SlideShare a Scribd company logo
THE MILLAU
VIADUCT
Cable-stayed bridge, @Millau,
France
PROJECT DATA
• Location: Millau, France
• Motorway bridge over the river Tarn in Millau and longest cable-
stayed bridge in the world
• construction period: 2001 - 2004
• construction: cable-stayed bridge
• construction method: bridge as a steel box superstructure using
an incremental launching method
• eight-section bridge with a length of 2,460 m
• highest piers: 343 m with steel structure
• seven reinforced concrete piers from approx. 78 m to 245 m
• cross-section change from single to double piers, 90 m below
the superstructure
PROJECT DATA
• Total width of span is 32.05m with 2 lanes on both the sides
• Longest span of bridge is 346m long
• Total cost of construction = 400 million euro
• Before construction of bridge ‘Fairy service’ took one & half hour
for crossing, but after construction of bridge this distance is passes
away in 5-10 minutes.
• It’s tallest pier is even taller than Eiffel Tower
• Tallest Pylons in the world
STRUCTURAL ELEMENTS
1. PYLONS & ABUTMENTS
~Each pylon is supported by four deep shafts, 15 m
(49 ft) deep and 5 m (16 ft) in diameter.
~The abutments are concrete structures that provide
anchorage for the deck to the ground at corners of
bridge
P1 P2 P3 P4 P5 P6 P7
94.50m 244.9m 221.0m 144.2m 136.4m 111.9m 77.56m
2. DECK
• The metallic deck, which appears very light despite its total
mass of around 36,000 tonnes (40,000 short tons), is 2,460 m
(8,070 ft) long and 32 m (105 ft) wide.
• These are composed of 173 central box beams, the spinal
column of the construction, onto which the lateral floors and
the lateral box beams were welded.
• The central box beams have a 4 m (13 ft) cross-section and a
length of 15–22 m (49–72 ft) for a total weight of 90 metric
tons (99 short tons). The deck has an inverse Airfoil shape,
providing negative lift in strong wind conditions.
3. MASTS
• The seven masts, each
87 m (285 ft) high and
weighing around 700
tonnes (690 long tons; 770
short tons), are set on top of
the pylons. Between each
of them, eleven stays
(metal cables) are
anchored, providing
support for the road deck.
4.STAYS
• Each mast of the viaduct is equipped with a monoaxial layer of
eleven pairs of stays laid face to face. Depending on their length, the
stays were made of 55 to 91 high tensile steel cables, or strands,
themselves formed of seven strands of steel (a central strand with six
intertwined strands).
• Each strand has triple protection against corrosion (galvanisation, a
coating of petroleum wax and an extruded polyethylene sheath).
The exterior envelope of the stays is itself coated along its entire
length with a double helical weatherstrip. The idea is to avoid running
water which, in high winds, could cause vibration in the stays and
compromise the stability of the viaduct.
• The stays were installed by the Freyssinet company.
5. SURFACE
• To allow for deformations of the metal deck under traffic, a special
surface of modified bitumen was installed by research teams
from Appia.
• The surface is somewhat flexible to adapt to deformations in the steel
deck without cracking, but it must nevertheless have sufficient strength
to withstand motorway conditions (fatigue, density, texture,
adherence, anti-rutting etc.).
• The "ideal formula" was found only after two years of research
6. ELECTRICAL
INSTALLATIONS
• The electrical installations of the
viaduct are large in proportion
to the size of the bridge.
• There are 30 km (19 mi) of high-
current cables, 20 km (12 mi)
of fibre optics, 10 km (6.2 mi) of
low-current cables and 357
telephone sockets allowing
maintenance teams to
communicate with each other
and with the command post.
• These are situated on the deck,
on the pylons and on the masts.
7. SAFETY MEASURES
• The pylons, deck, masts and stays are equipped with a multitude of sensors.
These are designed to detect the slightest movement in the viaduct and
measure its resistance to wear-and-tear over
time. Anemometers, accelerometers, inclinometers, temperature sensors are
all used for the instrumentation network.
• Twelve fibre optic extensometers were installed in the base of pylon P2. Being
the tallest of all, it is therefore under the most intense stress. These sensors
detect movements on the order of a micrometre. Other extensometers—
electrical this time—are distributed on top of P2 and P7. This apparatus is
capable of taking up to 100 readings per second. In high winds, they
continuously monitor the reactions of the viaduct to extreme conditions.
Accelerometers placed strategically on the deck monitor the oscillations that
can affect the metal structure. Displacements of the deck on the abutment
level are measured to the nearest millimetre. The stays are also instrumented,
and their ageing meticulously analysed. Additionally, two piezoelectric
sensors gather traffic data: weight of vehicles, average speed, density of the
flow of traffic, etc. This system can distinguish between fourteen different types
of vehicle.
• The data is transmitted by an Ethernet network to a computer in the IT room at
the management building situated near the toll plaza.
CONSTRUCTION OVERVIEW
• Temporary piers
used to help launch
and support the deck
as the the pylons
were constructed.
• The 2460m deck was
launched in two
pieces.
• Pylons and cables
were added on top
of the piers.
DECK LAUNCHING
• 7 temporary piers help
support the weight of the
deck.
• 2 deck segments are
launched from the each end
of te bhridge.
HYDRAULIC LAUNCHERS
• launchers push the pre-
fabricated deck
segments onto the
piers.
• cycle moves the deck
600mm. Total of 5000
cycles required.
NOSE RECOVERY
• Weight of steel
box-girder deck
sags as span is
completed.
• Nose recovery
system attached to
raise the deck to
the level of the
next pier.
COMPLETION
• Deck segments move towards each other at the
rate of 0.9 meter per hour.
• Two deck segments joined in May of 2004.
PHOTOES OF CONSTRUCTION
Hollow pier construction by moving
formwork with hydraulic crane
the millau viaduct
the millau viaduct
the millau viaduct

