The Millau Viaduct is the tallest cable-stayed bridge in the world, located in southern France. It features 7 pylons up to 343 meters tall that support a 2,460 meter long steel deck. The bridge's longest span is 346 meters and it was constructed between 2001-2004 to shorten travel time across the region.
Bridges: Classification of bridges – with respect to construction
materials, structural behavior of super structure, span, sub structure,
purpose. Temporary and movable bridges. Factors affecting site
selection. Various loads/stresses acting on bridges. Bridge hydrology –
design discharge, water way, afflux, scour depth, economical span.
Bridge components – foundation, piers, abutments, wing wall, approach,
bearings, floor, girders, cables, suspenders. Methods of erection of
different types of bridges. River training works and maintenance of
bridges. Testing and strengthening of bridges. Bridge architect.
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
The Akashi Kaikyo bridge - longest suspension bridge in the worldADARSH _
Case Study of the Longest Suspension Bridge in the world - The Akashi Kaikyo Bridge. In this presentation, various structural features of this bridge are discussed and a few videos provided helps us to get a better understanding of it.
Bridges: Classification of bridges – with respect to construction
materials, structural behavior of super structure, span, sub structure,
purpose. Temporary and movable bridges. Factors affecting site
selection. Various loads/stresses acting on bridges. Bridge hydrology –
design discharge, water way, afflux, scour depth, economical span.
Bridge components – foundation, piers, abutments, wing wall, approach,
bearings, floor, girders, cables, suspenders. Methods of erection of
different types of bridges. River training works and maintenance of
bridges. Testing and strengthening of bridges. Bridge architect.
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
Construction sequence for metro Project (Elevated and Underground) and Time cycle of the metro construction activity . For more details u can contact me on my mail id -shuklaakhilesh08@gmail.com
The Akashi Kaikyo bridge - longest suspension bridge in the worldADARSH _
Case Study of the Longest Suspension Bridge in the world - The Akashi Kaikyo Bridge. In this presentation, various structural features of this bridge are discussed and a few videos provided helps us to get a better understanding of it.
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...Rajesh Prasad
The paper deals with how an engineering challenge confronted in a busy yard due to presence of a distressed bridge(ROB) was replaced by a Cable Stayed Bridge by adopting safe practices with proper quality and within the time frame. The paper was presented today ie 18.08.17 in a lecture organised by IIBE at Institution of Engineers, Mumbai
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
Detailed Power point presentation on Implementation of 4 lane Cable Stayed Road over bridge at Bardhman- a future fast track model for construction over busy and longer Railway yards in India
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
A review on techniques and modelling methodologies used for checking electrom...nooriasukmaningtyas
The proper function of the integrated circuit (IC) in an inhibiting electromagnetic environment has always been a serious concern throughout the decades of revolution in the world of electronics, from disjunct devices to today’s integrated circuit technology, where billions of transistors are combined on a single chip. The automotive industry and smart vehicles in particular, are confronting design issues such as being prone to electromagnetic interference (EMI). Electronic control devices calculate incorrect outputs because of EMI and sensors give misleading values which can prove fatal in case of automotives. In this paper, the authors have non exhaustively tried to review research work concerned with the investigation of EMI in ICs and prediction of this EMI using various modelling methodologies and measurement setups.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
3. PROJECT DATA
• Location: Millau, France
• Motorway bridge over the river Tarn in Millau and longest cable-
stayed bridge in the world
• construction period: 2001 - 2004
• construction: cable-stayed bridge
• construction method: bridge as a steel box superstructure using
an incremental launching method
• eight-section bridge with a length of 2,460 m
• highest piers: 343 m with steel structure
• seven reinforced concrete piers from approx. 78 m to 245 m
• cross-section change from single to double piers, 90 m below
the superstructure
4. PROJECT DATA
• Total width of span is 32.05m with 2 lanes on both the sides
• Longest span of bridge is 346m long
• Total cost of construction = 400 million euro
• Before construction of bridge ‘Fairy service’ took one & half hour
for crossing, but after construction of bridge this distance is passes
away in 5-10 minutes.
• It’s tallest pier is even taller than Eiffel Tower
• Tallest Pylons in the world
5. STRUCTURAL ELEMENTS
1. PYLONS & ABUTMENTS
~Each pylon is supported by four deep shafts, 15 m
(49 ft) deep and 5 m (16 ft) in diameter.
~The abutments are concrete structures that provide
anchorage for the deck to the ground at corners of
bridge
P1 P2 P3 P4 P5 P6 P7
94.50m 244.9m 221.0m 144.2m 136.4m 111.9m 77.56m
6.
