BHK High rise Apartments in GurgaonSignature Global TITANIUM SPR  | 3.5 & 4.5BHK High rise Apartments in Gurgaon
Signature Global TITANIUM SPR | 3.5 & 4.5BHK High rise Apartments in Gurgaon
globalsignature2022
 
Expressways of India: A Comprehensive Guide
Expressways of India: A Comprehensive GuideExpressways of India: A Comprehensive Guide
Expressways of India: A Comprehensive Guide
narinav14
 
Floople Real Estate Market in the UK - Current Trends and Future Prospects
Floople Real Estate Market in the UK - Current Trends and Future ProspectsFloople Real Estate Market in the UK - Current Trends and Future Prospects
Floople Real Estate Market in the UK - Current Trends and Future Prospects
Floople
 

Recently uploaded (17)

Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptxAnilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
Anilesh Ahuja Pioneering a Paradigm Shift in Real Estate Success.pptx
 
Gianluigi Torzi | Managing Director and Head of Capital Markets
Gianluigi Torzi | Managing Director and Head of Capital MarketsGianluigi Torzi | Managing Director and Head of Capital Markets
Gianluigi Torzi | Managing Director and Head of Capital Markets
 
Why is Revit MEP Outsourcing considered an as good option for construction pr...
Why is Revit MEP Outsourcing considered an as good option for construction pr...Why is Revit MEP Outsourcing considered an as good option for construction pr...
Why is Revit MEP Outsourcing considered an as good option for construction pr...
 
Selling your home can be easy. Our team helps make it happen.
Selling your home can be easy. Our team helps make it happen.Selling your home can be easy. Our team helps make it happen.
Selling your home can be easy. Our team helps make it happen.
 
The Slifkin Real Estate Team Listing Presentation
The Slifkin Real Estate Team Listing PresentationThe Slifkin Real Estate Team Listing Presentation
The Slifkin Real Estate Team Listing Presentation
 
SVN Live 6.17.24 Weekly Property Broadcast
SVN Live 6.17.24 Weekly Property BroadcastSVN Live 6.17.24 Weekly Property Broadcast
SVN Live 6.17.24 Weekly Property Broadcast
 
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdfGUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
GUIA_LEGAL_CHAPTER_11_REAL STATE PROPERTY .pdf
 
Listing Turkey - Piyalepasa Istanbul Catalog
Listing Turkey -  Piyalepasa Istanbul CatalogListing Turkey -  Piyalepasa Istanbul Catalog
Listing Turkey - Piyalepasa Istanbul Catalog
 
Living in an UBER World - June '24 Sales Meeting
Living in an UBER World - June '24 Sales MeetingLiving in an UBER World - June '24 Sales Meeting
Living in an UBER World - June '24 Sales Meeting
 
Sunrise Infra Properties Company Profile Pradeep.pdf
Sunrise Infra Properties Company Profile Pradeep.pdfSunrise Infra Properties Company Profile Pradeep.pdf
Sunrise Infra Properties Company Profile Pradeep.pdf
 
Marbo Medic Real Estate - Belgrade City.pdf
Marbo Medic Real Estate - Belgrade City.pdfMarbo Medic Real Estate - Belgrade City.pdf
Marbo Medic Real Estate - Belgrade City.pdf
 
Office Building for Sale - 2810 City View Drive, Madison, WI
Office Building for Sale - 2810 City View Drive, Madison, WIOffice Building for Sale - 2810 City View Drive, Madison, WI
Office Building for Sale - 2810 City View Drive, Madison, WI
 
Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!Stark Builders: Where Quality Meets Craftsmanship!
Stark Builders: Where Quality Meets Craftsmanship!
 
Future of andhra pradesh real estate.pdf
Future of andhra pradesh real estate.pdfFuture of andhra pradesh real estate.pdf
Future of andhra pradesh real estate.pdf
 
Signature Global TITANIUM SPR | 3.5 & 4.5BHK High rise Apartments in Gurgaon
Signature Global TITANIUM SPR  | 3.5 & 4.5BHK High rise Apartments in GurgaonSignature Global TITANIUM SPR  | 3.5 & 4.5BHK High rise Apartments in Gurgaon
Signature Global TITANIUM SPR | 3.5 & 4.5BHK High rise Apartments in Gurgaon
 
Expressways of India: A Comprehensive Guide
Expressways of India: A Comprehensive GuideExpressways of India: A Comprehensive Guide
Expressways of India: A Comprehensive Guide
 
Floople Real Estate Market in the UK - Current Trends and Future Prospects
Floople Real Estate Market in the UK - Current Trends and Future ProspectsFloople Real Estate Market in the UK - Current Trends and Future Prospects
Floople Real Estate Market in the UK - Current Trends and Future Prospects
 

Top down construction by Sai Towers P Ltd.

  • 2. Why Top Down Construction Required • Distance between Boundary wall of Adjacent Existing Building and Building Line for New Building is too close and the depth of excavation is more than 6 meter and possibility of collapse the soil is higher during excavation. • Using Top Down Construction more Building and Basement Area can use. Suitable for two or more basement. • The first base slab level slab will act in such area as a strut member and the Retaining wall panels will not allow collapse of soil. • Water table is too high and difficult to cast Retaining wall, Diaphragm wall or Continuous Pile can use as a Retaining wall.
  • 3. METHODOLOGY OF TOP DOWN CONSTRUCTION • Setting out for alignment of bore cast in situ of piles . • Bore Cast in Situ Piles to be cast and dowels bar to be kept for Retaining wall panels. The center of piles and Retaining wall panels center line to be kept in same line. The Diameter of Piles preferred 600 mm, distance between two piles center to center preferred 3.33 meters (Suit for C/C distance of Columns), Depth of Piles to be confirmed by Structural Consultants. • Touching Piles can use as a Retaining wall with supporting arrangement during Excavation.
  • 4. • Water table is too high and difficult to cast Retaining wall, Diaphragm wall or Continuous Pile can use as a Retaining wall. • Instead of Column C1 to Column C8,Bore cast in Situ piles to be cast with dowel bars for different level slab and connecting Beams, The Diameter of Piles (suit as per Columns size), Reinforcement details (with dowels for Retaining wall and different level slabs and Beam), Depth of Piles to be confirmed by Structural Consultants. • Excavation to be done around 2 meter depth and retaining wall panels to be cast in stages with dowels bars with adjacent piles and dowel bars for next Retaining wall panel to be kept .if soil between piles collapsed soil nails with wire mesh to be kept on earth side to retain the same. Retaining wall panels to be cast with dowels up to the first base slab bottom.
  • 5. • Dressing and compaction of soil to be done for PCC bed for casting of first base slab. 50mm PCC (M15 Grade) to be done, the top levels of PCC to be keep the base slab level bottom. For beams excavation to be done in same alignment and dimensions as required and PCC or brick work to be done as per beam dimensions in Vertical face. • After PCC 3mm ply to be laid on PCC Surface and PVC sheet to be nailed with PCC surface so surface of PCC and Surface of Slab Concrete will separate. 7. Reinforcement to be completed as per drawings, for beams dowel bar to be used from Cast in Situ Piles. Dowel bars to be keep for adjacent slabs for Bottom Up Construction.
  • 6. • Concreting of Slab and Beam to be completed. • After 14 days of Concreting, PCC below slab to be break/removed excavation to be continued and retaining wall panels to be cast. Till final level of excavation. • Waterproofing to be done and base slab to be cast with dowels from Cast in Situ Piles. • Jacketing of Columns to be done if required If any query please mail – saitowers2000@gmail.com or visit - sai-towers.com