More Related Content

What's hot

6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
VATSAL PATEL
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acpJigar Shah
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
Rana Ibrahim
 
AKASHI KAIKYO BRIDGE
AKASHI KAIKYO BRIDGEAKASHI KAIKYO BRIDGE
AKASHI KAIKYO BRIDGE
gomathi gowda
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
Nouman Tahir
 
Building structure project 1 report
Building structure project 1 reportBuilding structure project 1 report
Building structure project 1 report
Adelinetingg
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
Robin Nirwal
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
Sadek Abdelraheem
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
Dr Fereidoun Dejahang
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentation
Bhismo Dev
 
Howrah bridge
Howrah bridgeHowrah bridge
Howrah bridge
PranavZane
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
MD DANIYAL
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
Akhilesh Kumar
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
Akhilesh Shukla
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
Bhalchandra Tankkar
 
Rio Antirio Bridge - Report
Rio Antirio Bridge - ReportRio Antirio Bridge - Report
Rio Antirio Bridge - Report
Ghulam Mustafa Vira
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
Satish Kambaliya
 

What's hot (20)

6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Cable stayed ppt acp
Cable stayed ppt acpCable stayed ppt acp
Cable stayed ppt acp
 
Golden gate bridge
Golden gate bridgeGolden gate bridge
Golden gate bridge
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
 
AKASHI KAIKYO BRIDGE
AKASHI KAIKYO BRIDGEAKASHI KAIKYO BRIDGE
AKASHI KAIKYO BRIDGE
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
 
Building structure project 1 report
Building structure project 1 reportBuilding structure project 1 report
Building structure project 1 report
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
 
Bracing connections
Bracing connectionsBracing connections
Bracing connections
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentation
 
Howrah bridge
Howrah bridgeHowrah bridge
Howrah bridge
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Rio Antirio Bridge - Report
Rio Antirio Bridge - ReportRio Antirio Bridge - Report
Rio Antirio Bridge - Report
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 

Similar to the millau viaduct

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
Mohammad Ali
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
ADARSH _
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
varun km
 
Form Active system
Form Active systemForm Active system
Form Active system
DanishPathan7
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Rajesh Prasad
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
ShuBham RaNa
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInAlfred Mangus
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
BUILDING CONSTRUCTION PRESENTATION TV TOWER
BUILDING CONSTRUCTION PRESENTATION TV TOWERBUILDING CONSTRUCTION PRESENTATION TV TOWER
BUILDING CONSTRUCTION PRESENTATION TV TOWER
JheelHome
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Rajesh Prasad
 
steelstructures-130906015820-.pdf
steelstructures-130906015820-.pdfsteelstructures-130906015820-.pdf
steelstructures-130906015820-.pdf
rubini32
 