7. 2. DECK
• The metallic deck, which appears very light despite its total
mass of around 36,000 tonnes (40,000 short tons), is 2,460 m
(8,070 ft) long and 32 m (105 ft) wide.
• These are composed of 173 central box beams, the spinal
column of the construction, onto which the lateral floors and
the lateral box beams were welded.
• The central box beams have a 4 m (13 ft) cross-section and a
length of 15–22 m (49–72 ft) for a total weight of 90 metric
tons (99 short tons). The deck has an inverse Airfoil shape,
providing negative lift in strong wind conditions.
8. 3. MASTS
• The seven masts, each
87 m (285 ft) high and
weighing around 700
tonnes (690 long tons; 770
short tons), are set on top of
the pylons. Between each
of them, eleven stays
(metal cables) are
anchored, providing
support for the road deck.
9. 4.STAYS
• Each mast of the viaduct is equipped with a monoaxial layer of
eleven pairs of stays laid face to face. Depending on their length, the
stays were made of 55 to 91 high tensile steel cables, or strands,
themselves formed of seven strands of steel (a central strand with six
intertwined strands).
• Each strand has triple protection against corrosion (galvanisation, a
coating of petroleum wax and an extruded polyethylene sheath).
The exterior envelope of the stays is itself coated along its entire
length with a double helical weatherstrip. The idea is to avoid running
water which, in high winds, could cause vibration in the stays and
compromise the stability of the viaduct.
• The stays were installed by the Freyssinet company.
10. 5. SURFACE
• To allow for deformations of the metal deck under traffic, a special
surface of modified bitumen was installed by research teams
from Appia.
• The surface is somewhat flexible to adapt to deformations in the steel
deck without cracking, but it must nevertheless have sufficient strength
to withstand motorway conditions (fatigue, density, texture,
adherence, anti-rutting etc.).
• The "ideal formula" was found only after two years of research
11. 6. ELECTRICAL
INSTALLATIONS
• The electrical installations of the
viaduct are large in proportion
to the size of the bridge.
• There are 30 km (19 mi) of high-
current cables, 20 km (12 mi)
of fibre optics, 10 km (6.2 mi) of
low-current cables and 357
telephone sockets allowing
maintenance teams to
communicate with each other
and with the command post.
• These are situated on the deck,
on the pylons and on the masts.
12. 7. SAFETY MEASURES
• The pylons, deck, masts and stays are equipped with a multitude of sensors.
These are designed to detect the slightest movement in the viaduct and
measure its resistance to wear-and-tear over
time. Anemometers, accelerometers, inclinometers, temperature sensors are
all used for the instrumentation network.
• Twelve fibre optic extensometers were installed in the base of pylon P2. Being
the tallest of all, it is therefore under the most intense stress. These sensors
detect movements on the order of a micrometre. Other extensometers—
electrical this time—are distributed on top of P2 and P7. This apparatus is
capable of taking up to 100 readings per second. In high winds, they
continuously monitor the reactions of the viaduct to extreme conditions.
Accelerometers placed strategically on the deck monitor the oscillations that
can affect the metal structure. Displacements of the deck on the abutment
level are measured to the nearest millimetre. The stays are also instrumented,
and their ageing meticulously analysed. Additionally, two piezoelectric
sensors gather traffic data: weight of vehicles, average speed, density of the
flow of traffic, etc. This system can distinguish between fourteen different types
of vehicle.
• The data is transmitted by an Ethernet network to a computer in the IT room at
the management building situated near the toll plaza.
13. CONSTRUCTION OVERVIEW
• Temporary piers
used to help launch
and support the deck
as the the pylons
were constructed.
• The 2460m deck was
launched in two
pieces.
• Pylons and cables
were added on top
of the piers.
14. DECK LAUNCHING
• 7 temporary piers help
support the weight of the
deck.
• 2 deck segments are
launched from the each end
of te bhridge.
15. HYDRAULIC LAUNCHERS
• launchers push the pre-
fabricated deck
segments onto the
piers.
• cycle moves the deck
600mm. Total of 5000
cycles required.
16. NOSE RECOVERY
• Weight of steel
box-girder deck
sags as span is
completed.
• Nose recovery
system attached to
raise the deck to
the level of the
next pier.
17. COMPLETION
• Deck segments move towards each other at the
rate of 0.9 meter per hour.
• Two deck segments joined in May of 2004.