Steel structures
Steel structuresSteel structures
Steel structures
Sukhdarshan Singh
 
The Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension BridgeThe Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension Bridge
elsayed ahmed
 
03 CONVEYER.pptx
03 CONVEYER.pptx03 CONVEYER.pptx
03 CONVEYER.pptx
DrGaneshKameDrKame
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
TV TOWER. BUILDING CONSTRUCTION PRESENTATION
TV TOWER. BUILDING CONSTRUCTION PRESENTATIONTV TOWER. BUILDING CONSTRUCTION PRESENTATION
TV TOWER. BUILDING CONSTRUCTION PRESENTATION
JheelHome
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
naqeeb04
 

Similar to the millau viaduct (20)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
The Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the worldThe Akashi Kaikyo bridge - longest suspension bridge in the world
The Akashi Kaikyo bridge - longest suspension bridge in the world
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
Form Active system
Form Active systemForm Active system
Form Active system
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedInCalifornia Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
California Orthotropic-October-2005 & Millau Normandie France Mangus LinkedIn
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
BUILDING CONSTRUCTION PRESENTATION TV TOWER
BUILDING CONSTRUCTION PRESENTATION TV TOWERBUILDING CONSTRUCTION PRESENTATION TV TOWER
BUILDING CONSTRUCTION PRESENTATION TV TOWER
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
steelstructures-130906015820-.pdf
steelstructures-130906015820-.pdfsteelstructures-130906015820-.pdf
steelstructures-130906015820-.pdf
 
Steel structures
Steel structuresSteel structures
Steel structures
 
The Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension BridgeThe Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension Bridge
 
03 CONVEYER.pptx
03 CONVEYER.pptx03 CONVEYER.pptx
03 CONVEYER.pptx
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
TV TOWER. BUILDING CONSTRUCTION PRESENTATION
TV TOWER. BUILDING CONSTRUCTION PRESENTATIONTV TOWER. BUILDING CONSTRUCTION PRESENTATION
TV TOWER. BUILDING CONSTRUCTION PRESENTATION
 
A mini project on the transmission tower
A mini project on the transmission towerA mini project on the transmission tower
A mini project on the transmission tower
 

Recently uploaded

Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
azkamurat
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 

Recently uploaded (20)

Ethernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.pptEthernet Routing and switching chapter 1.ppt
Ethernet Routing and switching chapter 1.ppt
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 

the millau viaduct

  • 2.
  • 3. PROJECT DATA • Location: Millau, France • Motorway bridge over the river Tarn in Millau and longest cable- stayed bridge in the world • construction period: 2001 - 2004 • construction: cable-stayed bridge • construction method: bridge as a steel box superstructure using an incremental launching method • eight-section bridge with a length of 2,460 m • highest piers: 343 m with steel structure • seven reinforced concrete piers from approx. 78 m to 245 m • cross-section change from single to double piers, 90 m below the superstructure
  • 4. PROJECT DATA • Total width of span is 32.05m with 2 lanes on both the sides • Longest span of bridge is 346m long • Total cost of construction = 400 million euro • Before construction of bridge ‘Fairy service’ took one & half hour for crossing, but after construction of bridge this distance is passes away in 5-10 minutes. • It’s tallest pier is even taller than Eiffel Tower • Tallest Pylons in the world
  • 5. STRUCTURAL ELEMENTS 1. PYLONS & ABUTMENTS ~Each pylon is supported by four deep shafts, 15 m (49 ft) deep and 5 m (16 ft) in diameter. ~The abutments are concrete structures that provide anchorage for the deck to the ground at corners of bridge P1 P2 P3 P4 P5 P6 P7 94.50m 244.9m 221.0m 144.2m 136.4m 111.9m 77.56m
  • 6.
  • 7. 2. DECK • The metallic deck, which appears very light despite its total mass of around 36,000 tonnes (40,000 short tons), is 2,460 m (8,070 ft) long and 32 m (105 ft) wide. • These are composed of 173 central box beams, the spinal column of the construction, onto which the lateral floors and the lateral box beams were welded. • The central box beams have a 4 m (13 ft) cross-section and a length of 15–22 m (49–72 ft) for a total weight of 90 metric tons (99 short tons). The deck has an inverse Airfoil shape, providing negative lift in strong wind conditions.
  • 8. 3. MASTS • The seven masts, each 87 m (285 ft) high and weighing around 700 tonnes (690 long tons; 770 short tons), are set on top of the pylons. Between each of them, eleven stays (metal cables) are anchored, providing support for the road deck.
  • 9. 4.STAYS • Each mast of the viaduct is equipped with a monoaxial layer of eleven pairs of stays laid face to face. Depending on their length, the stays were made of 55 to 91 high tensile steel cables, or strands, themselves formed of seven strands of steel (a central strand with six intertwined strands). • Each strand has triple protection against corrosion (galvanisation, a coating of petroleum wax and an extruded polyethylene sheath). The exterior envelope of the stays is itself coated along its entire length with a double helical weatherstrip. The idea is to avoid running water which, in high winds, could cause vibration in the stays and compromise the stability of the viaduct. • The stays were installed by the Freyssinet company.
  • 10. 5. SURFACE • To allow for deformations of the metal deck under traffic, a special surface of modified bitumen was installed by research teams from Appia. • The surface is somewhat flexible to adapt to deformations in the steel deck without cracking, but it must nevertheless have sufficient strength to withstand motorway conditions (fatigue, density, texture, adherence, anti-rutting etc.). • The "ideal formula" was found only after two years of research
  • 11. 6. ELECTRICAL INSTALLATIONS • The electrical installations of the viaduct are large in proportion to the size of the bridge. • There are 30 km (19 mi) of high- current cables, 20 km (12 mi) of fibre optics, 10 km (6.2 mi) of low-current cables and 357 telephone sockets allowing maintenance teams to communicate with each other and with the command post. • These are situated on the deck, on the pylons and on the masts.
  • 12. 7. SAFETY MEASURES • The pylons, deck, masts and stays are equipped with a multitude of sensors. These are designed to detect the slightest movement in the viaduct and measure its resistance to wear-and-tear over time. Anemometers, accelerometers, inclinometers, temperature sensors are all used for the instrumentation network. • Twelve fibre optic extensometers were installed in the base of pylon P2. Being the tallest of all, it is therefore under the most intense stress. These sensors detect movements on the order of a micrometre. Other extensometers— electrical this time—are distributed on top of P2 and P7. This apparatus is capable of taking up to 100 readings per second. In high winds, they continuously monitor the reactions of the viaduct to extreme conditions. Accelerometers placed strategically on the deck monitor the oscillations that can affect the metal structure. Displacements of the deck on the abutment level are measured to the nearest millimetre. The stays are also instrumented, and their ageing meticulously analysed. Additionally, two piezoelectric sensors gather traffic data: weight of vehicles, average speed, density of the flow of traffic, etc. This system can distinguish between fourteen different types of vehicle. • The data is transmitted by an Ethernet network to a computer in the IT room at the management building situated near the toll plaza.
  • 13. CONSTRUCTION OVERVIEW • Temporary piers used to help launch and support the deck as the the pylons were constructed. • The 2460m deck was launched in two pieces. • Pylons and cables were added on top of the piers.
  • 14. DECK LAUNCHING • 7 temporary piers help support the weight of the deck. • 2 deck segments are launched from the each end of te bhridge.
  • 15. HYDRAULIC LAUNCHERS • launchers push the pre- fabricated deck segments onto the piers. • cycle moves the deck 600mm. Total of 5000 cycles required.
  • 16. NOSE RECOVERY • Weight of steel box-girder deck sags as span is completed. • Nose recovery system attached to raise the deck to the level of the next pier.
  • 17. COMPLETION • Deck segments move towards each other at the rate of 0.9 meter per hour. • Two deck segments joined in May of 2004.
  • 18. PHOTOES OF CONSTRUCTION Hollow pier construction by moving formwork with hydraulic crane